SlideShare uma empresa Scribd logo
1 de 17
Baixar para ler offline
richard.hunt@ge.com
21, rue d’Artois, F-75008 PARIS CIGRE US National Committee
http://www.cigre.org 2019 Grid of the Future Symposium
The Substation of the Future
R. HUNT, T. SMITH, B. FLYNN
GE Grid Solutions
USA
SUMMARY
The growing trend for protection and control and substation automation is the digital
substation. This is generally understood to mean fully implementing process bus. While
adopting process bus provides great value, it is only a stepping stone. The long-term goal
must be to move away from the current single-purpose, hardware-based protection and
automation systems and replace them with a software-defined control system running virtual
services: a digitally enabled substation.
A digitally enabled substation is necessary to enable substation systems to adapt to the new
realities of changing distributed energy resources impacting feeder power flow, voltage, and
protection functions, and the changing operating requirements brought on by widely
distributed, inverter-based resources. Wind, solar, battery storage, and EVs maybe be
connected anywhere to the grid, and by different owners often concentrated in areas
negatively impacting the traditional grid. Operators and control functions must plan for and
adapt quickly to changes in available resources and load flows. Utilities, systems owners and
a host of new DER stakeholders will need to be able to roll out new applications and access
an increasing amount of grid data to optimize their investments. Old schemes will need to be
adapted quickly and reliably throughout the entire system.
The only way to provide the adaptability and flexibility required, with the speed required, is
using an application driven, hardware and vendor independent ecosystem, where the
substation is a critical control point to manage and improve power system operations.
KEYWORDS
Process bus, IEC 61850, distributed energy resources
2
THE SUBSTATION OF THE FUTURE
Figure 1 is the substation of the future. This substation is:
Fully modular, in that individual logical parts of the system, even at the primary equipment, have
a defined functionality and a defined interface between different modules.
Fully digital, in that all connections between the modules uses communications as defined by the
IEC 61850 Standard.
Virtual, in that every control and monitoring function is an independent application operating in a
local application server.
There are two main reasons to adopt this design for the station of the future. The first is the ability
quickly and efficiently design, build, commission, and operate the substation, eve if that process
involves the refurbishment of existing primary equipment. The second reason is the growing need to
quickly develop and rollout new applications to meet the changing needs of power system operations
as inverter-based resources, like wind, solar, and battery storage, become more prevalent, especially at
distribution. The major goal is to change the mindset from operating the substation better, to using the
substation to operate the power system better.
Modular design is necessary to provide the speed and the path to adopt this virtual future. Digital
communications is necessary to ease connections between modules and devices. But the real key is the
virtual applications. Applications can be developed by competent developers, including the utility, and
pushed out the all substations. This is conceptually moving away from the dedicated hardware and
firmware solutions of today to using an application-driven, hardware and vendor independent
ecosystem.
It is also the case that future substations will need to be tightly integrated with systems outside the
substation, acting as a data collection point or data concentrator, and a control / decision making point
on the power system. Substations will be tightly integrated with distribution automation systems and
may be the first line control point for these systems. Substations will interface with various
microgrids, to aggregate data and issue control commands. They could interface with SCADA systems
and cloud-based services for applications such as asset performance management, digital twins for
testing, and dynamic line ratings. Substation applications could also use intelligence and system
modeling for dynamic settings and local state estimation. The key is the ability to define and produce
these applications and push them out to the local application servers.
3
Figure 1: The Substation of the Future
The key parts of this substation of the future design to discuss are primary equipment modules, which
are the basic physical building blocks; process bus, which is the communications network for this
design; and the local application server, where the virtual applications run.
Smart Primary Equipment Module
The smart primary equipment module is a complete packaged solution for a portion of a substation.
An example is in the complete feeder bay of Figure 2. This bay is a physical module and a virtual
module, with a defined functionality (a double bus primary feeder bay) and defined interfaces in the
bus structure for the physical interface, and process bus communications for the virtual interface.
This module consists of all the primary equipment supplied as a single containerized or platformed
unit. The primary equipment is “smart” – that is, fully digital. Only digital communications using IEC
61850 will be used for status, control, and measurement for the bay. The circuit breaker and isolator
4
switches will also be “smart” devices, as there will be no physical wiring interface for external use,
only digital communications outputs provided from the equipment.
Digital instrument transformers (DITs) will be tightly integrated into this bay. DITs are non-
conventional instrument transformers, like Rogowski coils, fiber optic CTs, and optical CVTs, that
provide a natively digital output of sampled values as per IEC 61850-9-2 [1].
Beyond the process bus communications, the virtual part of this smart module is the application
functionality. This functionality, in terms of automation control, and protection, can be predefined as
an application to push into the local application server. Or it could be a pre-defined library module in
the protection and automation part of the local application server.
The simple definition of the smart primary equipment modules, then, is a pre-designed and pre-built
module delivered with all the primary equipment, a defined digital interface for all data for status,
control, and measurement, a defined power system functionality, and a defined virtual control and
protection functionality. Modern gas insulated switchgear sections are generally very close to being a
smart primary equipment module, if they use DITs and process bus communications. There are
ongoing projects to develop a similar functionality for air insulated switchgear.
Figure 2: “Smart Module” concept
Process bus
Process bus is essentially distributed I/O for protection and control. Digitization takes place in simple
I/O devices integrated into primary equipment, using the data models and message formats of the IEC
61850 Standard. Digital sampled values (SV) representing primary current and voltage, along with
status and control signals, are transmitted through a communications channel to protection and
automation equipment, or in the case of this substation, the local application server. Process bus
facilitates flexibility and adaptability because the basic data for state, status, and control of the
substation is available on the process bus network. Any application connected to this network can
subscribe to the data, without impacting other devices or applications, and without connecting to the
primary equipment.
5
The reason to use the IEC 61850 Standard for communications is to provide a “future proof” digital
substation architecture that can be easily configured, updated, and maintained. Configuration of a
process bus system is easily verified through standard tools, as the data models provide self-
description of the data being sent. The majority of messages are event driven, using a multicast
publish-subscribe model. This means adding a device or application is a matter of publishing messages
to the network and subscribing to the appropriate messages already on the network. It is these features
of IEC 61850 communications that make a process bus solution future proof. Any device or
application supporting IEC 61850 can connect to the network and interoperate with any other device
on the network while using the same configuration tools.
Figure 3: Process bus
Local Application Server
A local application server is a processing platform running software services using a services or
container-based architecture. This is the heart of virtualization. Every application is developed as a
service, running independently of each other, each entirely in its own container, as in Figure 4. Data
can be shared across or between applications as necessary, so functions like the security manager and
control plane are shared. This application server runs applications for use inside the substation such as
