TRAINING REPORT
On
A PROJECT ON ROAD WIDENING AND
UPGRADATION
Submitted for partial fulfilment of Awards of
BACHELOR OF TECHNOLOGY
IN
CIVIL ENGINEERING
2017
BY
Pradeep Yadav
(1342100038)
SURYA SCHOOL OF PLANNING ENGINEERING
AND MANAGEMENT
Lucknow
Affiliated to
Dr. A.P.J. Abdul Kalam Technical University,Lucknow
DEPARTMENT OF CIVIL ENGINEERING, SSPEM
ACKNOWLEDGEMENT
In our training period, we had to take the help and Guideline of a Respected
Person, who deserve our greatest gratitude. The completion of this training
gives us much pleasure. We would like to expand our deepest gratitude to all
those who have indirectly guided us in summer training.
Many people, especially our team members itself, have made valuable comment
suggestion on this proposal which gave us an inspiration to improve our
training. We thank all the people for their help directly and indirectly to
complete our trainning.
(SIGNATURE)
DECLARATION
In the city Chandauli the detailed work related to broadening and making rigid
of the 41 KM Chandauli-Saidpur (SH-69) way is mentioned in the no.(1)
8/1/16 to avoid the conjunction on Chandauli-Saidpur road in date 18/7/2016,
from change 4.697 to 12.700m to this way completely under taken by public
work department , a bodyof Government Of Uttar Pradesh.
We declare that this written submission represents ours ideas in our own words
and where others’ ideas or words have been included, we have adequately cited
and referenced the original sources. We also declared that we have adhered to
all principles of academic honesty and integrity and have not misrepresented or
fabricated or falsified any idea/data/fact/source in my submission. we
understand that any violation of the above will cause for disciplinary action by
the institute and can also evoke penal action from the sources which have not
been properly cited or from whom proper permission has not been taken when
needed.
Pradeep Yadav
SPECIFICATION
All the works shall be carried out as per P.W.D/M.O.R.T and H.IRC
detailed specifications and as per latest instructions received from
engineer in chief U.P.P.W.D., Chandauli.
INTRODUCTION
 Complete the project in the specified time horizon and allocated cost.
 Deliver value to the customers by providing excellent customer support.
As well as we know that P.W.D is the another construction of all construction it
will stand after 150 years in the Indian culture to make the faboralors structure ,
and they will develop in accordance of engineer and architecture .Roads are an
integral part of the transport system. A country’s road network should be
efficient in order to maximize economic and social benefits. They play a
significant role in achieving national development and contributing to the
overall performance and social functioning of the community. It is
acknowledged that roads enhance mobility, taking people out of isolation and
therefore poverty. In China for instance, the government has popularized this
belief by emphasizing that for any economy to develop, transport must start off
first which will later stimulate other sectors to develop in an orderly fashion CD
When military officers receive an order to check an area for the safety of the
citizens, they will need roads to get there as soon as possible. By that way
people can stay at their houses safe and sound. So people will love the their
leader and obey the laws of our country Surya School Of Planning &
Engineering Management
CONTENTS
OBJECT-1(ROAD WIDENING)
1.ACKNOWLEDGMENT
2. DECLARATION
3. SPECIFICATION
4.INTRODUCTION
5. DETAIL OF MEASUREMENT
6. PROJECT DRAWING
7. MAP
8. BILL OF QUANTITY
9. RESPONSIBILITY AND OBJECTIVE OF THE PROJECT
10. CONCRETING
11. ABSTRACT OF COST
12. ON SITE EXPERIMENT
a. DETERMINATION OF PENETRATION
b. CONPRESSIVE STRENGTH OF CONCRETE
13. CONCLUSION AND RESULT
14. SITE SAFETY
15. EXPERIENCE
DETAIL OF MEASUREMENT
Name of Items No. Dimension Quantity
L B H/D
1 construction of subgrade
And earthen shoulder with
Approved material obta-
-ined from borrow-
-pits with all lifts and leads
Spreading grading to
Required slope and compacted
To meet requirement of
Table 300-2 as per MORTH
IN CLAUSE NO 305
Km 11L.H.S 1*1 1022.00 6.111 .54 3371.99
R.H.S 1*1 700.00 4.47 .54 1689.6
R.H.S 1*1 322.00 6.11 .54 1062.4
Km 12 L.H.S. 1*1 520.00 6.11 .54 1715.6
R.H.S 1*1 850.00 5.2 .54 2386.8
Km 13 L.H.S. 1*1 700.00 3.87 .54 1462.8
R.H.S. 1*1 700.00 6.11 .54 2309.5
TOTAL = 14925.6 Cum
construction of subgrade
And earthen shoulder with
Approved material obta-
-ined from borrow-
Spreading grading to
Required slope and compacted
To meet requirement of
Table 300-2 as per MORTH
IN CLAUSE NO 305
Km 11 R.H.S. 1*1 700 1.64 1.20 1377.6
Km 12 L.H.S. 1*1 330 0.91 1.2 360.3
Km 13 L.H.S 1*1 700 2.24 1.05 1646.4
TOTAL=3384.36
2earthwork in excavation of
Foundation of structure as per
Drawing and technical specification
Including setting out construction of
Soring and breaking removal of stumps
And other deleterious matter dressing
Of side and bottom backfilling the
Execution earth to the extent
Required and utilising the remaining
