CONSTRUCTION TECHNOLOGY
& MANAGEMENT
BT CE - 307
Dr. Abhishek Jindal
Construction Project Planning
Construction Project Planning
 Stages of project planning
 Pre-tender planning
 Pre-construction planning
 Detailed construction planning
 Role of client and contractor
 Level of detail
 Process of development of plans
and schedules
 Work-breakdown structure
 Activity lists
 Assessment of work content
 Concept of productivities
 Estimating durations
 Sequence of activities
 Activity utility data
 Techniques of planning - Bar
charts, Gantt charts
Stages of Project Planning
• Bringing the idea you have for your project to life can be
a long process.
• Project planning breaks down the complex moving parts
of construction projects into a realistic and
actionable building plan.
• Construction project planning is the act of creating a
development plan for a construction project.
01 02 03 04
Project
Conception
and
Initiation
Project
Definition
/Planning
Project
Launch/
Execution
Project
Performance
/ Control
Stages of Project Planning
05
Project
Close
Project Life Cycle
Objectives
• Methods to reduce or eliminate risk of inaccurate opinions influencing
decisions that affect the pricing of the estimate.
• Fully use company’s resources and experience in preparation of the
estimate.
• Co-ordinate with all company departments.
• Analysis to improve on competitiveness of tenders based on past track
records.
Pre-tender Project Planning
Feasibility Assessment of Notices and
Invitations
Tender Appreciation
Pricing of Bill of Quantities Preliminary Contract Plan
Tender Finalization
Anticipation of Award / Post-tender
Administration
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5
Pre- tender Project Planning
Pre- construction Planning
• Pre-construction planning is a preliminary form of strategizing that’s done
before a job starts.
• The goal is to build or understand the full scope of a project and its
requirements.
Pre- construction Planning
•Project scope: The scope of work can be as detailed as necessary and
outlines what the construction crew will be doing, what the outcome is,
how long it will take and how they will get there.
•Budget: An initial budget limit must be set to determine the monetary
confines of a project. An appropriate plan will also include details about
how it was chosen, what it reflects and what comparable costs may be.
•Schedule: A schedule is always necessary to determine the progress of
a project. How long will it take to complete, will it stay on time and if not,
what kind of delay might there be?
Activity 1 Activity 2 Activity 3 Activity 4
Resources: Materials,
Manpower, Cost
Time allotted for
completion
Resources: Materials,
Manpower, Cost
Time allotted for
completion
Time allotted for
completion
Resources: Materials,
Manpower, Cost
Sequence of Activities - Hierarchy of Work as per planning
Detailed Construction Planning
Role of Client & Contractor
The client is the person for whom the project is carried out.
• Being responsible for the execution of the project from the initial idea to
implementation
• Choosing the players involved in all stages from design through construction to
long term management
• Ensuring that the needs of building users / customers are met
• Ensuring that the relevant permissions are secured (planning etc) in partnership
with the professionals appointed to the project
• May also be financier and eventual owner
Role of Client & Contractor
A contractor is an organisation (or sometimes a person), hired by the
client to carry out the work that is required for the completion of a project.
• Building permits application
• Property security
• Providing (temporary) facilities on site
• Taking care of generated waste
• On-site personnel management
• Site surveying
• Site engineering
• Schedule monitoring
Level of Detail
• LOD (Level of Detail) is the term used to describe how much
information a drawing or model contains.
• It is how you choose to show the construction details and
materials of a project.
• The project members could rely on LOD used in a model to aid in
information about design and documentation.
Process of development of plans and schedules
• Construction planning is a fundamental and challenging activity in the
management and execution of construction projects.
• It involves
 the choice of technology,
 the definition of work tasks,
 the estimation of the required resources
 durations for individual tasks, and
 the identification of any interactions among the different work tasks.
Process of development of plans and schedules
• A good construction plan is the basis for developing the budget and the schedule
for work.
• Developing the construction plan is a critical task in the management of
construction, even if the plan is not written or otherwise formally recorded.
• In addition to these technical aspects of construction planning, it may also be
necessary to make organizational decisions about the relationships between
project participants and even which organizations to include in a project.
• For example, the extent to which sub-contractors will be used on a project is
often determined during construction planning.
Work break-down structure