control and protection; applications to connect the substation with devices and systems coupled with
the substation such as DER management, fault detection and isolation, microgrid integration; and
connections to cloud applications and utility system operations.
The key requirement is the ability to quickly specify, prototype, test, and rollout applications as
needed for power system operations. As individual applications are independent, they can be rolled out
6
to an in-service application server without impacting the already running applications in this server.
This provides for quick and simple upgrades without risk.
The general concept of a local application server has been commonly known as “centralized protection
and control”. There are many permutations of how centralized protection and control can be
implemented, as described in the “Centralized Substation Protection and Control” report developed by
the IEEE Power System Relaying Committee. [2]. However, to date, centralized protection and control
has only focused on internal substation applications. A local application server provides these internal
applications, as well applications to connect and interact with the wider power system.
Figure 4: Application Server concept
Substation edge device
The actual architecture of the local application server can take many forms. One form is that of the
substation edge device of Figure 5, a container-based server running both a non-real time operating
system, and a real-time operating system for protection functions. A substation edge device is
generally built from hardware already developed for use in substations. The design process is simply a
matter of a new operating system to provide software containers. [3] The benefit of this design is
working off of hardware that is already designed for the substation environment.
Figure 5: Substation edge device
Card module server
Another option for a local application server is a card module sever, as in Figure 6. In this model,
application cards have processing capability, and add specific functions. The benefit to this concept is
the ability to back up functionality and move it to other application cards based on system load or on
7
card failure. The downside is the need to develop applications specifically to run on the card modules,
and the need to design rugged architecture for the substation environment.
Figure 6: Card module server
Multi-core processing platform
Another concept is to use multi-core processing industrial computing platforms, as in Figure 7. Every
function, or class of function, can be run on its own core, to isolate processing requirements between
devices. This type of application server has been successfully applied. The detriments are that
applications must be explicitly developed for the multi-core platform and finding a computing
platform that is environmentally rugged enough for the substation.
Figure 7: Multi-core processing platform
Local cloud application server
A fourth option is to use local cloud software, as in Figure 8. The cloud software runs inside the
substation only, running on multiple parallel processing platforms. Applications are developed for and
loaded into the cloud software. The cloud software can run multiple parallel instances of all
applications. The cloud operating system will spread application loading across all available
8
processing platforms and will rebalance the loading on hardware failure. The use of a local cloud has
the great advantages of being able to borrow tools and concepts from many other industries,
completely abstracting functionality from hardware, and providing for simple replacement of failed
hardware without requiring shutdowns or commissioning. The detriment is finding processing
platforms that are suitably rugged for use in utility substations.
Figure 8: Local cloud
Redundancy
One consideration of the using a local application server is that of redundancy for reliability, a topic
discussed in detail in the “Centralized Substation Protection and Control” report [2]. The substation
edge device, card module server, and multi-core processing platform will require redundant devices
for reliability. The local cloud application server natively provides for redundant hardware and
provides redundancy of application in the cloud software.
WHERE WE ARE TODAY
The substation of the future uses fully modular development of primary equipment and the
applications for a substation. The challenge is how to get from the substation of today to the substation
of tomorrow. To define the process, it is necessary to understand the baseline of how substations are
designed and built today.
The key assumption in this discussion is that new substations are fully digital substations, in that all
analog interfaces are digitized directly at the source, and all data is published digitally under the IEC
61850 Standard.
Modular design of I/O for bays
As opposed to the smart primary equipment modules discussed in Section 0, the substation of today is
built with primary equipment and secondary equipment as separate items. Every bay is designed for a
specific substation and built directly on site. Separate I/O devices are installed to digitize the control,
status, and measurements at the primary equipment. I/O devices are likely to be installed in
marshalling kiosks in the switchyard, with field wiring installed from the primary equipment to the
kiosks, as in Figure 9. The results in a modular design for the secondary I/O devices, not for the bay as
9
whole. The marshalling kiosk is installed in the switchyard, and copper cabling is pulled from all
primary devices to this kiosk. This is modular design of the process bus system, but not the physical
part of the substation.
To RIOTo RIO
Other signals
to RIO
To RIO
To RIO
MU
RIO
MU
RIO
Marshalling Kiosk To Process Bus
Figure 9: Bays today
Process interface units (PIUs) will exist close to the primary equipment and will be the interface
between the electrical physical world and the digital world. Their role will be to publish information
from the primary equipment and to control the primary equipment from digitized control signals on
the communications networks. These PIUs will control circuit breakers and switches, will also be
connected to traditional current transformers and voltage transformers, and will publish both
equipment signals and digital sampled values to IEDs for protection and operation purposes. The PIUs
shown in Figure 9 are merging units (MUs), that convert analog measurements to digital sampled
values; and remote I/O modules (RIOs), that are contact inputs and outputs for status and control.
This means that circuit breakers and isolators aren’t natively “smart”, as the analog to digital
conversion requires a separate device that must be installed and wired. However, this design can be
used for any substation installation, and is an easy retrofit solution when primary equipment is not
being replaced.
Individual application devices
Substations of today are still built around individual application devices for zones of protection, for
automation, and for SCADA control, as in Figure 10. Every zone has a relay and bay control unit
(BCU); and may have redundant relays for reliability. Station level devices like gateways, HMIs, and
substation controllers coordinate all control and reporting action. One challenge with this architecture
is the number of devices that must be managed. Another challenge is adding new functionality, or
enhancing existing functionality, means upgrading multiple devices in one substation. These devices
also, today, have integrated hardware and firmware, so new enhancements or applications means
updating the existing firmware and configuration, which can be an involved process, especially as re-
commissioning may be required.
10
BCU
Relay
A
Relay
B
BCU
Relay
A
Relay
B
BCU
Relay
A
Relay
B
BCU
Relay
A
Relay
B
BCU
Relay
A
Relay
B
BCU
Relay
A
Relay
B
Gateway HMI Controller
Station Bus
Process Bus
Figure 10: Individual zones of protection / station devices
DITs as application specific devices
DITs have been available for decades, but wide spread adoption has been slow, mostly due to
lack of experience with DITs, and low availability of process bus-capable IEDs. The
application of DITs is starting to become more common, mostly in the pilot project or
technology evaluation stage. The result is DITs are being installed as retrofit or add-on
devices to existing substations and primary equipment designs. They may require their own
mounting structure, as in Figure 11, or may be a temporary installation, as in Figure 12. In
these cases, the benefits of integrating DITs, such as size, weight, mounting locations, and
performance, are not fully realized. [4]
11
Figure 11: Stand alone DIT Figure 12: Temporary / pilot project DIT
Baseline of today
The baseline of today, then, is straightforward. Fully digital substations are the growing trend, adding
I/O devices such as MUs, RIOs, and DITs directly to primary equipment as part of the design and
build process. Individual devices are used for control and protection for each zone of equipment. This
step starts to take advantage of digitalization but is not true virtualization of functions.
