SlideShare uma empresa Scribd logo
1 de 17
© ESR Technology Ltd
The Forth Road Bridge:
Where Are We Today?
Dr Paul Roffey BSc, CEng MIMMM
Forensic Engineering & Materials
© ESR Technology Ltd
Overview
• Brief history of the Forth Road suspension bridge
• Basic construction
• Inspection – practices, previous, current
• Findings from 2012 inspection;
– Coating integrity
– Tensile strength evaluation
– Fatigue test data
– Fracture mechanisms
• Future
© ESR Technology Ltd
History & Construction
© ESR Technology Ltd
Timeline
Forth Rd Rail Bridge
(opened 1890)
Forth Rd Suspension Bridge
(opened 1964)
Forth Rd Cable Stay Bridge
(opening 2016)
© ESR Technology Ltd
Aerial spinning of wires
Construction
• Constructed in 1964 at a cost of £19.5
million
• 1006 metre span between towers
• Main cables have 11,618 high tensile
strength wires
• The main cables are approximately 60
cm thick, the total length of wire would
reach around the world 1.25 times!
• Wires were aerially spun across the
towers to build up the cables,
compacted and circumferentially
wrapped with 9 gauge wire followed by
lead paste and wrapping. Finally the
cables were painted.
Anchoring of wires
Installation of decks
Circumferential wires
© ESR Technology Ltd
Inspections
© ESR Technology Ltd
Inspection Process & Sampling
© ESR Technology Ltd
Previous Inspections
• 2004 - Bodycote
1st
main cable inspection in Europe at cost of £2.75m following discovery of
excessively corroded wires in US
10 panel locations investigated
Estimated 8 – 10% loss of strength in cables
Estimated closure of bridge in 2014 - 2020
Subsequently acoustic monitoring and dehumidification system added (2006-
09)
• 2008 – Faber Maunsell
3 panel locations investigated (2 in previous inspection) – cost of £3.78m
Agreed with previous estimation of strength loss but concluded more
optimistic date of 2017 - 2021 more likely
© ESR Technology Ltd
2012 Inspection
(Flint & Neill Ltd / ESR Technology)
• 8 panel locations investigated (4 East / 4 West)
• All locations not previously investigated
• Various ‘heights’ on cables
• Inspection carried out according to NCHRP 534
– Laboratory testing included chemical analyses, Preece testing,
galvanised coating weight loss, tensile testing, fatigue testing &
fracture analysis
• Results will allow 3rd
point to be plotted on strength loss & life
prediction and allow assessment of dehumidification system
effectiveness
© ESR Technology Ltd
Panel Locations
© ESR Technology Ltd
Laboratory Testing
© ESR Technology Ltd
Galvanic Coating Tests
Results showed wires adequately coated
© ESR Technology Ltd
Tensile Testing
Corrosion stage No. specimens Ave. UTS (MPa) <1544 MPa
Stage 1 65 1570 (51) 25 (38%)
Stage 2 271 1574 (51) 91 (34%)
Stage 3 467 1557 (64) 188 (40%)
Stage 4 280 1530 (±67) 173 (62%)
Total 1083 1555 (±63) 477 (44%)
Panel No. specimens Ave. UTS (MPa) <1544 MPa
(001) W94-92S 173 1572 (±67) 50
(002) W90-88N 183 1564 (±65) 62
(003) E94-92S 116 1589 (±56) 24
(004) W40-42S 69 1571 (±87) 26
(005) E100-98S 192 1544 (±51) 88
(006) E54-54S 61 1510 (±73) 45
(007) W52-50N 120 1535 (±44) 76
(008) E30-32S 169 1551 (±50) 106
Total East Cable 538 1549 (±59)
263
Total West Cable 545 1561 (±67)
214
Wedge location No. specimens Ave. UTS (MPa) <1544 MPa
12:00 94 1529 (±39) 58
01:30 124 1571 (±57) 44
03:00 143 1558 (±51) 52
04:30 135 1532 (±64) 75
06:00 121 1528 (±45) 78
07:30 134 1540 (±65) 69
09:00 184 1567 (±76) 67
10:30 148 1596 (±56) 34
• Performed to ASTM 586 and ASTM A370
• 254 mm gauge length
• 1083 tests
• Yield, UTS, elongation, RoA and E
© ESR Technology Ltd
Fatigue Testing
• Test end point was failure, or, 2 million cycles – only S3 &
S4 specimens.
• The average number of cycles was calculated at 958,852.
• Failure of the wire was found to occur when a fatigue crack
reached between 1154 to 2830 µm.
• The average crack depth however was calculated at 1420
µm.
• Lowest number of cycles was 36,222 on specimens with
~2000 µm crack.
Cyclic fatigue test summary (ASTM E466). Stage 3 Stage 4
No. of specimens 23 42
No. completed 2x106
cycles 12 5
No. of erroneous* 3 4
Failed 8 33
Average number of cycles to failure excluding
erroneous values
617,927 547,095
Minimum number of cycles 131,517 36,222
Maximum number of cycles 1,686,881 1,952,165
*Test specimens which failed within the grips or region of stripped galvanising.
• Performed in accordance with ASTM E466
• Instron fatigue rig with 50 kN transducer
• Mean tensile stress: 618 N/mm2
±139 N/mm2
• Loading: 40 Hz sine waveform
© ESR Technology Ltd
Fracture Mechanisms
In-situ Fatigue
Surface corrosion
Feathery propagation
Perpendicular ‘T’-crack
© ESR Technology Ltd
Where we are today...
• The inspections have shown that over a period of almost 50 years the
wires on the Forth Road Bridge have generally seen a reduction in
tensile strength.
• The current findings revealed that the newly installed dehumidification
system appears to be slowing down the rate of corrosion of the wires.
• The Forth Road Bridge main cables will continue to require internal
inspections and strength evaluations for the remainder of the life of the
bridge.
• External condition of cable is not indicative of internal condition.
• Further work required to fully understand the wire fracture mechanism.
• Loading restrictions will be in effect ~2017.
© ESR Technology Ltd
Forth Road Suspension Bridge
Questions?

