SlideShare uma empresa Scribd logo
1 de 17
Baixar para ler offline
The Digital
Transformation of
Progress Measurement
Jean-Luc Ozoux – EcoSys Solution Specialist
Confidential2
• Need to know where we are today to understand where we will finish
• Manage stakeholder expectations
• Identify areas of poor performance
• Analyze root causes and take corrective actions
Why is progress measurement important?
An Art Form?
Haphazard?
“Finger in the Air”
Confidential3
• Measure progress against the plan
• Support Earned Value Analysis
• Calculate performance driven forecast adjustments
What is the purpose of measuring progress?
MEASURE FORECASTON TARGET?
Confidential4
Where do we need to improve?
• Siloed and disconnected processes and data management
• Too subjective and open to interpretation
• Lack of standardization – no standard rules of credit
• Inefficient manual process with potential for error
• Data intensive – multiple sources requiring consolidation, manipulation and analysis
• Difficult to validate reliability and accuracy of information
• Optimism Bias – reporting “inaccurate” progress especially early in project lifecycle
Confidential5
The solution is “automated objectivity”
ObjectiveSubjective
Automated
Manual
Efficiency & Accuracy
• Remove silos
• Ability to drilldown into source data
• Auditable progress data
• System driven values
• Standardized processes
Confidential6
Cost Control
Different Sources, Data and Methods
Schedule
Activity or Task Start
and Finish
Construction Management
Installed Quantities
Design Software
Engineering
Deliverables3D
Information Management
Deliverables
Completions
Materials Management
Materials Requisitions,
Orders & Receipts
ERP
Accruals & Actuals
Progress
Confidential7
• Best suited for short duration tasks
• % based or rule based completions
• Rule based progress: 50/50, 20/80 or 0/100
Schedule
Activity or Task Start
and Finish
50/50 Rule – Once started task = 50% complete.
Balance earned on completion
20/80 Rule – Used if completion takes longer
0/100 Rule – 100% earned on completion
Standard Adaptor
File import
Standard Requirements
Web Services, APIs
Custom Requirements
Cost Control
Confidential8
• Cost Ratio method applied for activities occurring
throughout life of project e.g. Prelims, Overhead, etc.
• Invoice only project costs
ERP
Accruals & Actuals
PS
MM
CO
CATS
Project Cost Objects e.g.
WBS, Network Activities,
Orders, etc.
Purchase Orders, Purchase
Requisitions and Receipts
Planed Costs, Actual
Costs, Actual Revenue
Unapproved and
Approved Time
Forecasts
WBS, WBS Status, Network
and Network Activities
Cost Control
Confidential9
Cost Control
Design
• Track completion of engineering deliverables
based on progress milestones
• Visualize planned and actual progress
Design Software
Engineering
Deliverables3D
Confidential10
• Track completion of engineering deliverables
based on progress milestones
• Visualize planned and actual progress
Design Software
Engineering
Deliverables3D
Confidential11
• Tracking status of deliverable packages and
deliverable details
• Managing status; not started, in progress,
complete
Information Management
Deliverables
Completions
Confidential12
• Procurement driven progress based on material
receipts or contracted milestones
• 10% on PO, 20% on shipment, 30% on delivery,
40% at test and commissioning
Materials Management
Materials Receipts
ProcurementCost Control
Cost Breakdown Structure
Cost Budget
Account Codes
Budget
Commitments (Planned) Requisitions
Commitments (Actual) Material Orders
Actuals (Value of Work Done) Material Receipts
Actuals (Posted) Material Invoices
Confidential13
• Procurement driven progress based on material
receipts or contracted milestones
• 10% on PO, 20% on shipment, 30% on delivery,
40% at test and commissioning
Materials Management
Materials Receipts
Confidential14
Cost Control
• CWP Number (WBS Code)
• CWA Number
• Plant
• IWP Number
• Planned Man-hours
• Actual Man-hours
• Planned Start/Finish Date
• Actual Start/Finish Date
• Discipline
• Purpose
• Crew Size
• Best for repeatable tasks. Tasks requiring same
amounts of time, resources and effort
• Zero subjectivity
Construction Management
Installed Quantities
Construction
Confidential15
• Best for repeatable tasks. Tasks requiring same
amounts of time, resources and effort
• Zero subjectivity
Construction Management
Installed Quantities
Confidential16
Cost Control
Questions?
Schedule
Activity or Task Start
and Finish
Construction Management
Installed Quantities
Design Software
Engineering
Deliverables3D
Information Management
Deliverables
Completions
Materials Management
Materials Receipts
ERP
Accruals & Actuals
Data Management Options
Desktop/Office Data
Entry
Mobile/Field Data
Entry
Web Services API
3D Laser Scanning
Drones
Radio Frequency
Identification (RFID)
Progress
Thank you!
www.ecosys.net
info@ecosys.net