• Method that breaks a project down into a hierarchy of deliverables, tasks,
and subtasks.
• It gives a way of organizing and understanding your project scope in
smaller, manageable components.
• The WBS levels may be broadly categorized into five major levels.
Level 1: Program level
Level 2: Project level
Level 3: Task level
Level 4: Sub-Task Level
Level 5: Work Package level
Work break-down structure
• Upper three levels of the WBS are normally specified by the client.
• Lower levels are generated by the Contractor for in-house control.
Work break-down structure
Activity Lists
• Listing down different activities in a project / part / section of a project.
• Sequence / order / chronology of activities.
• Inter-dependence of activities.
Assessment of work content
• Assessing the quantum of work.
• Using work breakdown technique to break the project into considerate sub-parts.
• Making a chronological network of different activities under each part / sub-part.
Concept of productivities
Estimating durations
Sequence of Activities
Activity Utility Data
Techniques of planning - Bar charts, Gantt charts
SCHEDULING - Planning
• Process of listing of tasks, activities, milestones with a planned start and
finish date.
• Proper scheduling would ensure the completion of the project on time
and within budget.
• It outlines the pace of the work.
• Also, how the tasks are executed.
• Scheduling defines method and sequence in which materials are delivered.
• Finally, it permits adjustments to accommodate changes and
unanticipated events.
Techniques of planning - Bar charts, Gantt charts
• A Gantt chart, commonly used in project management, is one of the most
popular and useful ways of showing activities (tasks) displayed against time.
• On the left of the chart is a list of the activities and along the top is a suitable
time scale.
• Each activity is represented by a bar; the position and length of the bar
reflects the start date, duration and end date of the activity.
Techniques of planning - Bar charts, Gantt charts
Techniques of planning - Bar charts, Gantt charts
Benefits
• Clarity: Gantt chart has ability to show and clarify multiple tasks and timelines.
• Communication: It is a visual method to help project team members understand task
progress.
• Motivation: Gantt charts offer project teams the ability to focus work at the front of, or
at the tail end of a task timeline.
• Co-ordination: Project managers use these charts to break down projects into
manageable sets of tasks.
• Creativity: The use of Gantt charts often encourages new partnerships that might not
have evolved under traditional task assignment systems.
Techniques of planning - Bar charts, Gantt charts
Benefits
• Time Management: Time scheduling is considered as one of the major benefits of Gantt
charts
• Flexibility: It offers a view of project which can help team members adjust changes.
• Manageability: By using Gantt charts, project managers can make more focused,
effective decisions about resources and timetables.
• Efficiency: Visualizing resource usage during projects allows managers to make better use
of people, places, and things.
• Accountability: Using Gantt charts during critical projects allows both project managers
and participants to track team progress.
Techniques of planning - Bar charts, Gantt charts
Disadvantages
• Require more efforts for creating and managing the chart
• Updating a chart is very time consuming
• All tasks are not visible in a single view of a gantt
• Need to scroll and click additional buttons to view remaining items
• Stacks represents only the time and not the hours of the work
• Not easy to realign the tasks from on section to another
• Not easy to calculate the aggregates
Techniques of planning - Bar charts, Gantt charts
Development of a Bar Chart - Stages
• Breakdown – project into various activities each representing a manageable
unit.
• Decide – method for execution of project as well as each activity and their
sequence.
• Assign – duration of time for completion of each activity.
• Represent – above information in bar chart indicating relative position of
each activity.
Techniques of planning - Bar charts, Gantt charts
Techniques of planning - Bar charts, Gantt charts
Techniques of planning - Bar charts, Gantt charts
Techniques of planning - Bar charts, Gantt charts
Techniques of planning - Bar charts, Gantt charts
Limitations of Bar Charts
• Lack of Degree of details – only major activities, becomes
clumsy
Techniques of planning - Bar charts, Gantt charts
Limitations of Bar Charts
• Review of Project Progress – does not show progress of
project. Modifications could be done by hatching.
Techniques of planning - Bar charts, Gantt charts
Limitations of Bar Charts
• Activity Inter-relationship – not depicted
• Example – Pipeline project
Techniques of planning - Bar charts, Gantt charts
Limitations of Bar Charts
• Time Uncertainties – not consider uncertainties in time for
projects like research and development etc.
• No re-scheduling flexibility offered by Bar charts.
• Bar charts are suitable for smaller construction projects where time
estimations could be made with fair degree of certainty.
Techniques of planning - Bar charts, Gantt charts
END

