SlideShare uma empresa Scribd logo
1 de 27
1
Prepared By:
Mr.Premanand Desai L/EE
B.L.D.E.A’s SHREE SANGANABASAVA
MAHA SWAMIJI POLYTECHNIC,
VIJAYAPUR-03
E-mail ID:ssmp.premananddesai@bldea.org
cell no : +91 7892881829
COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T)
UNIT - 03
LIGHTING INSTALLATION
2
COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T)
UNIT - 03
LIGHTING INSTALLATION
3.1 Code of Practice for Lighting Installations.
1. No lighting circuits should contain more than 20 points or 800watt load.
2. Switches must always be placed only on live wires.
3. Each circuit should be provided with a separate cut-out in the distribution board for
their lives wire.
4. When the total load exceeds 8KVA (8KW) for lighting only, three phase supply is to be
taken and the load should be distributed equally over all the three phases.
5. The main switch of the service must be fixed within 150mm from meter Such that it
should be easily accessible to persons to disconnect in case of emergency.
6. The wall plug socket should be of three pin type with the third terminal connected to
earth.
7. The lighting circuit earth should be a separate one.
8. The switch board and plug socket should not be fixed where there are chances of
entering water traces.
9. The power or heating circuit must be drawn separately in A.E.H. installation from the
main board.
10. The switch board must be placed at 1.5M from the ground level.
11. All lamps or fixtures like ceiling fan should have a minimum clearance of 2.5M from floor
level.
12. When the total load exceeds 5KVA the installation must have earth leakage circuit
breaker.
13. The current rating of conductor used should be corresponding to the load connected.
14. All metallic parts such as iron clad or wires, bodies of a starters etc must be earthed
15. All installation must have a miniature circuit breaker corresponding to the load.
Installation having a load more han5 KVA must have E.L.C.B. also.
3
3.2 Interior Wiring
The wiring to be carried out inside the building where the cables are not subjected to
environmental disturbance like rain or sun heat but where safety towards living persons
and protection against mechanical injury to cables are to be given can be called as interior
wiring.
3.2.1 Types Interior Wiring
1. Cleat wiring
2. C.T.S / T.R.S wiring (Batten Wiring)
3. Casing and Capping system wiring.
4. Conduit system wiring.
a. Surface or Open Conduit wiring.
b. Concealed conduit wiring.
1. Cleat wiring
V.I.R.( Vulcanised India Rubber ) or P.V.C (Polyvinyl chloride) wires are drawn in the grooves
of the porcelain cleat which is fixed by screwing the porcelain cleats. Distance between cleats
is to be about 600mm.
Application:
It is used in temporary wiring as it is easier to assemble and dissemble the system. Here the
wiring cost is the cheapest. Temporary loads can easily be connected. However the system
cannot be used for permanent wirings.
2. C.T.S / T.R.S wiring (Batten Wiring)
Here cab tyres sheathed (C.T.S) or tough rubber sheathed (T.R.S) cables are used. These
wires are fixed on varnished Teak wood battens of 15mm thickness with the help of brass
or tin clips of appropriate size.
Application:
Such wiring systems were used for indoor domestic and commercial building lightings.
This is suitable for damp climate but not for outdoor Lighting’s work. This system is
cheaper than case and cap and conduit system but involves skilled labour.
4
3. Casing and Capping system wiring (wood or P.V.C).
V.I.R. Wires will be carried in double or triple groove of teak wood casing and capping.
Casing is fixed to supports by screws. Here the conductors are protected once again by
wood. However, there is risk of being damped and catching fire. Recently teak wood is
replaced by P.V.C for casing and capping system which are having good appearance.
Applications:
It is used in wiring indoor domestic and commercial building lighting’s.
4. Conduit system wiring.
In this system the PVC cables are drawn in conduit pipes
a. Surface or open conduit wiring: The conduit is fixed on support such as wall by means
of saddles. The distance between any two saddles is to be approximately 8OOmms.
PVC cables are drawn in these pipes using Tees (or junction box) and Elbows.
5
b. Concealed conduit wiring: Where the appearance is the main consideration
neglecting the cost, this wiring is preferred. The conduit pipe is concealed in the wall
or R.C.C. which gives protection against mechanical injury, fire and dampness,
simultaneously giving good look. While drawing the pipes in the grooves at the earlier
stage, binding wires are drawn inside the pipes called fish wires through the pipe by
pulling it out, so that the fish wire is taken out when the cables are inserted in the
pipe.
Application:
This system is used in heating circuit wiring and all other power wiring such as
workshop wirings, industrial wiring & pump set wiring etc and also for lighting wirings
of existing building. Here there is a good protection for the cables against mechanical
injuries and fires, and it lasts longer.
3.3 Factors to be considered while selecting the type of wiring system
1. Durability : Type of wiring selected should conform to standard specifications so that
it is durable i.e. without being affected by the weather conditions, fumes etc.,
2. Safety: The wiring must provide safety against leakage, shock and fire hazards for the
operating personal.
3. Appearance : Electrical wiring should give an aesthetic appeal to the interiors
4. Cost : It should not be prohibitively expensive
5. Accessibility: The switches and plug points provided should be easily accessible. There
must be provision for further extension of the wiring system, if necessary.
6. Mechanical Safety: The wiring must be protected against any mechanical damage.
7. Maintenance cost: The maintenance cost should be a minimum.
6
3.4 Materials required for Interior wiring.
1)Casing & capping: Varnished Teak wood case with twin grooves having a cross section
of 4Omm x 12.5mm along with varnished teak wood capping of 4mm thick and
4Omm width.
Or P.V.C case & cap of 30mm width and 11mm depth.
2)Batten for CTS system: Teak wood battens, 15mm thick of appropriate width (Such as
12.5mm, 19mm,25mm etc)
3)Clips for CTS System: Brass (or tin) clips of appropriate length (such as 30mm, 4Omm
etc) of thick (30 or 32 SWG). The unit of clips are in number of boxes (each box
contain 1OO numbers of clips)
4)P.V.C Conduit pipe: Major s specification of the pipe is about the diameter of the pipe
and its thickness
Examples: 1) 2Omm PVC Pipe 2mm thickness 2) 40mm PVC Pipe 3mm thick.
5)Saddles: Saddle material and its thickness and for which pipe it is required is to be
mention.
Examples: Tin saddle 1.5mm thick suitable for 2Omm P.V.C. pipe.
6) Cable: Apart from mentioning the type of insulation used the Conductor material and
size (area of cross section) are of prime importance along with the voltage grade while
specifying a cable. Now days all the conductor are standard (are called multi-strand)
by which both Conductivity (due to skin effect) and flexibility will improve.
The usual copper conductors sizes are 1 sq.mm, 1.5 sq.mm , 2.5 sqmm, 4 sqmm,
6sqmm etc., Similarly usual aluminium conductor sizes are 2.5 sqmm, 4 sqmm,
6sqmm, 10 sqmm, 16 sqmm, 25 sqmm, 35 sqmm, 50 sqmm, 70 sqmm, 95 sqmm, 120
sqmm etc.,
For calculating the size of conductor first the actual current is calculated. Then it is
to be multiplied with a factor called factor of safety which can be taken as 2
approximately to get the current rating required. Then referring the wire table the
size of the conductor can be determined. The present requirement of voltage grade
for cable is 1.1 KV.
7) Lamp holders:
Type : Batten or angle or pendent
Current range : 5A
Material used : Brass or bakelite.
Example: 5A brass batten holder with porcelain base 250 V grade.
7
8) S.P. Switch:
a.Current range : 5A or 15 A
b.No. of way : Single way or two ways.
c. Material used : Fully bakelite or porcelain base with bakelite cover.
d. Type : Tumbler or flush
e. Voltage grade : 250 V
9) D.P. Switch:
a. Current range : 15A , 30A or 60A
b. Type : Flush or Iron clad
c. Voltage grade : 250V
10) Ceiling Rose
a.Current range : 5A
b.No. of way : Two plate or three Plate
c. Material used : Bakelite.
d. Voltage grade : 250 V
Example: 5A, 2-plate, Bakelite ceiling rose 250V
11) Wall plug Socket
a.Current range : 5A or 15A
b.Type : Flush or tumbler
c. No. of Pins : 2-pins or 3-pins or 3/2 pins.
d.Material used : porcelain base Bakelite covered or fully bakelite.
e.Voltage grade : 250 V
12) Fluorescent lamp
a.Wattage of lamp : 20W or 40W
b.Length : 1.2M or 0.6M
c. Number of fixtures : Single or Double
d.Type : Street light fitting, industrial fitting, ordinary fittings.
e.Rated voltage : 230V to 250V
f. Colour of illumination : white or Green or Blue or Red.
13) Incandescent lamp:
a.Wattage of lamp : 15W, 25W, 40W, 60W, 100W, 20OW.
b.Type : Vacuum or gas filled.
c. Voltage rating : 230V to 250V.
d.Operating frequency : 50Hz supply.
8
14) Mercury vapour lamp:
a.Wattage : 80W, 120W, 250W.
b.Voltage rating : 230V or 250V.
c. Operating frequency : 50Hz supply.
d.Complete with choke, condenser, glass doom.
15) Ceiling fan:
a.Sweeping diameter : 900mm, 1050mm, 1200mm, and 1400mm.
b.Wattage : 80W, 100W.
c. Operating voltage : 220V or 250V
d.Operating : 50Hz supply.
e.Type of bearing : Bail bearing or bush bearing.
3.5 Symbols Uses in Interior wiring plan
9
3.5 Adequate lighting
Table 1- Recommended Illumination
Table 2 – Recommended illimitation
10
In order to get adequate lighting following point should be kept in mind
a. Luminaries of higher efficiency and suitable laminators according to purpose are to be
selected.
b. location of fitting to get even illumination.
c. Total illumination required is
(Ø)=
(𝐴𝑟𝑒𝑎 𝑡𝑜 𝑏𝑒 𝑖𝑙𝑙𝑢𝑚𝑖𝑛𝑎𝑡𝑒𝑑 )×(𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑙𝑙𝑢𝑚𝑖𝑛𝑎𝑡𝑖𝑜𝑛 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑)
𝐶𝑜−𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑜𝑓 𝑢𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 ×𝑚𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑓𝑎𝑐𝑡𝑜𝑟
Total wattage required =
Ø
𝐿𝑢𝑚𝑒𝑛𝑜𝑢𝑠 𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 𝑜𝑓 𝑙𝑎𝑚𝑝 𝑖𝑛 𝑙𝑢𝑚𝑒𝑛𝑠/𝑤𝑎𝑡𝑡
3.6 Procedure (only) for converting lighting to AEH installation.
1. Lighting circuit is retained as it is.
2. A separate earthing for power circuit is to be provided.
3. In the overhead service connection cable is to be replaced of sufficient capacity to
receive the total load along with service pipe.
4. A separate main switch capable of withstanding the total load is to be calculated and
estimated.
5. A fuse unit of required rating is to he provided for taking the total present load.
6. Requires addition of a control of suitable rating at the meter board for heating circuit.
7. Energy meters of sufficient capacity is to be replaced.
8. Existing 2-pin plug sockets are replaced by 3-pin plug sockets.
