CRITICAL PATH METHOD
Group members:-
• Mayank Jain- 541
• Pranali Patil- 542
• Vivek Khandka - 543
• Abhishek Sable- 544
• Rohan jambhulkar - 545
INTRODUCTION
 The critical path method is the sequence of activities that must be
completed on time in order for the project to be finished by its
deadline
 It helps project manager to schedule activities, allocate resources and
manage risk in a systematic and efficient way
 CPM in watch breaking down a project into individual activities or
tasks, identifying the dependencies between them, estimating their
duration and determining their criticality
 The critical path is determined by calculating the longest path of
critical activities through the project network
Benefits
 Reduce delays
 Visualize dependencies
 Improve organization
 Optimize efficiency
Limitations
 May offer a lack of flexibility.
 Greater potential for delays.
 Increased complexity.
 Reduced resource allocation.
 Great potential for misusing float
Key Steps
 Step 1: Activity specification
 Step 2: Activity sequence establishment
 Step 3: Network diagram
 Step 4: Estimates for each activity
 Step 5: Identification of the critical path
 Step 6: Critical path diagram to show project progresses
Conclusion
 Critical path identification is required for any project-
planning phase. This gives the project management the
correct completion date of the overall project and the
flexibility to float activities.
 A critical path diagram should be constantly updated with
actual information when the project progresses in order
to refine the activity length/project duration predictions.
THANK YOU

Mais conteúdo relacionado

Semelhante a OR presentation.pptx

Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
university(kust)
 

Semelhante a OR presentation.pptx (20)

schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
System Analysis Part 3 Week 3 courseistn
System Analysis Part 3 Week 3 courseistnSystem Analysis Part 3 Week 3 courseistn
System Analysis Part 3 Week 3 courseistn
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Creating value from Software Development though Project management
Creating value from Software Development though Project managementCreating value from Software Development though Project management
Creating value from Software Development though Project management
 
CISA Training - Chapter 3 - 2016
CISA Training - Chapter 3 - 2016CISA Training - Chapter 3 - 2016
CISA Training - Chapter 3 - 2016
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
3.project managementprocess
3.project managementprocess3.project managementprocess
3.project managementprocess
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 

Último

0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Renandantas16
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 

Último (20)

Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 

OR presentation.pptx

  • 1. CRITICAL PATH METHOD Group members:- • Mayank Jain- 541 • Pranali Patil- 542 • Vivek Khandka - 543 • Abhishek Sable- 544 • Rohan jambhulkar - 545
  • 2. INTRODUCTION  The critical path method is the sequence of activities that must be completed on time in order for the project to be finished by its deadline  It helps project manager to schedule activities, allocate resources and manage risk in a systematic and efficient way  CPM in watch breaking down a project into individual activities or tasks, identifying the dependencies between them, estimating their duration and determining their criticality  The critical path is determined by calculating the longest path of critical activities through the project network
  • 3. Benefits  Reduce delays  Visualize dependencies  Improve organization  Optimize efficiency
  • 4. Limitations  May offer a lack of flexibility.  Greater potential for delays.  Increased complexity.  Reduced resource allocation.  Great potential for misusing float
  • 5. Key Steps  Step 1: Activity specification  Step 2: Activity sequence establishment  Step 3: Network diagram  Step 4: Estimates for each activity  Step 5: Identification of the critical path  Step 6: Critical path diagram to show project progresses
  • 6. Conclusion  Critical path identification is required for any project- planning phase. This gives the project management the correct completion date of the overall project and the flexibility to float activities.  A critical path diagram should be constantly updated with actual information when the project progresses in order to refine the activity length/project duration predictions.