Earth locally for road work as per
MORTH clause 304
For drain .9*2 2572 1.5 1.8 13275.38
For duct .9*2 2592 1.20 1.05 5878.60
TOTAL=19154.03cum
3.)removal of universable soil including
Excavation loading and disposal upto
8000M.T.S. lead but excluding
Replacement by suitable soil which
Shall be paid separately as per clause
305 14925.6-3384.3 =11541.26
19154*2/3 =12769.
PROJECT SITE LOCATION
BILL OF QUANTITY
Name of work : Widening and strengthening of Chandauli-Sakaldiha-Saidpur
road (SH-69) in 41 KM
S.No. Name of item Qty. Unit Rate Amount
1. Construction of subgrade and earthen
Shoulder with approved material obtained
From borrowpits with all lifts and leads ,
Spreading ,grading to requireds slope. 14925.66 cum 18.00 268661.6
2 earth work in excavation of foundation of
Structures as per drawing and technical
Specification including settimgout ,
Construction shoring and brasing,removal of
Stumps and other deleterious matter. 19154.03 cum 93.64 1793583.7
3. removal of unserviceabale soil including
Excavation ,loading and disposal. 24310.62 cum 77.00 1871917.7
4 construction of granular subbase by
Providing close graded material ,spreading in
Uniform layer with motor grader on prepared
Surface . 7857.46 cum 3107.00 24413128
5. providing, laying and spreading of graded
Stone aggregrate to wet mixed macadam after
Mixing with four percent cement with water. 3142.98 cum 3755.00 11801904
6 providing and applying primer coat with
Bitumen emulsion on prepared surface of
Including cleaning of road surface . 28857.84 sqm 38.49 1110738
7 providing and applying tach coat with VG-10
Using bitumen distributer on surface. 65683.84 sqm 24.85 2129243.4
8 providing and lying dense graded bituminous
Macadum with 100 T.P.H. batch type H.M.P.
Producing an average output using crushed
Aggregrates of specified grading ,premixed
With bituminous binder as per jobmix and
Transporting the hot mixed toward worksite 2606.79 cum 11200.03 29196132.9
9 plain cement concrement 1:3:6 nominal mix
In foundation with crushed aggregrate 40 mm
Nominal size mechanically mixed, placed in
Foundation and compacted by vibration including
Curing for 14 days . 668.72 cum 5426,19 3628601.78
10 furnishing and placing reinforcement ,cement
Concrete M-20 in superstructure as per drawing
And technical specification . 6511.46 cum 6704.39 43655355.5
11 supplying fitting and placing HYSD bar
Reinforcement in superstructure complete
As per drawing and technical specification. 517.68 MT 62810.28 32515760
12 construction of subsurface drain with pipe
Of 110 mm think,over laid with pre cast
Concrete tiles in cement mortar 1:3. 925.92 RM 367.00 339812.64
13 construction of footpath over R.C.C slab
100mm thick over laid with pre-cast concrete 12602.80 sqm 778.00 9804978.40
RESPONSIBILITY AND OBJECTIVE OF THE PROJECT
Whole construction work shall be carried out as per PUBLIC WORK
DEPARTMENT /M.O.R.T. and H./I.R.C. and all the construction work related
to this project controlled by these government organisation .
1. With the help of this project the entire way of Chandauli-Gazipur
Highway is divided into six lanes which give results to avoiding all jam
conditions in Chandauli.
2. This project is also considered as to provide proper convenience to
moving traffic from Chandauli-Saidpur and viceversa.
3. In this project work there are also considered the work of expanding the
electric system in Chandauli and as well as to take care off general public
from any disturbance in convenience
4. In this project work there are also including the development of canal
bridge at the Chandauli.
CONCRETING
1 Plain cement concrement 1:3:6 nominal mix in foundation with crushed
aggregate 40 mm nominal size mechanically mixed placed in foundation and
compacted by vibration including curing for 14 days as per MORTH clause no.
408 for drain and duct.
2 plane/reinforced cement concrete M-20 in open foundation complete as per
drawing and technical specification as per MORTH clause 1500.
3 construction of footpath over RCC slab 100 mm thick ,over laid with pre-cast
concrete tiles in cement mortar 1:3 as per MORTH clause 409 The
ABSTRACT OF COST
Name of work – widening and strengthening of Chandauli-Sakaldiha-Saidpur road (SH -69)
in km 41.
SL No.Item of work Amount in Rs.
PART A
1 cost of BOQ 220177679.91
2conten. 1% 2301776.80
3 CESS 1% as per G.O 2057000.00
4 Est. charges 6.875% as per G.O. 25790000.00
5 CDF (Cost DepriciationFund )@
1.5% as per G.O. 3085000.00
TOTAL A = 253311456.71
PART B = 47610269.00
GRAND TOTAL = 300921725.71
SAY = 2842.62 lacks
ON SITE EXPERIMENT
1.DETERMINATION OF PENETRATION
STANDARD
IS: 1203 – 1978
DEFINITION
Penetration of a bituminous material is the distance in tenths of millimeter that
standard needle will penetrate vertically into a sample under standard conditions
of temperature, load and time.
APPARATUS
Standard Penetration apparatus
A metal or glass cylindrical flat-bottomed container essentially with the following
dimensions-
For penetration below 225
Diameter 55mm
Internal depth 35mm
For penetration between 225 and 350
Diameter 70mm
