SlideShare uma empresa Scribd logo
1 de 21
Re-Using Vent gas of calciner as
heat source for Fluidised bed
dryer of Plant-04
MENTOR :
Yati varshneya
SUBMITTED BY:
Priyanka Agrawal
Contents
1. Introduction
2. Heat flowing out of calciner vent.
3. Heat required in FBD
4. Modification required
5. Suggestions
Introduction
 Plant-04 is an absorbent making plant which manufactures
chlorine and sulphur guard.
 These absorbents are used in the petroleum refineries for
absorbing the impurities like sulphur and chlorine from crude
oil.
 The basic unit operation involved in manufacturing of these
absorbent are mixing, Granulation, Drying, Calcination,
Screening.
Mixing
Pan
Granulation
Fluidised
Bed Drying
Calcination Screening
Flow sheet of Material Flow
Introduction
Introduction
 In plant-04, 5 different types of absorbent are produced which differ in
their composition and method of manufacturing.
 In manufacturing of two of these products both drying and calcination
are required.
 So, for this the hot gas coming out of calciner vent can be used as
heat source for the fluidised bed dryer.
 The production of this product is approximately 200 MT/month and is
produced for four months/based on S&OP in a year.
Heat flowing out of calciner vent
39%
recycle
Vent gas
~2500m3/hr
T = 260°C
6 lakh KJ
T = 700°C
Hot gas
out
4500m3/hr
Schematic Diagram of Calcination Process
Heat flowing out of calciner vent
Approximately 6 lakh kilo joule of heat is coming out from calciner vent.
Blower air quantity (m3/hr) 4500
Recycle value 0.39
Vent gas (m3/hr) 2745
Approx. Vent flow rate (m3/hr) 2500
Temperature of vent gas °C 260
Reference temperature °C 61
Heat coming out (KJ/hr) 6,12,484.7
 Presently calciner is operated at 39% recycle of vent gas back to calciner
and rest is released into the atmosphere.
 The vent gas is at a very high temperature of 260°C so this heat can be utilised.
 In calculation the value of the flow rate of vent gas is approximated
to 2500m3/hr.
Heat coming out =
flow rate*density*specific heat*(Temp. Of vent gas-Reference temp)
Heat required by FBD
The main objective of FBD is to remove moisture of material and
for which hot air is passed through FBD.
So the heat load on FBD can be calculated in two ways:
1. Heat required by material.
2. Heat supplied to air by burner
552 kg/hr
T = 25°C
T = 60 °C
Heat required by FBD
1. Calculating Heat required by Material
Control Volume
Mixing
Chamber
Assumption
 Heat capacity of material in and out are same.
 In the FBD only moisture gets removed, no CO2 removal.
 The amount of material being carried to the cyclone separator by air is
negligible.
NOTE: The analysis is based on the data taken from 7-june-2015 to 14-
june-2015.
Formulae used
Heat load on FBD = heat needed to vaporise water +
heat needed to raise material temp.
Heat needed to vaporise water
= water to be vaporised *latent heat of vaporisation of water
Heat needed to raise material temp. =
mass flow rate of material*specific heat of material*(outlet temp. - inlet temp.)
Heat required by FBD
Material flow rate(kg/hr) 552. 00
Temperature at inlet(°C) 25.00
Temperature at outlet(°C) 60.00
Moisture content at inlet (%) 18.00
Moisture content at outlet(%) 2.00
water to be vaporised(kg/hr) 88.32
Latent heat of vaporisation(KJ/kg) 2,258.00
Heat needed to vaporise water(KJ/hr) 1,99,426.56
Cp of material(KJ/kgK) 0.85
Mass of dry Solid (kg/hr) 452.64
Heat needed by material(kg/hr) 13,488.22
Heat load on FBD (kg/hr) 2,12,914.78
Approximately 2.2 lakh kilo Joule of heat needed to be supplied to
the materiall
Heat required by FBD