Mais conteúdo relacionado

Mais procurados

Study of Vibration Analysis of Rotating Shaft with Transverse Crack
Study of Vibration Analysis of Rotating Shaft with Transverse CrackStudy of Vibration Analysis of Rotating Shaft with Transverse Crack
Study of Vibration Analysis of Rotating Shaft with Transverse CrackIJMERJOURNAL
 
E367 dah heavy duty
E367 dah heavy dutyE367 dah heavy duty
E367 dah heavy dutycsalas1986
 
TMQC-Pipeline NDT2015
TMQC-Pipeline NDT2015TMQC-Pipeline NDT2015
TMQC-Pipeline NDT2015Ping Hung Lee
 
Ut procedure general
Ut procedure generalUt procedure general
Ut procedure generalnaiduvs
 
Condition monitoring through non destructive testings of machine ppt
Condition monitoring through non destructive testings of machine pptCondition monitoring through non destructive testings of machine ppt
Condition monitoring through non destructive testings of machine pptmuchulucky
 
Alvarez superalloy718 2018-ppt
Alvarez superalloy718 2018-pptAlvarez superalloy718 2018-ppt
Alvarez superalloy718 2018-pptPedro Alvarez Moro
 
Fatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentFatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentNSW Environment and Planning
 
Defect Detection & Prevention in Cast Turbine Wheels
Defect Detection & Prevention in Cast Turbine WheelsDefect Detection & Prevention in Cast Turbine Wheels
Defect Detection & Prevention in Cast Turbine WheelsEddyfi
 
Presentation on Prospect of Non Destructive Testing and Condition Monitoring...
Presentation on Prospect of Non Destructive Testing and  Condition Monitoring...Presentation on Prospect of Non Destructive Testing and  Condition Monitoring...
Presentation on Prospect of Non Destructive Testing and Condition Monitoring...Ferdous Kabir
 
Metals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain Control
Metals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain ControlMetals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain Control
Metals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain ControlInstron
 
Covesion ppln
Covesion pplnCovesion ppln
Covesion pplnrobhaz
 
Research Overview Presentation
Research Overview PresentationResearch Overview Presentation
Research Overview PresentationMeaghan Ormrod
 
Metals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain Control
Metals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain ControlMetals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain Control
Metals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain ControlDavid Fry
 
Guided wave testing on insulated overhead pipeline for CUI
Guided wave testing on insulated overhead pipeline for CUIGuided wave testing on insulated overhead pipeline for CUI
Guided wave testing on insulated overhead pipeline for CUIPing Hung Lee
 