Internal depth 45mm
Needle shall be made up of straight, highly polished, cylindrical, hard steel rod.
Water bath 10 liters capacity thermostatically Controlled and maintained within
the temperature of 25 + 0.10C.
Thermometer capable of reading temperature up to 250 0C.
PROCEDURE
Soften the material to a pouring consistency at a temperature not more than 60 0C
for tars and pitches and not more than 90 0C for bitumen above the approximate
respective softening points.
Stir it thoroughly until it is homogeneous and free from air bubbles and water.
Pour the melt in to the container to a depth of at least 10mm in excess of the
expected penetration.
Protect the sample from dust and allow it to cool in atmosphere at a temperature
between 15 to 30 0C for 11/2 to 2hours for 45mm deep container and 1 to 11/2
hours for 35mm deep container.
Unless otherwise specified carry out testing at a temperature of 25 + 0.1oC.
Place it along with the transfer dish in the water bath at 25 + 0.10C and allow it
remain for 11/2 to 2hours for 45mm deep container and 1 to 11/2 hours for 35mm
deep container.
Fill the transfer dish with water from the water bath to a depth sufficient to cover
the mould completely.
Remove the transfer dish along with the mould from water bath after specified
period of time and put it upon the stand of penetration apparatus.
Adjust the needle (previously washed, cleaned well with benzene and dried) just to
make contact with the surface of the sample.
The sum of the weights of the needle, carrier and super imposed weights i.e. the
total moving weight shall be 100 0.25grams.
Bring the pointer to zero.
Penetration test for bitumen.
Release the needle for five seconds and measure the distance penetrated.
The sum of the weights of the needle, carrier and super imposed weights i.e. the
total moving weight shall be 100 0.25grams.
Bring the pointer to zero.
Penetration test for bitumen.
Release the needle for five seconds and measure the distance penetrated.
Make at least three determinations at points on the surface of the sample not less
than 10mm apart and not less than 10mm from the side of the dish.
After each test, return the sample and transfer dish to the water bath and wash the
needle with benzene and dry.
In case of material of penetration greater than 225 make three determinations on
each of two identical test specimens using a separate needle for each
determination, leaving the needle in the sample on completion of each
determination to avoid disturbance of the specimen.
REPORT
Express the depth of penetration of the needle in tenths of mm.
The value of penetration reported shall be the mean of not less than three
determinations whose values do not differ by more than the difference given
below
Penetration Maximum difference
0 to 49 2
50 to 149 4
150 to 249 6
250 and above 8
PRECISION
The duplicate results should not differ by more than the following
Penetration Repeatability Reproducibility
Below50 1 Unit 4 Units
Above50 3% of their mean 8% of their mean
PRECAUTIONS
If the sample contains extraneous matter, it should be sieved through I.S. Sieve 30
(IS: 460-1962).
To avoid over heating at the bottom of the container, use of an air oven or sand
bath is recommended.
While the needle is penetrating into the sample, if there is any movement of the
container, that determination shall be discarded.
2.COMPRESSIVE STRENGTH OF CONCRETE
concrete is generally subjected to compressive stress when used in the form of concrete or
mortar .
APPRATUS-
For measuring the compressive strength of concrete ,there are used (universal testing
machine)
In addition of these things , there are also used of
1 fineaggregrate sand .
2 Cementing material (cement ).
3 Clean water .
4 Tampering road 5/8”inch
COMPRESSIVE STRENGTH OF 1:3 MORTAR
CURED FOR 3 DAYS-
Compressive strength =3300 psi
CURED FOR 3 DAYS- Compressive strength=5900psi
CONCLUSION AND RESULTS
After developing this project –
1 The entire way of Railway Crossing intersection is divided into 4 lanes which
gives results to avoiding the all zam conditions in Chandauli
2 There are also considered as to provide proper convenience to moving traffic
from Chandauli to Gazipur.
3. There are providing the well develop proper way , for the same industrial
area like Mughalsarai , Ramnagar ,Chandhasi etc.
4. There are more saving of time and energy.
SITE SAFETY
 All visiotors and deliveries must to the site office.
 Safety helmets must be worn on this site.
 Safety footware must be worn on this site.
 High visibility garments must be worn on this site.
 Unauthorised entry to this site is strictly forbidden.
 No smoking on this site.
EXPERIENCE
This is very wonderful experiance . I felt very comfortable with engineers and
labours at Chandauli site .The engineers detected to us sincerely all things and
at govering any query and question they easely solve it with in simple words .
there are also available the primary medical treatment at the site in the condition
for any injuries and it is one of the most best condition at the site .
THANK YOU
Sadab

