Canadian Coast Guard Fleet Assets
117 Vessels
•42 Large Vessels
•25 Small Vessels
•5 Air Cushion
Vehicles
•45 Search and
Rescue (SAR)
Vessels
•22 Helicopters
5
Today’s Fleet / Tomorrow’s
Today’s Fleet 52 Configurations The Future Fleet 15 Configurations
30 + Classes 15 Classes
6
Coast Guard Fleet Renewal
• Since 2005, there have been upwards of
$7 billion of investment announcements in
the renewal of the Coast Guard’s Fleet.
• The first comprehensive long-term Fleet
Renewal Plan (FRP) was released in 2006.
• The last version of the Plan was completed
in 2012.
• The Plan is on a five-year cycle, and Coast
Guard is currently working to update it.
Period $ Projects Funded
2005 - 2008 $1.4B
– 9 Mid-Shore Patrol Vessels
– 3 Offshore Fisheries Science Vessels
– 1 Offshore Oceanographic Science Vessel
– 2 Air Cushion Vehicles
– 1 Polar Icebreaker
2009 $175M
– Major repair work on large vessels, and new
small vessels
2012 $5.2B
– 5 Medium Endurance Multi-Tasked Vessels
– 5 Offshore Patrol Vessels
– Small vessels, Search and Rescue (SAR)
Lifeboats and helicopters
– Repairing and refitting existing vessels
2014 $173M
– Repair of vessels, additional SAR Lifeboats
and procurement of small craft
Fleet Renewal Funding
7
Large Vessel Construction
8
CCG Small Vessel Outlook*
*Notional Schedule – Subject to change according to ship conditions and mission requirements
Near-Shore
Fishery
Research
Vessels (1)
Specialty
Vessel (1)
Mid-Shore
Science
Vessels (2)
Special Nav-
Aids Vessels
(2)
2017 2018 2019 2020 2021 2022 2023 2024
Definition/ DesignDefinition/ Design/ Build
Definition/DesignDefinition/Design / Build
Definition/ DesignDefinition /Design/Build
Definition / DesignDefinition /Design/Build
1
1
1
1
2
2
9
Marine Engineering - Small Craft Acquisition
10
Vessel Life Extension & Mid Life Modernization
11
Vessel Life Extensions for 2017/18
Total 2017/18 Forecast is 58M: includes equipment purchases, also
includes the following shipyard contracts:
•NGCC Pierre Radisson VLE (Alongside portion): April
2017 - August 2017
– Propulsion Control System Installation (awarded Februay2016)
– Alongside VLE (awarded March 2017)
•NGCC Des Grosseilliers VLE: November 2017 - September
2018
– Propulsion Control System Installation (awarded Februay2016)
– Regulatory and VLE work packages: Drydock and Alongside Contracts
• CCGS John P Tully VLE: October 2017 to April 2018
– Steel renewals
– Regulatory Regional work package
– Systems & Equipment VLE work package
12
Vessel Life Extensions for 2017-2018
• CCGS Ann Harvey Main Engine Replacement (during
Regional drydocking contract) dates TBD September?
– Remove and install main engines
– Hull Repair & Regulatory Docking Work Package, Regional & VLE items
• CCGS Ann Harvey Propulsion Control Installation
(Alongside) dates TBD
– Remove and install new PCS
– VLE and Regional Work Packages Ongoing
• CCGS Sir William Alexander Propulsion Control
Installation (Alongside) dates TBD…start work period
March / April 2018 ?
– Remove and install new PCS
– Regional Work Packages Ongoing
13
• Refits on CCG ships will continue to follow our 10
Year Refit Calendar.
• The new location for this information will be:
http://www.ccg-gcc.gc.ca/fleet-hub
Vessel Maintenance & Refit
14
Fleet Renewal - Work Underway
• The Fleet Renewal Plan will ensure that the Coast Guard meets the
needs of mariners today, and into the future with a fleet that:
– Addresses the Icebreaking challenge;
– Meets public expectations for environmental response;
– Delivers the required capacity in the North; and
– Ensures operational flexibility and adaptability.
15
Quest
Questions ?

