SlideShare uma empresa Scribd logo
1 de 1
Analyzing the Entrance to “The Ridge” Using the SCS
Curve Number Method
Aaron Reeser, Patrick Cusack, Rachel Cron, & Dr. Tom Owino
BE 3220, Biosystems Engineering, Clemson University, Clemson, SC, 29631
Abstract
Introduction
Materials and Methods
Data & Governing Equations
Conclusions
References
1. Purvis, J. C., Tyler, W., Sidlow, S. (1988) Maximum Rainfall Intensity in South Carolina By County. South Carolina Department of Natural
Resources. Retrieved on April 30, 2019 from http://www.dnr.sc.gov/climate/sco/Publications/max_rain_intensity.php#chart
2. Jarrett, A. (2016). Rain Gardens (Bioretention Cells) – A Stormwater BMP. Pennsylvania State University. Retrieved on April 30, 2019 from
https://extension.psu.edu/rain-gardens-bioretention-cells-a-stormwater-bmp
3. Low Impact Development Center, Inc. (2007) Bioretention Costs. Retrieved on April 30, 2019 from https://www.lid-
stormwater.net/bio_costs.htm
4. Ding, B., Rezanezhad, F., Gharedaghloo, B., Van Cappellen, P., Passeport, E. (2019) Bioretention cells under cold climate conditions: Effects
of freezing and thawing on water infiltration, soil structure, and nutrient removal. Science of The Total Environment. Vol. 649 (749-759)
5. WebSoilSurvey. United States Department of Agriculture Natural Resources Conservation Service. Retrieved on April 30, 2019 from
https://websoilsurvey.sc.egov.usda.gov/App/WebSoilSurvey.aspx
6. Massachusetts government. Demonstration 3: Permeable Paving Materials and Bioretention in a Parking Lot. Retrieved on April 30, 2019 from
https://www.mass.gov/service-details/demonstration-3-permeable-paving-materials-and-bioretention-in-a-parking-lot
Acknowledgements
We would like to thank Dr. Tom Owino for his assistance and knowledge about surface water runoff.
Additionally, we would like to thank the Clemson University EES department for the equipment and lab space.
Results and Discussion
Curve Numbers
Ground type CN Source
Impervious
ground
98 Table 9-5
Brush, forbes,
grass; B; Poor
67 Table 9-1
Woods/grass 73 WinTR-55
<50% grass 79 WinTR-55
Soil Data
Hydro Soil Group B
Area [acres] 179.2
Soil Type
Hiwassee clay loam
(severely eroded)
K factor 0.28
Slope 2-6%
The Ridge is a new apartment complex located near Clemson University. As shown in
Figure 1, the entrance to The Ridge experiences a significant amount of pooling at the base
of the driveway. Since this is the only entrance into the complex, this pooling becomes
problematic during colder months. Several cars have been observed sliding on the frozen
water. If a car accident were to occur at the site, the construction company that built the road
could be liable for the damage. Additionally, as severe storms become more frequent, the
amount of runoff at the site may increase. Using the amount of runoff from the area,
calculated using the SCS Curve Number Method and WinTR-55, a solution to reduce the
amount of runoff to the bottom of the entrance can be designed. The design solution must
account for the types of soil cover and surfaces in the surrounding area, the rate of
precipitation during a major storm event, and general economic and logistical feasibility.
The area of interest is shown below in Figure 2. Using the Curve Number Method, and the
values contained in Table 1, the amount of runoff from a 100 yr, 24h storm, at the current site was
calculated to be 7.58 inches. The calculated peak discharge from the surrounding area was estimated
to 3.519 cfs. Figure 3 shows the unit peak hydrograph for the current site. The current design
reduces runoff from the surrounding areas by only 21.04%. The group chose to reduce the amount of
runoff to the base of the driveway by theoretically placing a bioretention cell at the base of the straw
and brushy hills, as shown below in Figure 2. This bioretention cell would need to be designed for
the specific characteristics of the site. Since the soil type of the area, Hiwassee clay loam soil, has
low permeability, the soil must be excavated approximately 2 to 4 feet deep in order to install the
underdrain system of the bioretention cell. Additionally, a rock bed, PE diaphragm, and native
vegetation, such as New England Aster and the Water Canna, could be added. The cost of this
bioretention cell would range from $5,000 to $15,000. The bioretention cell was intentionally
designed to be over 10 feet wide in order to preserve the health of the vegetation in the cell. The
length of the bioretention cell was designed to create an area equal to the size of the area the cell
would collect water from divided by 7.5; from literature, this ratio would result in the retention cell
reducing runoff by 90%.
After performing a second analysis of the site including the bioretention cell, using the values
shown in Table 2, the amount of runoff was calculated to be 5.45 inches, while the peak discharge
was estimated to be 2.744 cfs. This new design reduces runoff from the surrounding areas by
42.38%. This bioretention cell does not completely eliminate runoff flowing to the base of the road.
Ways to completely eliminate ponding at the base of the hill are not logistically nor economically