9. If Necessary additional 3-pin plug sockets are to be provided to meet modern house
requirement.
10. Aerial cut out of requisite capacity are to be replaced.
11
3.7 Images of wiring Materials
D.P (Double pole) Switch D.P (Double pole) M.CB
Teak wood Main board
Bulkhead fitting Bakelite Angle Holder Ceiling rose
Fan Regulator (Electronic Type) Three pin Socket S.P Switch
PVC pipe PVC Elbow
PVC Tee
PVC Junction Multistrand PVC wire bundle saddles
Earthing G.I Pipe G.I wire for Earthing Hylam sheet
12
Example : 01
In the below shows figure.1 the plan of the House which is to be wired in Open Conduit /
Surface conduit System for Providing lighting outlets only.
a. List the lighting load
b. Draw the wiring plan
c. Prepare an estimate of cost for the electrification of the lighting outlets.
Figure.1 – plan of the House
Solution :
a) Lighting Load Table
Sl.
No
Place Area in m2 No. of light
point
No. of Fan
point
No. of
Lighting socket
Type of Fitting
1. Verandha 4×2=8 1×40 W
1×60 W
--- --- Bracket fitting
Bulk head fitting
2. Room 3.5×4=14 2×40 W 1×80 W 1×60 W Bracket fitting
Fluorescent fitting
3. Hall 4×3.5=14 2×40 W 1×80 W 1×60 W Bracket fitting
Fluorescent fitting
4. Kitchen 3.5×3=10.5 2×40 W --- 1×60 W Bracket fitting
5. Bath 2.5×1.5=3.75 1×40 W --- --- Bracket fitting
Total Numbers of Points 09 02 03 = 14 Points
Total wattage 380w 160w 180w = 720 watts
Since the Total load is only 720 watts , One circuit is Sufficient.
13
b) Wring Plan
MB - Meter Board , SB - Switch board , ------------------- Lighting Circuit
Assumption :
14
List of Materials
Size of wire for lighting circuit
Load Current =
𝑇𝑜𝑡𝑎𝑙 𝑤𝑎𝑡𝑡𝑎𝑔𝑒
𝑉𝑜𝑙𝑡𝑎𝑔𝑒
=
720
230
= 3.13 𝐴𝑚𝑝𝑠
Taking factor of safety 2
Load current ( 3.13 × 2 = 6.26 Amps
Therefore as per the wiring table 1 mm2 copper wire is selected.
1. 30 Amps , 250 V Flush type Indicator D.P = 01 No.
2. 7A , 1-Phase M.C.B , 250 V grade = 01 No.
3. 375 × 300 × 45 mm Varnished Teak wood Board = 01 No.
4. Bulkhead fitting (porcelain holder, Glass doom) = 01No.
5. 5A, Bakelite Angle Holder 250 Voltage grade (Bracket fitting) = 06 No’s.
6. 5A , 250V Two plate ceiling rose = 04 No’s.
7. Fan Regulator (Electronic Type) = 02 No’s.
8. 5A , 250V Three pin Socket flush type = 03 No’s.
9. 5A , 250V S.P Switch Flush type = 14 No’s.
Table for Calculation of length of 19mm diameter , 2mm thick PVC pipe, Elbows & Tees.
Sl.
No
Place Horizontal as
in plan
Vertical
drop
Vertical
rise
Total length
of pipe
Elbow Tees
1. Verandah 4+2 1 + 0.5 -- 7.5 01 03
2. Room 4 + (1.75×3) 1 0.5 10.75 01 03
3. Hall 4+3.5+(1.75×2) 1 0.5 12.5 03 02
4. Kitchen 3.5+(1.5×2) 1 -- 7.5 02 01
5. Bath &
Passage
1.5+1.5+0.75 -- -- -- 03 --
Total 38.25 10 09
10.19mm diameter , 2mm thick PVC pipe requirement - Adding 5% for wall crossing & wastage
= 38.25+ (38.25×5% ) = 40.16 or say 41 Meter
11. 19mm diameter , 2mm thick Elbow Requirement Adding 5% = 10 + (10×5%)
= 10.5 ≈ 11 Nos.
12.19mm diameter , 2mm thick Tees Requirement Adding 5% = 09 + (9×5%) = 9.45 ≈ 10 Nos.
13. 1 mm2 copper Multistrand PVC wire 1.1K.V voltage Graded = 41 × 3
= 123 /90 =1.36 ≈1.5 Coil
15
14. 19mm tin saddles = 41/0.75 = 54.66 ≈ 55 Nos.
15. Varnished Teak wood round blocks 75dia , 40mm thick = 11 Nos.
16. 250 × 200 × 45 mm Teak wood board = 2 Nos.
17. 150 × 150 × 45 mm Teak wood board = 2 Nos.
18. Length of 40mm dia G.I pipe, 3mm Thick (For earthing) = 1.5 Meter
19. 8 S.W.G – G.I wire (For Earthing ) = 1Kg
20. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, charcoal, salts etc.,
Estimation of cost :
Sl.
No List of Materials with Specification
Quantity Required Rate /
Item
Amount
In `
Quantity Units
1. 30 Amps , 250 V Flush type Indicator D.P 01 No. 450=00 450=00
2. 7A , 1-Phase M.C.B , 250 V Graded 01 No. 500=00 500=00
3. 375 × 300 × 45 mm Varnished Teak wood Board 01 No. 150=00 150=00
4. Bulkhead fitting 01 No. 200=00 200=00
5. 5A, Bakelite Angle Holder 250 Voltage grade 06 Nos. 25=00 150=00
6. 5A , 250V Two plate ceiling rose 04 No’s. 30=00 120=00
7. Fan Regulator (Electronic Type) 02 No’s. 150=00 300=00
8. 5A , 250V Three pin Socket flush type 03 No’s. 35=00 105=00
9. 5A , 250V S.P Switch Flush type 14 No’s. 20=00 280=00
10. 19mm diameter , 2mm thick PVC pipe 41/3 Meter
/
Pieces
25=00 342=00
11. 19mm diameter , 2mm thick Elbow 11 No’s. 05=00 55=00
12. 19mm diameter , 2mm thick Tees 10 No’s. 06=00 60=00
13. 1 mm2 copper Multistrand wire PVC cable
1.1K.V voltage Graded
1.5 Coil 1050=00 1575=00
14. 19mm tin saddles 55 Gross 150=00 150=00
15. Varnished Teak wood round blocks
75diameter, 40mm thick
11 Nos. 20=00 220=00
16. 250 × 200 × 45 mm Teak wood board 02 No’s. 150=00 300=00
17. 150 × 150 × 45 mm Teak wood board 02 No’s. 120=00 240=00
18. 40mm dia. G.I pipe, 3mm Thick (For earthing) 1.5 Meter 200=00 300=00
19. 8 S.W.G - G.I wire (For Earthing ) 01 Kg 150=00 150=00
20. Miscellaneous Materials such as wooden
wedges, Nut bolts ,Screws, Charcoal salts etc.,
Lumpsum -- -- 500=00
21. Contingency @5% on Materials Cost -- -- -- (6147 × 5%)
307=00
22. Labour Charge
a. lighting Points
b. Fixing Meter Board and wiring
c. For Earthing
14
01
--
Nos
No
--
125=00
100=00
250=00
1750=00
100=00
250=00
Grand Total ` 8554=00
Total Estimate of cost is Rupees Eight Thousand Five Hundred Fifty Four only.
16
Example : 02
The accompanying sketch shows the plan of a home. It is to be wired in surface conduit system
as an A.E.H installation with heating load of 1KW at bath and 2KW at kitchen.
a. Propose the load requirement for lighting
b. Draw the wiring diagram.
c. Prepare the schedule of materials for lighting and heating.
d. Prepare the estimate of cost for lighting and heating.
Figure.2 – Plan of the House
Solution :
a) Load Table
lighting Load is Exceeding More than 900Watts , hence Two Sub-circuits are required.
& Heating Circuit Should be drawn separately
Sl.
No
Place Area in
m2
No. of light
points
No. of Fan
points
No. of
Lighting sockets
No. of
heating sockets
Type of Fitting
1. Entrance ---- 1×40 W ---- ---- Bulk head fitting
2. Verandah 08 2×40 W 1×80 W 1×40 W --- Bracket fitting
3. Hall 12 2×40 W 1×80 W 1×40 W --- Fluorescent fitting
4. Kitchen 10 2×40 W 1×80 W
(Exhaust)
1×40 W 1×2KW Fluorescent fitting
5. Bed Room 12 2×40 W
1×40 W
1×80 W 1×40 W --- Fluorescent fitting
Bracket fitting
6. Passage --- 1×40 W --- --- --- Pendent Fitting
7. Bath 03 1×40 W --- --- 1×1KW Bracket fitting
Total Numbers of Points 12 04 04 02 = 22 Points
Total wattage
480w 320w 160w 03KW
= 3960 Watts
Lighting Load = 960Watts Heating Load
17
b) Wring Plan
Lighting Circuit No.1 ------------------ , Lighting Circuit No.2 ->->->->->->->-> , Heating circuit _______________
Lighting Load = 480+320+160 = 960Watts
Heating Load = 2000+1000 =3000 watts = 3KW
Total load on A.E.H installation = 960 + 3000 = 3960 Watts
No. of Lighting Circuit =
𝑇𝑜𝑡𝑎𝑙 𝑙𝑖𝑔ℎ𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑
800
=
960
800
= 1.2 ≈ 𝟐 𝐜𝐢𝐫𝐜𝐮𝐢𝐭𝐬.
No. of Heating Circuit =
𝑇𝑜𝑡𝑎𝑙 𝐻𝑒𝑎𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑
3000
=
3000
3000
= 𝟏 𝐜𝐢𝐫𝐜𝐮𝐢𝐭.
Size of wire for lighting circuit
Load per Circuit =
Total wattage
2
=
960
2
= 𝟒𝟖𝟎 𝐰𝐚𝐭𝐭𝐬 --------------- In Each Lighting Circuit.
Current per circuit =
480
230
= 2.08 Amps
Taking factor of safety 2
Load current ( 2.08 × 2 = 4.16 Amps
Therefore as per the wiring table 1 mm2 copper wire is selected.
18
I . List of Materials (Lighting Circuit)
1. 30 Amps , 250 V Flush type Indicator D.P = 01 No.
2. 5A , 1-Phase M.C.B , 250 V grade = 2 Nos.
3. 450 × 450 × 65 mm Varnished Teak wood Board = 01 No.
4. Bulkhead fitting (porcelain holder, Glass doom) = 01No.
5. 5A, Bakelite Angle Holder 250 Voltage grade (Bracket fitting) = 03 No’s.
6. 5A, Pendent Holder 250 Voltage grade = 01 No.
7. 5A , 250V Two plate ceiling rose = 10 No’s.
8. Fan Regulator (Electronic Type) = 03 No’s.
9. 5A , 250V Three pin Socket flush type = 04 No’s.
10.5A , 250V S.P Switch Flush type = 20 No’s.
Table for Calculation of length of 19mm diameter , 2mm thick PVC pipe, Elbows & Tees.
Sl.
No
Place Horizontal as in plan Vertical
drop
Vertical
rise
Total length
of pipe
Elbow Tees
1. Verandah 1+2+1+1+2=7 1 + 1=2 0.5 9.5 02 01
2. Hall 1.5+1.5+0.5+1.5=5 1 0.5 6.5 01 01
3. Bed 1.5+1.5+1.5+1+1.5=7 1+0.5=1.5 0.5 09 01 01
4. Kitchen 1+1+1.25+1.5+1.5+1.25=7.5 1 0.5 09 01 01
5. Bath 2 1+0.5=1.5 -- 3.5 02 01
6. Passage 0.75+1=1.75 1 0.5 3.25 01 01
Total 40.75 08 06
11.19mm diameter , 2mm thick PVC pipe requirement - Adding 10% for wall crossing &
wastage = 40.75+ (40.75×10% ) = 44.82 or say 45 Meter
12. 19mm diameter, 2mm thick Elbow Requirement Adding 5% = 08 + (08×5%) = 8.4 ≈ 09 Nos.
13. 19mm diameter , 2mm thick Tees Requirement Adding 5% = 06 + (6×5%) = 6.3 ≈ 07 Nos.
14. 1 mm2 copper Multistrand PVC wire 1.1K.V voltage Graded = 45 × 3 = 135/90 = 1.5 Coil
15. 19mm tin saddles = 45/0.75 = 60 Nos.
16. Varnished Teak wood round blocks 75dia , 40mm thick = 10 Nos.
17. 250 × 200 × 45 mm Teak wood board = 3 Nos.
18. 150 × 150 × 45 mm Teak wood board = 1 Nos.
19
19. 100 × 100 × 45 mm Square Teak wood board = 02 No.
20. Length of 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter
21. 8 S.W.G – G.I wire (For Earthing ) = 1Kg
22. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
Estimation of cost (For Lighting Circuit) :
Sl.
No List of Materials with Specification
Quantity Required Rate /
Item
Amount
In `
Quantity Units
1. 30 Amps , 250 V Flush type Indicator D.P 01 No. 250=00 250=00
2. 5A , 1-Phase M.C.B , 250 V Graded 02 No. 500=00 1000=00
3. 450 × 450 × 65 mm Varnished Teak wood Board 01 No. 150=00 150=00
4. Bulkhead fitting 01 No. 200=00 200=00
5. 5A, Bakelite Angle Holder 250 Voltage grade 03 Nos. 25=00 75=00
6. 5A, Pendent Holder 250 Voltage grade 01 No 20=00 20=00
7. 5A , 250V Two plate ceiling rose 10 No’s. 30=00 300=00
8. Fan Regulator (Electronic Type) 03 No’s. 150=00 450=00
9. 5A , 250V Three pin Socket flush type 04 No’s. 35=00 140=00
10. 5A , 250V S.P Switch Flush type 20 No’s. 20=00 400=00
11. 19mm diameter , 2mm thick PVC pipe 45 /3 Meter/
Pieces
25=00 375=00
12. 19mm diameter , 2mm thick Elbow 09 No’s. 05=00 45=00
13. 19mm diameter , 2mm thick Tees 07 No’s. 06=00 42=00
14. 1 mm2 copper Multistrand wire PVC cable
1.1K.V voltage Graded
1.5 Coil 1050=00 1575=00
15. 19mm tin saddles 60 Gross 150=00 200=00
16. Varnished Teak wood round blocks
75diameter, 40mm thick
10 Nos. 20=00 200=00
17. 250 × 200 × 45 mm Teak wood board 03 No’s. 150=00 450=00
18. 150 × 150 × 45 mm Teak wood board 01 No. 120=00 120=00
19. 100 × 100 × 45 mm Square Teak wood board 02 No’s. 40=00 40=00
20. 40mm dia. G.I pipe, 3mm Thick (For earthing) 1.5 Meter 200=00 300=00
21. 8 S.W.G - G.I wire (For Earthing ) 01 Kg 150=00 150=00
22. Miscellaneous Materials such as wooden
wedges, Nut bolts ,Screws, Charcoal salts etc.,
Lumpsum -- -- 500=00
23. Contingency @5% on Materials Cost -- -- -- (6982 × 5%)
350=00
24. Labour Charge
a. lighting Points
b. Fixing Meter Board and wiring
c. For Earthing work
14
01
--
Nos
No
--
125=00
100=00
250=00
1750=00
100=00
250=00
Total `
9432=00
≈ 9440=00
Total Estimate of cost is Rupees Eight Thousand Five Hundred Thirty Rupees only.
20
