SlideShare uma empresa Scribd logo
1 de 22
1
Mumbai Ahmadabad High Speed Rail Project
Rationale and Background
•The growing transport needs of the country requires construction of
High Speed Railway (HSR) in India.
•Any Railway System having speed potential in excess of 200 kmph
are considered as High Speed Railway.
•The MAHSR project started in 2012 with initial discussions between
Govt. of India and Govt. of Japan. Feasibility study undertaken by
Japanese consultants in December 2013 and report submitted in
July 2015. The project has been approved by Government of India vide
CCEA/31/2015 dated. 09.12.2015
Rationale and Background
•National High Speed Rail Corporation (NHSRCL), A Special Purpose
Vehicle under Ministry of Railways, Govt. of India was set up with
partnership of Govt of Maharashtra and Govt. Of Gujarat on 12th
February 2016.
•On 14th September 2017, Hon’ble Prime Minister of India, Shri
Narendra Modi and Hon’ble Prime Minister of Japan Shri Shinzo Abe
laid the foundation stone for first HSR project between Mumbai and
Ahmedabad.
•All out efforts are being made to complete the Project by 15th August
2022.
Sabarmati
Mumbai
Delhi
Sabarmati
Ahmedabad
Anand
Vadodara
Bharuch
Surat
Bilimora
Vapi
Boisar
Virar
Thane
Mumbai
Legend
Capital
Majorcities
* DNH: Dadra & Nagar Haveli
Gujarat
Maharashtra
Stations: 12 ( 8 in Gujarat
& 4 in Maharashtra)
All elevated except Mumbai
(underground)
Gujarat: 349.03 Km (8 districts)
DNH* : 4.30 Km (1 UT)
Maharashtra: 154.76 Km (3 districts)
Travel Time:
2.07 Hrs (limited Stops) 2.58 Hrs (all stops)
COST: 1,08000 CRORES
(including all escalation, Interest during Construction, taxes/duties)
Total Length: 508.09 Km
460.3 Km Viaducts (90.6%)
9.22 Km Bridges (1.8%)
25.87 Km Tunneling (5.1%)
(Longest Tunnel: 21 Km with 7 Km
undersea)
12.9 Km Cut/Fill (2.5%)
GAUGE: Standard 1435 mm
SPEED: 350 Km/h (design),
320 Km/h (operating)
GENERAL OVERVIEW OF PROJECT
SALIENT FEATURES: TECHNICAL
Project Component Description
Project Cost INR 1.08 Lakh Crores
Funding Agency JICA & MoR, and State
Governments (Maharashtra
and Gujarat)
Total Land Requirement 1415.75 Ha.
Total Length 508.17 km
Elevated Viaduct 469.53 km (9.22 kms Bridges)
Embankment (Cut/Fill) 12.9 Kms
Right of Way (ROW) 17.5 m
Tunnels 25.87 kms (8 Nos.)
Longest Tunnel 21 km (7.0 kms Undersea)
Tunnel Construction Technology TBM & NATM
Railway Crossings 25 locations
Maintenance Depots 7
Rolling Stock Depots 2 - Thane and Sabarmati.
Construction Yards At every 25 km
Track Gauge Standard (1,435 mm)
Maximum Design Speed 350 km/hr
Maximum Operation Speed 320 km/hr
Number of Lines Double Track
Distance between Track Centre 4.5 m
No
.
Stations Ch. (Km)
1 BKC,
Mumbai
0.000
2 Thane 27.950
3 Virar 65.170
4 Boisar 104.207
5 Vapi 167.940
6 Bilimora 216.580
7 Surat 264.580
8 Bharuch 323.110
9 Vadodara 397.060
10 Anand 447.380
11 Ahmedabad 500.190
12 Sabarmati 505.750
Travel Time :
2.07 Hrs (Limited Stops
2.58 Hrs (all stops)
• Reduction in travel time between Mumbai and Ahmedabad from 6.5