feasible for this site. Examples include filling the base of the road with concrete or adjusting the
shoulders of the road to divert water to storm drains. Not only are these adjustments expensive, but
since the street shown is the only entrance/exit from the complex, repaving the area would inhibit
residents from coming and going. The group chose to add a bioretention cell to the base of the steep
hill because it reduced the amount of runoff to the base of the driveway significantly while also
being the most feasible option logistically and economically. Over the course of performing
calculations and modeling the system, sources of error likely included approximating the shape of
each subarea, limited length input in WinTR-55, and idealizing the bioretention cell.
• WinTR-55 Modeling Software
• Web Soil Data website
• US Department of Natural
Resources website
• Tape measure
• iPhone Compass Application
• Charts and tables from class notes
The group visited the site to measure the dimensions
of the brushy hill, the straw hill, and the road with a
tape measure. Additionally, the slope of each section
was approximated using the compass app. The
group used Web Soil to determine the characteristics
of the site’s soil, US Department of Natural
Resources website to determine historical
precipitation data, and class notes to determine the
curve numbers for the site. The group then
calculated runoff using SCS Curve Number Method
equations and WinTR-55.
This project focuses on runoff at The Ridge apartment complex, aiming to reduce the amount
of water pooling at the entrance. Based on the initial calculations using runoff estimation
methods, like the curve number method and modeling the current design using WinTR-55, it
was concluded that an excess amount of water is being directed to the entrance. The amount
of runoff from a 100 yr, 24 hour storm at the current site was calculated to be 7.58 in, while
the peak discharge was calculated to be 3.519 cfs. Due to this flaw in the initial design, a new
layout that reduces the amount of runoff into the entrance is required. After reviewing several
possible solutions, a bioretention cell to contain and reduce the runoff was determined to be
the best option. It was the cheapest option, with a construction cost ranging from $5,000 to
$15,000. With the addition of a bioretention cell, the amount of runoff from a 100 yr, 24 hour
storm was calculated to be 5.45 inches, while the peak discharge was estimated to be 2.744
cfs. This option will reduce the amount of runoff to the entrance without shutting down the
road, which is the only access point in or out of the apartment complex. Since this issue was
not solved during the initial construction, building a bioretention cell is the best option to
reduce the amount of runoff that pools at the entrance to The Ridge apartment complex.
Certain technical questions may come to
mind when designing this new layout such
as: How much runoff is coming off the hill?
What is the surrounding soil comprised of?
How is this new design better than the old
one? The main objectives of this project are
to calculate the current amount of runoff on-
site using the SCS Curve Number Method &
design site adjustments to reduce the amount
of water pooling at the entrance of The
Ridge apartment complex in the most
environmentally, socially, and economically
beneficial way possible.
𝑆 =
1000
𝐶𝑁
− 10
𝑄 =
𝑃 − 0.2𝑆 2
𝑃 + 0.8𝑆
𝑊𝑒𝑖𝑔ℎ𝑡𝑒𝑑 𝑄 =
𝑄 ∗ 𝐴
𝐴
% 𝑅𝑢𝑛𝑜𝑓𝑓 𝑅𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 =
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑃𝑟𝑒𝑐𝑖𝑝𝑖𝑡𝑎𝑡𝑖𝑜𝑛 − 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑅𝑢𝑛𝑜𝑓𝑓
(𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑃𝑟𝑒𝑐𝑖𝑝𝑖𝑡𝑎𝑡𝑖𝑜𝑛)
∗ 100
𝐿 =
(𝑙0.8
∗ 𝑆 + 1 0.7
)
1900 ∗ 𝑌0.5
𝑡 𝑐 =
0.6
𝑙𝑎𝑔 𝑡𝑖𝑚𝑒
𝑄 𝑝 = 𝑞 𝑝 ∗ 𝐴 ∗ 𝑄
Figure 1: Pooled runoff at the entrance to The Ridge after a rain storm event
Figure 2: Above view of
surrounding areas that
contribute runoff to The
Ridge entrance.
Table 1: Weighted Q data, used to calculate runoff, for the current area design
Figure 3: Unit peak
hydrograph for a 100-yr
storm for the current area
design
Table 2: Weighted Q data, used to calculate runoff, for the proposed area design
Runoff at the entrance to The Ridge could have been initially avoided had the base of the
driveway been filled and shaped to divert water to the storm drains. Implementing a
bioretention cell is the most feasible option for reducing runoff to the base of The Ridge’s
entrance, as compared with other options such as repaving the base of the driveway, adding
additional storm drains, or improving the shoulders of the driveway to carry water more
efficiently. The reason reducing runoff at the site is important is because it would reduce
the risk of an accident occurring during the cold seasons when the water may freeze. An
accident caused by a design flaw could bring up a lawsuit between the resident and the
construction company. In addition to a bioretention cell being the most economically and
logistically feasible solution, it is also designed to be comprised of native vegetation and
environmentally-friendly, which is an over-arching goal of biosystems engineering.