NDT Service of TMQC- 2016
NDT Service of TMQC- 2016NDT Service of TMQC- 2016
NDT Service of TMQC- 2016Ping Hung Lee
 

Mais procurados (20)

Study of Vibration Analysis of Rotating Shaft with Transverse Crack
Study of Vibration Analysis of Rotating Shaft with Transverse CrackStudy of Vibration Analysis of Rotating Shaft with Transverse Crack
Study of Vibration Analysis of Rotating Shaft with Transverse Crack
 
E367 dah heavy duty
E367 dah heavy dutyE367 dah heavy duty
E367 dah heavy duty
 
TMQC-Pipeline NDT2015
TMQC-Pipeline NDT2015TMQC-Pipeline NDT2015
TMQC-Pipeline NDT2015
 
Ut procedure general
Ut procedure generalUt procedure general
Ut procedure general
 
Condition monitoring through non destructive testings of machine ppt
Condition monitoring through non destructive testings of machine pptCondition monitoring through non destructive testings of machine ppt
Condition monitoring through non destructive testings of machine ppt
 
Alvarez superalloy718 2018-ppt
Alvarez superalloy718 2018-pptAlvarez superalloy718 2018-ppt
Alvarez superalloy718 2018-ppt
 
Fatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker PennimentFatigue and fracture of safety critical equipment Walker Penniment
Fatigue and fracture of safety critical equipment Walker Penniment
 
Defect Detection & Prevention in Cast Turbine Wheels
Defect Detection & Prevention in Cast Turbine WheelsDefect Detection & Prevention in Cast Turbine Wheels
Defect Detection & Prevention in Cast Turbine Wheels
 
Presentation on Prospect of Non Destructive Testing and Condition Monitoring...
Presentation on Prospect of Non Destructive Testing and  Condition Monitoring...Presentation on Prospect of Non Destructive Testing and  Condition Monitoring...
Presentation on Prospect of Non Destructive Testing and Condition Monitoring...
 
Metals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain Control
Metals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain ControlMetals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain Control
Metals Tensile Testing Standards: ISO 6892-1 ASTM E8/8M for Strain Control
 
Cercage cables
Cercage cablesCercage cables
Cercage cables
 
Instron machine
Instron machineInstron machine
Instron machine
 
Smart Pigging
Smart PiggingSmart Pigging
Smart Pigging
 
Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical
 
Covesion ppln
Covesion pplnCovesion ppln
Covesion ppln
 
C0342011019
C0342011019C0342011019
C0342011019
 
Research Overview Presentation
Research Overview PresentationResearch Overview Presentation
Research Overview Presentation
 
Metals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain Control
Metals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain ControlMetals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain Control
Metals Tensile Testing Standards - ISO 6892-1 ASTM E8/8M - Strain Control
 
Guided wave testing on insulated overhead pipeline for CUI
Guided wave testing on insulated overhead pipeline for CUIGuided wave testing on insulated overhead pipeline for CUI
Guided wave testing on insulated overhead pipeline for CUI
 
NDT Service of TMQC- 2016
NDT Service of TMQC- 2016NDT Service of TMQC- 2016
NDT Service of TMQC- 2016
 

Semelhante a FESI Forth Road Bridge - Where Are We Today - P Roffey

Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)fikireyesus
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)fikireyesus
 
Pipe wizard olympus
Pipe wizard olympusPipe wizard olympus
Pipe wizard olympusSungsoo Han
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyNSW Environment and Planning
 
WIRE ROPE FLAW DETECTOR_Updated.pdf
WIRE ROPE FLAW DETECTOR_Updated.pdfWIRE ROPE FLAW DETECTOR_Updated.pdf
WIRE ROPE FLAW DETECTOR_Updated.pdfMMMatrixIntegritySdn
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...
Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...
Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...Yuga Lendistanu
 
Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013
Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013
Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013John Hansen
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Thorne & Derrick International
 
3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant
3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant
3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater ResistantThorne & Derrick International
 
FEM Newsletter Spring 2013
FEM Newsletter Spring 2013FEM Newsletter Spring 2013
FEM Newsletter Spring 2013Paul Roffey
 
Testing to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt BridgeTesting to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt BridgeEva Lantsoght
 
electrical-wiring_WHY DO WE NEED ALL THIS COPPER
electrical-wiring_WHY DO WE NEED ALL THIS COPPERelectrical-wiring_WHY DO WE NEED ALL THIS COPPER
electrical-wiring_WHY DO WE NEED ALL THIS COPPERFAZLANNIZAM
 
