The Hampton Bays Union Free School received its charter in 1908.  The new Middle School, located on Ponquogue Avenue, opened in April 2008 in celebration of the district’s Centennial. The Shinnecock (Ponquogue Point) Lighthouse located in Hampton Bays was built in 1858 and later demolished by the Coast Guard in 1948, but its iconography has informed the new building’s architectural identity. bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
The Hampton Bays Middle School has been designed and constructed to be a high performing sustainable building that has received LEED Silver Certification. It is responsive to the architectural identity of its community at large. It is also a fully functional (5-8) middle school embracing team teaching and cooperative learning.  It is a constant source of inspiration for the students who will spend a portion of their formative years here. “ M A I N  S T R E E T”  C O R R I D O R “ M A I N  S T R E E T”  C O R R I D O R  A C C E S S I N G  A L L  P O I N T S  bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
GARNERING PUBLIC SUPPORT BBS green
We knew where we were heading with the design.  We had done the research and put together a  plan . Now, we needed the public to believe in what we were planning, and vote ‘ yes ’.
 
H A M P T O N  B A Y S  M I D D L E  S C H O O L
 
 
H A M P T O N  B A Y S  M I D D L E  S C H O O L
VOTER APPROVAL BBS green
H A M P T O N  B A Y S  M I D D L E  S C H O O L
DESIGN  DEVELOPMENT & CONSTRUCTION DOCUMENTS BBS green
The performance of the exterior building envelope sets the standard for the performance of the entire project. Proper architectural detailing and design leads to the development of more efficient HVAC systems. Perimeter radiation heating was effectively removed from the project due to an improved exterior building envelope. More efficient HVAC systems consume less energy.  Building Performance bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
SILL DETAIL
HEAD DETAIL
JAMB DETAIL
Conventional construction detailing can lead to the development of an exterior building envelope that does not perform as well as it could. Gaps in insulation, air and moisture infiltration, and thermal bridging are key issues.  By rethinking the way we detail a building during the development of construction documents we can achieve a high performance exterior building envelope with minimal budget impact. Building Envelope bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
Hampton Bays  Middle School Locating the structural frame completely within the building envelope creates a thermal break between the inside and outside of the building. bbs
Hampton Bays  Middle School Thermal breaks at floor slabs prevent heat loss due to conduction. bbs
Hampton Bays  Middle School 3” thick insulation within the wall cavity is continuous from the top to the bottom. R-36 roof insulation has been used, (R-30 is the more typical standard requirement) bbs
Hampton Bays  Middle School Moisture is less likely to accumulate within a wall cavity when flashing is strategically located and proper ventilation of the wall cavity is provided. Preventing moisture infiltration is key in the prevention of mold growth and contributes to high levels of indoor air quality (IAQ). bbs
Hampton Bays  Middle School Combining all of these details creates a building envelope that will perform at a higher level than a more conventionally detailed building. bbs
The Hampton Bays Middle School performs at a higher level than a “baseline building” as defined by (ASHRAE 90.1-1999) and N.Y.S. Code standards. Performance criteria are based upon the comparison of U-values of wall and roof assemblies. bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
BUILDING PERFORMANCE   Baseline Building   vs.   Hampton Bays Middle School bbs Hampton Bays MS R = 19.65 Baseline Building R = 5 Wall Assembly R-values Baseline Building $ 420,647 Hampton Bays MS $ 311,143 Projected Annual Energy Costs Hampton Bays MS R = 33 Baseline Building R = 20 Roof Assembly R-values Hampton Bays MS U = 0.33 Baseline Building U = 0.60 Window Assembly U-values H A M P T O N  B A Y S  M I D D L E  S C H O O L
The product selection process has been focused upon using regional materials that preferably have some percentage of recycled content. Special attention has been given to the effects of product selection to indoor air quality.  Key IAQ performance criteria include low gas emissions as well as chemical and pollutant source control.  Product Selection bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
CONSTRUCTION OCCUPANCY LEED ‘SILVER’ BBS green
It was a part of our responsibility to monitor the construction phase of the Hampton Bays Middle School to be sure that goals set during the planning phases would be realized in actual construction. Construction Waste Management diverted 75% of waste material from landfills, sending it instead to recycling centers for re-use and/or re-manufacture. Intensive IAQ testing was conducted both during construction and before client occupancy. bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
Hampton Bays Middle School Construction Began: April 2006 Partial Occupancy: February 2008 Full Occupancy: September 2008 bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
H A M P T O N  B A Y S  M I D D L E  S C H O O L
LEED SILVER CERTIFICATION bbs H A M P T O N  B A Y S  M I D D L E  S C H O O L
H A M P T O N  B A Y S  M I D D L E  S C H O O L
“ Building it LEED was not the end… … It was just the beginning.” BBS green
H A M P T O N  B A Y S  M I D D L E  S C H O O L