Mais conteúdo relacionado

Mais procurados

Estimation of surface runoff in nallur amanikere
Estimation of surface runoff in nallur amanikereEstimation of surface runoff in nallur amanikere
Estimation of surface runoff in nallur amanikereeSAT Publishing House
 
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...Michael Hewitt, GISP
 
Statistical Model to Analyze the Impact of Land use Activity for District Lud...
Statistical Model to Analyze the Impact of Land use Activity for District Lud...Statistical Model to Analyze the Impact of Land use Activity for District Lud...
Statistical Model to Analyze the Impact of Land use Activity for District Lud...IRJET Journal
 
Rainfall runoff analysis of a compacted area
Rainfall runoff analysis of a compacted areaRainfall runoff analysis of a compacted area
Rainfall runoff analysis of a compacted areawalled ashwah
 
Water resource model modflow
Water resource model modflowWater resource model modflow
Water resource model modflowManoj Patley
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christijeshaml10
 
Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...
Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...
Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...Dhiraj Jhunjhunwala
 
RAINFALL RUNOFF MODELLING USING HEC-HMS
RAINFALL RUNOFF MODELLING                USING HEC-HMSRAINFALL RUNOFF MODELLING                USING HEC-HMS
RAINFALL RUNOFF MODELLING USING HEC-HMSPushp Aggarwal
 

Mais procurados (20)

Estimation of surface runoff in nallur amanikere
Estimation of surface runoff in nallur amanikereEstimation of surface runoff in nallur amanikere
Estimation of surface runoff in nallur amanikere
 
16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA
16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA
16 Aug-2013 - Ary van der Lely - A stratigraphic model of the MIA
 
GROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEMGROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEM
 
Runoff estimation and water management for Holetta River, Awash subbasin, Eth...
Runoff estimation and water management for Holetta River, Awash subbasin, Eth...Runoff estimation and water management for Holetta River, Awash subbasin, Eth...
Runoff estimation and water management for Holetta River, Awash subbasin, Eth...
 
Ph d presentation npc final
Ph d presentation npc finalPh d presentation npc final
Ph d presentation npc final
 
Caes yakima full report
Caes yakima full reportCaes yakima full report
Caes yakima full report
 
Water balance & management
Water balance & managementWater balance & management
Water balance & management
 
Understanding impacts of sustainable land management interventions using SWAT...
Understanding impacts of sustainable land management interventions using SWAT...Understanding impacts of sustainable land management interventions using SWAT...
Understanding impacts of sustainable land management interventions using SWAT...
 