2. Calculating Heat supplied to air by burner
7300m3/hr
T = 61°C
T = 35°C
T = 35°C
Heat required by FBD
Mixing
Chamber
To calculate the flow rate of air Anemometer was used.
At different positions velocity were taken under following situation
1. The damper at fresh air inlet of fbd was fully opened.
2. The velocity measurements were done after removing the mesh.
Assumption:
1. Considered the pipe to be perfectly cylindrical at the cross section
where velocity was calculated at different points.
2. Flow is Turbulent means flatter velocity profile.
3. The average velocity across the cross section was taken in calculation.
4. The burner is 98% efficient.
Formulae Used:
Flow rate = flow area* average velocity
Heat supplied to air by burner =
air flow rate*density*specific heat of air*(temp. at fbd inlet – fresh air temp.)
Heat required by FBD
Flow rate of air (m3/hr) 7,314.06
Temp of air at inlet(°C) 35.00
Temp of air at fbd in (°C) 61.00
heat supplied to air by burner (KJ/hr) 2,34,117.42
Approximately 2.34 lakh kilo Joule of heat needed to be supplied to be
supplied by the burner.
So, from the two methods of calculation heat required by FBD can be
approximated to 2.34 lakh KJ.
Heat required by FBD
LPG requirement for fulfilling this heat requirement
heat supplied to air by burner (KJ/hr) 2,34,117.42
Calorific value (KJ/kg) 48,070.00
burner efficiency 0.98
LPG required(kg/hr) 4.97
The LPG required by theoretical calculation comes out to be 5kg/hr
Plant LPG totalizer reading for duration under consideration is 2.05kg/hr
but is 4 kg/hr also in other days.
The possible reason for this congruity can be improper calibration of LPG totalizer.
Modification required
Pipe of Length =6m including the two 90°bend.
Diameter of pipe = 300mm excluding insulation, same as diameter of vent line.
The line would be installed diagonally from the point near the place where
the 39% recycle valve is to the point on the roof above which dilution chamber is.
Butterfly valve is required to control flow of gas depending on the temperature
required at FBD inlet.
Fabric filter will be required to remove 70 mg/m3 of particulate matter present
in vent gas.
Line to be added
to present system
Modification Required
Mixing
Chamber
39%
recycle
4500m3/hr
33 – 71%
recycle
Length = 6m
Dia = 300mm
Pressure Drop = PD by fabric filter + 30Pa
2500 m3/hr
Velocity = 10m/s
T=260°C
Modification Required
Flow rate of vent air
= 850- 1800m3/hr
Flow rate of fresh air
= 5550- 6500m3/hr
Flow rate at FBD in
= 7300m3/hr
Mixing
Chamber
Mixing
Chamber
Hot Air
Generator
Burner
Supply Fan
Hot air
Generator
Burne
r
Blower
Ground floor
1st floor
2nd floor
Vent Gas
39% Recycle
L=350m
L=275m
Temp. of air at FBD inlet(°C) 61 90
Temp of vent air(°C) 260 260
Temp. of fresh air(°C) 35 35
Flow rate of vent air (m3/hr) 2500 2500
Flow rate of FBD inlet (°C) 7300 7300
Fraction of vent air 0.33 0.71
Flow rate of vent air(m3/hr) 843.56 1784.4
Flow rate of fresh air (m3/hr) 6,456.4 5515.56
Heat required by FBD(KJ/hr) 2,33,667.5 494296.6
Calorific value KJ/kg 48,070.00 48,070.00
burner efficiency 0.98 0.98
LPG consumption (kg/hr) 4.960188267 10.49270595
LPG consumption per month(kg/month) 3571.335552 7554.748284
cost of LPG(Rs./kg) 40 40
Cost saved (Rs.) per month 1,42,853.42 3,02,189.93
Modification Required
Suggestions
 Screening should be done just after granulation process and
oversized particle should be recycled.
 Can control the burner firing from FBD inlet temp. reading instead
of cyclone inlet temp.
 One RTD should be placed near the outlet of the FBD for getting
correct value of product temp.
Thank You