NEXT TECHNOLOGY STEPS
To go from the basic digital substations of today, to fully modularized and virtualized substation of the
future, is likely to happen in intermediate steps, as utilities gain confidence with both the concept and
available technology. While much of the technology and tools can be borrowed from other industries,
the hardware that applications run on must be designed for the rugged environment of the utility
switchyard, and the expected 20-year minimum service life.
Advanced gateway application server
One next step is an advanced gateway application server as in Figure 13, and products designed on this
concept are becoming available in the market. This is the first step to becoming the substation edge
device described in Section 2.3.1. The hardware is built to meet the environmental requirements of the
substation, as defined in the IEEE 1613 [5] and IEC 61850-3 [6] Standards. Using proven, ruggedized
hardware, this gateway application server uses a container-based architecture to provide standard
gateway applications like SCADA controls services and an HMI. Other substation focused
applications like phasor data concentrators or microgrid control can be developed as separate services
and added at a later date, without impacting the already developed and already running applications.
Container 2Container 1
Resource
Management
App App
Container Engine
Bins / Libraries Bins / Libraries
Hypervisor
Hardware
Domain 0 Domain U
Container 3
App
Bins / Libraries
Container 4
App
Bins / Libraries
Figure 13: Container-based gateway as application server
12
The first pass at the advanced gateway application server does not include the real-time operating
system necessary to run protection applications. This is in part due to technical considerations about
running real-time and non-real-time operating systems in the same device. This is also in part about
utility confidence in the solution, and the desire for the protection group and the SCADA group to
have full ownership of their own devices.
Multi-zone protection relay
Another next step is a multi-zone protection relay of Figure 14, built on top of an existing
transmission-class protective relay hardware. This type of device can run multiple instances of an
entire zone of protection, using existing, proven algorithms, running on the same proven operating
system. This is relatively simple concept to develop off of existing hardware platforms. Once relays
become optimized for process bus, the only limitation to the number of protection zones is the number
of SV streams, and the capabilities of the processor. Busbar protection relays are coming on to the
market that accept up to 24 SV data streams, so the complete protection of small substations in a
single multi-zone relaying platform is possible.
Resource
Management
Real Time Hypervisor
Hardware
Domain 0
Real Time
Container
Engine
Real Time
Container
Real Time
Container
Real Time
Container
Real Time
Container
Zone 1
Protection
Zone
Protection
Bins / Libraries
Zone
Protection
Bins / Libraries
Zone
Protection
Bins / Libraries
Zone
Protection
Bins / Libraries
Real Time Domain
Figure 14: Multi-zone protection relay
Integrated DITs
A third next step, which is already available today, is to fully integrate DITs into circuit breakers. This
reduces the footprint for substations, the infrastructure for handling cables, and the number of cables
required. The examples of Figure 15 show DITs integrated into live-tank and dead-tank circuit
breakers, respectively, in air insulated switchgear. It is also possible to provide DITs for gas insulated
switchgear as well, resulting is smaller switchgear, and fewer devices under the insulating gas.
13
Figure 15: DITs integrated into primary equipment
Next generation substation
The next generation substation, the intermediate step between the basic digital substation of today, and
the fully modular and virtual substation of the future, is illustrated in Figure 16. An advanced gateway
application server, and two multi-zone protection relays for redundancy, and process bus-enabled
equipment. DITs integrated into switchgear in new applications.
The devices to support this architecture are available today, or becoming available today, so design
will become the standard architecture for substations.
Figure 16: Next generation substation
APPLICATIONS ENABLED BY THIS CONCEPT
One step for putting the substation of the future in place is installing the building blocks in place for a
modular, virtual substation. Another step is defining and developing the applications. Applications can
include asset performance management, a system digital twin for testing, integration into distribution
automation, microgrid control and integration, machine learning for dynamic settings, even local state
estimation. The possibilities are defined by the needs of a specific utility. All data from the substation
14
is available at the local application server through process bus communications, and the application
server can collect data from external sources such as distribution automation devices and SCADA
systems through standard wide-area communications.
Adaptive transformer loading
The adaptive transformer loading illustrated in Figure 17 is simply the idea of maximizing the capacity
of power transformers during changing system conditions. The concept is to take transformer
monitoring data, including winding temperature, hot spot data, and dissolved gas analysis, combine
this with load data, predicted load data, and meteorological data. The application then uses analytics to
control the cooling system, to pre-cool the transformer before predicted higher load occurs. This
permits the maximum capacity possible out of the transformer, while extending the service life by
reducing the rise, and reducing the time, that the windings experience a thermal overload.
Figure 17: Adaptive transformer loading
WAMS
One goal of the substation of the future is to use the substation to improve power system operations.
This means the substation must be a key piece of a Wide Area Monitoring System (WAMS) for both
transmission and distribution. The WAMS application at the substation provides critical data through a
larger deployment of phasor measurement units (PMUs) and MicroPMUs across the grid, combined in
15
a visualization like Figure 18. The system includes secure access and phasor data management in
substations and provides new tools for automation, operators, and engineers.
Possible uses for this data, or variations of this application, include near real-time stability monitoring,
sub-synchronous oscillation detection and dampening, system disturbance monitoring, short circuit
capacity calculations, fast voltage stability assessment for transmission corridors, and islanding
resynchronization and blackstart.
Figure 18: WAMs data
DERMS
The changes to power system operations are due in large part to the future high penetration of
distributed energy resources (DERs). DER data, control, and optimization will be part of future
substations, especially for utility grade resources. This data will play an important role in
understanding, managing and planning an increasing complex DER portfolio. Applications running in
the substation will determine the mitigation steps to reduce negative impacts involving voltage
stability, grid capacity, reverse power flow, unintentional islanding, short circuit current levels, and
more.
Substations will need to provide critical data for real time analysis and control algorithms, through a
DER Management System (DERMS) running as an application, as visualized in Figure 19.
16
Figure 19: DERMS overview
SUMMARY
The substation of the future is completely modular in design, completely digital in communications,
and fully virtual in functionality. This allows faster, more repeatable, lower cost design, build, and
refurbishment of substations of substation control systems. The important ability is to quickly develop
control applications to meet the changing requirements of power systems. The first steps on this path
are modular design of process bus systems, and the use of the advanced gateway application servers
and multi-zone protective relays becoming available in the market.
17
BIBLIOGRAPHY
[1] IEC 61850-9-2 Communication networks and systems for power utility automation – Part 9-2:
Specific communication service mapping (SCSM) – Sampled values over ISO/IEC 8802-3,
Geneva, Switzerland: IEC, 2011.
[2] IEEE Power System Relaying Committee Working Group, "Centralized Substation Protection and
Control," IEEE, New York, NY, 2015.
[3] R. Hunt, T. Smith, B. Flynn, "The Substation of the Future," IEEE Power and Energy Magazine,
July / August 2019.
[4] D. Stewart, A. Rose, R. Hunt, A. Varghese, "Practical Installation Benefits of Digital Instrument
Transform," in 2018 PAC World Conference, Sofia, Bulgaria, 2018.
[5] IEEE 1613.1 IEEE Standard Environmental and Testing Requirements for Communications
Networking Devices Installed in Transmission and Distribution Facilities, New York, NY: IEEE,
2013.
[6] IEC 61850-3 Communication networks and systems for power utility automation – Part 3: General
requirements, Geneva, Switzerland: IEC, 2013.