hrs to 2.5 hrs.
• High carrying capacity of about 750 passenger per train.
• Major connectivity boost to less developed areas, potential for
development of new production bases and townships along the
corridor.
• Boost to construction industry, technological enhancement of
Railways, long term infrastructure development.
• Creation of temporary and permanent employment.
• Decongestion of existing rail, road, and air traffic between Mumbai
and Ahmedabad
• Reduction in Green house gas emissions due to more efficient
transport option mode
Project Benefits
Key Alternatives chosen include:
• Route optimization and depot siting to avoid / minimize
environmentally and socially sensitive areas (such as forests and
mangroves, sanctuaries, hospitals, schools, densely populated
areas, etc.)
• Embankment option changed to Viaduct, thus substantially
reducing RoW and subsequent Land Acquisition requirement
• Elevated viaduct ensures continuity within spans, across the
alignment (LHS and RHS) without any physical severance for local
community as well as livestock
• Japanese Shinkansen technology chosen, which is one of the
most optimal among HSR, as regards noise emissions and energy
efficiency
Project Alternatives
SALIENT FEATURES: OPERATIONAL
TRAIN OPERATION PLAN (Source: Feasibility Study)
Year 2023 2033 2043 2053
Train Configuration 10 10/16 16 16
Number of Rakes 24 24 +11 44 71
Number of Trains
(per day/one-direction)
35 51 64 105
Train Capacity 750 750/1250 1250 1250
Traffic Volume (day/one direction) 17,900 31,700 56,800 92,900
Number of Trains
(per day/hour/one-direction)
Peak Hour: 3 4 6 8
Off peak: 2 3 3 6
Operational Control Centre: Sabarmati
Maintenance Depot/Workshop (Rolling Stock): Thane, Sabarmati 4
Inspection Light Maintenance Heavy Maintenance Others
(Period) Daily
(48 h)
Regular (30
days)
Bogie
(18 months)
General
(36 months)
Special &
Breakdown
Thane Depot √ √ √
Sabarmati Depot
& Workshop
√ √ √ √ √
• Power supply: 12 Traction substations, 2 Depot substations and 16
Distribution sub stations (12 Stations, 2 Depots & 2 Tunnel)
• OHE: 2X25 KV, Heavy Compound Catenary System
• Signalling: DS- ATC similar to Shinkansen
• Fitted with Disaster Prevention System for safe operation.
• State of the art High Speed Railway Training Institute at Vadodara
• Annual Energy requirements (Trains, Stations etc) -1100 million units 5
SALIENT FEATURES: MAINTENANCE
MAINTENANCE SCHEDULE
Shinkansen E7 Series JR East
X
Construction Methodology: Tunnel/ Via-duct Adopted
• Tunnel about 25-40 meters below ground
level,
• Elevated viaducts ensures continuity within
spans, across the alignment (LHS& RHS)
without any physical severance.
“THERE IS NO BIFURCATION OF
FOREST LAND”
Typical Cross Section in Tunnel & Via Duct
ALIGNMENT STUDY
•Minimum Radius (Horizontal): 6000m for 320 km/h
•Minimum Radius (Vertical): 25000m
•Over Head Clearance:7.7 m
•Maintainability of Asset
Technical
•Future Expansion to new area
•Connectivity with existing important places
•Development potential