Mais conteúdo relacionado

Mais procurados

Throttling calorimeter
Throttling calorimeterThrottling calorimeter
Throttling calorimeterKishan Trivedi
 
Improving Efficiency for Boiler and Steam System
Improving Efficiency for Boiler and Steam SystemImproving Efficiency for Boiler and Steam System
Improving Efficiency for Boiler and Steam SystemKamlesh Hariyani
 
A Study of Boiler Efficiency
A Study of Boiler EfficiencyA Study of Boiler Efficiency
A Study of Boiler EfficiencyEthan Grabill
 
Design With Solid works Software and Planning Calculation Analysis of Fire Tu...
Design With Solid works Software and Planning Calculation Analysis of Fire Tu...Design With Solid works Software and Planning Calculation Analysis of Fire Tu...
Design With Solid works Software and Planning Calculation Analysis of Fire Tu...IJRES Journal
 
Atm cooling tower efficiency HZL debari
Atm cooling tower efficiency HZL debariAtm cooling tower efficiency HZL debari
Atm cooling tower efficiency HZL debarimahesh meena
 
Post-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsPost-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsHamid Abroshan
 
waste heat recovery
waste heat recovery waste heat recovery
waste heat recovery Sagar Joshi
 
ALD Vacuum Carburizing and Low Pressure Carburizing | LPC
ALD Vacuum Carburizing and Low Pressure Carburizing | LPCALD Vacuum Carburizing and Low Pressure Carburizing | LPC
ALD Vacuum Carburizing and Low Pressure Carburizing | LPCALD Vacuum Systems Inc.
 
Process Calculation - simple distillation
Process Calculation - simple distillationProcess Calculation - simple distillation
Process Calculation - simple distillationChandran Udumbasseri
 
Eiettore nei sistemi a CO2 - G. De Bona - Danfoss
Eiettore nei sistemi a CO2 - G. De Bona - DanfossEiettore nei sistemi a CO2 - G. De Bona - Danfoss
Eiettore nei sistemi a CO2 - G. De Bona - DanfossCentro Studi Galileo
 
Refrigeration and cold storage
Refrigeration and cold storageRefrigeration and cold storage
Refrigeration and cold storageSachin Bhuva
 
Optimization of Skin Condenser Using Bundy Tube In Place Of Copper Tube
Optimization of Skin Condenser Using Bundy Tube In Place Of Copper TubeOptimization of Skin Condenser Using Bundy Tube In Place Of Copper Tube
Optimization of Skin Condenser Using Bundy Tube In Place Of Copper TubeIJMER
 
Improve Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater PerformanceImprove Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater PerformanceAditya Shah
 
Practrical1
Practrical1Practrical1
Practrical1sydur10
 
Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...
Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...
Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...IJERA Editor
 
DESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZERDESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZERGopi Chand
 

Mais procurados (20)

Throttling calorimeter
Throttling calorimeterThrottling calorimeter
Throttling calorimeter
 
Improving Efficiency for Boiler and Steam System
Improving Efficiency for Boiler and Steam SystemImproving Efficiency for Boiler and Steam System
Improving Efficiency for Boiler and Steam System
 
A Study of Boiler Efficiency
A Study of Boiler EfficiencyA Study of Boiler Efficiency
A Study of Boiler Efficiency
 
Energy conservation
Energy conservationEnergy conservation
Energy conservation
 
Design With Solid works Software and Planning Calculation Analysis of Fire Tu...
Design With Solid works Software and Planning Calculation Analysis of Fire Tu...Design With Solid works Software and Planning Calculation Analysis of Fire Tu...
Design With Solid works Software and Planning Calculation Analysis of Fire Tu...
 