Traction distribution
Traction distribution Traction distribution
Traction distribution Amit Kumar
 
9-24-CX-Rev-ASME presentation-final
9-24-CX-Rev-ASME presentation-final9-24-CX-Rev-ASME presentation-final
9-24-CX-Rev-ASME presentation-finalXiao CHEN
 

Semelhante a FESI Forth Road Bridge - Where Are We Today - P Roffey (20)

Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
 
Pipe wizard olympus
Pipe wizard olympusPipe wizard olympus
Pipe wizard olympus
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
Ellis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black BookEllis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black Book
 
Mechanical Testing.pptx
Mechanical Testing.pptxMechanical Testing.pptx
Mechanical Testing.pptx
 
FAMECA Transmission Earthing Devices
FAMECA Transmission Earthing Devices FAMECA Transmission Earthing Devices
FAMECA Transmission Earthing Devices
 
WIRE ROPE FLAW DETECTOR_Updated.pdf
WIRE ROPE FLAW DETECTOR_Updated.pdfWIRE ROPE FLAW DETECTOR_Updated.pdf
WIRE ROPE FLAW DETECTOR_Updated.pdf
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
80m XHD Webinar Slides
80m XHD Webinar Slides80m XHD Webinar Slides
80m XHD Webinar Slides
 
Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...
Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...
Weldability Study of AISI 1035 Steel Using Hydrated E6013 Electrode in Wet Tr...
 
Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013
Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013
Weld probe presentation- Given at COTEQ, Porto Galinhas, Brazil, June 2013
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
 
3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant
3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant
3M Scotchcast 82F2 Inline Submersible Offshore Cable Joint Seawater Resistant
 
FEM Newsletter Spring 2013
FEM Newsletter Spring 2013FEM Newsletter Spring 2013
FEM Newsletter Spring 2013
 
Testing to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt BridgeTesting to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt Bridge
 
Pullbox sizing
Pullbox sizingPullbox sizing
Pullbox sizing
 
electrical-wiring_WHY DO WE NEED ALL THIS COPPER
electrical-wiring_WHY DO WE NEED ALL THIS COPPERelectrical-wiring_WHY DO WE NEED ALL THIS COPPER
electrical-wiring_WHY DO WE NEED ALL THIS COPPER
 
Traction distribution
Traction distribution Traction distribution
Traction distribution
 
9-24-CX-Rev-ASME presentation-final
9-24-CX-Rev-ASME presentation-final9-24-CX-Rev-ASME presentation-final
9-24-CX-Rev-ASME presentation-final
 