Mais conteúdo relacionado

Mais procurados

Chris_Furtado_Resume
Chris_Furtado_ResumeChris_Furtado_Resume
Chris_Furtado_ResumeChris Furtado
 
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016Brad Keithley
 
Remote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectRemote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectAchmad Agung P
 
Structural rules bulk and tanker
Structural rules bulk and tankerStructural rules bulk and tanker
Structural rules bulk and tankerGeorge Teriakidis
 
Alaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood MackenzieAlaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood Mackenzieallalaskagasline
 
Western Canada Crude by Rail 2014-09-03
Western Canada Crude by Rail 2014-09-03Western Canada Crude by Rail 2014-09-03
Western Canada Crude by Rail 2014-09-03PLG Consulting
 
Regional Fuel Operations
Regional Fuel OperationsRegional Fuel Operations
Regional Fuel Operationsroddyt001
 
The Capacity of the Navy’s Shipyards to Maintain Its Submarines
The Capacity of the Navy’s Shipyards to Maintain Its SubmarinesThe Capacity of the Navy’s Shipyards to Maintain Its Submarines
The Capacity of the Navy’s Shipyards to Maintain Its SubmarinesCongressional Budget Office
 
Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...oilandgas
 
From Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for RailFrom Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for RailPLG Consulting
 
Port Congestion John Heylan
Port Congestion John HeylanPort Congestion John Heylan
Port Congestion John HeylanCanada Cruise
 
Norway_Maritime business seminar on 24.11.2016
Norway_Maritime business seminar on 24.11.2016Norway_Maritime business seminar on 24.11.2016
Norway_Maritime business seminar on 24.11.2016Business Finland
 
LNG fuelled ships recent development 2014 02
LNG fuelled ships recent development 2014 02LNG fuelled ships recent development 2014 02
LNG fuelled ships recent development 2014 02George Teriakidis
 
Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...
Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...
Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...Innovation Norway
 
Seagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking GraceSeagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking GraceJohn Hatley PE
 
North American Oil & Gas and Petrochemical Supply Chain: Latest Impact to Rail
North American Oil & Gas and Petrochemical Supply Chain: Latest Impact to RailNorth American Oil & Gas and Petrochemical Supply Chain: Latest Impact to Rail
North American Oil & Gas and Petrochemical Supply Chain: Latest Impact to RailPLG Consulting
 

Mais procurados (19)

Chris_Furtado_Resume
Chris_Furtado_ResumeChris_Furtado_Resume
Chris_Furtado_Resume
 
201507 caisson repair project final
201507 caisson repair project final201507 caisson repair project final
201507 caisson repair project final
 
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016
 
Remote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectRemote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar Project
 
CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...
CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...
CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...
 
Structural rules bulk and tanker
Structural rules bulk and tankerStructural rules bulk and tanker
Structural rules bulk and tanker
 
Alaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood MackenzieAlaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood Mackenzie
 
Western Canada Crude by Rail 2014-09-03
Western Canada Crude by Rail 2014-09-03Western Canada Crude by Rail 2014-09-03
Western Canada Crude by Rail 2014-09-03
 
Tanker Update 01 2015
Tanker Update 01 2015Tanker Update 01 2015
Tanker Update 01 2015
 
Regional Fuel Operations
Regional Fuel OperationsRegional Fuel Operations
Regional Fuel Operations
 
The Capacity of the Navy’s Shipyards to Maintain Its Submarines
The Capacity of the Navy’s Shipyards to Maintain Its SubmarinesThe Capacity of the Navy’s Shipyards to Maintain Its Submarines
The Capacity of the Navy’s Shipyards to Maintain Its Submarines
 
Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...
 
From Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for RailFrom Upstream to Downstream: Opportunities and Challenges for Rail
From Upstream to Downstream: Opportunities and Challenges for Rail
 
Port Congestion John Heylan
Port Congestion John HeylanPort Congestion John Heylan
Port Congestion John Heylan
 
Norway_Maritime business seminar on 24.11.2016
Norway_Maritime business seminar on 24.11.2016Norway_Maritime business seminar on 24.11.2016
Norway_Maritime business seminar on 24.11.2016
 
LNG fuelled ships recent development 2014 02
LNG fuelled ships recent development 2014 02LNG fuelled ships recent development 2014 02
LNG fuelled ships recent development 2014 02
 
Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...
Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...
Gassco - Future Gas Export from the Norwegian Continental Shelf - Thor Otto L...
 
Seagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking GraceSeagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking Grace
 
North American Oil & Gas and Petrochemical Supply Chain: Latest Impact to Rail
North American Oil & Gas and Petrochemical Supply Chain: Latest Impact to RailNorth American Oil & Gas and Petrochemical Supply Chain: Latest Impact to Rail
North American Oil & Gas and Petrochemical Supply Chain: Latest Impact to Rail
 

Semelhante a Canadian Coast Guard: Mari-Tech 2017 Presentation

Department of National Defence: Mari-Tech 2017 Presentation
Department of National Defence: Mari-Tech 2017 PresentationDepartment of National Defence: Mari-Tech 2017 Presentation
Department of National Defence: Mari-Tech 2017 PresentationRebecca Barton
 
Teekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings PresentationTeekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings PresentationAltera Infrastructure
 
9.GSL_AVRAVIPRAKASH.pptx
9.GSL_AVRAVIPRAKASH.pptx9.GSL_AVRAVIPRAKASH.pptx
9.GSL_AVRAVIPRAKASH.pptxDEBAYANGOSWAMI3
 
Teekay Offshore Partners Q1-2017 Earnings Presentation
Teekay Offshore Partners Q1-2017 Earnings PresentationTeekay Offshore Partners Q1-2017 Earnings Presentation
Teekay Offshore Partners Q1-2017 Earnings PresentationAltera Infrastructure
 
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...Global CCS Institute
 
Teekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationTeekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationTeekay LNG Partners L.P.
 
Teekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationTeekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationAltera Infrastructure
 
Inteligencia Windfarms.pptx
Inteligencia Windfarms.pptxInteligencia Windfarms.pptx
Inteligencia Windfarms.pptxLeyneth1
 
United States Coast Guard icebreaker program_seminar 2018
United States Coast Guard icebreaker program_seminar 2018United States Coast Guard icebreaker program_seminar 2018
United States Coast Guard icebreaker program_seminar 2018Business Finland
 
KYC Harbour Redevelopment - Town Hall No 1 Presentation
KYC	Harbour Redevelopment - Town Hall No 1 PresentationKYC	Harbour Redevelopment - Town Hall No 1 Presentation
KYC Harbour Redevelopment - Town Hall No 1 Presentationkingstonyc
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyThorne & Derrick International
 
2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major ProjectsEnbridge Inc.
 
Teekay Offshore Partners Q2-2017 Earnings Presentation
Teekay Offshore Partners Q2-2017 Earnings Presentation Teekay Offshore Partners Q2-2017 Earnings Presentation
Teekay Offshore Partners Q2-2017 Earnings Presentation Altera Infrastructure
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16Iain Cameron
 

Semelhante a Canadian Coast Guard: Mari-Tech 2017 Presentation (20)

Department of National Defence: Mari-Tech 2017 Presentation
Department of National Defence: Mari-Tech 2017 PresentationDepartment of National Defence: Mari-Tech 2017 Presentation
Department of National Defence: Mari-Tech 2017 Presentation
 
Teekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings PresentationTeekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings Presentation
 
9.GSL_AVRAVIPRAKASH.pptx
9.GSL_AVRAVIPRAKASH.pptx9.GSL_AVRAVIPRAKASH.pptx
9.GSL_AVRAVIPRAKASH.pptx
 
Teekay Offshore Partners Q1-2017 Earnings Presentation
Teekay Offshore Partners Q1-2017 Earnings PresentationTeekay Offshore Partners Q1-2017 Earnings Presentation
Teekay Offshore Partners Q1-2017 Earnings Presentation
 
Jan 10 2012 the status of shipbuilding
Jan 10 2012 the status of shipbuildingJan 10 2012 the status of shipbuilding
Jan 10 2012 the status of shipbuilding
 
Premier oil13a pres
Premier oil13a presPremier oil13a pres
Premier oil13a pres
 
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
Callide Oxyfuel Project - Jim Craigen - - Global CCS Institute – Nov 2011 Reg...
 
Master Plan
Master PlanMaster Plan
Master Plan
 
Teekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationTeekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings Presentation
 
Teekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationTeekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings Presentation
 
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
 
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
 
Inteligencia Windfarms.pptx
Inteligencia Windfarms.pptxInteligencia Windfarms.pptx
Inteligencia Windfarms.pptx
 
United States Coast Guard icebreaker program_seminar 2018
United States Coast Guard icebreaker program_seminar 2018United States Coast Guard icebreaker program_seminar 2018
United States Coast Guard icebreaker program_seminar 2018
 
KYC Harbour Redevelopment - Town Hall No 1 Presentation
KYC	Harbour Redevelopment - Town Hall No 1 PresentationKYC	Harbour Redevelopment - Town Hall No 1 Presentation
KYC Harbour Redevelopment - Town Hall No 1 Presentation
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects
 
Teekay Offshore Partners Q2-2017 Earnings Presentation
Teekay Offshore Partners Q2-2017 Earnings Presentation Teekay Offshore Partners Q2-2017 Earnings Presentation
Teekay Offshore Partners Q2-2017 Earnings Presentation
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16
 
Project Marketing Summary
Project Marketing SummaryProject Marketing Summary
Project Marketing Summary
 

Último

2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31JSchaus & Associates
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfSERUDS INDIA
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCNAP Global Network
 
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfPeace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfNAP Global Network
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processNAP Global Network
 
Lorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final PresentationLorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final PresentationCuyahoga County Planning Commission
 
Honasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfHonasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfSocial Samosa
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Menggugurkan Kandungan 087776558899
 