Atm cooling tower efficiency HZL debari
Atm cooling tower efficiency HZL debariAtm cooling tower efficiency HZL debari
Atm cooling tower efficiency HZL debari
 
4.1 boiler
4.1 boiler4.1 boiler
4.1 boiler
 
Post-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsPost-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plants
 
waste heat recovery
waste heat recovery waste heat recovery
waste heat recovery
 
ALD Vacuum Carburizing and Low Pressure Carburizing | LPC
ALD Vacuum Carburizing and Low Pressure Carburizing | LPCALD Vacuum Carburizing and Low Pressure Carburizing | LPC
ALD Vacuum Carburizing and Low Pressure Carburizing | LPC
 
Process Calculation - simple distillation
Process Calculation - simple distillationProcess Calculation - simple distillation
Process Calculation - simple distillation
 
Eiettore nei sistemi a CO2 - G. De Bona - Danfoss
Eiettore nei sistemi a CO2 - G. De Bona - DanfossEiettore nei sistemi a CO2 - G. De Bona - Danfoss
Eiettore nei sistemi a CO2 - G. De Bona - Danfoss
 
Refrigeration and cold storage
Refrigeration and cold storageRefrigeration and cold storage
Refrigeration and cold storage
 
Conserve energy
Conserve energyConserve energy
Conserve energy
 
Optimization of Skin Condenser Using Bundy Tube In Place Of Copper Tube
Optimization of Skin Condenser Using Bundy Tube In Place Of Copper TubeOptimization of Skin Condenser Using Bundy Tube In Place Of Copper Tube
Optimization of Skin Condenser Using Bundy Tube In Place Of Copper Tube
 
Improve Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater PerformanceImprove Shale Oil Crude Heater Performance
Improve Shale Oil Crude Heater Performance
 
Whrs final project
Whrs final projectWhrs final project
Whrs final project
 
Practrical1
Practrical1Practrical1
Practrical1
 
Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...
Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...
Effect of Combustion Air Pre-Heating In Carbon Monoxide Emission in Diesel Fi...
 
DESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZERDESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZER
 

Destaque

炉排型污泥焚烧炉设计探讨
炉排型污泥焚烧炉设计探讨炉排型污泥焚烧炉设计探讨
炉排型污泥焚烧炉设计探讨Qiang Niu
 
T 10 kaolin as high performance extender pigment for coatings - by s.v. kam...
T 10   kaolin as high performance extender pigment for coatings - by s.v. kam...T 10   kaolin as high performance extender pigment for coatings - by s.v. kam...
T 10 kaolin as high performance extender pigment for coatings - by s.v. kam...Gn Tewari
 
Portland Cements, Calcium and Magnesium Compounds
Portland Cements, Calcium and Magnesium CompoundsPortland Cements, Calcium and Magnesium Compounds
Portland Cements, Calcium and Magnesium CompoundsZanny Barluado
 
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILNENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILNISA Interchange
 
Burner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsBurner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsGerard B. Hawkins
 
Evaluation of pozzolanic reactivity of calcined kaolinite
Evaluation of pozzolanic reactivity of calcined kaoliniteEvaluation of pozzolanic reactivity of calcined kaolinite
Evaluation of pozzolanic reactivity of calcined kaoliniteeSAT Publishing House
 
HVAC Cooling Load Calculation
HVAC Cooling Load CalculationHVAC Cooling Load Calculation
HVAC Cooling Load CalculationOrange Slides
 

Destaque (12)

炉排型污泥焚烧炉设计探讨
炉排型污泥焚烧炉设计探讨炉排型污泥焚烧炉设计探讨
炉排型污泥焚烧炉设计探讨
 
AUTOMATION of BIOMASS BOILER
AUTOMATION of BIOMASS BOILERAUTOMATION of BIOMASS BOILER
AUTOMATION of BIOMASS BOILER
 
T 10 kaolin as high performance extender pigment for coatings - by s.v. kam...
T 10   kaolin as high performance extender pigment for coatings - by s.v. kam...T 10   kaolin as high performance extender pigment for coatings - by s.v. kam...
T 10 kaolin as high performance extender pigment for coatings - by s.v. kam...
 