Swat model
Swat model Swat model
Swat model
 
Presentation_Niraj_Final
Presentation_Niraj_Final Presentation_Niraj_Final
Presentation_Niraj_Final
 
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
 
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
Matt MacConnell, Lehigh River Stocking Association, “Lausanne Tunnel Remediat...
 
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
 
2013.05.21 public meeting_3
2013.05.21 public meeting_32013.05.21 public meeting_3
2013.05.21 public meeting_3
 
Statistical Model to Analyze the Impact of Land use Activity for District Lud...
Statistical Model to Analyze the Impact of Land use Activity for District Lud...Statistical Model to Analyze the Impact of Land use Activity for District Lud...
Statistical Model to Analyze the Impact of Land use Activity for District Lud...
 
Rainfall runoff analysis of a compacted area
Rainfall runoff analysis of a compacted areaRainfall runoff analysis of a compacted area
Rainfall runoff analysis of a compacted area
 
Water resource model modflow
Water resource model modflowWater resource model modflow
Water resource model modflow
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christi
 
Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...
Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...
Using Computer-simulated hydrological model (SWAT) to estimate the ground-wat...
 
RAINFALL RUNOFF MODELLING USING HEC-HMS
RAINFALL RUNOFF MODELLING                USING HEC-HMSRAINFALL RUNOFF MODELLING                USING HEC-HMS
RAINFALL RUNOFF MODELLING USING HEC-HMS
 

Semelhante a Hydrology Final Poster

Capstone Midterm
Capstone MidtermCapstone Midterm
Capstone Midtermdchewni
 
Charleston midterm
Charleston midtermCharleston midterm
Charleston midtermbtdubos
 
Final Report_Edited by JC and KP
Final Report_Edited by JC and KPFinal Report_Edited by JC and KP
Final Report_Edited by JC and KPJared Cordes
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage designdobariya axit
 
Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.Jonathan Damora
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxPRACHI DESSAI
 
Charleston presentation final
Charleston presentation finalCharleston presentation final
Charleston presentation finalkcreswell
 
Midterm cu stormwater report.docx
Midterm cu stormwater report.docxMidterm cu stormwater report.docx
Midterm cu stormwater report.docxcbwalke
 
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Fu Michael Justin
 
Hydrology final poster
Hydrology final posterHydrology final poster
Hydrology final posterAshtonGuest
 
130618_ CF_rainwater harvest_report_issue 2
130618_ CF_rainwater harvest_report_issue 2130618_ CF_rainwater harvest_report_issue 2
130618_ CF_rainwater harvest_report_issue 2Gordon Hirst
 
Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Ashleigh Hough
 
Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Ashleigh Hough
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wallvikas Meena
 
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IAASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IADavid Koser
 
Macro Sustainability Methodologies project
Macro Sustainability Methodologies projectMacro Sustainability Methodologies project
Macro Sustainability Methodologies projectShironika Farrior
 
Water Efficiency Presentation
Water Efficiency PresentationWater Efficiency Presentation
Water Efficiency Presentationcurt_jawdy
 

Semelhante a Hydrology Final Poster (20)

Capstone Midterm
Capstone MidtermCapstone Midterm
Capstone Midterm
 
Charleston midterm
Charleston midtermCharleston midterm
Charleston midterm
 
Final Report_Edited by JC and KP
Final Report_Edited by JC and KPFinal Report_Edited by JC and KP
Final Report_Edited by JC and KP
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
 
Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.Group Project to Design Water Infrastructure for a Theoretical Small Town.
Group Project to Design Water Infrastructure for a Theoretical Small Town.
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptx
 
Charleston presentation final
Charleston presentation finalCharleston presentation final
Charleston presentation final
 
Midterm cu stormwater report.docx
Midterm cu stormwater report.docxMidterm cu stormwater report.docx
Midterm cu stormwater report.docx
 
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
 
Hydrology final poster
Hydrology final posterHydrology final poster
Hydrology final poster
 
7th class
7th class7th class
7th class
 
130618_ CF_rainwater harvest_report_issue 2
130618_ CF_rainwater harvest_report_issue 2130618_ CF_rainwater harvest_report_issue 2
130618_ CF_rainwater harvest_report_issue 2
 
Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015
 
Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wall
 
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IAASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
 
Macro Sustainability Methodologies project
Macro Sustainability Methodologies projectMacro Sustainability Methodologies project
Macro Sustainability Methodologies project
 
Poster
PosterPoster
Poster
 
CE573_Poster2
CE573_Poster2CE573_Poster2
CE573_Poster2
 
Water Efficiency Presentation
Water Efficiency PresentationWater Efficiency Presentation
Water Efficiency Presentation
 

Mais de Patrick Cusack

Utilization of Biosolids: Soil Fertilization & Energy Production
Utilization of Biosolids: Soil Fertilization & Energy ProductionUtilization of Biosolids: Soil Fertilization & Energy Production
Utilization of Biosolids: Soil Fertilization & Energy ProductionPatrick Cusack
 
Final presentation for utilization of biosludge
Final presentation for utilization of biosludgeFinal presentation for utilization of biosludge
Final presentation for utilization of biosludgePatrick Cusack
 
NOT Final Senior Design Project
NOT Final Senior Design ProjectNOT Final Senior Design Project
NOT Final Senior Design ProjectPatrick Cusack
 
Microbial Fuel Cell Presentation
Microbial Fuel Cell PresentationMicrobial Fuel Cell Presentation
Microbial Fuel Cell PresentationPatrick Cusack
 
Heat & Mass Final Project
Heat & Mass Final ProjectHeat & Mass Final Project
Heat & Mass Final ProjectPatrick Cusack
 
Bioprocessing Engineering Design Presentation
Bioprocessing Engineering Design PresentationBioprocessing Engineering Design Presentation
Bioprocessing Engineering Design PresentationPatrick Cusack
 

Mais de Patrick Cusack (7)

Utilization of Biosolids: Soil Fertilization & Energy Production
Utilization of Biosolids: Soil Fertilization & Energy ProductionUtilization of Biosolids: Soil Fertilization & Energy Production
Utilization of Biosolids: Soil Fertilization & Energy Production
 
Final presentation for utilization of biosludge
Final presentation for utilization of biosludgeFinal presentation for utilization of biosludge
Final presentation for utilization of biosludge
 
NOT Final Senior Design Project
NOT Final Senior Design ProjectNOT Final Senior Design Project
NOT Final Senior Design Project
 
Biological Kinetics
Biological Kinetics Biological Kinetics
Biological Kinetics
 
Microbial Fuel Cell Presentation
Microbial Fuel Cell PresentationMicrobial Fuel Cell Presentation
Microbial Fuel Cell Presentation
 
Heat & Mass Final Project
Heat & Mass Final ProjectHeat & Mass Final Project
Heat & Mass Final Project
 
Bioprocessing Engineering Design Presentation
Bioprocessing Engineering Design PresentationBioprocessing Engineering Design Presentation
Bioprocessing Engineering Design Presentation
 