Mais conteúdo relacionado

Mais procurados

CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGEAnkit Gautam
 
A Comparative Analysis on Design of Rigid Runway Pavements
A Comparative Analysis on Design of Rigid Runway PavementsA Comparative Analysis on Design of Rigid Runway Pavements
A Comparative Analysis on Design of Rigid Runway PavementsYash Gang
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
L&t PARKCIRCUS
L&t PARKCIRCUSL&t PARKCIRCUS
L&t PARKCIRCUSRajdip Das
 
China road construction industry report, 2010
China road construction industry report, 2010China road construction industry report, 2010
China road construction industry report, 2010ResearchInChina
 
Dhruv atal 030
Dhruv atal 030Dhruv atal 030
Dhruv atal 030DRatal2505
 
Internship Report
Internship ReportInternship Report
Internship Reportprathagarg
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th semRajat kashv
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2Ravi Mehta
 
Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)Er Mohtisham Ali
 
Report on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaReport on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaNarayan Gupta
 
Traning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementTraning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementNIWASHISH VISWAS
 
Summer traning report
Summer traning reportSummer traning report
Summer traning reportAmit Raj
 
Materials investigation and pavement design for upgrading Gachororo road to b...
Materials investigation and pavement design for upgrading Gachororo road to b...Materials investigation and pavement design for upgrading Gachororo road to b...
Materials investigation and pavement design for upgrading Gachororo road to b...byebi basema fabrice
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
Highway construction Report
Highway construction Report Highway construction Report
Highway construction Report Vikas Sukhwal
 

Mais procurados (20)

CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGE
 
A Comparative Analysis on Design of Rigid Runway Pavements
A Comparative Analysis on Design of Rigid Runway PavementsA Comparative Analysis on Design of Rigid Runway Pavements
A Comparative Analysis on Design of Rigid Runway Pavements
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
L&t PARKCIRCUS
L&t PARKCIRCUSL&t PARKCIRCUS
L&t PARKCIRCUS
 