Mais conteúdo relacionado

Mais procurados

Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
19saurabh89
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
Sumit Kumar
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
pamu17
 

Mais procurados (20)

STATIC AND DIGITAL RELAYS
STATIC AND DIGITAL RELAYSSTATIC AND DIGITAL RELAYS
STATIC AND DIGITAL RELAYS
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Chapter1 breakdown in gases
Chapter1 breakdown in gasesChapter1 breakdown in gases
Chapter1 breakdown in gases
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
Seminor on resonant and soft switching converter
Seminor on resonant and soft switching converterSeminor on resonant and soft switching converter
Seminor on resonant and soft switching converter
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformers
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission lines
 
Hvdc system.pptx
Hvdc system.pptxHvdc system.pptx
Hvdc system.pptx
 
Over current protection
Over current protectionOver current protection
Over current protection
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relay
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul Mehra
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 

Semelhante a The Substation of the Future; CIGRE

Intelligent electrical system
Intelligent electrical systemIntelligent electrical system
Intelligent electrical system
muddulakshmi
 
Critical Information Infrastructure Systems Worldwide
Critical Information Infrastructure Systems WorldwideCritical Information Infrastructure Systems Worldwide
Critical Information Infrastructure Systems Worldwide
Angela Hays
 

Semelhante a The Substation of the Future; CIGRE (20)

How the Convergence of IT and OT Enables Smart Grid Development
How the Convergence of IT and OT Enables Smart Grid DevelopmentHow the Convergence of IT and OT Enables Smart Grid Development
How the Convergence of IT and OT Enables Smart Grid Development
 
Substation Automation in Smart Grid
Substation Automation in Smart GridSubstation Automation in Smart Grid
Substation Automation in Smart Grid
 
Effect on Substation Engineering Costs of IEC61850 & System Configuration Tools
Effect on Substation Engineering Costs of IEC61850 & System Configuration ToolsEffect on Substation Engineering Costs of IEC61850 & System Configuration Tools
Effect on Substation Engineering Costs of IEC61850 & System Configuration Tools
 
Smart distribution system the need of automation & it application in powe...
Smart distribution system the need of automation & it application in powe...Smart distribution system the need of automation & it application in powe...
Smart distribution system the need of automation & it application in powe...
 