Mais conteúdo relacionado

Mais procurados

The Case Studies for Project Control Platform - Maurizio M. Granata Business ...
The Case Studies for Project Control Platform - Maurizio M. Granata Business ...The Case Studies for Project Control Platform - Maurizio M. Granata Business ...
The Case Studies for Project Control Platform - Maurizio M. Granata Business ...Mediehuset Ingeniøren Live
 
Ibrahim alamri cv 20199 new
Ibrahim alamri cv 20199 newIbrahim alamri cv 20199 new
Ibrahim alamri cv 20199 newAlamer Omani
 
Carl Souchereau, SNC Lavalin T&D: Both Sides of the Fence
Carl Souchereau, SNC Lavalin T&D: Both Sides of the FenceCarl Souchereau, SNC Lavalin T&D: Both Sides of the Fence
Carl Souchereau, SNC Lavalin T&D: Both Sides of the FenceUMT
 
Greg bisanz resume april 26 2013 verdana
Greg bisanz resume april 26 2013 verdanaGreg bisanz resume april 26 2013 verdana
Greg bisanz resume april 26 2013 verdanaGregory Bisanz
 
Actuaries and Examiners Talk Numbers: Go Figure!
Actuaries and Examiners Talk Numbers:  Go Figure!Actuaries and Examiners Talk Numbers:  Go Figure!
Actuaries and Examiners Talk Numbers: Go Figure!Sedgwick
 
Security a Revenue Center: How Security Can Drive Your Business
Security a Revenue Center: How Security Can Drive Your BusinessSecurity a Revenue Center: How Security Can Drive Your Business
Security a Revenue Center: How Security Can Drive Your Businessshira koper
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics rightThomas Cream
 
list of services linkedin
list of services linkedinlist of services linkedin
list of services linkedinWill Dean
 
Best Practices - Barcode Strategy
Best Practices - Barcode StrategyBest Practices - Barcode Strategy
Best Practices - Barcode Strategyjohnnyg14
 
Gregory Shireman PM 12 05 2016
Gregory Shireman  PM 12 05 2016Gregory Shireman  PM 12 05 2016
Gregory Shireman PM 12 05 2016Greg Shireman
 
(134835645) management information system
(134835645) management  information system(134835645) management  information system
(134835645) management information systemgappu23
 
Project fusion engagement kick off
Project fusion engagement kick offProject fusion engagement kick off
Project fusion engagement kick offmaxalus
 
Project Fusion Engagement Kick-Off
Project Fusion Engagement Kick-OffProject Fusion Engagement Kick-Off
Project Fusion Engagement Kick-OffRalph Hatem
 
Financial controls management protiviti governance portal
Financial controls management protiviti governance portalFinancial controls management protiviti governance portal
Financial controls management protiviti governance portalSARVJEET KAUSHAL
 

Mais procurados (18)

The Case Studies for Project Control Platform - Maurizio M. Granata Business ...
The Case Studies for Project Control Platform - Maurizio M. Granata Business ...The Case Studies for Project Control Platform - Maurizio M. Granata Business ...
The Case Studies for Project Control Platform - Maurizio M. Granata Business ...
 