Mais conteúdo relacionado

Mais procurados

Projects presentation1
Projects presentation1Projects presentation1
Projects presentation1Eamon Hannaway
 
Concrete Contractor in Albany NY
Concrete Contractor in Albany NYConcrete Contractor in Albany NY
Concrete Contractor in Albany NYCalvinarnold843
 
P:\Images\Developer Profile\Final Developer Slideshow\Dv Compressed
P:\Images\Developer Profile\Final Developer Slideshow\Dv CompressedP:\Images\Developer Profile\Final Developer Slideshow\Dv Compressed
P:\Images\Developer Profile\Final Developer Slideshow\Dv Compressedguest237a20
 
Item #12 ppt Judson Nature Trail Building
Item #12   ppt Judson Nature Trail BuildingItem #12   ppt Judson Nature Trail Building
Item #12 ppt Judson Nature Trail Buildingahcitycouncil
 
Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams
 
Tall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the TopTall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the TopRDH Building Science
 
Arl Project List
Arl Project ListArl Project List
Arl Project Listanthee13
 
Hencken & Gaines Portfolio of Building Projects in Maryland
Hencken & Gaines Portfolio of Building Projects in MarylandHencken & Gaines Portfolio of Building Projects in Maryland
Hencken & Gaines Portfolio of Building Projects in MarylandThomas Gaines
 

Mais procurados (10)

Projects presentation1
Projects presentation1Projects presentation1
Projects presentation1
 
Concrete Contractor in Albany NY
Concrete Contractor in Albany NYConcrete Contractor in Albany NY
Concrete Contractor in Albany NY
 
P:\Images\Developer Profile\Final Developer Slideshow\Dv Compressed
P:\Images\Developer Profile\Final Developer Slideshow\Dv CompressedP:\Images\Developer Profile\Final Developer Slideshow\Dv Compressed
P:\Images\Developer Profile\Final Developer Slideshow\Dv Compressed
 
Item #12 ppt Judson Nature Trail Building
Item #12   ppt Judson Nature Trail BuildingItem #12   ppt Judson Nature Trail Building
Item #12 ppt Judson Nature Trail Building
 
Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams Resume 2016
Ben Williams Resume 2016
 
Tall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the TopTall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the Top
 
Arl Project List
Arl Project ListArl Project List
Arl Project List
 
Building Checks slide show
Building Checks slide showBuilding Checks slide show
Building Checks slide show
 
Building Checks slide show
Building Checks slide showBuilding Checks slide show
Building Checks slide show
 
Hencken & Gaines Portfolio of Building Projects in Maryland
Hencken & Gaines Portfolio of Building Projects in MarylandHencken & Gaines Portfolio of Building Projects in Maryland
Hencken & Gaines Portfolio of Building Projects in Maryland
 

Semelhante a Creating Better Learning Environments - Part 3

Creating Better Learning Environments - Part 1
Creating Better Learning Environments - Part 1Creating Better Learning Environments - Part 1
Creating Better Learning Environments - Part 1Meg Thompson
 
54 S c i e n t i f i c A m e r i c a n E a r t h 3 . 0PE.docx
54 S c i e n t i f i c  A m e r i c a n  E a r t h 3 . 0PE.docx54 S c i e n t i f i c  A m e r i c a n  E a r t h 3 . 0PE.docx
54 S c i e n t i f i c A m e r i c a n E a r t h 3 . 0PE.docxalinainglis
 
Greening What's Already Here
Greening What's Already HereGreening What's Already Here
Greening What's Already Hereaiahouston
 