China road construction industry report, 2010
China road construction industry report, 2010China road construction industry report, 2010
China road construction industry report, 2010
 
Dhruv atal 030
Dhruv atal 030Dhruv atal 030
Dhruv atal 030
 
Internship Report
Internship ReportInternship Report
Internship Report
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th sem
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2
 
Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)Summer Training Report (GAMMON INDIA)
Summer Training Report (GAMMON INDIA)
 
Report on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaReport on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL Patna
 
Traning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementTraning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavement
 
Training report 2
Training report 2Training report 2
Training report 2
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
 
Materials investigation and pavement design for upgrading Gachororo road to b...
Materials investigation and pavement design for upgrading Gachororo road to b...Materials investigation and pavement design for upgrading Gachororo road to b...
Materials investigation and pavement design for upgrading Gachororo road to b...
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Highway construction Report
Highway construction Report Highway construction Report
Highway construction Report
 
railway
railwayrailway
railway
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 

Semelhante a Sadab

Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCCRakshita Raghunath
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT Deepak Kumar
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Munir Hussain
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro1392pramod
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methodsHalim Rahman
 
A study on construction of road over bridge by the application of fly ash at ...
A study on construction of road over bridge by the application of fly ash at ...A study on construction of road over bridge by the application of fly ash at ...
A study on construction of road over bridge by the application of fly ash at ...aneesh narayan
 
Project report on CC road
Project report on CC roadProject report on CC road
Project report on CC roadvikash mishra
 
most final report of industrial training for college
most final report of industrial training for collegemost final report of industrial training for college
most final report of industrial training for collegeindrajeet kumar
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering MeasurmentSultan M Muzahir
 
PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUSubhendu Samui
 

Semelhante a Sadab (20)

Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
Bridge report
Bridge reportBridge report
Bridge report
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)
 
Siddharth Srivastava
Siddharth SrivastavaSiddharth Srivastava
Siddharth Srivastava
 
Paper
PaperPaper
Paper
 
Metroppt
MetropptMetroppt
Metroppt
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
 
A study on construction of road over bridge by the application of fly ash at ...
A study on construction of road over bridge by the application of fly ash at ...A study on construction of road over bridge by the application of fly ash at ...
A study on construction of road over bridge by the application of fly ash at ...
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
 
Project report on CC road
Project report on CC roadProject report on CC road
Project report on CC road
 
most final report of industrial training for college
most final report of industrial training for collegemost final report of industrial training for college
most final report of industrial training for college
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDU
 