Mais conteúdo relacionado

Mais procurados

Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?maria_singh
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costingJanak Mehta
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
Job layout per
Job layout perJob layout per
Job layout perraj balar
 
Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...A Makwana
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 

Mais procurados (20)

Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Job layout per
Job layout perJob layout per
Job layout per
 
Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Contracts
ContractsContracts
Contracts
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 

Semelhante a CTM - 02 - Construction Project Planning.pptx

7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptxgezaegebre1
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptxJanak82
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
Introduction to Project Management Assessment Notes
Introduction to Project Management Assessment NotesIntroduction to Project Management Assessment Notes
Introduction to Project Management Assessment NotesShaun Wilson
 
Construction planning.ppt
Construction planning.pptConstruction planning.ppt
Construction planning.pptVinayakNaik80
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdfssuserc0e4e0
 

Semelhante a CTM - 02 - Construction Project Planning.pptx (20)

Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
Project Management
Project ManagementProject Management
Project Management
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
Project management.pptx
Project management.pptxProject management.pptx
Project management.pptx
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
Introduction to Project Management Assessment Notes
Introduction to Project Management Assessment NotesIntroduction to Project Management Assessment Notes
Introduction to Project Management Assessment Notes
 
Construction planning.ppt
Construction planning.pptConstruction planning.ppt
Construction planning.ppt
 
system analysis and design Class 3
system analysis and design Class 3system analysis and design Class 3
system analysis and design Class 3
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Project Planning | Accounting
Project Planning | AccountingProject Planning | Accounting
Project Planning | Accounting
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 

Último

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 

Último (20)