LmP House Final
LmP House FinalLmP House Final
LmP House FinalLaura Dawe
 
90 Ee Building Designtec
90 Ee Building Designtec90 Ee Building Designtec
90 Ee Building Designteccrownjade
 
presentation_indoorclimatecomfort (2)
presentation_indoorclimatecomfort (2)presentation_indoorclimatecomfort (2)
presentation_indoorclimatecomfort (2)Adam Haj-hamad
 
Leed & Historic Tax Credit Certification
Leed & Historic Tax Credit CertificationLeed & Historic Tax Credit Certification
Leed & Historic Tax Credit CertificationHeritage Ohio
 
Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...
Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...
Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...Sustainable Business Partnership
 
Innovation and Product/ Technology Implications of the Code for Sustainable H...
Innovation and Product/ Technology Implications of the Code for Sustainable H...Innovation and Product/ Technology Implications of the Code for Sustainable H...
Innovation and Product/ Technology Implications of the Code for Sustainable H...Sustainable Business Partnership
 
Environmental Programs Status Update 02 18 10
Environmental Programs Status Update 02 18 10Environmental Programs Status Update 02 18 10
Environmental Programs Status Update 02 18 10ckrout
 
Council house 2 sustainable building example
Council house 2 sustainable building exampleCouncil house 2 sustainable building example
Council house 2 sustainable building exampleUET Lahore
 
Presentation cased study communal centre
Presentation cased study communal centrePresentation cased study communal centre
Presentation cased study communal centreAffif Mazlan
 
Sustainable Housing
Sustainable HousingSustainable Housing
Sustainable Housingstariq48
 
Final Science Day
Final  Science  DayFinal  Science  Day
Final Science Daystariq48
 
High performance green building marketing brochure 3 20-08
High performance green building marketing brochure 3 20-08High performance green building marketing brochure 3 20-08
High performance green building marketing brochure 3 20-08crossbridgeinc
 
ULX Jan Feb 2010
ULX Jan Feb 2010ULX Jan Feb 2010
ULX Jan Feb 2010Virtual ULI
 
JordanBosseResume1
JordanBosseResume1JordanBosseResume1
JordanBosseResume1Jordan Bosse
 

Semelhante a Creating Better Learning Environments - Part 3 (20)

Creating Better Learning Environments - Part 1
Creating Better Learning Environments - Part 1Creating Better Learning Environments - Part 1
Creating Better Learning Environments - Part 1
 
54 S c i e n t i f i c A m e r i c a n E a r t h 3 . 0PE.docx
54 S c i e n t i f i c  A m e r i c a n  E a r t h 3 . 0PE.docx54 S c i e n t i f i c  A m e r i c a n  E a r t h 3 . 0PE.docx
54 S c i e n t i f i c A m e r i c a n E a r t h 3 . 0PE.docx
 
Greening What's Already Here
Greening What's Already HereGreening What's Already Here
Greening What's Already Here
 
Achieving Green Savings and Sustainability
Achieving Green Savings and SustainabilityAchieving Green Savings and Sustainability
Achieving Green Savings and Sustainability
 
LmP House Final
LmP House FinalLmP House Final
LmP House Final
 
90 Ee Building Designtec
90 Ee Building Designtec90 Ee Building Designtec
90 Ee Building Designtec
 
presentation_indoorclimatecomfort (2)
presentation_indoorclimatecomfort (2)presentation_indoorclimatecomfort (2)
presentation_indoorclimatecomfort (2)
 
Leed & Historic Tax Credit Certification
Leed & Historic Tax Credit CertificationLeed & Historic Tax Credit Certification
Leed & Historic Tax Credit Certification
 
Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...
Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...
Steve Charter, Green Gauge Trust - "Introduction to Sustainable Construction:...
 
Town Lake Center 5th Floor Renovation- LEED Profile
Town Lake Center 5th Floor Renovation- LEED Profile Town Lake Center 5th Floor Renovation- LEED Profile
Town Lake Center 5th Floor Renovation- LEED Profile
 
Innovation and Product/ Technology Implications of the Code for Sustainable H...
Innovation and Product/ Technology Implications of the Code for Sustainable H...Innovation and Product/ Technology Implications of the Code for Sustainable H...
Innovation and Product/ Technology Implications of the Code for Sustainable H...
 