II. List of Materials (For Heating circuit)
1. Length of 19mm dia. 2mm thick PVC conduit
= 0.5 +1+2+2+2+2.5+0.5+1 = 11.5 ≈ 04 pieces
2. Size of wire for heating circuit
Load current =
3000
230
= 13.4 𝐴𝑚𝑝𝑠
Allowing factor of safety of 2 ( ×
Therefore From wiring table 4mm2 Copper PVC insulated , 250V wire is selected.
3. Length of wire = Length of Conduit × 3 = 11.5 × 3 = 34.5 meter
4. Conduit accessories :
a. 19mm Bends = 04 Nos.
b. 19mm Junction box = 01 No.
c. 19mm saddles = 12 Nos (Every one Meter one saddle)
5. Wiring Accessories :
a. 3 Pin Socket Flush type , 16A , 250 V = 02 Nos.
b. D.P switch 30A , 250V = 02 Nos.
c. 250mm×250mm×65mm Teak wood board = 02 Nos.
d. M.C.B 20 Amps = 01 No.
e. 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter
f. 8 S.W.G – G.I wire (For Earthing ) = 1Kg
g. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
21
Estimation of cost (For Heating Circuit) :
Sl.
No List of Materials with Specification
Quantity Required Rate /
Item
Amount
In `
Quantity Units
1. 19mm dia. 2mm thick PVC conduit 04 Pieces 45 =00 180=00
2. 4mm2 copper Multistrand wire PVC cable
1.1K.V voltage Graded
34.5 Meter 25=00 863=00
3. 19mm dia. 2mm thick PVC conduit Bend 04 Nos. 08=00 32=00
4. 19 mm Junction Box 01 No. 15=00 15=00
5. 19mm saddles 12 Gross 40=00 40=00
6. Three Pin Socket Flush type 16A , 250 V, 01 No. 100=00 200=00
7. D.P switch Flush Type 30A , 250V 02 Nos. 250=00 500=00
8. 250mm×2500mm×65mm Teak wood board 02 Nos. 150=00 300=00
9. M.C.B 20 Amps 01 No. 1000=00 1000=00
10. 40mm diameter, G.I pipe, 3mm Thick (For
earthing)
2.5 Meter 150=00 375=00
11. 8 S.W.G – G.I wire (For Earthing ) 01 Kg 150=00 150=00
12. Miscellaneous Materials such as wooden
wedges, Nut bolts ,Screws, Charcoal salts etc.,
Lumpsum -- -- 400=00
13. Contingency @5% on Materials Cost -- -- -- (4055 × 5%)
203=00
14. Labour Charge
a. Heating Points
b. For Earthing work
02
--
Nos
--
275=00
250=00
550=00
250=00
Total `
5058=00
≈ 5060=00
Total Estimate of cost is Rupees Five Thousand Sixty Rupees only.
Grand Total :
Estimate of cost for lighting ` 9440 =00
Estimate of Cost for Heating ` 5060= 00
Grand Total ` ` 14,500= 00
Total Estimate of cost is Rupees Fourteen
Thousand Five Hundred Rupees only.
22
Example : 03
The Accompanying sketch shows plan of a residential building, Which has to be wired Up as
A.E.H Installation.
a. Propose the lighting and heating load number of lighting circuit.
b. Draw the wiring plane using standard conventions.
c. Prepare the Schedule of materials for Lighting circuit.
d. Prepare the Schedule of materials for Heating circuit.
Note : Use Concealed Conduit System of wiring
a. Propose the lighting and heating load number of lighting circuit.
lighting Load is 865 Watts , only Sub-circuits are required, because No. of points are 20 only.
& Heating Circuit Should be drawn separately
Sl.
No
Place Area in
m2
No. of light
points
No. of Fan
points
No. of
Lighting sockets
No. of
heating sockets
Type of Fitting
1. Entrance ---- 1×60 W ---- ---- Bulk head fitting
2. Verandah 08 2×40 W ---- ---- --- Pendent fitting
3. Hall 16 2×40 W 1×80 W 2×60 W --- Fluorescent fitting
4. Room 12 1×40 W
1×40 W
1×80 W 1×60 W --- Fluorescent fitting
Angle batten fitting
5. Kitchen 08 2×40 W --- 1×60 W 1×1KW Angle batten fitting
6. Bath 06 1×40 W --- --- 1×2KW Angle Fitting
7. Store 04 1×40 W --- --- --- Pendent Fitting
8. Passage 02 1×25 W --- --- --- Ceiling Fitting
Total Numbers of Points 12 02 04 02 = 20 Points
Total wattage
465w 160w 240w 03KW
= 3865 Watts
Lighting Load = 865 Watts Heating Load
23
Lighting Load = 465+160+240 = 865 Watts
Heating Load = 2000+1000 =3000 watts = 3KW
Total load on A.E.H installation = 865 + 3000 = 3865 Watts
No. of Lighting Circuit =
𝑇𝑜𝑡𝑎𝑙 𝑙𝑖𝑔ℎ𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑
800
=
865
800
= 1.08 ≈ 𝟏 𝐂𝐢𝐫𝐜𝐮𝐢𝐭𝐬.
No. of Heating Circuit =
𝑇𝑜𝑡𝑎𝑙 𝐻𝑒𝑎𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑
3000
=
3000
3000
= 𝟏 𝐜𝐢𝐫𝐜𝐮𝐢𝐭.
Size of wire for lighting circuit
Load Current =
865
230
= 3.76 Amps
Taking factor of safety 2
Load current ( 3.76 × 2 = 7.52 Amps
Therefore as per the wiring table 1.5 mm2 copper PVC 1.1 KV voltage Grade wire is selected.
b. Wiring plane
24
C . Schedule / List of Materials (Lighting Circuit)
1. 30 Amps , 250 V Flush type Indicator D.P = 01 No.
2. 8A, 1-Phase M.C.B , 250 V grade = 1 Nos.
3. 450 × 450 × 45 mm Concealing Teak wood Block with Hylem Cover Plate = 01 No.
4. Bulkhead fitting (porcelain holder, Glass doom) = 01No.
5. 5A, Bakelite Angle Holder 250 Voltage grade (Bracket fitting) = 04 No’s.
6. 5A, Pendent Holder 250 Voltage grade = 02 Nos.
7. 5A, 250V Bakelite Straight batten holder = 01No.
8. 5A , 250V Two plate ceiling rose = 07 No’s.
9. Fan Regulator (Electronic Type) = 02 No’s.
10. 5A , 250V Three pin Socket flush type = 04 No’s.
11. 5A , 250V S.P Switch Flush type = 17 No’s.
Table for Calculation of length of 19mm diameter , 2mm thick PVC pipe, Elbows & Tees.
Sl. No Place Horizontal as in plan Vertical drop Total length of
pipe
Elbow Junction
Box
1. Verandah 2+2 1+1.5+0.5 7 03 03
2. Hall 4+3 1.5+1.5+0.5+0.5 11 04 05
3. Room 1.5+4 1.5+0.5+0.5 08 03 07
4. Kitchen 4+1+1 1.5+0.5+0.5 8.5 05 04
5. Bath 01 0.5 1.5 01 01
6. Store 01 --- 01 -- 01
7. Passage 2+0.5 1.5 04 01 03
Total 14 41 17 24
12. 19mm diameter , 2mm thick PVC pipe requirement - Adding 10% for wall crossing &
wastage = 41+ (41×10% ) = 45.1 or say 46 Meter
13. 19mm diameter, 2mm thick Elbow Requirement = 17 + 3 Extra = 20 Nos.
14. 19mm diameter , 2mm Junction Box Requirement = 24 + 1 Extra = 25 Nos.
15. 1 mm2
copper Multistrand PVC wire 1.1K.V voltage Graded
= 46× 3 = 138/90 = 1.53 Coil or 138 Meter
16. ‘J’ Hooks =
𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒
0.5𝑚
=
14
0.5𝑚
= 28 Nos.
17. Concealing Teak wood round blocks 75dia , 25mm thick = 12 Nos.
18. 100 × 100 × 45 mm Concealing Teak wood board with hylem cover plate = 01 No.
19. 100 × 150 × 45 mm Concealing Teak wood board with hylem cover plate = 01 Nos.
20. 100 × 200 × 45 mm Concealing Teak wood board with hylem cover plate = 03 Nos.
21. 100 × 250 × 45 mm Concealing Teak wood board with hylem cover plate = 01 No
22. Length of 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter
23. 8 S.W.G – G.I wire (For Earthing ) = 1Kg
24. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
25
Estimation of cost (For Lighting Circuit) :
Sl.
No List of Materials with Specification
Quantity Required Rate /
Item
Amount
In `
Quantity Units
1. 30 Amps , 250 V Flush type Indicator D.P 01 No. 250=00 250=00
2. 8A , 1-Phase M.C.B , 250 V Graded 01 No. 1000=00 1000=00
3. 450 × 450 × 45 mm Concealing Teak wood Block
with Hylem Cover Plate
01 No. 300=00 300=00
4. Bulkhead fitting 01 No. 200=00 200=00
5. 5A, Bakelite Angle Holder 250 Voltage grade 04 Nos. 25=00 100=00
6. 5A, Pendent Holder 250 Voltage grade 02 No. 20=00 40=00
7. 5A, 250V Bakelite Straight batten holder 01 No. 20=00 20=00
8. 5A , 250V Two plate ceiling rose 07 No’s. 30=00 210=00
9. Fan Regulator (Electronic Type) 02 No’s. 150=00 300=00
10. 5A , 250V Three pin Socket flush type 04 No’s. 35=00 140=00
11. 5A , 250V S.P Switch Flush type 17 No’s. 20=00 340=00
12. 19mm diameter , 2mm thick PVC pipe 46 /3 Meter/
Pieces
25=00 384=00
13. 19mm diameter , 2mm thick Elbow 20 No’s. 05=00 100=00
14. 19mm diameter , 2mm Junction Box 25 No’s. 10=00 250=00
15. 1 mm2 copper Multistrand wire PVC cable
1.1K.V voltage Graded
1.53 Coil 1050=00 1606=50
16. ‘J’ Hooks 28 Gross 300=00 300=00
17. Concealing Teak wood round blocks 75dia ,
25mm thick
12 Nos. 20=00 240=00
18. 100 × 100 × 45 mm Concealing Teak wood
board with hylem cover plate
01 No. 150=00 150=00
19. 100 × 150 × 45 mm Concealing Teak wood
board with hylem cover plate
01 No. 160=00 160=00
20. 100 × 200 × 45 mm Concealing Teak wood
board with hylem cover plate
03 No’s. 180=00 540=00
21. 40mm dia. G.I pipe, 3mm Thick (For earthing) 1.5 Meter 200=00 300=00
22. 8 S.W.G - G.I wire (For Earthing ) 01 Kg 150=00 150=00
23. Miscellaneous Materials such as wooden
wedges, Nut bolts ,Screws, Charcoal salts etc.,
Lumpsum -- -- 500=00
24. Contingency @5% on Materials Cost -- -- -- (7630 × 5%)
381=50
25. Labour Charge
a. lighting Points
b. Fixing Meter Board and wiring
c. For Earthing work
20
01
--
Nos
No
--
125=00
100=00
250=00
2500=00
100=00
250=00
Total ` 10861=00
Total Estimate of cost is Rupees Ten Thousand Eight Hundred Sixty one Rupees only.
26
d. Schedule / List of Materials (Heating Circuit)
1. length of conduit 25mm Dia, 2mm think PVC
Horizontal length = 4+2+2+4+3= 15meter
Vertical length = 1+1.75+1.75 = 4.5 meter
Add 10% extra for wastage etc., 19.5 × 0.1 = 1.95meter
Total length of conduit = 19.5+1.95 = 21.45 ≈ 22meter = 22/3 ≈ 8 pieces
2.Conduit accessories suitable for 25mm dia. Conduit
Conduit Elbows = 4Nos.
Conduit Junction box = 1No.
‘J’ hooks =
𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒
0.5
=
4.5
0.5
= 𝟗𝐍𝐨𝐬.
3. Size and length of wire for Heating circuit
Load current =
𝑇𝑜𝑡𝑎𝑙 ℎ𝑒𝑎𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑
𝑆𝑢𝑝𝑝𝑙𝑦 𝑉𝑜𝑙𝑡𝑎𝑔𝑒
=
3000
230
=13.04 Amps
Allowing factor of safety of 2 ( ×
4 sq.mm copper PVC insulated 1.1 KV grade wire is Selected
Length of wire is 22 × 3 = 66 Meter
Total Length of wire by adding 5% wastage = 66×0.05= 69.3 ≈70Meter
4. DP switch 15A, 250V Flush type Bakelite = 2Nos.
5. Wall Plug Socket 15A,250V Flush type Bakelite=2Nos.
6. Switch board 150×200×45mm Varnished teak wood with Hylem cover plate 3mm Thick = 2Nos
7. M.C.B 20 Amps = 01 No.
8. 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter
9. 8 S.W.G – G.I wire (For Earthing ) = 1Kg
10. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
27
Estimation of cost (For Heating Circuit) :
Sl.
No List of Materials with Specification
Quantity Required Rate /
Item
Amount
In `
Quantity Units
1. 19mm dia. 2mm thick PVC conduit 08 Pieces 45 =00 360=00
2. 19mm dia. 2mm thick PVC conduit Bend 04 Nos. 08=00 32=00
3. 19 mm Junction Box 01 No. 15=00 15=00
4. 4mm2 copper Multistrand wire PVC cable
1.1K.V voltage Graded
70 Meter 25=00 1750=00
5. ‘J’ hooks 09 Gross 100=00 100=00
6. Three Pin Socket Flush type 16A , 250 V, 01 No. 100=00 200=00
7. D.P switch 30A Flush type, 250V grade 02 Nos. 250=00 500=00
8. 150×200×45mm Varnished teak wood with Hylem
cover plate 3mm
02 Nos. 150=00 300=00
9. M.C.B 20 Amps , 1-Phase 01 No. 1000=00 1000=00
10. 40mm diameter, G.I pipe, 3mm Thick
(For earthing)
2.5 Meter 150=00 375=00
11. 8 S.W.G – G.I wire (For Earthing ) 01 Kg 150=00 150=00
12. Miscellaneous Materials such as wooden
wedges, Nut bolts ,Screws, Charcoal salts etc.,
Lumpsum -- -- 400=00
13. Contingency @5% on Materials Cost -- -- -- (5182 × 5%)
259=00
14. Labour Charge
a. Heating Points
b. For Earthing work
02
--
Nos
--
275=00
250=00
550=00
250=00
Total ` 6241=00
Total Estimate of cost is Rupees Six Thousand Two Hundred forty one Rupees only.
Grand Total :
Estimate of cost for lighting ` 10861 = 00
Estimate of Cost for Heating ` 6241 = 00
Grand Total ` ` 17,102= 00
Total Estimate of cost is Rupees Seventeen
Thousand one Hundred Two Rupees only.