Main report
Main reportMain report
Main report
 
Paper on IEC 61850
Paper on IEC 61850Paper on IEC 61850
Paper on IEC 61850
 
Energy Meters using Internet of Things Platform
Energy Meters using Internet of Things PlatformEnergy Meters using Internet of Things Platform
Energy Meters using Internet of Things Platform
 
IRJET- Smart Power Optimization with IoT
IRJET-  	  Smart Power Optimization with IoTIRJET-  	  Smart Power Optimization with IoT
IRJET- Smart Power Optimization with IoT
 
International journal of engineering issues vol 2015 - no 2 - paper2
International journal of engineering issues   vol 2015 - no 2 - paper2International journal of engineering issues   vol 2015 - no 2 - paper2
International journal of engineering issues vol 2015 - no 2 - paper2
 
Advanced Metering Infrastructure Standards and protocol
Advanced Metering Infrastructure Standards and protocolAdvanced Metering Infrastructure Standards and protocol
Advanced Metering Infrastructure Standards and protocol
 
White paper tower power, inc. energy management, iot,
White paper tower power, inc.   energy management, iot, White paper tower power, inc.   energy management, iot,
White paper tower power, inc. energy management, iot,
 
Solar tracking with mobile
Solar tracking with mobileSolar tracking with mobile
Solar tracking with mobile
 
Modernization of Electrical Substation Automation Systems Using IEC61850
Modernization of Electrical Substation Automation Systems Using IEC61850Modernization of Electrical Substation Automation Systems Using IEC61850
Modernization of Electrical Substation Automation Systems Using IEC61850
 
Smart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case StudiesSmart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case Studies
 
Intelligent electrical system
Intelligent electrical systemIntelligent electrical system
Intelligent electrical system
 
Design and Implementation of Multi-SCADA System for Drone-Based Reliability R...
Design and Implementation of Multi-SCADA System for Drone-Based Reliability R...Design and Implementation of Multi-SCADA System for Drone-Based Reliability R...
Design and Implementation of Multi-SCADA System for Drone-Based Reliability R...
 
Power system automation
Power system automationPower system automation
Power system automation
 
IoT Based Control and Monitoring of Smart Grid and Power Theft Detection by L...
IoT Based Control and Monitoring of Smart Grid and Power Theft Detection by L...IoT Based Control and Monitoring of Smart Grid and Power Theft Detection by L...
IoT Based Control and Monitoring of Smart Grid and Power Theft Detection by L...
 
Iec61850 overview and benefits paper general
Iec61850 overview and benefits paper generalIec61850 overview and benefits paper general
Iec61850 overview and benefits paper general
 
Critical Information Infrastructure Systems Worldwide
Critical Information Infrastructure Systems WorldwideCritical Information Infrastructure Systems Worldwide
Critical Information Infrastructure Systems Worldwide
 

Mais de Power System Operation

SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
Power System Operation
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
Power System Operation
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
Power System Operation
 

Mais de Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Último

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Último (20)

Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 

The Substation of the Future; CIGRE

  • 1. richard.hunt@ge.com 21, rue d’Artois, F-75008 PARIS CIGRE US National Committee http://www.cigre.org 2019 Grid of the Future Symposium The Substation of the Future R. HUNT, T. SMITH, B. FLYNN GE Grid Solutions USA SUMMARY The growing trend for protection and control and substation automation is the digital substation. This is generally understood to mean fully implementing process bus. While adopting process bus provides great value, it is only a stepping stone. The long-term goal must be to move away from the current single-purpose, hardware-based protection and automation systems and replace them with a software-defined control system running virtual services: a digitally enabled substation. A digitally enabled substation is necessary to enable substation systems to adapt to the new realities of changing distributed energy resources impacting feeder power flow, voltage, and protection functions, and the changing operating requirements brought on by widely distributed, inverter-based resources. Wind, solar, battery storage, and EVs maybe be connected anywhere to the grid, and by different owners often concentrated in areas negatively impacting the traditional grid. Operators and control functions must plan for and adapt quickly to changes in available resources and load flows. Utilities, systems owners and a host of new DER stakeholders will need to be able to roll out new applications and access an increasing amount of grid data to optimize their investments. Old schemes will need to be adapted quickly and reliably throughout the entire system. The only way to provide the adaptability and flexibility required, with the speed required, is using an application driven, hardware and vendor independent ecosystem, where the substation is a critical control point to manage and improve power system operations. KEYWORDS Process bus, IEC 61850, distributed energy resources
  • 2. 2 THE SUBSTATION OF THE FUTURE Figure 1 is the substation of the future. This substation is: Fully modular, in that individual logical parts of the system, even at the primary equipment, have a defined functionality and a defined interface between different modules. Fully digital, in that all connections between the modules uses communications as defined by the IEC 61850 Standard. Virtual, in that every control and monitoring function is an independent application operating in a local application server. There are two main reasons to adopt this design for the station of the future. The first is the ability quickly and efficiently design, build, commission, and operate the substation, eve if that process involves the refurbishment of existing primary equipment. The second reason is the growing need to quickly develop and rollout new applications to meet the changing needs of power system operations as inverter-based resources, like wind, solar, and battery storage, become more prevalent, especially at distribution. The major goal is to change the mindset from operating the substation better, to using the substation to operate the power system better. Modular design is necessary to provide the speed and the path to adopt this virtual future. Digital communications is necessary to ease connections between modules and devices. But the real key is the virtual applications. Applications can be developed by competent developers, including the utility, and pushed out the all substations. This is conceptually moving away from the dedicated hardware and firmware solutions of today to using an application-driven, hardware and vendor independent ecosystem. It is also the case that future substations will need to be tightly integrated with systems outside the substation, acting as a data collection point or data concentrator, and a control / decision making point on the power system. Substations will be tightly integrated with distribution automation systems and may be the first line control point for these systems. Substations will interface with various microgrids, to aggregate data and issue control commands. They could interface with SCADA systems and cloud-based services for applications such as asset performance management, digital twins for testing, and dynamic line ratings. Substation applications could also use intelligence and system modeling for dynamic settings and local state estimation. The key is the ability to define and produce these applications and push them out to the local application servers.
  • 3. 3 Figure 1: The Substation of the Future The key parts of this substation of the future design to discuss are primary equipment modules, which are the basic physical building blocks; process bus, which is the communications network for this design; and the local application server, where the virtual applications run. Smart Primary Equipment Module The smart primary equipment module is a complete packaged solution for a portion of a substation. An example is in the complete feeder bay of Figure 2. This bay is a physical module and a virtual module, with a defined functionality (a double bus primary feeder bay) and defined interfaces in the bus structure for the physical interface, and process bus communications for the virtual interface. This module consists of all the primary equipment supplied as a single containerized or platformed unit. The primary equipment is “smart” – that is, fully digital. Only digital communications using IEC 61850 will be used for status, control, and measurement for the bay. The circuit breaker and isolator
  • 4. 4 switches will also be “smart” devices, as there will be no physical wiring interface for external use, only digital communications outputs provided from the equipment. Digital instrument transformers (DITs) will be tightly integrated into this bay. DITs are non- conventional instrument transformers, like Rogowski coils, fiber optic CTs, and optical CVTs, that provide a natively digital output of sampled values as per IEC 61850-9-2 [1]. Beyond the process bus communications, the virtual part of this smart module is the application functionality. This functionality, in terms of automation control, and protection, can be predefined as an application to push into the local application server. Or it could be a pre-defined library module in the protection and automation part of the local application server. The simple definition of the smart primary equipment modules, then, is a pre-designed and pre-built module delivered with all the primary equipment, a defined digital interface for all data for status, control, and measurement, a defined power system functionality, and a defined virtual control and protection functionality. Modern gas insulated switchgear sections are generally very close to being a smart primary equipment module, if they use DITs and process bus communications. There are ongoing projects to develop a similar functionality for air insulated switchgear. Figure 2: “Smart Module” concept Process bus Process bus is essentially distributed I/O for protection and control. Digitization takes place in simple I/O devices integrated into primary equipment, using the data models and message formats of the IEC 61850 Standard. Digital sampled values (SV) representing primary current and voltage, along with status and control signals, are transmitted through a communications channel to protection and automation equipment, or in the case of this substation, the local application server. Process bus facilitates flexibility and adaptability because the basic data for state, status, and control of the substation is available on the process bus network. Any application connected to this network can subscribe to the data, without impacting other devices or applications, and without connecting to the primary equipment.
  • 5. 5 The reason to use the IEC 61850 Standard for communications is to provide a “future proof” digital substation architecture that can be easily configured, updated, and maintained. Configuration of a process bus system is easily verified through standard tools, as the data models provide self- description of the data being sent. The majority of messages are event driven, using a multicast publish-subscribe model. This means adding a device or application is a matter of publishing messages to the network and subscribing to the appropriate messages already on the network. It is these features of IEC 61850 communications that make a process bus solution future proof. Any device or application supporting IEC 61850 can connect to the network and interoperate with any other device on the network while using the same configuration tools. Figure 3: Process bus Local Application Server A local application server is a processing platform running software services using a services or container-based architecture. This is the heart of virtualization. Every application is developed as a service, running independently of each other, each entirely in its own container, as in Figure 4. Data can be shared across or between applications as necessary, so functions like the security manager and control plane are shared. This application server runs applications for use inside the substation such as control and protection; applications to connect the substation with devices and systems coupled with the substation such as DER management, fault detection and isolation, microgrid integration; and connections to cloud applications and utility system operations. The key requirement is the ability to quickly specify, prototype, test, and rollout applications as needed for power system operations. As individual applications are independent, they can be rolled out
