www.wizardea.com | contact@wizardea.com
Learning Objectives
Upon completion of this topic you will learn about
– The processes, activities and documentation items for Project
Time Management
– Elements (and deliverables) for Project Time Management
– Tools and techniques of the key activities of the Project Time
Management
3
www.wizardea.com | contact@wizardea.com
Key Activities of Time Management
• Define Activities: The process of identifying the specific
actions to be performed to produce the project
deliverables.
• Sequence Activities: The process of identifying and
documenting relationships among the project activities.
• Estimate Activity Resource: The process of estimating the
type and qualities of material, people, equipment, or
supplies required to perform each activities.
5
www.wizardea.com | contact@wizardea.com
Key Activities of Time Management
• Estimate Activity Duration: The process of approximating
the number of work periods needed to complete individual
activities with specific resources.
• Develop Schedule: The process of analyzing activity
sequences, durations, resource requirements, and
schedule constrains to create the project schedule.
• Control Schedule: The process of monitoring the status of
the project to update project progress and managing
changes to the schedule baseline.
6
www.wizardea.com | contact@wizardea.com
Define Activities > Tools and Techniques
Rolling Wave Planning
Rolling wave planning is a form of progressive elaboration planning
where the work to be accomplished in the near term is planned in
detail at a low level of WBS, while work far in the future is planned for
the WBS components that are at relatively high level of the WBS.
Templates
A standard activity list or a portion of activity list from a
previous project is often usable as a template for new project.
9
www.wizardea.com | contact@wizardea.com
Define Activities > Outputs
Activity List
Activity list is a comprehensive list including all schedule activities required on the
project.
Activity Attributes
Activity attributes extend the description of the activity by identifying the multiple
components associated with each activity.
The component of each activity evolve over time.
During the initial stages of the project they include the Activity ID, WBS ID, and
activity name, and when completed may include activity codes, activity description,
predecessor activities, successor activities, logical relationships, leads and lags,
resource requirements, imposed dates, constrain and assumptions.
Milestone List
A milestone is a significant point or event in the project.
10
www.wizardea.com | contact@wizardea.com
Sequence Activities > Tools and Techniques
Activity
A
Activity
B
Finish to Start (FS) Relationship
Activity
A
Activity
B
Start to Start (SS) Relationship
Activity
A
Activity
B
Finish to Finish (FF) Relationship
Activity
A
Activity
B
Start to Finish (SF) Relationship
• Precedence diagramming method (PDM)
• PDM is a method used in Critical Path Methodology (CPM) for constructing a project
schedule network diagram that uses boxes or rectangular, referred to as nodes, to
represent activities and connect them with arrows that show the logical relationships
that exists between them.
13
www.wizardea.com | contact@wizardea.com
Sequence Activities > Tools and Techniques
Dependency Determination
Mandatory dependency
Discretionary dependency
External dependency
Appling Leads and Lags
A lead allows an acceleration of a successor activity
A lag directs a delay in the successor activity
14
Activity
A
Activity
B
L=3
FS Relationship: The Start of B must lag (L)
the Finish of A by 3 days
Activity
A
Activity
B
L=4
SS Relationship: The Start of B must lag (L)
the Start of A by 4 days
Activity
A
Activity
B
L=5
FF Relationship: The Finish of B must lag (L)
the Finish of A by 5 days
Activity
A
Activity
B
L=6
SF Relationship: The Finish of B must lag (L)
the Start of A by 6 days
www.wizardea.com | contact@wizardea.com
Sequence Activities > Outputs
Network Diagram
Any schematic display of the logical relationships of Project Activities.
Always drawn from left to right to reflect project chronology. Often
incorrectly referred to as a “PERT Chart”.
Network Diagram Rules of Thumbs
There is a starting point
There is an ending point
There are predecessors for all activities
There are successors for all activities (no hangers!)
There are no loops
15
www.wizardea.com | contact@wizardea.com
Estimate Activity Resource > Inputs
• Resource Calendars
• A calendar that documents the working and nonworking days that
determine the dates that a resource is available or not.
