3. OUTLINE OF
PRESENTATION
Purpose of Presentation
Background
Program Areas (General)
Project Summary
Project Areas
Design Parameters for New WTPS
Project Scope
Responsibilities (General)
Bidding Instructions
Bid Evaluation
General Advice
End of Presentation
Questions, Concerns, Queries……!
4. Purpose of Pre-Bid Meeting
1. To provide background information regarding the contract
2. Opportunity for clarifications from bidders & Executing Agency
3. Dissemination of any important information regarding the project
5. Background
Water Supply and Sanitation Infrastructure Improvement
Program (WSSIIP)
Objective: The program aims to improve efficiency, quality and sustainability of the potable water services
and improve sanitation in GT and other area along the coast – Uitvlugt, Sheet Anchor & Diamond
Aging
infrastructure
assets
Poor water
quality (raw
water)
Poor access
to adequate
sanitation
Low Level of
Service + no
continuity of
supply
Rapid
development
in program
areas
Increase in
NRW-losses
6. Background Cont.
Water Supply and Sanitation Infrastructure Improvement
Program - Components
Reduce the level of NRW in program
areas
Improve access to sanitation in
program areas
Improve pressure, quality and
continuity of the water supply service in
program areas
Strengthen GWI performance in its
operational and management practice
8. Project Summary
Title: Procurement of Plant: Design, Supply and Installation Water
Treatment Facilities and Upgrade of Reticulation at Uitvlugt, Diamond
and Goed Banana Land
Procurement Method: International Competitive Bidding
Contract type: Turnkey (Design and Build)
Donor: Inter-American Development Bank & European Union
Objective: Improved water service in program areas
Expected Outcome: Improved water quality (treated water), continuity of
supply, increase LOS, better quality of life!
12. Design Parameters for New Water
Treatment Plants - Summary
Water Treatment
Plant
Serving Areas Capacity Source -
Boreholes
Population
Served
1. Uitvlugt Hague back, Cornelia Ida,
Anna Catherina, Leonora,
Stewartville, Uitvlugt,
Zeeburg, De William, Met
En Meerzerg, De Kinderen
10MLD Uitvlugt & Leonora 26,736
2. Diamond Arcadia, Mocha,
Herstelling, Providence,
Farm, Covent Garden,
Prospect, Diamond,
Kaneville
12MLD Diamond & Lamaha Canal 33,750
3. Sheet Anchor Sheet Anchor (Borlam or
No. 37 to Sheet Anchor),
Cumberland, Canfield,
RoseHall
8MLD Sheet Anchor &
Cumberland
15,124
13. Design Parameters for New WTP Cont.
Storage has been catered for 12 hrs. of treated water storage to be provided
in each service area.
Water quality baseline The WHO standard has been established as the
target for the treated water quality - (pH, turbidity, iron content).
Process Guarantee WHO Guidelines for Potable Water 100% of the time.
Production capacity Able to produce the required design capacity 100% of
the time.
14. Project Scope- General for New WTPs
Chemical building complete
Complete lime dosing system with necessary accessories
Multiple Tray Aerator
Circular clarifier/Solids Contact
Rapid sand filters
Baffled storage reservoir(s)
Sludge holding ponds or sludge thickeners
On site process piping
Onsite chlorine generator
Emergency generator, electrical supply and systems and control systems as needed to operate the plant
Installation of transmission mains to and from the WTPs
All works as detailed in Employer’s Requirements, Specifications, Bills of Quantities and Drawings; and
as approved by the Employer’s Representative.
Important to Note:
Duration of contract = 36
months
24 months execution
12 months defects liability
period
16. Responsibilities - General
The Contractor is required to:
mobilize the specified resources required (construction materials facilities, plant, water,
fuel…etc. ) to the site and deploy sufficient manpower for works execution.
manage all technical issues in relation with the works.
undertake overall design, planning and execution of the construction works.
The Employer will have the role of:
overall supervision of the construction works.
overseeing quality of works.
monitoring and controlling work targets/progress as approved on contractor’s program
of works.
approving the completion of scheduled tasks or work packages.
17. Bidding Instructions
The number of lots comprising this bid is:
Lot 1 – Design, Construction and Installation of Water Treatment Plant
and Mains at Uitvlugt, West Coast Demerara, Region No. 3 and Design,
Construction and Installation of Water Treatment Plant at Sheet Anchor,
East Bank Berbice, Region No. 6
Lot 2 – Design, Construction and Installation of Water Treatment Plant at
Diamond, East Bank Demerara, Region No. 4
18. Bidding Instructions Con’t
Deadline for Bid submission: 6th September, 2016 (time 09:00hrs)
Request for clarification: 2 weeks prior to closing of bid
Bid Validity: 120 days
Bid Security: Lot 1 – GY$37,702,000.00 & Lot 2 – GY$23,131,000.00
Bid Closing: 6th September, 2016
Submittal: Three copies of Bid plus (1) soft copy of the bid document (Cd)
(pdf format)
Note:
Further details can be found in the ITB and Bid Data Sheet!
19. Bid Evaluation
Technical
Evaluation
Economic
Evaluation
1. Energy efficiency of design
2. Operational costs
3. Reliability of equipment
4. Ability to meet treated water quality
& quantity
1. Time for completion of works
2. Operational and maintenance
3. Total Life Cycle Cost Assessment
4. Functional guarantee of the
facilities
21. General Advice!
Bidders need to understand fully the strategy and the scope of the works
involved in this project and submit reasonable offer.
Contract will be administered in accordance with the conditions of contract.
Make sure that all evaluation criteria are adequately addressed as outlined in
the bidding document.
No late submission of bid will be accepted.
If you have any queries or concerns do not hesitate to make contact with
GWI.
Honesty is the best policy – no fabrication of information in your submittal!