  • 6. 6 to an in-service application server without impacting the already running applications in this server. This provides for quick and simple upgrades without risk. The general concept of a local application server has been commonly known as “centralized protection and control”. There are many permutations of how centralized protection and control can be implemented, as described in the “Centralized Substation Protection and Control” report developed by the IEEE Power System Relaying Committee. [2]. However, to date, centralized protection and control has only focused on internal substation applications. A local application server provides these internal applications, as well applications to connect and interact with the wider power system. Figure 4: Application Server concept Substation edge device The actual architecture of the local application server can take many forms. One form is that of the substation edge device of Figure 5, a container-based server running both a non-real time operating system, and a real-time operating system for protection functions. A substation edge device is generally built from hardware already developed for use in substations. The design process is simply a matter of a new operating system to provide software containers. [3] The benefit of this design is working off of hardware that is already designed for the substation environment. Figure 5: Substation edge device Card module server Another option for a local application server is a card module sever, as in Figure 6. In this model, application cards have processing capability, and add specific functions. The benefit to this concept is the ability to back up functionality and move it to other application cards based on system load or on
  • 7. 7 card failure. The downside is the need to develop applications specifically to run on the card modules, and the need to design rugged architecture for the substation environment. Figure 6: Card module server Multi-core processing platform Another concept is to use multi-core processing industrial computing platforms, as in Figure 7. Every function, or class of function, can be run on its own core, to isolate processing requirements between devices. This type of application server has been successfully applied. The detriments are that applications must be explicitly developed for the multi-core platform and finding a computing platform that is environmentally rugged enough for the substation. Figure 7: Multi-core processing platform Local cloud application server A fourth option is to use local cloud software, as in Figure 8. The cloud software runs inside the substation only, running on multiple parallel processing platforms. Applications are developed for and loaded into the cloud software. The cloud software can run multiple parallel instances of all applications. The cloud operating system will spread application loading across all available
  • 8. 8 processing platforms and will rebalance the loading on hardware failure. The use of a local cloud has the great advantages of being able to borrow tools and concepts from many other industries, completely abstracting functionality from hardware, and providing for simple replacement of failed hardware without requiring shutdowns or commissioning. The detriment is finding processing platforms that are suitably rugged for use in utility substations. Figure 8: Local cloud Redundancy One consideration of the using a local application server is that of redundancy for reliability, a topic discussed in detail in the “Centralized Substation Protection and Control” report [2]. The substation edge device, card module server, and multi-core processing platform will require redundant devices for reliability. The local cloud application server natively provides for redundant hardware and provides redundancy of application in the cloud software. WHERE WE ARE TODAY The substation of the future uses fully modular development of primary equipment and the applications for a substation. The challenge is how to get from the substation of today to the substation of tomorrow. To define the process, it is necessary to understand the baseline of how substations are designed and built today. The key assumption in this discussion is that new substations are fully digital substations, in that all analog interfaces are digitized directly at the source, and all data is published digitally under the IEC 61850 Standard. Modular design of I/O for bays As opposed to the smart primary equipment modules discussed in Section 0, the substation of today is built with primary equipment and secondary equipment as separate items. Every bay is designed for a specific substation and built directly on site. Separate I/O devices are installed to digitize the control, status, and measurements at the primary equipment. I/O devices are likely to be installed in marshalling kiosks in the switchyard, with field wiring installed from the primary equipment to the kiosks, as in Figure 9. The results in a modular design for the secondary I/O devices, not for the bay as
  • 9. 9 whole. The marshalling kiosk is installed in the switchyard, and copper cabling is pulled from all primary devices to this kiosk. This is modular design of the process bus system, but not the physical part of the substation. To RIOTo RIO Other signals to RIO To RIO To RIO MU RIO MU RIO Marshalling Kiosk To Process Bus Figure 9: Bays today Process interface units (PIUs) will exist close to the primary equipment and will be the interface between the electrical physical world and the digital world. Their role will be to publish information from the primary equipment and to control the primary equipment from digitized control signals on the communications networks. These PIUs will control circuit breakers and switches, will also be connected to traditional current transformers and voltage transformers, and will publish both equipment signals and digital sampled values to IEDs for protection and operation purposes. The PIUs shown in Figure 9 are merging units (MUs), that convert analog measurements to digital sampled values; and remote I/O modules (RIOs), that are contact inputs and outputs for status and control. This means that circuit breakers and isolators aren’t natively “smart”, as the analog to digital conversion requires a separate device that must be installed and wired. However, this design can be used for any substation installation, and is an easy retrofit solution when primary equipment is not being replaced. Individual application devices Substations of today are still built around individual application devices for zones of protection, for automation, and for SCADA control, as in Figure 10. Every zone has a relay and bay control unit (BCU); and may have redundant relays for reliability. Station level devices like gateways, HMIs, and substation controllers coordinate all control and reporting action. One challenge with this architecture is the number of devices that must be managed. Another challenge is adding new functionality, or enhancing existing functionality, means upgrading multiple devices in one substation. These devices also, today, have integrated hardware and firmware, so new enhancements or applications means updating the existing firmware and configuration, which can be an involved process, especially as re- commissioning may be required.
  • 10. 10 BCU Relay A Relay B BCU Relay A Relay B BCU Relay A Relay B BCU Relay A Relay B BCU Relay A Relay B BCU Relay A Relay B Gateway HMI Controller Station Bus Process Bus Figure 10: Individual zones of protection / station devices DITs as application specific devices DITs have been available for decades, but wide spread adoption has been slow, mostly due to lack of experience with DITs, and low availability of process bus-capable IEDs. The application of DITs is starting to become more common, mostly in the pilot project or technology evaluation stage. The result is DITs are being installed as retrofit or add-on devices to existing substations and primary equipment designs. They may require their own mounting structure, as in Figure 11, or may be a temporary installation, as in Figure 12. In these cases, the benefits of integrating DITs, such as size, weight, mounting locations, and performance, are not fully realized. [4]