FESI Forth Road Bridge - Where Are We Today - P Roffey

  • 1. © ESR Technology Ltd The Forth Road Bridge: Where Are We Today? Dr Paul Roffey BSc, CEng MIMMM Forensic Engineering & Materials
  • 2. © ESR Technology Ltd Overview • Brief history of the Forth Road suspension bridge • Basic construction • Inspection – practices, previous, current • Findings from 2012 inspection; – Coating integrity – Tensile strength evaluation – Fatigue test data – Fracture mechanisms • Future
  • 3. © ESR Technology Ltd History & Construction
  • 4. © ESR Technology Ltd Timeline Forth Rd Rail Bridge (opened 1890) Forth Rd Suspension Bridge (opened 1964) Forth Rd Cable Stay Bridge (opening 2016)
  • 5. © ESR Technology Ltd Aerial spinning of wires Construction • Constructed in 1964 at a cost of £19.5 million • 1006 metre span between towers • Main cables have 11,618 high tensile strength wires • The main cables are approximately 60 cm thick, the total length of wire would reach around the world 1.25 times! • Wires were aerially spun across the towers to build up the cables, compacted and circumferentially wrapped with 9 gauge wire followed by lead paste and wrapping. Finally the cables were painted. Anchoring of wires Installation of decks Circumferential wires
  • 6. © ESR Technology Ltd Inspections
  • 7. © ESR Technology Ltd Inspection Process & Sampling
  • 8. © ESR Technology Ltd Previous Inspections • 2004 - Bodycote 1st main cable inspection in Europe at cost of £2.75m following discovery of excessively corroded wires in US 10 panel locations investigated Estimated 8 – 10% loss of strength in cables Estimated closure of bridge in 2014 - 2020 Subsequently acoustic monitoring and dehumidification system added (2006- 09) • 2008 – Faber Maunsell 3 panel locations investigated (2 in previous inspection) – cost of £3.78m Agreed with previous estimation of strength loss but concluded more optimistic date of 2017 - 2021 more likely
  • 9. © ESR Technology Ltd 2012 Inspection (Flint & Neill Ltd / ESR Technology) • 8 panel locations investigated (4 East / 4 West) • All locations not previously investigated • Various ‘heights’ on cables • Inspection carried out according to NCHRP 534 – Laboratory testing included chemical analyses, Preece testing, galvanised coating weight loss, tensile testing, fatigue testing & fracture analysis • Results will allow 3rd point to be plotted on strength loss & life prediction and allow assessment of dehumidification system effectiveness
  • 10. © ESR Technology Ltd Panel Locations
  • 11. © ESR Technology Ltd Laboratory Testing
  • 12. © ESR Technology Ltd Galvanic Coating Tests Results showed wires adequately coated
  • 13. © ESR Technology Ltd Tensile Testing Corrosion stage No. specimens Ave. UTS (MPa) <1544 MPa Stage 1 65 1570 (51) 25 (38%) Stage 2 271 1574 (51) 91 (34%) Stage 3 467 1557 (64) 188 (40%) Stage 4 280 1530 (±67) 173 (62%) Total 1083 1555 (±63) 477 (44%) Panel No. specimens Ave. UTS (MPa) <1544 MPa (001) W94-92S 173 1572 (±67) 50 (002) W90-88N 183 1564 (±65) 62 (003) E94-92S 116 1589 (±56) 24 (004) W40-42S 69 1571 (±87) 26 (005) E100-98S 192 1544 (±51) 88 (006) E54-54S 61 1510 (±73) 45 (007) W52-50N 120 1535 (±44) 76 (008) E30-32S 169 1551 (±50) 106 Total East Cable 538 1549 (±59) 263 Total West Cable 545 1561 (±67) 214 Wedge location No. specimens Ave. UTS (MPa) <1544 MPa 12:00 94 1529 (±39) 58 01:30 124 1571 (±57) 44 03:00 143 1558 (±51) 52 04:30 135 1532 (±64) 75 06:00 121 1528 (±45) 78 07:30 134 1540 (±65) 69 09:00 184 1567 (±76) 67 10:30 148 1596 (±56) 34 • Performed to ASTM 586 and ASTM A370 • 254 mm gauge length • 1083 tests • Yield, UTS, elongation, RoA and E
  • 14. © ESR Technology Ltd Fatigue Testing • Test end point was failure, or, 2 million cycles – only S3 & S4 specimens. • The average number of cycles was calculated at 958,852. • Failure of the wire was found to occur when a fatigue crack reached between 1154 to 2830 µm. • The average crack depth however was calculated at 1420 µm. • Lowest number of cycles was 36,222 on specimens with ~2000 µm crack. Cyclic fatigue test summary (ASTM E466). Stage 3 Stage 4 No. of specimens 23 42 No. completed 2x106 cycles 12 5 No. of erroneous* 3 4 Failed 8 33 Average number of cycles to failure excluding erroneous values 617,927 547,095 Minimum number of cycles 131,517 36,222 Maximum number of cycles 1,686,881 1,952,165 *Test specimens which failed within the grips or region of stripped galvanising. • Performed in accordance with ASTM E466 • Instron fatigue rig with 50 kN transducer • Mean tensile stress: 618 N/mm2 ±139 N/mm2 • Loading: 40 Hz sine waveform
  • 15. © ESR Technology Ltd Fracture Mechanisms In-situ Fatigue Surface corrosion Feathery propagation Perpendicular ‘T’-crack
  • 16. © ESR Technology Ltd Where we are today... • The inspections have shown that over a period of almost 50 years the wires on the Forth Road Bridge have generally seen a reduction in tensile strength. • The current findings revealed that the newly installed dehumidification system appears to be slowing down the rate of corrosion of the wires. • The Forth Road Bridge main cables will continue to require internal inspections and strength evaluations for the remainder of the life of the bridge. • External condition of cable is not indicative of internal condition. • Further work required to fully understand the wire fracture mechanism. • Loading restrictions will be in effect ~2017.
  • 17. © ESR Technology Ltd Forth Road Suspension Bridge Questions?