Operational
•Location of station, River Bridges
•Minimum Disturbance to Forest & Wild Life
•Minimum Interference with existing structures i.e.
highway, metro, Location of Bridges
Obligatory
Points
Selecting 3
Most
Feasible
Options
ALIGNMENT OF
MAHASAMRIDHI
MARG
S.N. Alignment Alternative-1
(Tunnel)
Alternative -2
(Via Duct)
Alternative -3
(Along IR)
1 Proposed Terminal Bandra Kurla Complex
(Business Center)
Bandra Kurla Complex
(Business Center)
Lokmanya
Tilak (IR station)
2 Passenger
Connectivity
Connected With Metro
2B, Metro 3, Metro 8
(proposed), Airport
(Santacruz Chembur Link
Road)
Connected With
Metro 2B, Metro 8
(proposed), Airport
(Santacruz Chembur
Link Road)
Connected with
Lokmanya Tilak Station
of IR
3 Possibility of future
extension
Possible connection with
Pune, Nagpur
Possible connection
with Pune, Nagpur
Possible connection with
Pune, Nagpur
4 Development
Potential
Very High Due to
Integration with IFSC
Very High Due to
Integration with IFSC
Low, Since terminal is
heavily populated
Most Feasible Alignment: Operational Issues
S.
N.
Alignment Alternative-1
(Tunnel)
Alternative -2
(Via Duct)
Alternative -3
(Along IR)
1 Horizontal Curve Min 6000R Min 6000R Radius 1500 R
2 Vertical Curve 25000 m 25000 m 25000 m
3 Infringement with
Ex/ Pro Structure
Metro 5, Metro 4 Metro 2B, Metro 5, Metro 4,
Eastern Expressway, CSMT
Kalyan Line- 2 locations, Trans
Harbour 2 locations and other
flyovers
• 22 different
locations of Road
Over Bridges &
Foot Over Bridge
4 Speed Potential Speed Potential: 320
km/h
Speed Potential: 320 km/h Speed Potential: 110
km/h
Most Feasible Alignment: Technical Aspects
S.N. Alignment Alternative-1
(Tunnel)
Alternative -2
(Via Duct)
Alternative -3
(Along IR)
1 Wild Life Alignment Passes
through ESZ and PA of
TCFS, ESZ of SGNP &
TWLS. The alignment
also touches PA 0f TWLS
(0.11 Ha). The
construction is proposed
as under ground tunnel
in TCFS, thus minimal
impact on wild life.
Alignment Passes
through ESZ and PA of
TCFS, ESZ of SGNP &
TWLS. The alignment
also touches PA of
TWLS (0.11 Ha).
Alignment Passes
over existing
alignment of IR thus
completely avoiding
the TCFS.
2 Wildlife The alignment is along existing PWD road while passing through ESZ of
TWLS & SGNP.A wildlife overpass & underpass will also be provided, as
per suggestion of NBWL, to bridge lost connectivity of SGNP & TWLS.
3 Forest The alignment passes through Reserved Forest, Protected Forest, Private
Forest etc. at various locations.
Most Feasible Alignment: Obligatory Points
Finalization of Alignment
• A detailed study of 3 alternatives has been done
during feasibility study by dedicated team of
Engineers and Technicians of NHSRCL & Japanese
Consultants.
• Minimum use of forest land, minimal disturbance to
wild life and human habitation were considered.
FINALIZED
ALIGNMENT
Alt-2 & 3
(Viaduct/ IR)
Alt-1 (Tunnel)
MAHSR Alignment in Thane District – Ch: 7.043 to Ch: 46.700 (39.657 Km)
MAHSR Alignment in Palghar District – Ch:46.700 to CH:155.642 (108.942 Km)
Thanks….
36