Environmental Programs Status Update 02 18 10
Environmental Programs Status Update 02 18 10Environmental Programs Status Update 02 18 10
Environmental Programs Status Update 02 18 10
 
Council house 2 sustainable building example
Council house 2 sustainable building exampleCouncil house 2 sustainable building example
Council house 2 sustainable building example
 
Presentation cased study communal centre
Presentation cased study communal centrePresentation cased study communal centre
Presentation cased study communal centre
 
Sustainable Housing
Sustainable HousingSustainable Housing
Sustainable Housing
 
Final Science Day
Final  Science  DayFinal  Science  Day
Final Science Day
 
High performance green building marketing brochure 3 20-08
High performance green building marketing brochure 3 20-08High performance green building marketing brochure 3 20-08
High performance green building marketing brochure 3 20-08
 
ULX Jan Feb 2010
ULX Jan Feb 2010ULX Jan Feb 2010
ULX Jan Feb 2010
 
ULX Jan Feb 2010
ULX Jan Feb 2010ULX Jan Feb 2010
ULX Jan Feb 2010
 
JordanBosseResume1
JordanBosseResume1JordanBosseResume1
JordanBosseResume1
 

Mais de Meg Thompson

Mentoring & Coaching
Mentoring & CoachingMentoring & Coaching
Mentoring & CoachingMeg Thompson
 
Technical Compentencies
Technical CompentenciesTechnical Compentencies
Technical CompentenciesMeg Thompson
 
Introduction to School Energy Management
Introduction to School Energy ManagementIntroduction to School Energy Management
Introduction to School Energy ManagementMeg Thompson
 
School Emergency Preparedness
School Emergency PreparednessSchool Emergency Preparedness
School Emergency PreparednessMeg Thompson
 
School Fire Safety Inspections
School Fire Safety InspectionsSchool Fire Safety Inspections
School Fire Safety InspectionsMeg Thompson
 
Health & Safety 12.11
Health & Safety 12.11Health & Safety 12.11
Health & Safety 12.11Meg Thompson
 
Revitalizing Fatigued Employees
Revitalizing Fatigued EmployeesRevitalizing Fatigued Employees
Revitalizing Fatigued EmployeesMeg Thompson
 
EPA PCB Presentation
EPA PCB PresentationEPA PCB Presentation
EPA PCB PresentationMeg Thompson
 
5 High Liability Issues at k-12 Schools
5 High Liability Issues at k-12 Schools5 High Liability Issues at k-12 Schools
5 High Liability Issues at k-12 SchoolsMeg Thompson
 
Managing Change: Creating a Successful Work Plan
Managing Change: Creating a Successful Work PlanManaging Change: Creating a Successful Work Plan
Managing Change: Creating a Successful Work PlanMeg Thompson
 
Facilities Assessment Panel Presentation
Facilities Assessment Panel PresentationFacilities Assessment Panel Presentation
Facilities Assessment Panel PresentationMeg Thompson
 
The Dirty Details: Understanding the New Law & Guidance for Managing School F...
The Dirty Details: Understanding the New Law & Guidance for Managing School F...The Dirty Details: Understanding the New Law & Guidance for Managing School F...
The Dirty Details: Understanding the New Law & Guidance for Managing School F...Meg Thompson
 
Creative Solutions for Today's Educational Facilities' Needs - Kobet
Creative Solutions for Today's Educational Facilities' Needs - KobetCreative Solutions for Today's Educational Facilities' Needs - Kobet
Creative Solutions for Today's Educational Facilities' Needs - KobetMeg Thompson
 
Critical Importance of Well-Maintained Facilities - Thurnau
Critical Importance of Well-Maintained Facilities - ThurnauCritical Importance of Well-Maintained Facilities - Thurnau
Critical Importance of Well-Maintained Facilities - ThurnauMeg Thompson
 
Education 2011: How Should Your District Be Thinking About School Facilities ...
Education 2011: How Should Your District Be Thinking About School Facilities ...Education 2011: How Should Your District Be Thinking About School Facilities ...
Education 2011: How Should Your District Be Thinking About School Facilities ...Meg Thompson
 