Último

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 

Último (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 

Hydrology Final Poster

  • 1. Analyzing the Entrance to “The Ridge” Using the SCS Curve Number Method Aaron Reeser, Patrick Cusack, Rachel Cron, & Dr. Tom Owino BE 3220, Biosystems Engineering, Clemson University, Clemson, SC, 29631 Abstract Introduction Materials and Methods Data & Governing Equations Conclusions References 1. Purvis, J. C., Tyler, W., Sidlow, S. (1988) Maximum Rainfall Intensity in South Carolina By County. South Carolina Department of Natural Resources. Retrieved on April 30, 2019 from http://www.dnr.sc.gov/climate/sco/Publications/max_rain_intensity.php#chart 2. Jarrett, A. (2016). Rain Gardens (Bioretention Cells) – A Stormwater BMP. Pennsylvania State University. Retrieved on April 30, 2019 from https://extension.psu.edu/rain-gardens-bioretention-cells-a-stormwater-bmp 3. Low Impact Development Center, Inc. (2007) Bioretention Costs. Retrieved on April 30, 2019 from https://www.lid- stormwater.net/bio_costs.htm 4. Ding, B., Rezanezhad, F., Gharedaghloo, B., Van Cappellen, P., Passeport, E. (2019) Bioretention cells under cold climate conditions: Effects of freezing and thawing on water infiltration, soil structure, and nutrient removal. Science of The Total Environment. Vol. 649 (749-759) 5. WebSoilSurvey. United States Department of Agriculture Natural Resources Conservation Service. Retrieved on April 30, 2019 from https://websoilsurvey.sc.egov.usda.gov/App/WebSoilSurvey.aspx 6. Massachusetts government. Demonstration 3: Permeable Paving Materials and Bioretention in a Parking Lot. Retrieved on April 30, 2019 from https://www.mass.gov/service-details/demonstration-3-permeable-paving-materials-and-bioretention-in-a-parking-lot Acknowledgements We would like to thank Dr. Tom Owino for his assistance and knowledge about surface water runoff. Additionally, we would like to thank the Clemson University EES department for the equipment and lab space. Results and Discussion Curve Numbers Ground type CN Source Impervious ground 98 Table 9-5 Brush, forbes, grass; B; Poor 67 Table 9-1 Woods/grass 73 WinTR-55 <50% grass 79 WinTR-55 Soil Data Hydro Soil Group B Area [acres] 179.2 Soil Type Hiwassee clay loam (severely eroded) K factor 0.28 Slope 2-6% The Ridge is a new apartment complex located near Clemson University. As shown in Figure 1, the entrance to The Ridge experiences a significant amount of pooling at the base of the driveway. Since this is the only entrance into the complex, this pooling becomes problematic during colder months. Several cars have been observed sliding on the frozen water. If a car accident were to occur at the site, the construction company that built the road could be liable for the damage. Additionally, as severe storms become more frequent, the amount of runoff at the site may increase. Using the amount of runoff from the area, calculated using the SCS Curve Number Method and WinTR-55, a solution to reduce the amount of runoff to the bottom of the entrance can be designed. The design solution must account for the types of soil cover and surfaces in the surrounding area, the rate of precipitation during a major storm event, and general economic and logistical feasibility. The area of interest is shown below in Figure 2. Using the Curve Number Method, and the values contained in Table 1, the amount of runoff from a 100 yr, 24h storm, at the current site was calculated to be 7.58 inches. The calculated peak discharge from the surrounding area was estimated to 3.519 cfs. Figure 3 shows the unit peak hydrograph for the current site. The current design reduces runoff from the surrounding areas by only 21.04%. The group chose to reduce the amount of runoff to the base of the driveway by theoretically placing a bioretention cell at the base of the straw and brushy hills, as shown below in Figure 2. This bioretention cell would need to be designed for the specific characteristics of the site. Since the soil type of the area, Hiwassee clay loam soil, has low permeability, the soil must be excavated approximately 2 to 4 feet deep in order to install the underdrain system of the bioretention cell. Additionally, a rock bed, PE diaphragm, and native vegetation, such as New England Aster and the Water Canna, could be added. The cost of this bioretention cell would range from $5,000 to $15,000. The bioretention cell was intentionally designed to be over 10 feet wide in order to preserve the health of the vegetation in the cell. The length of the bioretention cell was designed to create an area equal to the size of the area the cell would collect water from divided by 7.5; from literature, this ratio would result in the retention cell reducing runoff by 90%. After performing a second analysis of the site including the bioretention cell, using the values shown in Table 2, the amount of runoff was calculated to be 5.45 inches, while the peak discharge was estimated to be 2.744 cfs. This new design reduces runoff from the surrounding areas by 42.38%. This bioretention cell does not completely eliminate runoff flowing to the base of the road. Ways to completely