Mais conteúdo relacionado

Mais procurados

Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasShantanu Patil
 
MultiModal Transportation in New DElhi
MultiModal Transportation in New DElhiMultiModal Transportation in New DElhi
MultiModal Transportation in New DElhiHamza Hashmi
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
Delhi metro and Economics
Delhi metro and EconomicsDelhi metro and Economics
Delhi metro and EconomicsKunal Bhadane
 
Monorail Mumbai
Monorail MumbaiMonorail Mumbai
Monorail MumbaiSahim Khan
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail projectDocumentStory
 
Construction challenge of bridge in hilly areas
 Construction challenge of bridge in hilly areas Construction challenge of bridge in hilly areas
Construction challenge of bridge in hilly areasShashank Naruka
 
Case studies ppp
Case studies pppCase studies ppp
Case studies pppamityasum23
 
Tram seminar ppt
Tram seminar pptTram seminar ppt
Tram seminar pptashik ks
 
Infrastructure of transportation
Infrastructure of transportationInfrastructure of transportation
Infrastructure of transportationSiddhi Vakharia
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in DelhiJaspal Singh
 
Mass transit system
Mass transit systemMass transit system
Mass transit systemSagar Kaptan
 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMChandanPadhi3
 
Transportation analysis at anand vihar
Transportation analysis at anand viharTransportation analysis at anand vihar
Transportation analysis at anand viharSneha Lata
 
seminar presentation on high speed train
 seminar presentation on high speed train seminar presentation on high speed train
seminar presentation on high speed trainmechanical Singh
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyIPPAI
 
Presentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanPresentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanAamir Rajput Khan
 

Mais procurados (20)

Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly Areas
 
MultiModal Transportation in New DElhi
MultiModal Transportation in New DElhiMultiModal Transportation in New DElhi
MultiModal Transportation in New DElhi
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Rapid transit system
Rapid transit systemRapid transit system
Rapid transit system
 
Delhi metro and Economics
Delhi metro and EconomicsDelhi metro and Economics
Delhi metro and Economics
 
report
reportreport
report
 
Monorail Mumbai
Monorail MumbaiMonorail Mumbai
Monorail Mumbai
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail project
 
Construction challenge of bridge in hilly areas
 Construction challenge of bridge in hilly areas Construction challenge of bridge in hilly areas
Construction challenge of bridge in hilly areas
 
Case studies ppp
Case studies pppCase studies ppp
Case studies ppp
 
Tram seminar ppt
Tram seminar pptTram seminar ppt
Tram seminar ppt
 
Infrastructure of transportation
Infrastructure of transportationInfrastructure of transportation
Infrastructure of transportation
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in Delhi
 
Mass transit system
Mass transit systemMass transit system
Mass transit system
 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEM
 
ahmedabad BRTS study
ahmedabad BRTS studyahmedabad BRTS study
ahmedabad BRTS study
 
Transportation analysis at anand vihar
Transportation analysis at anand viharTransportation analysis at anand vihar
Transportation analysis at anand vihar
 
seminar presentation on high speed train
 seminar presentation on high speed train seminar presentation on high speed train
seminar presentation on high speed train
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
 
Presentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanPresentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir Khan
 

Semelhante a 428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx

Cantonment metro station a case study1 rajkumar
Cantonment metro station   a case study1  rajkumarCantonment metro station   a case study1  rajkumar
Cantonment metro station a case study1 rajkumarSanjeev Dyamannavar
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Nishanth Patil
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081Anush verma
 
INTELLIGENT TRANSPORTATION SYSTEMS
INTELLIGENT TRANSPORTATION SYSTEMSINTELLIGENT TRANSPORTATION SYSTEMS
INTELLIGENT TRANSPORTATION SYSTEMSKona Mahesh
 
Doubling progress report
Doubling progress reportDoubling progress report
Doubling progress reportNeha Singh
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiShobhit Acharya
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET Journal
 
Metro elevated structures AR.pdf
Metro elevated structures AR.pdfMetro elevated structures AR.pdf
Metro elevated structures AR.pdfAshutoshRankawat
 
Metro elevated structures AR.pdf
Metro elevated structures AR.pdfMetro elevated structures AR.pdf
Metro elevated structures AR.pdfAshutoshRankawat
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)sharda university
 
Railway Engineering by Sharda University
Railway Engineering by Sharda UniversityRailway Engineering by Sharda University
Railway Engineering by Sharda UniversityFatila Carrol
 
Transport poster
Transport posterTransport poster
Transport posterGordon Best
 
Introduction to railway engineering
Introduction to railway engineeringIntroduction to railway engineering
Introduction to railway engineeringMuhammad Taimur Khan
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptxAswin132028
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeJangid Devendra
 

Semelhante a 428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx (20)

Cantonment metro station a case study1 rajkumar
Cantonment metro station   a case study1  rajkumarCantonment metro station   a case study1  rajkumar
Cantonment metro station a case study1 rajkumar
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081
 