Boiler classification by, Engr REHAN Khan salarzai
Boiler classification by, Engr REHAN Khan salarzaiBoiler classification by, Engr REHAN Khan salarzai
Boiler classification by, Engr REHAN Khan salarzai
 
Rotary Dryer Sizing and Design
Rotary Dryer Sizing and DesignRotary Dryer Sizing and Design
Rotary Dryer Sizing and Design
 
Portland Cements, Calcium and Magnesium Compounds
Portland Cements, Calcium and Magnesium CompoundsPortland Cements, Calcium and Magnesium Compounds
Portland Cements, Calcium and Magnesium Compounds
 
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILNENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
 
Burner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsBurner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia Plants
 
Poster presentation
Poster presentationPoster presentation
Poster presentation
 
fluidised bed dryer
fluidised bed dryerfluidised bed dryer
fluidised bed dryer
 
Evaluation of pozzolanic reactivity of calcined kaolinite
Evaluation of pozzolanic reactivity of calcined kaoliniteEvaluation of pozzolanic reactivity of calcined kaolinite
Evaluation of pozzolanic reactivity of calcined kaolinite
 
HVAC Cooling Load Calculation
HVAC Cooling Load CalculationHVAC Cooling Load Calculation
HVAC Cooling Load Calculation
 

Semelhante a priyanka_re-using vent gas

Aph operation and emergency handling
Aph operation and emergency handlingAph operation and emergency handling
Aph operation and emergency handlingParag Agrawal
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetdrazil
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetRohit Meena
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetRohit Meena
 
RE NEXT_WHRS_Paint 24-02-20.pptx
RE NEXT_WHRS_Paint 24-02-20.pptxRE NEXT_WHRS_Paint 24-02-20.pptx
RE NEXT_WHRS_Paint 24-02-20.pptxKarthikSrinivasan94
 
Paper id 2620141
Paper id 2620141Paper id 2620141
Paper id 2620141IJRAT
 
Separating and throttling calorimeter for steam
Separating and throttling calorimeter for steamSeparating and throttling calorimeter for steam
Separating and throttling calorimeter for steamSaif al-din ali
 
Report on Industrial Training
Report on Industrial TrainingReport on Industrial Training
Report on Industrial TrainingNashiyat Fyza
 
boiler and cogeneration training material
boiler and cogeneration training materialboiler and cogeneration training material
boiler and cogeneration training materialHarshit Kumar Mishra
 
case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)Vikram Kataria
 
Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)SANDEEP YADAV
 
IJSRED-V2I5P17
IJSRED-V2I5P17IJSRED-V2I5P17
IJSRED-V2I5P17IJSRED
 
Multipurpose Device Using Single Vapor Compression Refrigeration Cycle
Multipurpose Device Using Single Vapor Compression Refrigeration CycleMultipurpose Device Using Single Vapor Compression Refrigeration Cycle
Multipurpose Device Using Single Vapor Compression Refrigeration CycleIRJET Journal
 
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]IJMER
 
WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL
WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL
WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL IAEME Publication
 
Board exam on druyers
Board exam on druyersBoard exam on druyers
Board exam on druyersCharltonInao1
 

Semelhante a priyanka_re-using vent gas (20)

Aph operation and emergency handling
Aph operation and emergency handlingAph operation and emergency handling
Aph operation and emergency handling
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
RE NEXT_WHRS_Paint 24-02-20.pptx
RE NEXT_WHRS_Paint 24-02-20.pptxRE NEXT_WHRS_Paint 24-02-20.pptx
RE NEXT_WHRS_Paint 24-02-20.pptx
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Paper id 2620141
Paper id 2620141Paper id 2620141
Paper id 2620141
 
Separating and throttling calorimeter for steam
Separating and throttling calorimeter for steamSeparating and throttling calorimeter for steam
Separating and throttling calorimeter for steam
 
training report
training reporttraining report
training report
 
Report on Industrial Training
Report on Industrial TrainingReport on Industrial Training
Report on Industrial Training
 
boiler and cogeneration training material
boiler and cogeneration training materialboiler and cogeneration training material
boiler and cogeneration training material
 
case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)case study on dance food processing industry(process integration)
case study on dance food processing industry(process integration)
 
Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
IJSRED-V2I5P17
IJSRED-V2I5P17IJSRED-V2I5P17
IJSRED-V2I5P17
 
Multipurpose Device Using Single Vapor Compression Refrigeration Cycle
Multipurpose Device Using Single Vapor Compression Refrigeration CycleMultipurpose Device Using Single Vapor Compression Refrigeration Cycle
Multipurpose Device Using Single Vapor Compression Refrigeration Cycle
 