Ibrahim alamri cv 20199 new
Ibrahim alamri cv 20199 newIbrahim alamri cv 20199 new
Ibrahim alamri cv 20199 new
 
Carl Souchereau, SNC Lavalin T&D: Both Sides of the Fence
Carl Souchereau, SNC Lavalin T&D: Both Sides of the FenceCarl Souchereau, SNC Lavalin T&D: Both Sides of the Fence
Carl Souchereau, SNC Lavalin T&D: Both Sides of the Fence
 
Greg bisanz resume april 26 2013 verdana
Greg bisanz resume april 26 2013 verdanaGreg bisanz resume april 26 2013 verdana
Greg bisanz resume april 26 2013 verdana
 
Senseity
SenseitySenseity
Senseity
 
Actuaries and Examiners Talk Numbers: Go Figure!
Actuaries and Examiners Talk Numbers:  Go Figure!Actuaries and Examiners Talk Numbers:  Go Figure!
Actuaries and Examiners Talk Numbers: Go Figure!
 
Security a Revenue Center: How Security Can Drive Your Business
Security a Revenue Center: How Security Can Drive Your BusinessSecurity a Revenue Center: How Security Can Drive Your Business
Security a Revenue Center: How Security Can Drive Your Business
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 
list of services linkedin
list of services linkedinlist of services linkedin
list of services linkedin
 
PM Foundation
PM FoundationPM Foundation
PM Foundation
 
Best Practices - Barcode Strategy
Best Practices - Barcode StrategyBest Practices - Barcode Strategy
Best Practices - Barcode Strategy
 
IT Audit - Evolve and Stay in the Game
IT Audit - Evolve and Stay in the GameIT Audit - Evolve and Stay in the Game
IT Audit - Evolve and Stay in the Game
 
Gregory Shireman PM 12 05 2016
Gregory Shireman  PM 12 05 2016Gregory Shireman  PM 12 05 2016
Gregory Shireman PM 12 05 2016
 
(134835645) management information system
(134835645) management  information system(134835645) management  information system
(134835645) management information system
 
Project fusion engagement kick off
Project fusion engagement kick offProject fusion engagement kick off
Project fusion engagement kick off
 
Project Fusion Engagement Kick-Off
Project Fusion Engagement Kick-OffProject Fusion Engagement Kick-Off
Project Fusion Engagement Kick-Off
 
Financial controls management protiviti governance portal
Financial controls management protiviti governance portalFinancial controls management protiviti governance portal
Financial controls management protiviti governance portal
 
Timothy Scerri Resume
Timothy Scerri ResumeTimothy Scerri Resume
Timothy Scerri Resume
 

Semelhante a Jean-Luc Ozoux

3 Ways That Data Helps Reduce Review Cycles - Webinar, May 2016
3 Ways That Data Helps Reduce Review Cycles - Webinar, May 20163 Ways That Data Helps Reduce Review Cycles - Webinar, May 2016
3 Ways That Data Helps Reduce Review Cycles - Webinar, May 2016Aconex
 
Data center migration
Data center migrationData center migration
Data center migrationTANMOY ROY
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Beyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical TrialsBeyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical TrialsMontrium
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfHuyNguyen657394
 
Transforming the customer experience crb
Transforming the customer experience   crbTransforming the customer experience   crb
Transforming the customer experience crbrobgirvan
 
Project_Integration_Managemen.pptx
Project_Integration_Managemen.pptxProject_Integration_Managemen.pptx
Project_Integration_Managemen.pptxIvarsLinde1
 
ClickSoftware Case Study Ohio Department of Commerce
ClickSoftware Case Study Ohio Department of CommerceClickSoftware Case Study Ohio Department of Commerce
ClickSoftware Case Study Ohio Department of CommerceClickSoftware
 
Projectcontrol
ProjectcontrolProjectcontrol
ProjectcontrolRaj Sampat
 
DSS Case on Planpower
DSS Case on PlanpowerDSS Case on Planpower
DSS Case on PlanpowerSubhasis Maji
 
Project management
Project managementProject management
Project managementSameer Kumar
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 
Pwims generic level1
Pwims generic level1Pwims generic level1
Pwims generic level1SoftTechLive
 