Surat BRTS - Abhijit Lokre
Surat BRTS - Abhijit LokreSurat BRTS - Abhijit Lokre
Surat BRTS - Abhijit Lokre
 
INTELLIGENT TRANSPORTATION SYSTEMS
INTELLIGENT TRANSPORTATION SYSTEMSINTELLIGENT TRANSPORTATION SYSTEMS
INTELLIGENT TRANSPORTATION SYSTEMS
 
Doubling progress report
Doubling progress reportDoubling progress report
Doubling progress report
 
wdfcil
wdfcilwdfcil
wdfcil
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
 
Metro project in inda
Metro project in indaMetro project in inda
Metro project in inda
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
 
Metro elevated structures AR.pdf
Metro elevated structures AR.pdfMetro elevated structures AR.pdf
Metro elevated structures AR.pdf
 
Metro elevated structures AR.pdf
Metro elevated structures AR.pdfMetro elevated structures AR.pdf
Metro elevated structures AR.pdf
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
Railway Engineering by Sharda University
Railway Engineering by Sharda UniversityRailway Engineering by Sharda University
Railway Engineering by Sharda University
 
Transport poster
Transport posterTransport poster
Transport poster
 
R.R.A.C.L-WB1.pdf
R.R.A.C.L-WB1.pdfR.R.A.C.L-WB1.pdf
R.R.A.C.L-WB1.pdf
 
Introduction to railway engineering
Introduction to railway engineeringIntroduction to railway engineering
Introduction to railway engineering
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptx
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gauge
 

Último

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Último (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx

  • 1. 1 Mumbai Ahmadabad High Speed Rail Project
  • 2. Rationale and Background •The growing transport needs of the country requires construction of High Speed Railway (HSR) in India. •Any Railway System having speed potential in excess of 200 kmph are considered as High Speed Railway. •The MAHSR project started in 2012 with initial discussions between Govt. of India and Govt. of Japan. Feasibility study undertaken by Japanese consultants in December 2013 and report submitted in July 2015. The project has been approved by Government of India vide CCEA/31/2015 dated. 09.12.2015
  • 3. Rationale and Background •National High Speed Rail Corporation (NHSRCL), A Special Purpose Vehicle under Ministry of Railways, Govt. of India was set up with partnership of Govt of Maharashtra and Govt. Of Gujarat on 12th February 2016. •On 14th September 2017, Hon’ble Prime Minister of India, Shri Narendra Modi and Hon’ble Prime Minister of Japan Shri Shinzo Abe laid the foundation stone for first HSR project between Mumbai and Ahmedabad. •All out efforts are being made to complete the Project by 15th August 2022.
  • 4. Sabarmati Mumbai Delhi Sabarmati Ahmedabad Anand Vadodara Bharuch Surat Bilimora Vapi Boisar Virar Thane Mumbai Legend Capital Majorcities * DNH: Dadra & Nagar Haveli Gujarat Maharashtra Stations: 12 ( 8 in Gujarat & 4 in Maharashtra) All elevated except Mumbai (underground) Gujarat: 349.03 Km (8 districts) DNH* : 4.30 Km (1 UT) Maharashtra: 154.76 Km (3 districts) Travel Time: 2.07 Hrs (limited Stops) 2.58 Hrs (all stops) COST: 1,08000 CRORES (including all escalation, Interest during Construction, taxes/duties) Total Length: 508.09 Km 460.3 Km Viaducts (90.6%) 9.22 Km Bridges (1.8%) 25.87 Km Tunneling (5.1%) (Longest Tunnel: 21 Km with 7 Km undersea) 12.9 Km Cut/Fill (2.5%) GAUGE: Standard 1435 mm SPEED: 350 Km/h (design), 320 Km/h (operating) GENERAL OVERVIEW OF PROJECT
  • 5. SALIENT FEATURES: TECHNICAL Project Component Description Project Cost INR 1.08 Lakh Crores Funding Agency JICA & MoR, and State Governments (Maharashtra and Gujarat) Total Land Requirement 1415.75 Ha. Total Length 508.17 km Elevated Viaduct 469.53 km (9.22 kms Bridges) Embankment (Cut/Fill) 12.9 Kms Right of Way (ROW) 17.5 m Tunnels 25.87 kms (8 Nos.) Longest Tunnel 21 km (7.0 kms Undersea) Tunnel Construction Technology TBM & NATM Railway Crossings 25 locations Maintenance Depots 7 Rolling Stock Depots 2 - Thane and Sabarmati. Construction Yards At every 25 km Track Gauge Standard (1,435 mm) Maximum Design Speed 350 km/hr Maximum Operation Speed 320 km/hr Number of Lines Double Track Distance between Track Centre 4.5 m No . Stations Ch. (Km) 1 BKC, Mumbai 0.000 2 Thane 27.950 3 Virar 65.170 4 Boisar 104.207 5 Vapi 167.940 6 Bilimora 216.580 7 Surat 264.580 8 Bharuch 323.110 9 Vadodara 397.060 10 Anand 447.380 11 Ahmedabad 500.190 12 Sabarmati 505.750 Travel Time : 2.07 Hrs (Limited Stops 2.58 Hrs (all stops)
  • 6. • Reduction in travel time between Mumbai and Ahmedabad from 6.5 hrs to 2.5 hrs. • High carrying capacity of about 750 passenger per train. • Major connectivity boost to less developed areas, potential for development of new production bases and townships along the corridor. • Boost to construction industry, technological enhancement of Railways, long term infrastructure development. • Creation of temporary and permanent employment. • Decongestion of existing rail, road, and air traffic between Mumbai and Ahmedabad • Reduction in Green house gas emissions due to more efficient transport option mode Project Benefits
  • 7. Key Alternatives chosen include: • Route optimization and depot siting to avoid / minimize environmentally and socially sensitive areas (such as forests and mangroves, sanctuaries, hospitals, schools, densely populated areas, etc.) • Embankment option changed to Viaduct, thus substantially reducing RoW and subsequent Land Acquisition requirement • Elevated viaduct ensures continuity within spans, across the alignment (LHS and RHS) without any physical severance for local community as well as livestock • Japanese Shinkansen technology chosen, which is one of the most optimal among HSR, as regards noise emissions and energy efficiency Project Alternatives