Mais conteúdo relacionado

Mais procurados

Electrical wiring system
Electrical wiring systemElectrical wiring system
Electrical wiring systemshweta saini
 
UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION PremanandDesai
 
HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)Arshad Hussain
 
Electrical wiring domestic and industries
Electrical wiring domestic and industriesElectrical wiring domestic and industries
Electrical wiring domestic and industriesPavan Kumar Mallepoola
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its typesJay Ranvir
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxJeffrey Dorsey
 
Electrical supply & distribution
Electrical supply & distributionElectrical supply & distribution
Electrical supply & distributionYingHongKang
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presentionRazu Khan
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiringPatel Mit
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculationsPankaj Chavan
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineeringNishkam Dhiman
 

Mais procurados (20)

Electrical wiring system
Electrical wiring systemElectrical wiring system
Electrical wiring system
 
ELECTRICAL WIRING
ELECTRICAL WIRINGELECTRICAL WIRING
ELECTRICAL WIRING
 
UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION
 
HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
 
Electrical wiring domestic and industries
Electrical wiring domestic and industriesElectrical wiring domestic and industries
Electrical wiring domestic and industries
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
 
Transformer basic
Transformer basicTransformer basic
Transformer basic
 
Electrical supply & distribution
Electrical supply & distributionElectrical supply & distribution
Electrical supply & distribution
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presention
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
Electric substation
Electric substation Electric substation
Electric substation
 
Distribution System
Distribution SystemDistribution System
Distribution System
 
Electrical Wiring Practices and Diagrams
Electrical Wiring Practices and DiagramsElectrical Wiring Practices and Diagrams
Electrical Wiring Practices and Diagrams
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineering
 
Industrial wiring
Industrial wiringIndustrial wiring
Industrial wiring
 
Panel designing
Panel designingPanel designing
Panel designing
 
Power cables
Power cablesPower cables
Power cables
 

Semelhante a UNIT - 03 LIGHTING INSTALLATION

Electrical wiring system - and estimation
Electrical wiring system -  and estimation Electrical wiring system -  and estimation
Electrical wiring system - and estimation Mahfuz Sikder
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiringAbhidada123
 
Electrical services WITH WIRING FUSES DISTRIBUTION SYSTEMS
Electrical services WITH WIRING FUSES DISTRIBUTION SYSTEMSElectrical services WITH WIRING FUSES DISTRIBUTION SYSTEMS
Electrical services WITH WIRING FUSES DISTRIBUTION SYSTEMSMADHUMITHA355894
 
WIRING SYSTEM (CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer
     WIRING SYSTEM(CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer     WIRING SYSTEM(CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer
WIRING SYSTEM (CONDUIT AND CASING CAPPING) Working of Fan with Of DimmerEMEY GUJJAR
 
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjCableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjKamalMohamed47
 
Types of Wires and Cables
Types of Wires and CablesTypes of Wires and Cables
Types of Wires and CablesOsama Naseem
 
Presentation on cables
Presentation on cablesPresentation on cables
Presentation on cablesFaizanAli244
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvAlexander Decker
 
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...Mahesh Chandra Manav
 
Domestic wiring
Domestic wiringDomestic wiring
Domestic wiringVima Mali
 
DOMESTIC WIRING
DOMESTIC WIRINGDOMESTIC WIRING
DOMESTIC WIRINGSjcit
 
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...maharshi solanki
 
Underground Cables
Underground Cables Underground Cables
Underground Cables Parth Pawar
 
unit4domesticwiringandinstruments-220608154915-ac268fee.pdf
unit4domesticwiringandinstruments-220608154915-ac268fee.pdfunit4domesticwiringandinstruments-220608154915-ac268fee.pdf
unit4domesticwiringandinstruments-220608154915-ac268fee.pdfraghuRAGHU56
 

Semelhante a UNIT - 03 LIGHTING INSTALLATION (20)

Electrical wiring system - and estimation
Electrical wiring system -  and estimation Electrical wiring system -  and estimation
Electrical wiring system - and estimation
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiring
 
Irfan
IrfanIrfan
Irfan
 
Electrical services WITH WIRING FUSES DISTRIBUTION SYSTEMS
Electrical services WITH WIRING FUSES DISTRIBUTION SYSTEMSElectrical services WITH WIRING FUSES DISTRIBUTION SYSTEMS
Electrical services WITH WIRING FUSES DISTRIBUTION SYSTEMS
 
WIRING SYSTEM (CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer
     WIRING SYSTEM(CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer     WIRING SYSTEM(CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer
WIRING SYSTEM (CONDUIT AND CASING CAPPING) Working of Fan with Of Dimmer
 
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjCableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
 
Types of Wires and Cables
Types of Wires and CablesTypes of Wires and Cables
Types of Wires and Cables
 
System of wiring
System of wiringSystem of wiring
System of wiring
 
Presentation on cables
Presentation on cablesPresentation on cables
Presentation on cables
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
 
Unit I.pdf
Unit I.pdfUnit I.pdf
Unit I.pdf
 
Eat 105 Chapter 3
Eat 105  Chapter 3Eat 105  Chapter 3
Eat 105 Chapter 3
 
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
Iec 62305 for lightning and surge protection follow in india nbc 2016 by bis(...
 