  • 11. 11 Figure 11: Stand alone DIT Figure 12: Temporary / pilot project DIT Baseline of today The baseline of today, then, is straightforward. Fully digital substations are the growing trend, adding I/O devices such as MUs, RIOs, and DITs directly to primary equipment as part of the design and build process. Individual devices are used for control and protection for each zone of equipment. This step starts to take advantage of digitalization but is not true virtualization of functions. NEXT TECHNOLOGY STEPS To go from the basic digital substations of today, to fully modularized and virtualized substation of the future, is likely to happen in intermediate steps, as utilities gain confidence with both the concept and available technology. While much of the technology and tools can be borrowed from other industries, the hardware that applications run on must be designed for the rugged environment of the utility switchyard, and the expected 20-year minimum service life. Advanced gateway application server One next step is an advanced gateway application server as in Figure 13, and products designed on this concept are becoming available in the market. This is the first step to becoming the substation edge device described in Section 2.3.1. The hardware is built to meet the environmental requirements of the substation, as defined in the IEEE 1613 [5] and IEC 61850-3 [6] Standards. Using proven, ruggedized hardware, this gateway application server uses a container-based architecture to provide standard gateway applications like SCADA controls services and an HMI. Other substation focused applications like phasor data concentrators or microgrid control can be developed as separate services and added at a later date, without impacting the already developed and already running applications. Container 2Container 1 Resource Management App App Container Engine Bins / Libraries Bins / Libraries Hypervisor Hardware Domain 0 Domain U Container 3 App Bins / Libraries Container 4 App Bins / Libraries Figure 13: Container-based gateway as application server
  • 12. 12 The first pass at the advanced gateway application server does not include the real-time operating system necessary to run protection applications. This is in part due to technical considerations about running real-time and non-real-time operating systems in the same device. This is also in part about utility confidence in the solution, and the desire for the protection group and the SCADA group to have full ownership of their own devices. Multi-zone protection relay Another next step is a multi-zone protection relay of Figure 14, built on top of an existing transmission-class protective relay hardware. This type of device can run multiple instances of an entire zone of protection, using existing, proven algorithms, running on the same proven operating system. This is relatively simple concept to develop off of existing hardware platforms. Once relays become optimized for process bus, the only limitation to the number of protection zones is the number of SV streams, and the capabilities of the processor. Busbar protection relays are coming on to the market that accept up to 24 SV data streams, so the complete protection of small substations in a single multi-zone relaying platform is possible. Resource Management Real Time Hypervisor Hardware Domain 0 Real Time Container Engine Real Time Container Real Time Container Real Time Container Real Time Container Zone 1 Protection Zone Protection Bins / Libraries Zone Protection Bins / Libraries Zone Protection Bins / Libraries Zone Protection Bins / Libraries Real Time Domain Figure 14: Multi-zone protection relay Integrated DITs A third next step, which is already available today, is to fully integrate DITs into circuit breakers. This reduces the footprint for substations, the infrastructure for handling cables, and the number of cables required. The examples of Figure 15 show DITs integrated into live-tank and dead-tank circuit breakers, respectively, in air insulated switchgear. It is also possible to provide DITs for gas insulated switchgear as well, resulting is smaller switchgear, and fewer devices under the insulating gas.
  • 13. 13 Figure 15: DITs integrated into primary equipment Next generation substation The next generation substation, the intermediate step between the basic digital substation of today, and the fully modular and virtual substation of the future, is illustrated in Figure 16. An advanced gateway application server, and two multi-zone protection relays for redundancy, and process bus-enabled equipment. DITs integrated into switchgear in new applications. The devices to support this architecture are available today, or becoming available today, so design will become the standard architecture for substations. Figure 16: Next generation substation APPLICATIONS ENABLED BY THIS CONCEPT One step for putting the substation of the future in place is installing the building blocks in place for a modular, virtual substation. Another step is defining and developing the applications. Applications can include asset performance management, a system digital twin for testing, integration into distribution automation, microgrid control and integration, machine learning for dynamic settings, even local state estimation. The possibilities are defined by the needs of a specific utility. All data from the substation
  • 14. 14 is available at the local application server through process bus communications, and the application server can collect data from external sources such as distribution automation devices and SCADA systems through standard wide-area communications. Adaptive transformer loading The adaptive transformer loading illustrated in Figure 17 is simply the idea of maximizing the capacity of power transformers during changing system conditions. The concept is to take transformer monitoring data, including winding temperature, hot spot data, and dissolved gas analysis, combine this with load data, predicted load data, and meteorological data. The application then uses analytics to control the cooling system, to pre-cool the transformer before predicted higher load occurs. This permits the maximum capacity possible out of the transformer, while extending the service life by reducing the rise, and reducing the time, that the windings experience a thermal overload. Figure 17: Adaptive transformer loading WAMS One goal of the substation of the future is to use the substation to improve power system operations. This means the substation must be a key piece of a Wide Area Monitoring System (WAMS) for both transmission and distribution. The WAMS application at the substation provides critical data through a larger deployment of phasor measurement units (PMUs) and MicroPMUs across the grid, combined in
  • 15. 15 a visualization like Figure 18. The system includes secure access and phasor data management in substations and provides new tools for automation, operators, and engineers. Possible uses for this data, or variations of this application, include near real-time stability monitoring, sub-synchronous oscillation detection and dampening, system disturbance monitoring, short circuit capacity calculations, fast voltage stability assessment for transmission corridors, and islanding resynchronization and blackstart. Figure 18: WAMs data DERMS The changes to power system operations are due in large part to the future high penetration of distributed energy resources (DERs). DER data, control, and optimization will be part of future substations, especially for utility grade resources. This data will play an important role in understanding, managing and planning an increasing complex DER portfolio. Applications running in the substation will determine the mitigation steps to reduce negative impacts involving voltage stability, grid capacity, reverse power flow, unintentional islanding, short circuit current levels, and more. Substations will need to provide critical data for real time analysis and control algorithms, through a DER Management System (DERMS) running as an application, as visualized in Figure 19.
  • 16. 16 Figure 19: DERMS overview SUMMARY The substation of the future is completely modular in design, completely digital in communications, and fully virtual in functionality. This allows faster, more repeatable, lower cost design, build, and refurbishment of substations of substation control systems. The important ability is to quickly develop control applications to meet the changing requirements of power systems. The first steps on this path are modular design of process bus systems, and the use of the advanced gateway application servers and multi-zone protective relays becoming available in the market.
  • 17. 17 BIBLIOGRAPHY [1] IEC 61850-9-2 Communication networks and systems for power utility automation – Part 9-2: Specific communication service mapping (SCSM) – Sampled values over ISO/IEC 8802-3, Geneva, Switzerland: IEC, 2011. [2] IEEE Power System Relaying Committee Working Group, "Centralized Substation Protection and Control," IEEE, New York, NY, 2015. [3] R. Hunt, T. Smith, B. Flynn, "The Substation of the Future," IEEE Power and Energy Magazine, July / August 2019. [4] D. Stewart, A. Rose, R. Hunt, A. Varghese, "Practical Installation Benefits of Digital Instrument Transform," in 2018 PAC World Conference, Sofia, Bulgaria, 2018. [5] IEEE 1613.1 IEEE Standard Environmental and Testing Requirements for Communications Networking Devices Installed in Transmission and Distribution Facilities, New York, NY: IEEE, 2013. [6] IEC 61850-3 Communication networks and systems for power utility automation – Part 3: General requirements, Geneva, Switzerland: IEC, 2013.