Managing Upward: Strategies for Working with your Boss
Managing Upward: Strategies for Working with your BossManaging Upward: Strategies for Working with your Boss
Managing Upward: Strategies for Working with your BossMeg Thompson
 
Managing Difficult Personalities
Managing Difficult PersonalitiesManaging Difficult Personalities
Managing Difficult PersonalitiesMeg Thompson
 

Mais de Meg Thompson (20)

Mentoring & Coaching
Mentoring & CoachingMentoring & Coaching
Mentoring & Coaching
 
Technical Compentencies
Technical CompentenciesTechnical Compentencies
Technical Compentencies
 
Introduction to School Energy Management
Introduction to School Energy ManagementIntroduction to School Energy Management
Introduction to School Energy Management
 
School Emergency Preparedness
School Emergency PreparednessSchool Emergency Preparedness
School Emergency Preparedness
 
Budget & Finance
Budget & FinanceBudget & Finance
Budget & Finance
 
School Fire Safety Inspections
School Fire Safety InspectionsSchool Fire Safety Inspections
School Fire Safety Inspections
 
Health & Safety 12.11
Health & Safety 12.11Health & Safety 12.11
Health & Safety 12.11
 
Revitalizing Fatigued Employees
Revitalizing Fatigued EmployeesRevitalizing Fatigued Employees
Revitalizing Fatigued Employees
 
EPA PCB Presentation
EPA PCB PresentationEPA PCB Presentation
EPA PCB Presentation
 
5 High Liability Issues at k-12 Schools
5 High Liability Issues at k-12 Schools5 High Liability Issues at k-12 Schools
5 High Liability Issues at k-12 Schools
 
Managing Change: Creating a Successful Work Plan
Managing Change: Creating a Successful Work PlanManaging Change: Creating a Successful Work Plan
Managing Change: Creating a Successful Work Plan
 
Facilities Assessment Panel Presentation
Facilities Assessment Panel PresentationFacilities Assessment Panel Presentation
Facilities Assessment Panel Presentation
 
The Dirty Details: Understanding the New Law & Guidance for Managing School F...
The Dirty Details: Understanding the New Law & Guidance for Managing School F...The Dirty Details: Understanding the New Law & Guidance for Managing School F...
The Dirty Details: Understanding the New Law & Guidance for Managing School F...
 
Creative Solutions for Today's Educational Facilities' Needs - Kobet
Creative Solutions for Today's Educational Facilities' Needs - KobetCreative Solutions for Today's Educational Facilities' Needs - Kobet
Creative Solutions for Today's Educational Facilities' Needs - Kobet
 
Critical Importance of Well-Maintained Facilities - Thurnau
Critical Importance of Well-Maintained Facilities - ThurnauCritical Importance of Well-Maintained Facilities - Thurnau
Critical Importance of Well-Maintained Facilities - Thurnau
 
Education 2011: How Should Your District Be Thinking About School Facilities ...
Education 2011: How Should Your District Be Thinking About School Facilities ...Education 2011: How Should Your District Be Thinking About School Facilities ...
Education 2011: How Should Your District Be Thinking About School Facilities ...
 
Mentoring
MentoringMentoring
Mentoring
 
Budget & Finance
Budget & FinanceBudget & Finance
Budget & Finance
 
Managing Upward: Strategies for Working with your Boss
Managing Upward: Strategies for Working with your BossManaging Upward: Strategies for Working with your Boss
Managing Upward: Strategies for Working with your Boss
 
Managing Difficult Personalities
Managing Difficult PersonalitiesManaging Difficult Personalities
Managing Difficult Personalities
 