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]
 
WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL
WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL
WASTE HEAT RECOVERY TO INCREASE BOILER EFFICIENCY USING BAGASSE AS FUEL
 
30120140502013
3012014050201330120140502013
30120140502013
 
Board exam on druyers
Board exam on druyersBoard exam on druyers
Board exam on druyers
 

priyanka_re-using vent gas

  • 1. Re-Using Vent gas of calciner as heat source for Fluidised bed dryer of Plant-04 MENTOR : Yati varshneya SUBMITTED BY: Priyanka Agrawal
  • 2. Contents 1. Introduction 2. Heat flowing out of calciner vent. 3. Heat required in FBD 4. Modification required 5. Suggestions
  • 3. Introduction  Plant-04 is an absorbent making plant which manufactures chlorine and sulphur guard.  These absorbents are used in the petroleum refineries for absorbing the impurities like sulphur and chlorine from crude oil.  The basic unit operation involved in manufacturing of these absorbent are mixing, Granulation, Drying, Calcination, Screening.
  • 5. Introduction  In plant-04, 5 different types of absorbent are produced which differ in their composition and method of manufacturing.  In manufacturing of two of these products both drying and calcination are required.  So, for this the hot gas coming out of calciner vent can be used as heat source for the fluidised bed dryer.  The production of this product is approximately 200 MT/month and is produced for four months/based on S&OP in a year.
  • 6. Heat flowing out of calciner vent 39% recycle Vent gas ~2500m3/hr T = 260°C 6 lakh KJ T = 700°C Hot gas out 4500m3/hr Schematic Diagram of Calcination Process
  • 7. Heat flowing out of calciner vent Approximately 6 lakh kilo joule of heat is coming out from calciner vent. Blower air quantity (m3/hr) 4500 Recycle value 0.39 Vent gas (m3/hr) 2745 Approx. Vent flow rate (m3/hr) 2500 Temperature of vent gas °C 260 Reference temperature °C 61 Heat coming out (KJ/hr) 6,12,484.7  Presently calciner is operated at 39% recycle of vent gas back to calciner and rest is released into the atmosphere.  The vent gas is at a very high temperature of 260°C so this heat can be utilised.  In calculation the value of the flow rate of vent gas is approximated to 2500m3/hr. Heat coming out = flow rate*density*specific heat*(Temp. Of vent gas-Reference temp)
  • 8. Heat required by FBD The main objective of FBD is to remove moisture of material and for which hot air is passed through FBD. So the heat load on FBD can be calculated in two ways: 1. Heat required by material. 2. Heat supplied to air by burner
  • 9. 552 kg/hr T = 25°C T = 60 °C Heat required by FBD 1. Calculating Heat required by Material Control Volume Mixing Chamber
  • 10. Assumption  Heat capacity of material in and out are same.  In the FBD only moisture gets removed, no CO2 removal.  The amount of material being carried to the cyclone separator by air is negligible. NOTE: The analysis is based on the data taken from 7-june-2015 to 14- june-2015. Formulae used Heat load on FBD = heat needed to vaporise water + heat needed to raise material temp. Heat needed to vaporise water = water to be vaporised *latent heat of vaporisation of water Heat needed to raise material temp. = mass flow rate of material*specific heat of material*(outlet temp. - inlet temp.) Heat required by FBD
  • 11. Material flow rate(kg/hr) 552. 00 Temperature at inlet(°C) 25.00 Temperature at outlet(°C) 60.00 Moisture content at inlet (%) 18.00 Moisture content at outlet(%) 2.00 water to be vaporised(kg/hr) 88.32 Latent heat of vaporisation(KJ/kg) 2,258.00 Heat needed to vaporise water(KJ/hr) 1,99,426.56 Cp of material(KJ/kgK) 0.85 Mass of dry Solid (kg/hr) 452.64 Heat needed by material(kg/hr) 13,488.22 Heat load on FBD (kg/hr) 2,12,914.78 Approximately 2.2 lakh kilo Joule of heat needed to be supplied to the materiall Heat required by FBD