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...kumargunjan9515
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgergMadhuKothuru
 
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...HyderabadDolls
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehousesubs7
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberSareena Khatun
 
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In MumbaiVasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In MumbaiPriya Reddy
 
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...kumargunjan9515
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
 

Último (20)

2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfPeace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
Lorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final PresentationLorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final Presentation
 
Honasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfHonasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdf
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
 
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
 
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In MumbaiVasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
 

Canadian Coast Guard: Mari-Tech 2017 Presentation

  • 1. Canadian Coast Guard Update on CCG Procurement April 19th , 2017
  • 3. 3 Evolving Operational Landscape The Coast Guard is trusted and relied upon to deliver a wide variety of services to Canadians:
  • 4. 4 Canadian Coast Guard Fleet Assets 117 Vessels •42 Large Vessels •25 Small Vessels •5 Air Cushion Vehicles •45 Search and Rescue (SAR) Vessels •22 Helicopters
  • 5. 5 Today’s Fleet / Tomorrow’s Today’s Fleet 52 Configurations The Future Fleet 15 Configurations 30 + Classes 15 Classes
  • 6. 6 Coast Guard Fleet Renewal • Since 2005, there have been upwards of $7 billion of investment announcements in the renewal of the Coast Guard’s Fleet. • The first comprehensive long-term Fleet Renewal Plan (FRP) was released in 2006. • The last version of the Plan was completed in 2012. • The Plan is on a five-year cycle, and Coast Guard is currently working to update it. Period $ Projects Funded 2005 - 2008 $1.4B – 9 Mid-Shore Patrol Vessels – 3 Offshore Fisheries Science Vessels – 1 Offshore Oceanographic Science Vessel – 2 Air Cushion Vehicles – 1 Polar Icebreaker 2009 $175M – Major repair work on large vessels, and new small vessels 2012 $5.2B – 5 Medium Endurance Multi-Tasked Vessels – 5 Offshore Patrol Vessels – Small vessels, Search and Rescue (SAR) Lifeboats and helicopters – Repairing and refitting existing vessels 2014 $173M – Repair of vessels, additional SAR Lifeboats and procurement of small craft Fleet Renewal Funding
  • 8. 8 CCG Small Vessel Outlook* *Notional Schedule – Subject to change according to ship conditions and mission requirements Near-Shore Fishery Research Vessels (1) Specialty Vessel (1) Mid-Shore Science Vessels (2) Special Nav- Aids Vessels (2) 2017 2018 2019 2020 2021 2022 2023 2024 Definition/ DesignDefinition/ Design/ Build Definition/DesignDefinition/Design / Build Definition/ DesignDefinition /Design/Build Definition / DesignDefinition /Design/Build 1 1 1 1 2 2
  • 9. 9 Marine Engineering - Small Craft Acquisition
  • 10. 10 Vessel Life Extension & Mid Life Modernization
  • 11. 11 Vessel Life Extensions for 2017/18 Total 2017/18 Forecast is 58M: includes equipment purchases, also includes the following shipyard contracts: •NGCC Pierre Radisson VLE (Alongside portion): April 2017 - August 2017 – Propulsion Control System Installation (awarded Februay2016) – Alongside VLE (awarded March 2017) •NGCC Des Grosseilliers VLE: November 2017 - September 2018 – Propulsion Control System Installation (awarded Februay2016) – Regulatory and VLE work packages: Drydock and Alongside Contracts • CCGS John P Tully VLE: October 2017 to April 2018 – Steel renewals – Regulatory Regional work package – Systems & Equipment VLE work package
  • 12. 12 Vessel Life Extensions for 2017-2018 • CCGS Ann Harvey Main Engine Replacement (during Regional drydocking contract) dates TBD September? – Remove and install main engines – Hull Repair & Regulatory Docking Work Package, Regional & VLE items • CCGS Ann Harvey Propulsion Control Installation (Alongside) dates TBD – Remove and install new PCS – VLE and Regional Work Packages Ongoing • CCGS Sir William Alexander Propulsion Control Installation (Alongside) dates TBD…start work period March / April 2018 ? – Remove and install new PCS – Regional Work Packages Ongoing
  • 13. 13 • Refits on CCG ships will continue to follow our 10 Year Refit Calendar. • The new location for this information will be: http://www.ccg-gcc.gc.ca/fleet-hub Vessel Maintenance & Refit
  • 14. 14 Fleet Renewal - Work Underway • The Fleet Renewal Plan will ensure that the Coast Guard meets the needs of mariners today, and into the future with a fleet that: – Addresses the Icebreaking challenge; – Meets public expectations for environmental response; – Delivers the required capacity in the North; and – Ensures operational flexibility and adaptability.