Domestic wiring
Domestic wiringDomestic wiring
Domestic wiring
 
Wiring_Con.ppt
Wiring_Con.pptWiring_Con.ppt
Wiring_Con.ppt
 
DOMESTIC WIRING
DOMESTIC WIRINGDOMESTIC WIRING
DOMESTIC WIRING
 
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
 
Residential wiring PPT.pptx
Residential wiring PPT.pptxResidential wiring PPT.pptx
Residential wiring PPT.pptx
 
Underground Cables
Underground Cables Underground Cables
Underground Cables
 
unit4domesticwiringandinstruments-220608154915-ac268fee.pdf
unit4domesticwiringandinstruments-220608154915-ac268fee.pdfunit4domesticwiringandinstruments-220608154915-ac268fee.pdf
unit4domesticwiringandinstruments-220608154915-ac268fee.pdf
 

Mais de PremanandDesai

Week-11 - Assembly drawing - Synchronous Motor
Week-11 - Assembly drawing -  Synchronous Motor Week-11 - Assembly drawing -  Synchronous Motor
Week-11 - Assembly drawing - Synchronous Motor PremanandDesai
 
Week-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsWeek-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsPremanandDesai
 
Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor PremanandDesai
 
Week-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephaseWeek-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephasePremanandDesai
 
Week-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxWeek-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxPremanandDesai
 
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxWeek-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxPremanandDesai
 
Week-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxWeek-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxPremanandDesai
 
Week-04 -Motor control Panel board
Week-04 -Motor control Panel boardWeek-04 -Motor control Panel board
Week-04 -Motor control Panel boardPremanandDesai
 
Week-03 - Electrical wiring of Residential, Hospital , small workshop
Week-03 - Electrical wiring of  Residential, Hospital , small workshopWeek-03 - Electrical wiring of  Residential, Hospital , small workshop
Week-03 - Electrical wiring of Residential, Hospital , small workshopPremanandDesai
 
Week-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsWeek-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsPremanandDesai
 
Week-01 - INTRODUCTION to CAD
Week-01  - INTRODUCTION to CADWeek-01  - INTRODUCTION to CAD
Week-01 - INTRODUCTION to CADPremanandDesai
 
Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP PremanandDesai
 
Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) PremanandDesai
 
Week - 11 - Metering section and Auxiliary Relays
Week  - 11 - Metering section  and Auxiliary RelaysWeek  - 11 - Metering section  and Auxiliary Relays
Week - 11 - Metering section and Auxiliary RelaysPremanandDesai
 
Week 10 - Control Panel & Power gears
Week  10 - Control Panel &  Power gearsWeek  10 - Control Panel &  Power gears
Week 10 - Control Panel & Power gearsPremanandDesai
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - labPremanandDesai
 
Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing PremanandDesai
 
Week- 08 - Feeder protection and Bus–Bar Protection.
Week- 08 - Feeder protection and  Bus–Bar Protection.Week- 08 - Feeder protection and  Bus–Bar Protection.
Week- 08 - Feeder protection and Bus–Bar Protection.PremanandDesai
 
Week 07 - Alternator Protection
Week   07 - Alternator Protection Week   07 - Alternator Protection
Week 07 - Alternator Protection PremanandDesai
 
WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection PremanandDesai
 

Mais de PremanandDesai (20)

Week-11 - Assembly drawing - Synchronous Motor
Week-11 - Assembly drawing -  Synchronous Motor Week-11 - Assembly drawing -  Synchronous Motor
Week-11 - Assembly drawing - Synchronous Motor
 
Week-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsWeek-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - Alternators
 
Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor
 
Week-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephaseWeek-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-Threephase
 
Week-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxWeek-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptx
 
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxWeek-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
 
Week-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxWeek-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptx
 
Week-04 -Motor control Panel board
Week-04 -Motor control Panel boardWeek-04 -Motor control Panel board
Week-04 -Motor control Panel board
 
Week-03 - Electrical wiring of Residential, Hospital , small workshop
Week-03 - Electrical wiring of  Residential, Hospital , small workshopWeek-03 - Electrical wiring of  Residential, Hospital , small workshop
Week-03 - Electrical wiring of Residential, Hospital , small workshop
 
Week-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsWeek-02 - Single line diagram of Substations
Week-02 - Single line diagram of Substations
 
Week-01 - INTRODUCTION to CAD
Week-01  - INTRODUCTION to CADWeek-01  - INTRODUCTION to CAD
Week-01 - INTRODUCTION to CAD
 
Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP
 
Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC)
 
Week - 11 - Metering section and Auxiliary Relays
Week  - 11 - Metering section  and Auxiliary RelaysWeek  - 11 - Metering section  and Auxiliary Relays
Week - 11 - Metering section and Auxiliary Relays
 
Week 10 - Control Panel & Power gears
Week  10 - Control Panel &  Power gearsWeek  10 - Control Panel &  Power gears
Week 10 - Control Panel & Power gears
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
 
Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing
 
Week- 08 - Feeder protection and Bus–Bar Protection.
Week- 08 - Feeder protection and  Bus–Bar Protection.Week- 08 - Feeder protection and  Bus–Bar Protection.
Week- 08 - Feeder protection and Bus–Bar Protection.
 
Week 07 - Alternator Protection
Week   07 - Alternator Protection Week   07 - Alternator Protection
Week 07 - Alternator Protection
 
WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection
 

Último

Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 

Último (20)

Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 

UNIT - 03 LIGHTING INSTALLATION

  • 1. 1 Prepared By: Mr.Premanand Desai L/EE B.L.D.E.A’s SHREE SANGANABASAVA MAHA SWAMIJI POLYTECHNIC, VIJAYAPUR-03 E-mail ID:ssmp.premananddesai@bldea.org cell no : +91 7892881829 COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T) UNIT - 03 LIGHTING INSTALLATION
  • 2. 2 COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T) UNIT - 03 LIGHTING INSTALLATION 3.1 Code of Practice for Lighting Installations. 1. No lighting circuits should contain more than 20 points or 800watt load. 2. Switches must always be placed only on live wires. 3. Each circuit should be provided with a separate cut-out in the distribution board for their lives wire. 4. When the total load exceeds 8KVA (8KW) for lighting only, three phase supply is to be taken and the load should be distributed equally over all the three phases. 5. The main switch of the service must be fixed within 150mm from meter Such that it should be easily accessible to persons to disconnect in case of emergency. 6. The wall plug socket should be of three pin type with the third terminal connected to earth. 7. The lighting circuit earth should be a separate one. 8. The switch board and plug socket should not be fixed where there are chances of entering water traces. 9. The power or heating circuit must be drawn separately in A.E.H. installation from the main board. 10. The switch board must be placed at 1.5M from the ground level. 11. All lamps or fixtures like ceiling fan should have a minimum clearance of 2.5M from floor level. 12. When the total load exceeds 5KVA the installation must have earth leakage circuit breaker. 13. The current rating of conductor used should be corresponding to the load connected. 14. All metallic parts such as iron clad or wires, bodies of a starters etc must be earthed 15. All installation must have a miniature circuit breaker corresponding to the load. Installation having a load more han5 KVA must have E.L.C.B. also.
  • 3. 3 3.2 Interior Wiring The wiring to be carried out inside the building where the cables are not subjected to environmental disturbance like rain or sun heat but where safety towards living persons and protection against mechanical injury to cables are to be given can be called as interior wiring. 3.2.1 Types Interior Wiring 1. Cleat wiring 2. C.T.S / T.R.S wiring (Batten Wiring) 3. Casing and Capping system wiring. 4. Conduit system wiring. a. Surface or Open Conduit wiring. b. Concealed conduit wiring. 1. Cleat wiring V.I.R.( Vulcanised India Rubber ) or P.V.C (Polyvinyl chloride) wires are drawn in the grooves of the porcelain cleat which is fixed by screwing the porcelain cleats. Distance between cleats is to be about 600mm. Application: It is used in temporary wiring as it is easier to assemble and dissemble the system. Here the wiring cost is the cheapest. Temporary loads can easily be connected. However the system cannot be used for permanent wirings. 2. C.T.S / T.R.S wiring (Batten Wiring) Here cab tyres sheathed (C.T.S) or tough rubber sheathed (T.R.S) cables are used. These wires are fixed on varnished Teak wood battens of 15mm thickness with the help of brass or tin clips of appropriate size. Application: Such wiring systems were used for indoor domestic and commercial building lightings. This is suitable for damp climate but not for outdoor Lighting’s work. This system is cheaper than case and cap and conduit system but involves skilled labour.
  • 4. 4 3. Casing and Capping system wiring (wood or P.V.C). V.I.R. Wires will be carried in double or triple groove of teak wood casing and capping. Casing is fixed to supports by screws. Here the conductors are protected once again by wood. However, there is risk of being damped and catching fire. Recently teak wood is replaced by P.V.C for casing and capping system which are having good appearance. Applications: It is used in wiring indoor domestic and commercial building lighting’s. 4. Conduit system wiring. In this system the PVC cables are drawn in conduit pipes a. Surface or open conduit wiring: The conduit is fixed on support such as wall by means of saddles. The distance between any two saddles is to be approximately 8OOmms. PVC cables are drawn in these pipes using Tees (or junction box) and Elbows.
  • 5. 5 b. Concealed conduit wiring: Where the appearance is the main consideration neglecting the cost, this wiring is preferred. The conduit pipe is concealed in the wall or R.C.C. which gives protection against mechanical injury, fire and dampness, simultaneously giving good look. While drawing the pipes in the grooves at the earlier stage, binding wires are drawn inside the pipes called fish wires through the pipe by pulling it out, so that the fish wire is taken out when the cables are inserted in the pipe. Application: This system is used in heating circuit wiring and all other power wiring such as workshop wirings, industrial wiring & pump set wiring etc and also for lighting wirings of existing building. Here there is a good protection for the cables against mechanical injuries and fires, and it lasts longer. 3.3 Factors to be considered while selecting the type of wiring system 1. Durability : Type of wiring selected should conform to standard specifications so that it is durable i.e. without being affected by the weather conditions, fumes etc., 2. Safety: The wiring must provide safety against leakage, shock and fire hazards for the operating personal. 3. Appearance : Electrical wiring should give an aesthetic appeal to the interiors 4. Cost : It should not be prohibitively expensive 5. Accessibility: The switches and plug points provided should be easily accessible. There must be provision for further extension of the wiring system, if necessary. 6. Mechanical Safety: The wiring must be protected against any mechanical damage. 7. Maintenance cost: The maintenance cost should be a minimum.
  • 6. 6 3.4 Materials required for Interior wiring. 1)Casing & capping: Varnished Teak wood case with twin grooves having a cross section of 4Omm x 12.5mm along with varnished teak wood capping of 4mm thick and 4Omm width. Or P.V.C case & cap of 30mm width and 11mm depth. 2)Batten for CTS system: Teak wood battens, 15mm thick of appropriate width (Such as 12.5mm, 19mm,25mm etc) 3)Clips for CTS System: Brass (or tin) clips of appropriate length (such as 30mm, 4Omm etc) of thick (30 or 32 SWG). The unit of clips are in number of boxes (each box contain 1OO numbers of clips) 4)P.V.C Conduit pipe: Major s specification of the pipe is about the diameter of the pipe and its thickness Examples: 1) 2Omm PVC Pipe 2mm thickness 2) 40mm PVC Pipe 3mm thick. 5)Saddles: Saddle material and its thickness and for which pipe it is required is to be mention. Examples: Tin saddle 1.5mm thick suitable for 2Omm P.V.C. pipe. 6) Cable: Apart from mentioning the type of insulation used the Conductor material and size (area of cross section) are of prime importance along with the voltage grade while specifying a cable. Now days all the conductor are standard (are called multi-strand) by which both Conductivity (due to skin effect) and flexibility will improve. The usual copper conductors sizes are 1 sq.mm, 1.5 sq.mm , 2.5 sqmm, 4 sqmm, 6sqmm etc., Similarly usual aluminium conductor sizes are 2.5 sqmm, 4 sqmm, 6sqmm, 10 sqmm, 16 sqmm, 25 sqmm, 35 sqmm, 50 sqmm, 70 sqmm, 95 sqmm, 120 sqmm etc., For calculating the size of conductor first the actual current is calculated. Then it is to be multiplied with a factor called factor of safety which can be taken as 2 approximately to get the current rating required. Then referring the wire table the size of the conductor can be determined. The present requirement of voltage grade for cable is 1.1 KV. 7) Lamp holders: Type : Batten or angle or pendent Current range : 5A Material used : Brass or bakelite. Example: 5A brass batten holder with porcelain base 250 V grade.
  • 7. 7 8) S.P. Switch: a.Current range : 5A or 15 A b.No. of way : Single way or two ways. c. Material used : Fully bakelite or porcelain base with bakelite cover. d. Type : Tumbler or flush e. Voltage grade : 250 V 9) D.P. Switch: a. Current range : 15A , 30A or 60A b. Type : Flush or Iron clad c. Voltage grade : 250V 10) Ceiling Rose a.Current range : 5A b.No. of way : Two plate or three Plate c. Material used : Bakelite. d. Voltage grade : 250 V Example: 5A, 2-plate, Bakelite ceiling rose 250V 11) Wall plug Socket a.Current range : 5A or 15A b.Type : Flush or tumbler c. No. of Pins : 2-pins or 3-pins or 3/2 pins. d.Material used : porcelain base Bakelite covered or fully bakelite. e.Voltage grade : 250 V 12) Fluorescent lamp a.Wattage of lamp : 20W or 40W b.Length : 1.2M or 0.6M c. Number of fixtures : Single or Double d.Type : Street light fitting, industrial fitting, ordinary fittings. e.Rated voltage : 230V to 250V f. Colour of illumination : white or Green or Blue or Red. 13) Incandescent lamp: a.Wattage of lamp : 15W, 25W, 40W, 60W, 100W, 20OW. b.Type : Vacuum or gas filled. c. Voltage rating : 230V to 250V. d.Operating frequency : 50Hz supply.
  • 8. 8 14) Mercury vapour lamp: a.Wattage : 80W, 120W, 250W. b.Voltage rating : 230V or 250V. c. Operating frequency : 50Hz supply. d.Complete with choke, condenser, glass doom. 15) Ceiling fan: a.Sweeping diameter : 900mm, 1050mm, 1200mm, and 1400mm. b.Wattage : 80W, 100W. c. Operating voltage : 220V or 250V d.Operating : 50Hz supply. e.Type of bearing : Bail bearing or bush bearing. 3.5 Symbols Uses in Interior wiring plan
  • 9. 9 3.5 Adequate lighting Table 1- Recommended Illumination Table 2 – Recommended illimitation
  • 10. 10 In order to get adequate lighting following point should be kept in mind a. Luminaries of higher efficiency and suitable laminators according to purpose are to be selected. b. location of fitting to get even illumination. c. Total illumination required is (Ø)= (𝐴𝑟𝑒𝑎 𝑡𝑜 𝑏𝑒 𝑖𝑙𝑙𝑢𝑚𝑖𝑛𝑎𝑡𝑒𝑑 )×(𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑙𝑙𝑢𝑚𝑖𝑛𝑎𝑡𝑖𝑜𝑛 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑) 𝐶𝑜−𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑜𝑓 𝑢𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 ×𝑚𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑓𝑎𝑐𝑡𝑜𝑟 Total wattage required = Ø 𝐿𝑢𝑚𝑒𝑛𝑜𝑢𝑠 𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 𝑜𝑓 𝑙𝑎𝑚𝑝 𝑖𝑛 𝑙𝑢𝑚𝑒𝑛𝑠/𝑤𝑎𝑡𝑡 3.6 Procedure (only) for converting lighting to AEH installation. 1. Lighting circuit is retained as it is. 2. A separate earthing for power circuit is to be provided. 3. In the overhead service connection cable is to be replaced of sufficient capacity to receive the total load along with service pipe. 4. A separate main switch capable of withstanding the total load is to be calculated and estimated. 5. A fuse unit of required rating is to he provided for taking the total present load. 6. Requires addition of a control of suitable rating at the meter board for heating circuit. 7. Energy meters of sufficient capacity is to be replaced. 8. Existing 2-pin plug sockets are replaced by 3-pin plug sockets. 9. If Necessary additional 3-pin plug sockets are to be provided to meet modern house requirement. 10. Aerial cut out of requisite capacity are to be replaced.