Sadab

  • 1. TRAINING REPORT On A PROJECT ON ROAD WIDENING AND UPGRADATION Submitted for partial fulfilment of Awards of BACHELOR OF TECHNOLOGY IN CIVIL ENGINEERING 2017 BY Pradeep Yadav (1342100038) SURYA SCHOOL OF PLANNING ENGINEERING AND MANAGEMENT Lucknow Affiliated to Dr. A.P.J. Abdul Kalam Technical University,Lucknow
  • 2. DEPARTMENT OF CIVIL ENGINEERING, SSPEM ACKNOWLEDGEMENT In our training period, we had to take the help and Guideline of a Respected Person, who deserve our greatest gratitude. The completion of this training gives us much pleasure. We would like to expand our deepest gratitude to all those who have indirectly guided us in summer training. Many people, especially our team members itself, have made valuable comment suggestion on this proposal which gave us an inspiration to improve our training. We thank all the people for their help directly and indirectly to complete our trainning. (SIGNATURE)
  • 3. DECLARATION In the city Chandauli the detailed work related to broadening and making rigid of the 41 KM Chandauli-Saidpur (SH-69) way is mentioned in the no.(1) 8/1/16 to avoid the conjunction on Chandauli-Saidpur road in date 18/7/2016, from change 4.697 to 12.700m to this way completely under taken by public work department , a bodyof Government Of Uttar Pradesh. We declare that this written submission represents ours ideas in our own words and where others’ ideas or words have been included, we have adequately cited and referenced the original sources. We also declared that we have adhered to all principles of academic honesty and integrity and have not misrepresented or fabricated or falsified any idea/data/fact/source in my submission. we understand that any violation of the above will cause for disciplinary action by the institute and can also evoke penal action from the sources which have not been properly cited or from whom proper permission has not been taken when needed. Pradeep Yadav
  • 4. SPECIFICATION All the works shall be carried out as per P.W.D/M.O.R.T and H.IRC detailed specifications and as per latest instructions received from engineer in chief U.P.P.W.D., Chandauli.
  • 5.
  • 6. INTRODUCTION  Complete the project in the specified time horizon and allocated cost.  Deliver value to the customers by providing excellent customer support. As well as we know that P.W.D is the another construction of all construction it will stand after 150 years in the Indian culture to make the faboralors structure , and they will develop in accordance of engineer and architecture .Roads are an integral part of the transport system. A country’s road network should be efficient in order to maximize economic and social benefits. They play a significant role in achieving national development and contributing to the overall performance and social functioning of the community. It is acknowledged that roads enhance mobility, taking people out of isolation and therefore poverty. In China for instance, the government has popularized this belief by emphasizing that for any economy to develop, transport must start off first which will later stimulate other sectors to develop in an orderly fashion CD When military officers receive an order to check an area for the safety of the citizens, they will need roads to get there as soon as possible. By that way people can stay at their houses safe and sound. So people will love the their leader and obey the laws of our country Surya School Of Planning & Engineering Management
  • 7. CONTENTS OBJECT-1(ROAD WIDENING) 1.ACKNOWLEDGMENT 2. DECLARATION 3. SPECIFICATION 4.INTRODUCTION 5. DETAIL OF MEASUREMENT 6. PROJECT DRAWING 7. MAP 8. BILL OF QUANTITY 9. RESPONSIBILITY AND OBJECTIVE OF THE PROJECT 10. CONCRETING 11. ABSTRACT OF COST 12. ON SITE EXPERIMENT a. DETERMINATION OF PENETRATION b. CONPRESSIVE STRENGTH OF CONCRETE 13. CONCLUSION AND RESULT 14. SITE SAFETY 15. EXPERIENCE
  • 8.
  • 9. DETAIL OF MEASUREMENT Name of Items No. Dimension Quantity L B H/D 1 construction of subgrade And earthen shoulder with Approved material obta- -ined from borrow- -pits with all lifts and leads Spreading grading to Required slope and compacted To meet requirement of Table 300-2 as per MORTH IN CLAUSE NO 305 Km 11L.H.S 1*1 1022.00 6.111 .54 3371.99 R.H.S 1*1 700.00 4.47 .54 1689.6 R.H.S 1*1 322.00 6.11 .54 1062.4 Km 12 L.H.S. 1*1 520.00 6.11 .54 1715.6 R.H.S 1*1 850.00 5.2 .54 2386.8 Km 13 L.H.S. 1*1 700.00 3.87 .54 1462.8 R.H.S. 1*1 700.00 6.11 .54 2309.5 TOTAL = 14925.6 Cum construction of subgrade And earthen shoulder with Approved material obta- -ined from borrow-
  • 10. Spreading grading to Required slope and compacted To meet requirement of Table 300-2 as per MORTH IN CLAUSE NO 305 Km 11 R.H.S. 1*1 700 1.64 1.20 1377.6 Km 12 L.H.S. 1*1 330 0.91 1.2 360.3 Km 13 L.H.S 1*1 700 2.24 1.05 1646.4 TOTAL=3384.36 2earthwork in excavation of Foundation of structure as per Drawing and technical specification Including setting out construction of Soring and breaking removal of stumps And other deleterious matter dressing Of side and bottom backfilling the Execution earth to the extent Required and utilising the remaining Earth locally for road work as per MORTH clause 304 For drain .9*2 2572 1.5 1.8 13275.38 For duct .9*2 2592 1.20 1.05 5878.60 TOTAL=19154.03cum