18
www.wizardea.com | contact@wizardea.com
Estimate Activity Resource > Outputs
• Activity Resource Requirement
• An identification and description of the types of quantities of
resources required for each schedule activity in a work package
• Resource Breakdown Structure
• A hierarchical structure of identified resources by resource category
and type
19
www.wizardea.com | contact@wizardea.com
Estimate Activity Durations > Tools and
Techniques
Analogous Estimating
Top down estimating, uses actual duration of activities from previous projects
Parametric Estimating
Top down estimating, activity duration can be uses a mathematical model to
determine estimates
Estimating the basis for activity duration can be quantitatively determine by multiply
the quantity of work to be performed by the productivity rate. e.g. Function Point
Estimation, Use Case Estimation.
Three Point Estimating
Estimating an average of the most likely, optimistic, pessimistic estimated duration.
23
www.wizardea.com | contact@wizardea.com
Estimate Activity Durations > Tools and
Techniques
Multi Point Estimating (PERT)
Program Evaluation and Review Technique (PERT)
Calculation:
Mean = (P + 4M + O)/6
Standard Deviation = (P-O)/6
Variance = ((P-O)/6)2
Here, P = Pessimistic Estimation, O = Optimistic Estimation and M = Most likely Estimation
Reserve Analysis
Called time reserve, contingency, or buffer
Purpose – To add time to individual activities or the overall project
duration for schedule risks
Accumulated for the project and included in the project contingency
fund or management reserve
Note: Authors discourage adding time to individual activities since this is a form of padding
24
www.wizardea.com | contact@wizardea.com
• Complete the table using the formulas of PERT
25
Activity O M P Expected
Duration
Activity
Standard
deviation
Range of the
Estimates
A 14 27 47
B 41 60 89
C 39 44 48
D 29 37 42
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Critical Path Method (CPM)
• Critical Path Method (CPM), is a procedure for using network analysis
to identify those tasks which are on the critical path: ie where any delay
in the completion of these tasks will lengthen the project timescale,
unless action is taken.
• For all tasks off the critical path, a degree of tolerance is possible (eg.
late start, late completion, early start, etc.).
• Network charts and CPM analysis used to be carried out by hand.
• Software is now available which requires the user only to enter the
tasks, duration of each task and dependencies upon other tasks; a
network chart and CPM is then automatically created.
29
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Why Critical Path Method (CPM)
• The CPM formally identifies tasks which must be completed on time
for the whole project to be completed on time
• Identifies which tasks can be delayed for a while if resource needs to
be reallocated to catch up on missed tasks
• It helps you to identify the minimum length of time needed to
complete a project
• The CPM determines both the early start and the late start date for
each activity in the schedule.
30
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Critical Chain Method (CCM)
• Critical Chain Method (CCM), is a schedule network analysis
techniques that modifies the project schedule to account for limited
resources.
• Initially, the project schedule network diagram is built using duration
estimates with required dependencies and defined constrains as input.
The critical path is then calculated. After the critical path is designed,
resource availability is entered and the resource-limited schedule result
is determined. The resulting schedule often has an altered critical path.
35
www.wizardea.com | contact@wizardea.com
Control Schedule
Inputs Tools & Techniques Outputs
Schedule management
plan
Project Schedule
Work performance
information
Organization process
assets
Performance reviews
Variance analysis
Project management
software
Resource leveling
What-if scenario analysis
Adjusting leads and lags
Progress reporting
Schedule compression
Scheduling tool
Work performance
measurements
Organizational process assets
updates
Change requests
Project management plan
updates
Project document updates
37
37
www.wizardea.com | contact@wizardea.com
Control Schedule > Tools and Techniques
• Progress reporting
• Actual Start and Finish Dates
• Remaining duration for unfinished tasks
• Percent completion (from Earned Value Analysis)
• Schedule Change Control System
• Part of Integrated Change Control
• Performance Measurements
• Schedule Variance (SV), Schedule Performance Index (SPI) (from
Earned Value Analysis)
• Schedule Comparison Bar Charts
• Tracking Gantt
38
GetFREETemplatesatwww.wizardea.com