Creating Better Learning Environments - Part 3

  • 1. The Hampton Bays Union Free School received its charter in 1908. The new Middle School, located on Ponquogue Avenue, opened in April 2008 in celebration of the district’s Centennial. The Shinnecock (Ponquogue Point) Lighthouse located in Hampton Bays was built in 1858 and later demolished by the Coast Guard in 1948, but its iconography has informed the new building’s architectural identity. bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 2. The Hampton Bays Middle School has been designed and constructed to be a high performing sustainable building that has received LEED Silver Certification. It is responsive to the architectural identity of its community at large. It is also a fully functional (5-8) middle school embracing team teaching and cooperative learning. It is a constant source of inspiration for the students who will spend a portion of their formative years here. “ M A I N S T R E E T” C O R R I D O R “ M A I N S T R E E T” C O R R I D O R A C C E S S I N G A L L P O I N T S bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 4. We knew where we were heading with the design. We had done the research and put together a plan . Now, we needed the public to believe in what we were planning, and vote ‘ yes ’.
  • 5.  
  • 6. H A M P T O N B A Y S M I D D L E S C H O O L
  • 7.  
  • 8.  
  • 9. H A M P T O N B A Y S M I D D L E S C H O O L
  • 11. H A M P T O N B A Y S M I D D L E S C H O O L
  • 12. DESIGN DEVELOPMENT & CONSTRUCTION DOCUMENTS BBS green
  • 13. The performance of the exterior building envelope sets the standard for the performance of the entire project. Proper architectural detailing and design leads to the development of more efficient HVAC systems. Perimeter radiation heating was effectively removed from the project due to an improved exterior building envelope. More efficient HVAC systems consume less energy. Building Performance bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 17. Conventional construction detailing can lead to the development of an exterior building envelope that does not perform as well as it could. Gaps in insulation, air and moisture infiltration, and thermal bridging are key issues. By rethinking the way we detail a building during the development of construction documents we can achieve a high performance exterior building envelope with minimal budget impact. Building Envelope bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 18. Hampton Bays Middle School Locating the structural frame completely within the building envelope creates a thermal break between the inside and outside of the building. bbs
  • 19. Hampton Bays Middle School Thermal breaks at floor slabs prevent heat loss due to conduction. bbs
  • 20. Hampton Bays Middle School 3” thick insulation within the wall cavity is continuous from the top to the bottom. R-36 roof insulation has been used, (R-30 is the more typical standard requirement) bbs
  • 21. Hampton Bays Middle School Moisture is less likely to accumulate within a wall cavity when flashing is strategically located and proper ventilation of the wall cavity is provided. Preventing moisture infiltration is key in the prevention of mold growth and contributes to high levels of indoor air quality (IAQ). bbs
  • 22. Hampton Bays Middle School Combining all of these details creates a building envelope that will perform at a higher level than a more conventionally detailed building. bbs
  • 23. The Hampton Bays Middle School performs at a higher level than a “baseline building” as defined by (ASHRAE 90.1-1999) and N.Y.S. Code standards. Performance criteria are based upon the comparison of U-values of wall and roof assemblies. bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 24. BUILDING PERFORMANCE Baseline Building vs. Hampton Bays Middle School bbs Hampton Bays MS R = 19.65 Baseline Building R = 5 Wall Assembly R-values Baseline Building $ 420,647 Hampton Bays MS $ 311,143 Projected Annual Energy Costs Hampton Bays MS R = 33 Baseline Building R = 20 Roof Assembly R-values Hampton Bays MS U = 0.33 Baseline Building U = 0.60 Window Assembly U-values H A M P T O N B A Y S M I D D L E S C H O O L
  • 25. The product selection process has been focused upon using regional materials that preferably have some percentage of recycled content. Special attention has been given to the effects of product selection to indoor air quality. Key IAQ performance criteria include low gas emissions as well as chemical and pollutant source control. Product Selection bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 26. CONSTRUCTION OCCUPANCY LEED ‘SILVER’ BBS green
  • 27. It was a part of our responsibility to monitor the construction phase of the Hampton Bays Middle School to be sure that goals set during the planning phases would be realized in actual construction. Construction Waste Management diverted 75% of waste material from landfills, sending it instead to recycling centers for re-use and/or re-manufacture. Intensive IAQ testing was conducted both during construction and before client occupancy. bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 28. Hampton Bays Middle School Construction Began: April 2006 Partial Occupancy: February 2008 Full Occupancy: September 2008 bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 29. H A M P T O N B A Y S M I D D L E S C H O O L
  • 30. LEED SILVER CERTIFICATION bbs H A M P T O N B A Y S M I D D L E S C H O O L
  • 31. H A M P T O N B A Y S M I D D L E S C H O O L
  • 32. “ Building it LEED was not the end… … It was just the beginning.” BBS green
  • 33. H A M P T O N B A Y S M I D D L E S C H O O L