  • 12. 2. Calculating Heat supplied to air by burner 7300m3/hr T = 61°C T = 35°C T = 35°C Heat required by FBD Mixing Chamber
  • 13. To calculate the flow rate of air Anemometer was used. At different positions velocity were taken under following situation 1. The damper at fresh air inlet of fbd was fully opened. 2. The velocity measurements were done after removing the mesh. Assumption: 1. Considered the pipe to be perfectly cylindrical at the cross section where velocity was calculated at different points. 2. Flow is Turbulent means flatter velocity profile. 3. The average velocity across the cross section was taken in calculation. 4. The burner is 98% efficient. Formulae Used: Flow rate = flow area* average velocity Heat supplied to air by burner = air flow rate*density*specific heat of air*(temp. at fbd inlet – fresh air temp.) Heat required by FBD
  • 14. Flow rate of air (m3/hr) 7,314.06 Temp of air at inlet(°C) 35.00 Temp of air at fbd in (°C) 61.00 heat supplied to air by burner (KJ/hr) 2,34,117.42 Approximately 2.34 lakh kilo Joule of heat needed to be supplied to be supplied by the burner. So, from the two methods of calculation heat required by FBD can be approximated to 2.34 lakh KJ. Heat required by FBD LPG requirement for fulfilling this heat requirement heat supplied to air by burner (KJ/hr) 2,34,117.42 Calorific value (KJ/kg) 48,070.00 burner efficiency 0.98 LPG required(kg/hr) 4.97 The LPG required by theoretical calculation comes out to be 5kg/hr Plant LPG totalizer reading for duration under consideration is 2.05kg/hr but is 4 kg/hr also in other days. The possible reason for this congruity can be improper calibration of LPG totalizer.
  • 15. Modification required Pipe of Length =6m including the two 90°bend. Diameter of pipe = 300mm excluding insulation, same as diameter of vent line. The line would be installed diagonally from the point near the place where the 39% recycle valve is to the point on the roof above which dilution chamber is. Butterfly valve is required to control flow of gas depending on the temperature required at FBD inlet. Fabric filter will be required to remove 70 mg/m3 of particulate matter present in vent gas.
  • 16. Line to be added to present system Modification Required Mixing Chamber
  • 17. 39% recycle 4500m3/hr 33 – 71% recycle Length = 6m Dia = 300mm Pressure Drop = PD by fabric filter + 30Pa 2500 m3/hr Velocity = 10m/s T=260°C Modification Required Flow rate of vent air = 850- 1800m3/hr Flow rate of fresh air = 5550- 6500m3/hr Flow rate at FBD in = 7300m3/hr Mixing Chamber
  • 18. Mixing Chamber Hot Air Generator Burner Supply Fan Hot air Generator Burne r Blower Ground floor 1st floor 2nd floor Vent Gas 39% Recycle L=350m L=275m
  • 19. Temp. of air at FBD inlet(°C) 61 90 Temp of vent air(°C) 260 260 Temp. of fresh air(°C) 35 35 Flow rate of vent air (m3/hr) 2500 2500 Flow rate of FBD inlet (°C) 7300 7300 Fraction of vent air 0.33 0.71 Flow rate of vent air(m3/hr) 843.56 1784.4 Flow rate of fresh air (m3/hr) 6,456.4 5515.56 Heat required by FBD(KJ/hr) 2,33,667.5 494296.6 Calorific value KJ/kg 48,070.00 48,070.00 burner efficiency 0.98 0.98 LPG consumption (kg/hr) 4.960188267 10.49270595 LPG consumption per month(kg/month) 3571.335552 7554.748284 cost of LPG(Rs./kg) 40 40 Cost saved (Rs.) per month 1,42,853.42 3,02,189.93 Modification Required
  • 20. Suggestions  Screening should be done just after granulation process and oversized particle should be recycled.  Can control the burner firing from FBD inlet temp. reading instead of cyclone inlet temp.  One RTD should be placed near the outlet of the FBD for getting correct value of product temp.