  • 11. 3.)removal of universable soil including Excavation loading and disposal upto 8000M.T.S. lead but excluding Replacement by suitable soil which Shall be paid separately as per clause 305 14925.6-3384.3 =11541.26 19154*2/3 =12769.
  • 13. BILL OF QUANTITY Name of work : Widening and strengthening of Chandauli-Sakaldiha-Saidpur road (SH-69) in 41 KM S.No. Name of item Qty. Unit Rate Amount 1. Construction of subgrade and earthen Shoulder with approved material obtained From borrowpits with all lifts and leads , Spreading ,grading to requireds slope. 14925.66 cum 18.00 268661.6 2 earth work in excavation of foundation of Structures as per drawing and technical Specification including settimgout , Construction shoring and brasing,removal of Stumps and other deleterious matter. 19154.03 cum 93.64 1793583.7 3. removal of unserviceabale soil including Excavation ,loading and disposal. 24310.62 cum 77.00 1871917.7 4 construction of granular subbase by Providing close graded material ,spreading in Uniform layer with motor grader on prepared Surface . 7857.46 cum 3107.00 24413128 5. providing, laying and spreading of graded Stone aggregrate to wet mixed macadam after Mixing with four percent cement with water. 3142.98 cum 3755.00 11801904 6 providing and applying primer coat with Bitumen emulsion on prepared surface of Including cleaning of road surface . 28857.84 sqm 38.49 1110738 7 providing and applying tach coat with VG-10 Using bitumen distributer on surface. 65683.84 sqm 24.85 2129243.4
  • 14. 8 providing and lying dense graded bituminous Macadum with 100 T.P.H. batch type H.M.P. Producing an average output using crushed Aggregrates of specified grading ,premixed With bituminous binder as per jobmix and Transporting the hot mixed toward worksite 2606.79 cum 11200.03 29196132.9 9 plain cement concrement 1:3:6 nominal mix In foundation with crushed aggregrate 40 mm Nominal size mechanically mixed, placed in Foundation and compacted by vibration including Curing for 14 days . 668.72 cum 5426,19 3628601.78 10 furnishing and placing reinforcement ,cement Concrete M-20 in superstructure as per drawing And technical specification . 6511.46 cum 6704.39 43655355.5 11 supplying fitting and placing HYSD bar Reinforcement in superstructure complete As per drawing and technical specification. 517.68 MT 62810.28 32515760 12 construction of subsurface drain with pipe Of 110 mm think,over laid with pre cast Concrete tiles in cement mortar 1:3. 925.92 RM 367.00 339812.64 13 construction of footpath over R.C.C slab 100mm thick over laid with pre-cast concrete 12602.80 sqm 778.00 9804978.40
  • 15. RESPONSIBILITY AND OBJECTIVE OF THE PROJECT Whole construction work shall be carried out as per PUBLIC WORK DEPARTMENT /M.O.R.T. and H./I.R.C. and all the construction work related to this project controlled by these government organisation . 1. With the help of this project the entire way of Chandauli-Gazipur Highway is divided into six lanes which give results to avoiding all jam conditions in Chandauli. 2. This project is also considered as to provide proper convenience to moving traffic from Chandauli-Saidpur and viceversa. 3. In this project work there are also considered the work of expanding the electric system in Chandauli and as well as to take care off general public from any disturbance in convenience 4. In this project work there are also including the development of canal bridge at the Chandauli. CONCRETING 1 Plain cement concrement 1:3:6 nominal mix in foundation with crushed aggregate 40 mm nominal size mechanically mixed placed in foundation and compacted by vibration including curing for 14 days as per MORTH clause no. 408 for drain and duct. 2 plane/reinforced cement concrete M-20 in open foundation complete as per drawing and technical specification as per MORTH clause 1500. 3 construction of footpath over RCC slab 100 mm thick ,over laid with pre-cast concrete tiles in cement mortar 1:3 as per MORTH clause 409 The
  • 16. ABSTRACT OF COST Name of work – widening and strengthening of Chandauli-Sakaldiha-Saidpur road (SH -69) in km 41. SL No.Item of work Amount in Rs. PART A 1 cost of BOQ 220177679.91 2conten. 1% 2301776.80 3 CESS 1% as per G.O 2057000.00 4 Est. charges 6.875% as per G.O. 25790000.00 5 CDF (Cost DepriciationFund )@ 1.5% as per G.O. 3085000.00 TOTAL A = 253311456.71 PART B = 47610269.00 GRAND TOTAL = 300921725.71 SAY = 2842.62 lacks ON SITE EXPERIMENT 1.DETERMINATION OF PENETRATION STANDARD IS: 1203 – 1978 DEFINITION Penetration of a bituminous material is the distance in tenths of millimeter that standard needle will penetrate vertically into a sample under standard conditions