  • 11. 11 3.7 Images of wiring Materials D.P (Double pole) Switch D.P (Double pole) M.CB Teak wood Main board Bulkhead fitting Bakelite Angle Holder Ceiling rose Fan Regulator (Electronic Type) Three pin Socket S.P Switch PVC pipe PVC Elbow PVC Tee PVC Junction Multistrand PVC wire bundle saddles Earthing G.I Pipe G.I wire for Earthing Hylam sheet
  • 12. 12 Example : 01 In the below shows figure.1 the plan of the House which is to be wired in Open Conduit / Surface conduit System for Providing lighting outlets only. a. List the lighting load b. Draw the wiring plan c. Prepare an estimate of cost for the electrification of the lighting outlets. Figure.1 – plan of the House Solution : a) Lighting Load Table Sl. No Place Area in m2 No. of light point No. of Fan point No. of Lighting socket Type of Fitting 1. Verandha 4×2=8 1×40 W 1×60 W --- --- Bracket fitting Bulk head fitting 2. Room 3.5×4=14 2×40 W 1×80 W 1×60 W Bracket fitting Fluorescent fitting 3. Hall 4×3.5=14 2×40 W 1×80 W 1×60 W Bracket fitting Fluorescent fitting 4. Kitchen 3.5×3=10.5 2×40 W --- 1×60 W Bracket fitting 5. Bath 2.5×1.5=3.75 1×40 W --- --- Bracket fitting Total Numbers of Points 09 02 03 = 14 Points Total wattage 380w 160w 180w = 720 watts Since the Total load is only 720 watts , One circuit is Sufficient.
  • 13. 13 b) Wring Plan MB - Meter Board , SB - Switch board , ------------------- Lighting Circuit Assumption :
  • 14. 14 List of Materials Size of wire for lighting circuit Load Current = 𝑇𝑜𝑡𝑎𝑙 𝑤𝑎𝑡𝑡𝑎𝑔𝑒 𝑉𝑜𝑙𝑡𝑎𝑔𝑒 = 720 230 = 3.13 𝐴𝑚𝑝𝑠 Taking factor of safety 2 Load current ( 3.13 × 2 = 6.26 Amps Therefore as per the wiring table 1 mm2 copper wire is selected. 1. 30 Amps , 250 V Flush type Indicator D.P = 01 No. 2. 7A , 1-Phase M.C.B , 250 V grade = 01 No. 3. 375 × 300 × 45 mm Varnished Teak wood Board = 01 No. 4. Bulkhead fitting (porcelain holder, Glass doom) = 01No. 5. 5A, Bakelite Angle Holder 250 Voltage grade (Bracket fitting) = 06 No’s. 6. 5A , 250V Two plate ceiling rose = 04 No’s. 7. Fan Regulator (Electronic Type) = 02 No’s. 8. 5A , 250V Three pin Socket flush type = 03 No’s. 9. 5A , 250V S.P Switch Flush type = 14 No’s. Table for Calculation of length of 19mm diameter , 2mm thick PVC pipe, Elbows & Tees. Sl. No Place Horizontal as in plan Vertical drop Vertical rise Total length of pipe Elbow Tees 1. Verandah 4+2 1 + 0.5 -- 7.5 01 03 2. Room 4 + (1.75×3) 1 0.5 10.75 01 03 3. Hall 4+3.5+(1.75×2) 1 0.5 12.5 03 02 4. Kitchen 3.5+(1.5×2) 1 -- 7.5 02 01 5. Bath & Passage 1.5+1.5+0.75 -- -- -- 03 -- Total 38.25 10 09 10.19mm diameter , 2mm thick PVC pipe requirement - Adding 5% for wall crossing & wastage = 38.25+ (38.25×5% ) = 40.16 or say 41 Meter 11. 19mm diameter , 2mm thick Elbow Requirement Adding 5% = 10 + (10×5%) = 10.5 ≈ 11 Nos. 12.19mm diameter , 2mm thick Tees Requirement Adding 5% = 09 + (9×5%) = 9.45 ≈ 10 Nos. 13. 1 mm2 copper Multistrand PVC wire 1.1K.V voltage Graded = 41 × 3 = 123 /90 =1.36 ≈1.5 Coil
  • 15. 15 14. 19mm tin saddles = 41/0.75 = 54.66 ≈ 55 Nos. 15. Varnished Teak wood round blocks 75dia , 40mm thick = 11 Nos. 16. 250 × 200 × 45 mm Teak wood board = 2 Nos. 17. 150 × 150 × 45 mm Teak wood board = 2 Nos. 18. Length of 40mm dia G.I pipe, 3mm Thick (For earthing) = 1.5 Meter 19. 8 S.W.G – G.I wire (For Earthing ) = 1Kg 20. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, charcoal, salts etc., Estimation of cost : Sl. No List of Materials with Specification Quantity Required Rate / Item Amount In ` Quantity Units 1. 30 Amps , 250 V Flush type Indicator D.P 01 No. 450=00 450=00 2. 7A , 1-Phase M.C.B , 250 V Graded 01 No. 500=00 500=00 3. 375 × 300 × 45 mm Varnished Teak wood Board 01 No. 150=00 150=00 4. Bulkhead fitting 01 No. 200=00 200=00 5. 5A, Bakelite Angle Holder 250 Voltage grade 06 Nos. 25=00 150=00 6. 5A , 250V Two plate ceiling rose 04 No’s. 30=00 120=00 7. Fan Regulator (Electronic Type) 02 No’s. 150=00 300=00 8. 5A , 250V Three pin Socket flush type 03 No’s. 35=00 105=00 9. 5A , 250V S.P Switch Flush type 14 No’s. 20=00 280=00 10. 19mm diameter , 2mm thick PVC pipe 41/3 Meter / Pieces 25=00 342=00 11. 19mm diameter , 2mm thick Elbow 11 No’s. 05=00 55=00 12. 19mm diameter , 2mm thick Tees 10 No’s. 06=00 60=00 13. 1 mm2 copper Multistrand wire PVC cable 1.1K.V voltage Graded 1.5 Coil 1050=00 1575=00 14. 19mm tin saddles 55 Gross 150=00 150=00 15. Varnished Teak wood round blocks 75diameter, 40mm thick 11 Nos. 20=00 220=00 16. 250 × 200 × 45 mm Teak wood board 02 No’s. 150=00 300=00 17. 150 × 150 × 45 mm Teak wood board 02 No’s. 120=00 240=00 18. 40mm dia. G.I pipe, 3mm Thick (For earthing) 1.5 Meter 200=00 300=00 19. 8 S.W.G - G.I wire (For Earthing ) 01 Kg 150=00 150=00 20. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, Charcoal salts etc., Lumpsum -- -- 500=00 21. Contingency @5% on Materials Cost -- -- -- (6147 × 5%) 307=00 22. Labour Charge a. lighting Points b. Fixing Meter Board and wiring c. For Earthing 14 01 -- Nos No -- 125=00 100=00 250=00 1750=00 100=00 250=00 Grand Total ` 8554=00 Total Estimate of cost is Rupees Eight Thousand Five Hundred Fifty Four only.
  • 16. 16 Example : 02 The accompanying sketch shows the plan of a home. It is to be wired in surface conduit system as an A.E.H installation with heating load of 1KW at bath and 2KW at kitchen. a. Propose the load requirement for lighting b. Draw the wiring diagram. c. Prepare the schedule of materials for lighting and heating. d. Prepare the estimate of cost for lighting and heating. Figure.2 – Plan of the House Solution : a) Load Table lighting Load is Exceeding More than 900Watts , hence Two Sub-circuits are required. & Heating Circuit Should be drawn separately Sl. No Place Area in m2 No. of light points No. of Fan points No. of Lighting sockets No. of heating sockets Type of Fitting 1. Entrance ---- 1×40 W ---- ---- Bulk head fitting 2. Verandah 08 2×40 W 1×80 W 1×40 W --- Bracket fitting 3. Hall 12 2×40 W 1×80 W 1×40 W --- Fluorescent fitting 4. Kitchen 10 2×40 W 1×80 W (Exhaust) 1×40 W 1×2KW Fluorescent fitting 5. Bed Room 12 2×40 W 1×40 W 1×80 W 1×40 W --- Fluorescent fitting Bracket fitting 6. Passage --- 1×40 W --- --- --- Pendent Fitting 7. Bath 03 1×40 W --- --- 1×1KW Bracket fitting Total Numbers of Points 12 04 04 02 = 22 Points Total wattage 480w 320w 160w 03KW = 3960 Watts Lighting Load = 960Watts Heating Load
  • 17. 17 b) Wring Plan Lighting Circuit No.1 ------------------ , Lighting Circuit No.2 ->->->->->->->-> , Heating circuit _______________ Lighting Load = 480+320+160 = 960Watts Heating Load = 2000+1000 =3000 watts = 3KW Total load on A.E.H installation = 960 + 3000 = 3960 Watts No. of Lighting Circuit = 𝑇𝑜𝑡𝑎𝑙 𝑙𝑖𝑔ℎ𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑 800 = 960 800 = 1.2 ≈ 𝟐 𝐜𝐢𝐫𝐜𝐮𝐢𝐭𝐬. No. of Heating Circuit = 𝑇𝑜𝑡𝑎𝑙 𝐻𝑒𝑎𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑 3000 = 3000 3000 = 𝟏 𝐜𝐢𝐫𝐜𝐮𝐢𝐭. Size of wire for lighting circuit Load per Circuit = Total wattage 2 = 960 2 = 𝟒𝟖𝟎 𝐰𝐚𝐭𝐭𝐬 --------------- In Each Lighting Circuit. Current per circuit = 480 230 = 2.08 Amps Taking factor of safety 2 Load current ( 2.08 × 2 = 4.16 Amps Therefore as per the wiring table 1 mm2 copper wire is selected.
  • 18. 18 I . List of Materials (Lighting Circuit) 1. 30 Amps , 250 V Flush type Indicator D.P = 01 No. 2. 5A , 1-Phase M.C.B , 250 V grade = 2 Nos. 3. 450 × 450 × 65 mm Varnished Teak wood Board = 01 No. 4. Bulkhead fitting (porcelain holder, Glass doom) = 01No. 5. 5A, Bakelite Angle Holder 250 Voltage grade (Bracket fitting) = 03 No’s. 6. 5A, Pendent Holder 250 Voltage grade = 01 No. 7. 5A , 250V Two plate ceiling rose = 10 No’s. 8. Fan Regulator (Electronic Type) = 03 No’s. 9. 5A , 250V Three pin Socket flush type = 04 No’s. 10.5A , 250V S.P Switch Flush type = 20 No’s. Table for Calculation of length of 19mm diameter , 2mm thick PVC pipe, Elbows & Tees. Sl. No Place Horizontal as in plan Vertical drop Vertical rise Total length of pipe Elbow Tees 1. Verandah 1+2+1+1+2=7 1 + 1=2 0.5 9.5 02 01 2. Hall 1.5+1.5+0.5+1.5=5 1 0.5 6.5 01 01 3. Bed 1.5+1.5+1.5+1+1.5=7 1+0.5=1.5 0.5 09 01 01 4. Kitchen 1+1+1.25+1.5+1.5+1.25=7.5 1 0.5 09 01 01 5. Bath 2 1+0.5=1.5 -- 3.5 02 01 6. Passage 0.75+1=1.75 1 0.5 3.25 01 01 Total 40.75 08 06 11.19mm diameter , 2mm thick PVC pipe requirement - Adding 10% for wall crossing & wastage = 40.75+ (40.75×10% ) = 44.82 or say 45 Meter 12. 19mm diameter, 2mm thick Elbow Requirement Adding 5% = 08 + (08×5%) = 8.4 ≈ 09 Nos. 13. 19mm diameter , 2mm thick Tees Requirement Adding 5% = 06 + (6×5%) = 6.3 ≈ 07 Nos. 14. 1 mm2 copper Multistrand PVC wire 1.1K.V voltage Graded = 45 × 3 = 135/90 = 1.5 Coil 15. 19mm tin saddles = 45/0.75 = 60 Nos. 16. Varnished Teak wood round blocks 75dia , 40mm thick = 10 Nos. 17. 250 × 200 × 45 mm Teak wood board = 3 Nos. 18. 150 × 150 × 45 mm Teak wood board = 1 Nos.
  • 19. 19 19. 100 × 100 × 45 mm Square Teak wood board = 02 No. 20. Length of 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter 21. 8 S.W.G – G.I wire (For Earthing ) = 1Kg 22. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc., Estimation of cost (For Lighting Circuit) : Sl. No List of Materials with Specification Quantity Required Rate / Item Amount In ` Quantity Units 1. 30 Amps , 250 V Flush type Indicator D.P 01 No. 250=00 250=00 2. 5A , 1-Phase M.C.B , 250 V Graded 02 No. 500=00 1000=00 3. 450 × 450 × 65 mm Varnished Teak wood Board 01 No. 150=00 150=00 4. Bulkhead fitting 01 No. 200=00 200=00 5. 5A, Bakelite Angle Holder 250 Voltage grade 03 Nos. 25=00 75=00 6. 5A, Pendent Holder 250 Voltage grade 01 No 20=00 20=00 7. 5A , 250V Two plate ceiling rose 10 No’s. 30=00 300=00 8. Fan Regulator (Electronic Type) 03 No’s. 150=00 450=00 9. 5A , 250V Three pin Socket flush type 04 No’s. 35=00 140=00 10. 5A , 250V S.P Switch Flush type 20 No’s. 20=00 400=00 11. 19mm diameter , 2mm thick PVC pipe 45 /3 Meter/ Pieces 25=00 375=00 12. 19mm diameter , 2mm thick Elbow 09 No’s. 05=00 45=00 13. 19mm diameter , 2mm thick Tees 07 No’s. 06=00 42=00 14. 1 mm2 copper Multistrand wire PVC cable 1.1K.V voltage Graded 1.5 Coil 1050=00 1575=00 15. 19mm tin saddles 60 Gross 150=00 200=00 16. Varnished Teak wood round blocks 75diameter, 40mm thick 10 Nos. 20=00 200=00 17. 250 × 200 × 45 mm Teak wood board 03 No’s. 150=00 450=00 18. 150 × 150 × 45 mm Teak wood board 01 No. 120=00 120=00 19. 100 × 100 × 45 mm Square Teak wood board 02 No’s. 40=00 40=00 20. 40mm dia. G.I pipe, 3mm Thick (For earthing) 1.5 Meter 200=00 300=00 21. 8 S.W.G - G.I wire (For Earthing ) 01 Kg 150=00 150=00 22. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, Charcoal salts etc., Lumpsum -- -- 500=00 23. Contingency @5% on Materials Cost -- -- -- (6982 × 5%) 350=00 24. Labour Charge a. lighting Points b. Fixing Meter Board and wiring c. For Earthing work 14 01 -- Nos No -- 125=00 100=00 250=00 1750=00 100=00 250=00 Total ` 9432=00 ≈ 9440=00 Total Estimate of cost is Rupees Eight Thousand Five Hundred Thirty Rupees only.