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 

CTM - 02 - Construction Project Planning.pptx

  • 1. CONSTRUCTION TECHNOLOGY & MANAGEMENT BT CE - 307 Dr. Abhishek Jindal Construction Project Planning
  • 2. Construction Project Planning  Stages of project planning  Pre-tender planning  Pre-construction planning  Detailed construction planning  Role of client and contractor  Level of detail  Process of development of plans and schedules  Work-breakdown structure  Activity lists  Assessment of work content  Concept of productivities  Estimating durations  Sequence of activities  Activity utility data  Techniques of planning - Bar charts, Gantt charts
  • 3. Stages of Project Planning • Bringing the idea you have for your project to life can be a long process. • Project planning breaks down the complex moving parts of construction projects into a realistic and actionable building plan. • Construction project planning is the act of creating a development plan for a construction project.
  • 4. 01 02 03 04 Project Conception and Initiation Project Definition /Planning Project Launch/ Execution Project Performance / Control Stages of Project Planning 05 Project Close Project Life Cycle
  • 5. Objectives • Methods to reduce or eliminate risk of inaccurate opinions influencing decisions that affect the pricing of the estimate. • Fully use company’s resources and experience in preparation of the estimate. • Co-ordinate with all company departments. • Analysis to improve on competitiveness of tenders based on past track records. Pre-tender Project Planning
  • 6. Feasibility Assessment of Notices and Invitations Tender Appreciation Pricing of Bill of Quantities Preliminary Contract Plan Tender Finalization Anticipation of Award / Post-tender Administration Stage 1 Stage 2 Stage 3 Stage 4 Stage 5 Pre- tender Project Planning
  • 7. Pre- construction Planning • Pre-construction planning is a preliminary form of strategizing that’s done before a job starts. • The goal is to build or understand the full scope of a project and its requirements.
  • 8. Pre- construction Planning •Project scope: The scope of work can be as detailed as necessary and outlines what the construction crew will be doing, what the outcome is, how long it will take and how they will get there. •Budget: An initial budget limit must be set to determine the monetary confines of a project. An appropriate plan will also include details about how it was chosen, what it reflects and what comparable costs may be. •Schedule: A schedule is always necessary to determine the progress of a project. How long will it take to complete, will it stay on time and if not, what kind of delay might there be?
  • 9. Activity 1 Activity 2 Activity 3 Activity 4 Resources: Materials, Manpower, Cost Time allotted for completion Resources: Materials, Manpower, Cost Time allotted for completion Time allotted for completion Resources: Materials, Manpower, Cost Sequence of Activities - Hierarchy of Work as per planning Detailed Construction Planning
  • 10. Role of Client & Contractor The client is the person for whom the project is carried out. • Being responsible for the execution of the project from the initial idea to implementation • Choosing the players involved in all stages from design through construction to long term management • Ensuring that the needs of building users / customers are met • Ensuring that the relevant permissions are secured (planning etc) in partnership with the professionals appointed to the project • May also be financier and eventual owner
  • 11. Role of Client & Contractor A contractor is an organisation (or sometimes a person), hired by the client to carry out the work that is required for the completion of a project. • Building permits application • Property security • Providing (temporary) facilities on site • Taking care of generated waste • On-site personnel management • Site surveying • Site engineering • Schedule monitoring
  • 12. Level of Detail • LOD (Level of Detail) is the term used to describe how much information a drawing or model contains. • It is how you choose to show the construction details and materials of a project. • The project members could rely on LOD used in a model to aid in information about design and documentation.
  • 13. Process of development of plans and schedules • Construction planning is a fundamental and challenging activity in the management and execution of construction projects. • It involves  the choice of technology,  the definition of work tasks,  the estimation of the required resources  durations for individual tasks, and  the identification of any interactions among the different work tasks.
  • 14. Process of development of plans and schedules • A good construction plan is the basis for developing the budget and the schedule for work. • Developing the construction plan is a critical task in the management of construction, even if the plan is not written or otherwise formally recorded. • In addition to these technical aspects of construction planning, it may also be necessary to make organizational decisions about the relationships between project participants and even which organizations to include in a project. • For example, the extent to which sub-contractors will be used on a project is often determined during construction planning.
  • 15. Work break-down structure • Method that breaks a project down into a hierarchy of deliverables, tasks, and subtasks. • It gives a way of organizing and understanding your project scope in smaller, manageable components. • The WBS levels may be broadly categorized into five major levels. Level 1: Program level Level 2: Project level Level 3: Task level Level 4: Sub-Task Level Level 5: Work Package level
  • 16. Work break-down structure • Upper three levels of the WBS are normally specified by the client. • Lower levels are generated by the Contractor for in-house control.
  • 18. Activity Lists • Listing down different activities in a project / part / section of a project. • Sequence / order / chronology of activities. • Inter-dependence of activities.
  • 19. Assessment of work content • Assessing the quantum of work. • Using work breakdown technique to break the project into considerate sub-parts. • Making a chronological network of different activities under each part / sub-part.
  • 20. Concept of productivities Estimating durations Sequence of Activities Activity Utility Data
  • 21. Techniques of planning - Bar charts, Gantt charts SCHEDULING - Planning • Process of listing of tasks, activities, milestones with a planned start and finish date. • Proper scheduling would ensure the completion of the project on time and within budget. • It outlines the pace of the work. • Also, how the tasks are executed. • Scheduling defines method and sequence in which materials are delivered. • Finally, it permits adjustments to accommodate changes and unanticipated events.
  • 22. Techniques of planning - Bar charts, Gantt charts • A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks) displayed against time. • On the left of the chart is a list of the activities and along the top is a suitable time scale. • Each activity is represented by a bar; the position and length of the bar reflects the start date, duration and end date of the activity.
  • 23. Techniques of planning - Bar charts, Gantt charts
  • 24. Techniques of planning - Bar charts, Gantt charts Benefits • Clarity: Gantt chart has ability to show and clarify multiple tasks and timelines. • Communication: It is a visual method to help project team members understand task progress. • Motivation: Gantt charts offer project teams the ability to focus work at the front of, or at the tail end of a task timeline. • Co-ordination: Project managers use these charts to break down projects into manageable sets of tasks. • Creativity: The use of Gantt charts often encourages new partnerships that might not have evolved under traditional task assignment systems.
  • 25. Techniques of planning - Bar charts, Gantt charts Benefits • Time Management: Time scheduling is considered as one of the major benefits of Gantt charts • Flexibility: It offers a view of project which can help team members adjust changes. • Manageability: By using Gantt charts, project managers can make more focused, effective decisions about resources and timetables. • Efficiency: Visualizing resource usage during projects allows managers to make better use of people, places, and things. • Accountability: Using Gantt charts during critical projects allows both project managers and participants to track team progress.
  • 26. Techniques of planning - Bar charts, Gantt charts Disadvantages • Require more efforts for creating and managing the chart • Updating a chart is very time consuming • All tasks are not visible in a single view of a gantt • Need to scroll and click additional buttons to view remaining items • Stacks represents only the time and not the hours of the work • Not easy to realign the tasks from on section to another • Not easy to calculate the aggregates
  • 27. Techniques of planning - Bar charts, Gantt charts Development of a Bar Chart - Stages • Breakdown – project into various activities each representing a manageable unit. • Decide – method for execution of project as well as each activity and their sequence. • Assign – duration of time for completion of each activity. • Represent – above information in bar chart indicating relative position of each activity.
  • 28. Techniques of planning - Bar charts, Gantt charts
  • 29. Techniques of planning - Bar charts, Gantt charts
  • 30. Techniques of planning - Bar charts, Gantt charts
  • 31. Techniques of planning - Bar charts, Gantt charts
  • 32. Techniques of planning - Bar charts, Gantt charts
  • 33. Limitations of Bar Charts • Lack of Degree of details – only major activities, becomes clumsy Techniques of planning - Bar charts, Gantt charts
  • 34. Limitations of Bar Charts • Review of Project Progress – does not show progress of project. Modifications could be done by hatching. Techniques of planning - Bar charts, Gantt charts
  • 35. Limitations of Bar Charts • Activity Inter-relationship – not depicted • Example – Pipeline project Techniques of planning - Bar charts, Gantt charts
  • 36. Limitations of Bar Charts • Time Uncertainties – not consider uncertainties in time for projects like research and development etc. • No re-scheduling flexibility offered by Bar charts. • Bar charts are suitable for smaller construction projects where time estimations could be made with fair degree of certainty. Techniques of planning - Bar charts, Gantt charts
  • 37. END