eliminate ponding at the base of the hill are not logistically nor economically feasible for this site. Examples include filling the base of the road with concrete or adjusting the shoulders of the road to divert water to storm drains. Not only are these adjustments expensive, but since the street shown is the only entrance/exit from the complex, repaving the area would inhibit residents from coming and going. The group chose to add a bioretention cell to the base of the steep hill because it reduced the amount of runoff to the base of the driveway significantly while also being the most feasible option logistically and economically. Over the course of performing calculations and modeling the system, sources of error likely included approximating the shape of each subarea, limited length input in WinTR-55, and idealizing the bioretention cell. • WinTR-55 Modeling Software • Web Soil Data website • US Department of Natural Resources website • Tape measure • iPhone Compass Application • Charts and tables from class notes The group visited the site to measure the dimensions of the brushy hill, the straw hill, and the road with a tape measure. Additionally, the slope of each section was approximated using the compass app. The group used Web Soil to determine the characteristics of the site’s soil, US Department of Natural Resources website to determine historical precipitation data, and class notes to determine the curve numbers for the site. The group then calculated runoff using SCS Curve Number Method equations and WinTR-55. This project focuses on runoff at The Ridge apartment complex, aiming to reduce the amount of water pooling at the entrance. Based on the initial calculations using runoff estimation methods, like the curve number method and modeling the current design using WinTR-55, it was concluded that an excess amount of water is being directed to the entrance. The amount of runoff from a 100 yr, 24 hour storm at the current site was calculated to be 7.58 in, while the peak discharge was calculated to be 3.519 cfs. Due to this flaw in the initial design, a new layout that reduces the amount of runoff into the entrance is required. After reviewing several possible solutions, a bioretention cell to contain and reduce the runoff was determined to be the best option. It was the cheapest option, with a construction cost ranging from $5,000 to $15,000. With the addition of a bioretention cell, the amount of runoff from a 100 yr, 24 hour storm was calculated to be 5.45 inches, while the peak discharge was estimated to be 2.744 cfs. This option will reduce the amount of runoff to the entrance without shutting down the road, which is the only access point in or out of the apartment complex. Since this issue was not solved during the initial construction, building a bioretention cell is the best option to reduce the amount of runoff that pools at the entrance to The Ridge apartment complex. Certain technical questions may come to mind when designing this new layout such as: How much runoff is coming off the hill? What is the surrounding soil comprised of? How is this new design better than the old one? The main objectives of this project are to calculate the current amount of runoff on- site using the SCS Curve Number Method & design site adjustments to reduce the amount of water pooling at the entrance of The Ridge apartment complex in the most environmentally, socially, and economically beneficial way possible. 𝑆 = 1000 𝐶𝑁 − 10 𝑄 = 𝑃 − 0.2𝑆 2 𝑃 + 0.8𝑆 𝑊𝑒𝑖𝑔ℎ𝑡𝑒𝑑 𝑄 = 𝑄 ∗ 𝐴 𝐴 % 𝑅𝑢𝑛𝑜𝑓𝑓 𝑅𝑒𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑃𝑟𝑒𝑐𝑖𝑝𝑖𝑡𝑎𝑡𝑖𝑜𝑛 − 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑅𝑢𝑛𝑜𝑓𝑓 (𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑃𝑟𝑒𝑐𝑖𝑝𝑖𝑡𝑎𝑡𝑖𝑜𝑛) ∗ 100 𝐿 = (𝑙0.8 ∗ 𝑆 + 1 0.7 ) 1900 ∗ 𝑌0.5 𝑡 𝑐 = 0.6 𝑙𝑎𝑔 𝑡𝑖𝑚𝑒 𝑄 𝑝 = 𝑞 𝑝 ∗ 𝐴 ∗ 𝑄 Figure 1: Pooled runoff at the entrance to The Ridge after a rain storm event Figure 2: Above view of surrounding areas that contribute runoff to The Ridge entrance. Table 1: Weighted Q data, used to calculate runoff, for the current area design Figure 3: Unit peak hydrograph for a 100-yr storm for the current area design Table 2: Weighted Q data, used to calculate runoff, for the proposed area design Runoff at the entrance to The Ridge could have been initially avoided had the base of the driveway been filled and shaped to divert water to the storm drains. Implementing a bioretention cell is the most feasible option for reducing runoff to the base of The Ridge’s entrance, as compared with other options such as repaving the base of the driveway, adding additional storm drains, or improving the shoulders of the driveway to carry water more efficiently. The reason reducing runoff at the site is important is because it would reduce the risk of an accident occurring during the cold seasons when the water may freeze. An accident caused by a design flaw could bring up a lawsuit between the resident and the construction company. In addition to a bioretention cell being the most economically and logistically feasible solution, it is also designed to be comprised of native vegetation and environmentally-friendly, which is an over-arching goal of biosystems engineering.