Yurii Chaika: Delivery Excellence in consulting model - importance, component...
Yurii Chaika: Delivery Excellence in consulting model - importance, component...Yurii Chaika: Delivery Excellence in consulting model - importance, component...
Yurii Chaika: Delivery Excellence in consulting model - importance, component...Lviv Startup Club
 

Semelhante a Jean-Luc Ozoux (20)

3 Ways That Data Helps Reduce Review Cycles - Webinar, May 2016
3 Ways That Data Helps Reduce Review Cycles - Webinar, May 20163 Ways That Data Helps Reduce Review Cycles - Webinar, May 2016
3 Ways That Data Helps Reduce Review Cycles - Webinar, May 2016
 
Data center migration
Data center migrationData center migration
Data center migration
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
Beyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical TrialsBeyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical Trials
 
Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdf
 
Transforming the customer experience crb
Transforming the customer experience   crbTransforming the customer experience   crb
Transforming the customer experience crb
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
Project_Integration_Managemen.pptx
Project_Integration_Managemen.pptxProject_Integration_Managemen.pptx
Project_Integration_Managemen.pptx
 
ClickSoftware Case Study Ohio Department of Commerce
ClickSoftware Case Study Ohio Department of CommerceClickSoftware Case Study Ohio Department of Commerce
ClickSoftware Case Study Ohio Department of Commerce
 
Arindam_Sen_Gupta_CV_2_
Arindam_Sen_Gupta_CV_2_Arindam_Sen_Gupta_CV_2_
Arindam_Sen_Gupta_CV_2_
 
Projectcontrol
ProjectcontrolProjectcontrol
Projectcontrol
 
DSS Case on Planpower
DSS Case on PlanpowerDSS Case on Planpower
DSS Case on Planpower
 
Project management
Project managementProject management
Project management
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
Robert Latest cv
Robert Latest cvRobert Latest cv
Robert Latest cv
 
Pwims generic level1
Pwims generic level1Pwims generic level1
Pwims generic level1
 
Yurii Chaika: Delivery Excellence in consulting model - importance, component...
Yurii Chaika: Delivery Excellence in consulting model - importance, component...Yurii Chaika: Delivery Excellence in consulting model - importance, component...
Yurii Chaika: Delivery Excellence in consulting model - importance, component...
 

Mais de ProjectControlsExpo (16)

Subash Tavares
Subash TavaresSubash Tavares
Subash Tavares
 
Saurabh Bhandari
Saurabh BhandariSaurabh Bhandari
Saurabh Bhandari
 
Mike Younger
Mike YoungerMike Younger
Mike Younger
 
Martin Paver
Martin PaverMartin Paver
Martin Paver
 
Jason Hones
Jason HonesJason Hones
Jason Hones
 
James Lea
James Lea James Lea
James Lea
 
Isabelle Linden
Isabelle Linden Isabelle Linden
Isabelle Linden
 
Iain Minns
Iain MinnsIain Minns
Iain Minns
 
Holding
HoldingHolding
Holding
 
Ed Davey
Ed DaveyEd Davey
Ed Davey
 
Dawn Thompson
Dawn ThompsonDawn Thompson
Dawn Thompson
 
Cameron stewart
Cameron stewartCameron stewart
Cameron stewart
 
Bob arnold
Bob arnoldBob arnold
Bob arnold
 
Ben fitzgerald
Ben fitzgeraldBen fitzgerald
Ben fitzgerald
 
Tim fenemore
Tim fenemoreTim fenemore
Tim fenemore
 
Andrew langridge
Andrew langridgeAndrew langridge
Andrew langridge
 

Último

Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 

Último (20)

Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 

Jean-Luc Ozoux

  • 1. The Digital Transformation of Progress Measurement Jean-Luc Ozoux – EcoSys Solution Specialist
  • 2. Confidential2 • Need to know where we are today to understand where we will finish • Manage stakeholder expectations • Identify areas of poor performance • Analyze root causes and take corrective actions Why is progress measurement important? An Art Form? Haphazard? “Finger in the Air”
  • 3. Confidential3 • Measure progress against the plan • Support Earned Value Analysis • Calculate performance driven forecast adjustments What is the purpose of measuring progress? MEASURE FORECASTON TARGET?
  • 4. Confidential4 Where do we need to improve? • Siloed and disconnected processes and data management • Too subjective and open to interpretation • Lack of standardization – no standard rules of credit • Inefficient manual process with potential for error • Data intensive – multiple sources requiring consolidation, manipulation and analysis • Difficult to validate reliability and accuracy of information • Optimism Bias – reporting “inaccurate” progress especially early in project lifecycle
  • 5. Confidential5 The solution is “automated objectivity” ObjectiveSubjective Automated Manual Efficiency & Accuracy • Remove silos • Ability to drilldown into source data • Auditable progress data • System driven values • Standardized processes
  • 6. Confidential6 Cost Control Different Sources, Data and Methods Schedule Activity or Task Start and Finish Construction Management Installed Quantities Design Software Engineering Deliverables3D Information Management Deliverables Completions Materials Management Materials Requisitions, Orders & Receipts ERP Accruals & Actuals Progress
  • 7. Confidential7 • Best suited for short duration tasks • % based or rule based completions • Rule based progress: 50/50, 20/80 or 0/100 Schedule Activity or Task Start and Finish 50/50 Rule – Once started task = 50% complete. Balance earned on completion 20/80 Rule – Used if completion takes longer 0/100 Rule – 100% earned on completion Standard Adaptor File import Standard Requirements Web Services, APIs Custom Requirements Cost Control
  • 8. Confidential8 • Cost Ratio method applied for activities occurring throughout life of project e.g. Prelims, Overhead, etc. • Invoice only project costs ERP Accruals & Actuals PS MM CO CATS Project Cost Objects e.g. WBS, Network Activities, Orders, etc. Purchase Orders, Purchase Requisitions and Receipts Planed Costs, Actual Costs, Actual Revenue Unapproved and Approved Time Forecasts WBS, WBS Status, Network and Network Activities Cost Control
  • 9. Confidential9 Cost Control Design • Track completion of engineering deliverables based on progress milestones • Visualize planned and actual progress Design Software Engineering Deliverables3D
  • 10. Confidential10 • Track completion of engineering deliverables based on progress milestones • Visualize planned and actual progress Design Software Engineering Deliverables3D
  • 11. Confidential11 • Tracking status of deliverable packages and deliverable details • Managing status; not started, in progress, complete Information Management Deliverables Completions
  • 12. Confidential12 • Procurement driven progress based on material receipts or contracted milestones • 10% on PO, 20% on shipment, 30% on delivery, 40% at test and commissioning Materials Management Materials Receipts ProcurementCost Control Cost Breakdown Structure Cost Budget Account Codes Budget Commitments (Planned) Requisitions Commitments (Actual) Material Orders Actuals (Value of Work Done) Material Receipts Actuals (Posted) Material Invoices
  • 13. Confidential13 • Procurement driven progress based on material receipts or contracted milestones • 10% on PO, 20% on shipment, 30% on delivery, 40% at test and commissioning Materials Management Materials Receipts
  • 14. Confidential14 Cost Control • CWP Number (WBS Code) • CWA Number • Plant • IWP Number • Planned Man-hours • Actual Man-hours • Planned Start/Finish Date • Actual Start/Finish Date • Discipline • Purpose • Crew Size • Best for repeatable tasks. Tasks requiring same amounts of time, resources and effort • Zero subjectivity Construction Management Installed Quantities Construction
  • 15. Confidential15 • Best for repeatable tasks. Tasks requiring same amounts of time, resources and effort • Zero subjectivity Construction Management Installed Quantities
  • 16. Confidential16 Cost Control Questions? Schedule Activity or Task Start and Finish Construction Management Installed Quantities Design Software Engineering Deliverables3D Information Management Deliverables Completions Materials Management Materials Receipts ERP Accruals & Actuals Data Management Options Desktop/Office Data Entry Mobile/Field Data Entry Web Services API 3D Laser Scanning Drones Radio Frequency Identification (RFID) Progress