  • 17. of temperature, load and time. APPARATUS Standard Penetration apparatus A metal or glass cylindrical flat-bottomed container essentially with the following dimensions- For penetration below 225 Diameter 55mm Internal depth 35mm For penetration between 225 and 350 Diameter 70mm Internal depth 45mm Needle shall be made up of straight, highly polished, cylindrical, hard steel rod. Water bath 10 liters capacity thermostatically Controlled and maintained within the temperature of 25 + 0.10C. Thermometer capable of reading temperature up to 250 0C. PROCEDURE Soften the material to a pouring consistency at a temperature not more than 60 0C for tars and pitches and not more than 90 0C for bitumen above the approximate respective softening points. Stir it thoroughly until it is homogeneous and free from air bubbles and water. Pour the melt in to the container to a depth of at least 10mm in excess of the expected penetration. Protect the sample from dust and allow it to cool in atmosphere at a temperature between 15 to 30 0C for 11/2 to 2hours for 45mm deep container and 1 to 11/2 hours for 35mm deep container. Unless otherwise specified carry out testing at a temperature of 25 + 0.1oC. Place it along with the transfer dish in the water bath at 25 + 0.10C and allow it remain for 11/2 to 2hours for 45mm deep container and 1 to 11/2 hours for 35mm deep container. Fill the transfer dish with water from the water bath to a depth sufficient to cover the mould completely. Remove the transfer dish along with the mould from water bath after specified period of time and put it upon the stand of penetration apparatus. Adjust the needle (previously washed, cleaned well with benzene and dried) just to make contact with the surface of the sample. The sum of the weights of the needle, carrier and super imposed weights i.e. the total moving weight shall be 100 0.25grams. Bring the pointer to zero. Penetration test for bitumen. Release the needle for five seconds and measure the distance penetrated. The sum of the weights of the needle, carrier and super imposed weights i.e. the total moving weight shall be 100 0.25grams. Bring the pointer to zero. Penetration test for bitumen. Release the needle for five seconds and measure the distance penetrated. Make at least three determinations at points on the surface of the sample not less than 10mm apart and not less than 10mm from the side of the dish. After each test, return the sample and transfer dish to the water bath and wash the needle with benzene and dry. In case of material of penetration greater than 225 make three determinations on
  • 18. each of two identical test specimens using a separate needle for each determination, leaving the needle in the sample on completion of each determination to avoid disturbance of the specimen. REPORT Express the depth of penetration of the needle in tenths of mm. The value of penetration reported shall be the mean of not less than three determinations whose values do not differ by more than the difference given below Penetration Maximum difference 0 to 49 2 50 to 149 4 150 to 249 6 250 and above 8 PRECISION The duplicate results should not differ by more than the following Penetration Repeatability Reproducibility Below50 1 Unit 4 Units Above50 3% of their mean 8% of their mean PRECAUTIONS If the sample contains extraneous matter, it should be sieved through I.S. Sieve 30 (IS: 460-1962). To avoid over heating at the bottom of the container, use of an air oven or sand bath is recommended. While the needle is penetrating into the sample, if there is any movement of the container, that determination shall be discarded. 2.COMPRESSIVE STRENGTH OF CONCRETE concrete is generally subjected to compressive stress when used in the form of concrete or mortar . APPRATUS- For measuring the compressive strength of concrete ,there are used (universal testing machine) In addition of these things , there are also used of 1 fineaggregrate sand . 2 Cementing material (cement ). 3 Clean water . 4 Tampering road 5/8”inch COMPRESSIVE STRENGTH OF 1:3 MORTAR CURED FOR 3 DAYS- Compressive strength =3300 psi CURED FOR 3 DAYS- Compressive strength=5900psi
  • 19. CONCLUSION AND RESULTS After developing this project – 1 The entire way of Railway Crossing intersection is divided into 4 lanes which gives results to avoiding the all zam conditions in Chandauli 2 There are also considered as to provide proper convenience to moving traffic from Chandauli to Gazipur. 3. There are providing the well develop proper way , for the same industrial area like Mughalsarai , Ramnagar ,Chandhasi etc. 4. There are more saving of time and energy. SITE SAFETY  All visiotors and deliveries must to the site office.  Safety helmets must be worn on this site.  Safety footware must be worn on this site.  High visibility garments must be worn on this site.  Unauthorised entry to this site is strictly forbidden.  No smoking on this site.
  • 20. EXPERIENCE This is very wonderful experiance . I felt very comfortable with engineers and labours at Chandauli site .The engineers detected to us sincerely all things and at govering any query and question they easely solve it with in simple words . there are also available the primary medical treatment at the site in the condition for any injuries and it is one of the most best condition at the site .
  • 21.