  • 8. SALIENT FEATURES: OPERATIONAL TRAIN OPERATION PLAN (Source: Feasibility Study) Year 2023 2033 2043 2053 Train Configuration 10 10/16 16 16 Number of Rakes 24 24 +11 44 71 Number of Trains (per day/one-direction) 35 51 64 105 Train Capacity 750 750/1250 1250 1250 Traffic Volume (day/one direction) 17,900 31,700 56,800 92,900 Number of Trains (per day/hour/one-direction) Peak Hour: 3 4 6 8 Off peak: 2 3 3 6 Operational Control Centre: Sabarmati Maintenance Depot/Workshop (Rolling Stock): Thane, Sabarmati 4
  • 9. Inspection Light Maintenance Heavy Maintenance Others (Period) Daily (48 h) Regular (30 days) Bogie (18 months) General (36 months) Special & Breakdown Thane Depot √ √ √ Sabarmati Depot & Workshop √ √ √ √ √ • Power supply: 12 Traction substations, 2 Depot substations and 16 Distribution sub stations (12 Stations, 2 Depots & 2 Tunnel) • OHE: 2X25 KV, Heavy Compound Catenary System • Signalling: DS- ATC similar to Shinkansen • Fitted with Disaster Prevention System for safe operation. • State of the art High Speed Railway Training Institute at Vadodara • Annual Energy requirements (Trains, Stations etc) -1100 million units 5 SALIENT FEATURES: MAINTENANCE MAINTENANCE SCHEDULE
  • 10. Shinkansen E7 Series JR East X Construction Methodology: Tunnel/ Via-duct Adopted • Tunnel about 25-40 meters below ground level, • Elevated viaducts ensures continuity within spans, across the alignment (LHS& RHS) without any physical severance. “THERE IS NO BIFURCATION OF FOREST LAND”
  • 11. Typical Cross Section in Tunnel & Via Duct
  • 12. ALIGNMENT STUDY •Minimum Radius (Horizontal): 6000m for 320 km/h •Minimum Radius (Vertical): 25000m •Over Head Clearance:7.7 m •Maintainability of Asset Technical •Future Expansion to new area •Connectivity with existing important places •Development potential Operational •Location of station, River Bridges •Minimum Disturbance to Forest & Wild Life •Minimum Interference with existing structures i.e. highway, metro, Location of Bridges Obligatory Points
  • 15. S.N. Alignment Alternative-1 (Tunnel) Alternative -2 (Via Duct) Alternative -3 (Along IR) 1 Proposed Terminal Bandra Kurla Complex (Business Center) Bandra Kurla Complex (Business Center) Lokmanya Tilak (IR station) 2 Passenger Connectivity Connected With Metro 2B, Metro 3, Metro 8 (proposed), Airport (Santacruz Chembur Link Road) Connected With Metro 2B, Metro 8 (proposed), Airport (Santacruz Chembur Link Road) Connected with Lokmanya Tilak Station of IR 3 Possibility of future extension Possible connection with Pune, Nagpur Possible connection with Pune, Nagpur Possible connection with Pune, Nagpur 4 Development Potential Very High Due to Integration with IFSC Very High Due to Integration with IFSC Low, Since terminal is heavily populated Most Feasible Alignment: Operational Issues
  • 16. S. N. Alignment Alternative-1 (Tunnel) Alternative -2 (Via Duct) Alternative -3 (Along IR) 1 Horizontal Curve Min 6000R Min 6000R Radius 1500 R 2 Vertical Curve 25000 m 25000 m 25000 m 3 Infringement with Ex/ Pro Structure Metro 5, Metro 4 Metro 2B, Metro 5, Metro 4, Eastern Expressway, CSMT Kalyan Line- 2 locations, Trans Harbour 2 locations and other flyovers • 22 different locations of Road Over Bridges & Foot Over Bridge 4 Speed Potential Speed Potential: 320 km/h Speed Potential: 320 km/h Speed Potential: 110 km/h Most Feasible Alignment: Technical Aspects
  • 17. S.N. Alignment Alternative-1 (Tunnel) Alternative -2 (Via Duct) Alternative -3 (Along IR) 1 Wild Life Alignment Passes through ESZ and PA of TCFS, ESZ of SGNP & TWLS. The alignment also touches PA 0f TWLS (0.11 Ha). The construction is proposed as under ground tunnel in TCFS, thus minimal impact on wild life. Alignment Passes through ESZ and PA of TCFS, ESZ of SGNP & TWLS. The alignment also touches PA of TWLS (0.11 Ha). Alignment Passes over existing alignment of IR thus completely avoiding the TCFS. 2 Wildlife The alignment is along existing PWD road while passing through ESZ of TWLS & SGNP.A wildlife overpass & underpass will also be provided, as per suggestion of NBWL, to bridge lost connectivity of SGNP & TWLS. 3 Forest The alignment passes through Reserved Forest, Protected Forest, Private Forest etc. at various locations. Most Feasible Alignment: Obligatory Points
  • 18. Finalization of Alignment • A detailed study of 3 alternatives has been done during feasibility study by dedicated team of Engineers and Technicians of NHSRCL & Japanese Consultants. • Minimum use of forest land, minimal disturbance to wild life and human habitation were considered.
  • 20. MAHSR Alignment in Thane District – Ch: 7.043 to Ch: 46.700 (39.657 Km)
  • 21. MAHSR Alignment in Palghar District – Ch:46.700 to CH:155.642 (108.942 Km)