  • 20. 20 II. List of Materials (For Heating circuit) 1. Length of 19mm dia. 2mm thick PVC conduit = 0.5 +1+2+2+2+2.5+0.5+1 = 11.5 ≈ 04 pieces 2. Size of wire for heating circuit Load current = 3000 230 = 13.4 𝐴𝑚𝑝𝑠 Allowing factor of safety of 2 ( × Therefore From wiring table 4mm2 Copper PVC insulated , 250V wire is selected. 3. Length of wire = Length of Conduit × 3 = 11.5 × 3 = 34.5 meter 4. Conduit accessories : a. 19mm Bends = 04 Nos. b. 19mm Junction box = 01 No. c. 19mm saddles = 12 Nos (Every one Meter one saddle) 5. Wiring Accessories : a. 3 Pin Socket Flush type , 16A , 250 V = 02 Nos. b. D.P switch 30A , 250V = 02 Nos. c. 250mm×250mm×65mm Teak wood board = 02 Nos. d. M.C.B 20 Amps = 01 No. e. 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter f. 8 S.W.G – G.I wire (For Earthing ) = 1Kg g. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
  • 21. 21 Estimation of cost (For Heating Circuit) : Sl. No List of Materials with Specification Quantity Required Rate / Item Amount In ` Quantity Units 1. 19mm dia. 2mm thick PVC conduit 04 Pieces 45 =00 180=00 2. 4mm2 copper Multistrand wire PVC cable 1.1K.V voltage Graded 34.5 Meter 25=00 863=00 3. 19mm dia. 2mm thick PVC conduit Bend 04 Nos. 08=00 32=00 4. 19 mm Junction Box 01 No. 15=00 15=00 5. 19mm saddles 12 Gross 40=00 40=00 6. Three Pin Socket Flush type 16A , 250 V, 01 No. 100=00 200=00 7. D.P switch Flush Type 30A , 250V 02 Nos. 250=00 500=00 8. 250mm×2500mm×65mm Teak wood board 02 Nos. 150=00 300=00 9. M.C.B 20 Amps 01 No. 1000=00 1000=00 10. 40mm diameter, G.I pipe, 3mm Thick (For earthing) 2.5 Meter 150=00 375=00 11. 8 S.W.G – G.I wire (For Earthing ) 01 Kg 150=00 150=00 12. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, Charcoal salts etc., Lumpsum -- -- 400=00 13. Contingency @5% on Materials Cost -- -- -- (4055 × 5%) 203=00 14. Labour Charge a. Heating Points b. For Earthing work 02 -- Nos -- 275=00 250=00 550=00 250=00 Total ` 5058=00 ≈ 5060=00 Total Estimate of cost is Rupees Five Thousand Sixty Rupees only. Grand Total : Estimate of cost for lighting ` 9440 =00 Estimate of Cost for Heating ` 5060= 00 Grand Total ` ` 14,500= 00 Total Estimate of cost is Rupees Fourteen Thousand Five Hundred Rupees only.
  • 22. 22 Example : 03 The Accompanying sketch shows plan of a residential building, Which has to be wired Up as A.E.H Installation. a. Propose the lighting and heating load number of lighting circuit. b. Draw the wiring plane using standard conventions. c. Prepare the Schedule of materials for Lighting circuit. d. Prepare the Schedule of materials for Heating circuit. Note : Use Concealed Conduit System of wiring a. Propose the lighting and heating load number of lighting circuit. lighting Load is 865 Watts , only Sub-circuits are required, because No. of points are 20 only. & Heating Circuit Should be drawn separately Sl. No Place Area in m2 No. of light points No. of Fan points No. of Lighting sockets No. of heating sockets Type of Fitting 1. Entrance ---- 1×60 W ---- ---- Bulk head fitting 2. Verandah 08 2×40 W ---- ---- --- Pendent fitting 3. Hall 16 2×40 W 1×80 W 2×60 W --- Fluorescent fitting 4. Room 12 1×40 W 1×40 W 1×80 W 1×60 W --- Fluorescent fitting Angle batten fitting 5. Kitchen 08 2×40 W --- 1×60 W 1×1KW Angle batten fitting 6. Bath 06 1×40 W --- --- 1×2KW Angle Fitting 7. Store 04 1×40 W --- --- --- Pendent Fitting 8. Passage 02 1×25 W --- --- --- Ceiling Fitting Total Numbers of Points 12 02 04 02 = 20 Points Total wattage 465w 160w 240w 03KW = 3865 Watts Lighting Load = 865 Watts Heating Load
  • 23. 23 Lighting Load = 465+160+240 = 865 Watts Heating Load = 2000+1000 =3000 watts = 3KW Total load on A.E.H installation = 865 + 3000 = 3865 Watts No. of Lighting Circuit = 𝑇𝑜𝑡𝑎𝑙 𝑙𝑖𝑔ℎ𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑 800 = 865 800 = 1.08 ≈ 𝟏 𝐂𝐢𝐫𝐜𝐮𝐢𝐭𝐬. No. of Heating Circuit = 𝑇𝑜𝑡𝑎𝑙 𝐻𝑒𝑎𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑 3000 = 3000 3000 = 𝟏 𝐜𝐢𝐫𝐜𝐮𝐢𝐭. Size of wire for lighting circuit Load Current = 865 230 = 3.76 Amps Taking factor of safety 2 Load current ( 3.76 × 2 = 7.52 Amps Therefore as per the wiring table 1.5 mm2 copper PVC 1.1 KV voltage Grade wire is selected. b. Wiring plane
  • 24. 24 C . Schedule / List of Materials (Lighting Circuit) 1. 30 Amps , 250 V Flush type Indicator D.P = 01 No. 2. 8A, 1-Phase M.C.B , 250 V grade = 1 Nos. 3. 450 × 450 × 45 mm Concealing Teak wood Block with Hylem Cover Plate = 01 No. 4. Bulkhead fitting (porcelain holder, Glass doom) = 01No. 5. 5A, Bakelite Angle Holder 250 Voltage grade (Bracket fitting) = 04 No’s. 6. 5A, Pendent Holder 250 Voltage grade = 02 Nos. 7. 5A, 250V Bakelite Straight batten holder = 01No. 8. 5A , 250V Two plate ceiling rose = 07 No’s. 9. Fan Regulator (Electronic Type) = 02 No’s. 10. 5A , 250V Three pin Socket flush type = 04 No’s. 11. 5A , 250V S.P Switch Flush type = 17 No’s. Table for Calculation of length of 19mm diameter , 2mm thick PVC pipe, Elbows & Tees. Sl. No Place Horizontal as in plan Vertical drop Total length of pipe Elbow Junction Box 1. Verandah 2+2 1+1.5+0.5 7 03 03 2. Hall 4+3 1.5+1.5+0.5+0.5 11 04 05 3. Room 1.5+4 1.5+0.5+0.5 08 03 07 4. Kitchen 4+1+1 1.5+0.5+0.5 8.5 05 04 5. Bath 01 0.5 1.5 01 01 6. Store 01 --- 01 -- 01 7. Passage 2+0.5 1.5 04 01 03 Total 14 41 17 24 12. 19mm diameter , 2mm thick PVC pipe requirement - Adding 10% for wall crossing & wastage = 41+ (41×10% ) = 45.1 or say 46 Meter 13. 19mm diameter, 2mm thick Elbow Requirement = 17 + 3 Extra = 20 Nos. 14. 19mm diameter , 2mm Junction Box Requirement = 24 + 1 Extra = 25 Nos. 15. 1 mm2 copper Multistrand PVC wire 1.1K.V voltage Graded = 46× 3 = 138/90 = 1.53 Coil or 138 Meter 16. ‘J’ Hooks = 𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒 0.5𝑚 = 14 0.5𝑚 = 28 Nos. 17. Concealing Teak wood round blocks 75dia , 25mm thick = 12 Nos. 18. 100 × 100 × 45 mm Concealing Teak wood board with hylem cover plate = 01 No. 19. 100 × 150 × 45 mm Concealing Teak wood board with hylem cover plate = 01 Nos. 20. 100 × 200 × 45 mm Concealing Teak wood board with hylem cover plate = 03 Nos. 21. 100 × 250 × 45 mm Concealing Teak wood board with hylem cover plate = 01 No 22. Length of 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter 23. 8 S.W.G – G.I wire (For Earthing ) = 1Kg 24. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
  • 25. 25 Estimation of cost (For Lighting Circuit) : Sl. No List of Materials with Specification Quantity Required Rate / Item Amount In ` Quantity Units 1. 30 Amps , 250 V Flush type Indicator D.P 01 No. 250=00 250=00 2. 8A , 1-Phase M.C.B , 250 V Graded 01 No. 1000=00 1000=00 3. 450 × 450 × 45 mm Concealing Teak wood Block with Hylem Cover Plate 01 No. 300=00 300=00 4. Bulkhead fitting 01 No. 200=00 200=00 5. 5A, Bakelite Angle Holder 250 Voltage grade 04 Nos. 25=00 100=00 6. 5A, Pendent Holder 250 Voltage grade 02 No. 20=00 40=00 7. 5A, 250V Bakelite Straight batten holder 01 No. 20=00 20=00 8. 5A , 250V Two plate ceiling rose 07 No’s. 30=00 210=00 9. Fan Regulator (Electronic Type) 02 No’s. 150=00 300=00 10. 5A , 250V Three pin Socket flush type 04 No’s. 35=00 140=00 11. 5A , 250V S.P Switch Flush type 17 No’s. 20=00 340=00 12. 19mm diameter , 2mm thick PVC pipe 46 /3 Meter/ Pieces 25=00 384=00 13. 19mm diameter , 2mm thick Elbow 20 No’s. 05=00 100=00 14. 19mm diameter , 2mm Junction Box 25 No’s. 10=00 250=00 15. 1 mm2 copper Multistrand wire PVC cable 1.1K.V voltage Graded 1.53 Coil 1050=00 1606=50 16. ‘J’ Hooks 28 Gross 300=00 300=00 17. Concealing Teak wood round blocks 75dia , 25mm thick 12 Nos. 20=00 240=00 18. 100 × 100 × 45 mm Concealing Teak wood board with hylem cover plate 01 No. 150=00 150=00 19. 100 × 150 × 45 mm Concealing Teak wood board with hylem cover plate 01 No. 160=00 160=00 20. 100 × 200 × 45 mm Concealing Teak wood board with hylem cover plate 03 No’s. 180=00 540=00 21. 40mm dia. G.I pipe, 3mm Thick (For earthing) 1.5 Meter 200=00 300=00 22. 8 S.W.G - G.I wire (For Earthing ) 01 Kg 150=00 150=00 23. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, Charcoal salts etc., Lumpsum -- -- 500=00 24. Contingency @5% on Materials Cost -- -- -- (7630 × 5%) 381=50 25. Labour Charge a. lighting Points b. Fixing Meter Board and wiring c. For Earthing work 20 01 -- Nos No -- 125=00 100=00 250=00 2500=00 100=00 250=00 Total ` 10861=00 Total Estimate of cost is Rupees Ten Thousand Eight Hundred Sixty one Rupees only.
  • 26. 26 d. Schedule / List of Materials (Heating Circuit) 1. length of conduit 25mm Dia, 2mm think PVC Horizontal length = 4+2+2+4+3= 15meter Vertical length = 1+1.75+1.75 = 4.5 meter Add 10% extra for wastage etc., 19.5 × 0.1 = 1.95meter Total length of conduit = 19.5+1.95 = 21.45 ≈ 22meter = 22/3 ≈ 8 pieces 2.Conduit accessories suitable for 25mm dia. Conduit Conduit Elbows = 4Nos. Conduit Junction box = 1No. ‘J’ hooks = 𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒 0.5 = 4.5 0.5 = 𝟗𝐍𝐨𝐬. 3. Size and length of wire for Heating circuit Load current = 𝑇𝑜𝑡𝑎𝑙 ℎ𝑒𝑎𝑡𝑖𝑛𝑔 𝑙𝑜𝑎𝑑 𝑆𝑢𝑝𝑝𝑙𝑦 𝑉𝑜𝑙𝑡𝑎𝑔𝑒 = 3000 230 =13.04 Amps Allowing factor of safety of 2 ( × 4 sq.mm copper PVC insulated 1.1 KV grade wire is Selected Length of wire is 22 × 3 = 66 Meter Total Length of wire by adding 5% wastage = 66×0.05= 69.3 ≈70Meter 4. DP switch 15A, 250V Flush type Bakelite = 2Nos. 5. Wall Plug Socket 15A,250V Flush type Bakelite=2Nos. 6. Switch board 150×200×45mm Varnished teak wood with Hylem cover plate 3mm Thick = 2Nos 7. M.C.B 20 Amps = 01 No. 8. 40mm diameter, G.I pipe, 3mm Thick (For earthing) = 1.5 Meter 9. 8 S.W.G – G.I wire (For Earthing ) = 1Kg 10. Miscellaneous Materials such as wooden wedges, Nut bolts , Screws, charcoal, salts etc.,
  • 27. 27 Estimation of cost (For Heating Circuit) : Sl. No List of Materials with Specification Quantity Required Rate / Item Amount In ` Quantity Units 1. 19mm dia. 2mm thick PVC conduit 08 Pieces 45 =00 360=00 2. 19mm dia. 2mm thick PVC conduit Bend 04 Nos. 08=00 32=00 3. 19 mm Junction Box 01 No. 15=00 15=00 4. 4mm2 copper Multistrand wire PVC cable 1.1K.V voltage Graded 70 Meter 25=00 1750=00 5. ‘J’ hooks 09 Gross 100=00 100=00 6. Three Pin Socket Flush type 16A , 250 V, 01 No. 100=00 200=00 7. D.P switch 30A Flush type, 250V grade 02 Nos. 250=00 500=00 8. 150×200×45mm Varnished teak wood with Hylem cover plate 3mm 02 Nos. 150=00 300=00 9. M.C.B 20 Amps , 1-Phase 01 No. 1000=00 1000=00 10. 40mm diameter, G.I pipe, 3mm Thick (For earthing) 2.5 Meter 150=00 375=00 11. 8 S.W.G – G.I wire (For Earthing ) 01 Kg 150=00 150=00 12. Miscellaneous Materials such as wooden wedges, Nut bolts ,Screws, Charcoal salts etc., Lumpsum -- -- 400=00 13. Contingency @5% on Materials Cost -- -- -- (5182 × 5%) 259=00 14. Labour Charge a. Heating Points b. For Earthing work 02 -- Nos -- 275=00 250=00 550=00 250=00 Total ` 6241=00 Total Estimate of cost is Rupees Six Thousand Two Hundred forty one Rupees only. Grand Total : Estimate of cost for lighting ` 10861 = 00 Estimate of Cost for Heating ` 6241 = 00 Grand Total ` ` 17,102= 00 Total Estimate of cost is Rupees Seventeen Thousand one Hundred Two Rupees only.