SlideShare uma empresa Scribd logo
1 de 22
Baixar para ler offline
Tiago de Barros Correia
Director
February 29, 2016
Paris, France
Impact and Value During and
After Construction
22
Topics
 Brazilian tidbits and Brazilian Power Sector
overview
 About us
 Brazilian strategy to develop key
infrastructure projects
 Impact and value
33
 Total area 8,515 million km2 (83% of Europe)
 Total Population – 2015 205 million inhabitants (27% of Europe)
 Overall GDP – 2014 U$1,715 billion
 Installed capacity 141,631 MW
 Peak load 84,958 MW (Feb 2014)
 Electricity Consumption per Capita 2,664.15 kWh
 Average Energy Consumption Growth Annual Rate 4%
BRASIL SUMMARY
Electricity Supply Mix
80% of the electricity supply
mix is renewable
4,441 plants in operation
with a total 141 GW of
installed capacity
834 new projects granted,
increasing the capacity by
27% (39 GW) by 2021
Fossil Fuel
19%
Nuclear
1%
Biomass
9%
Hydro
65%
Wind
6%
Solar
0%
Transmission Grid
230kV ac
345kV ac
440kV ac
500kV ac
700kV ac
600kV cc
800kV cc
125,644 km of transmission
lines
Expansion of 10,400 km
until 2019 (8%)
Auctioning of R$ 30 billion
of new Investments only in
2016
If our Transmission Grid Were in Europe...
77
Topics
 Brazilian tidbits and Brazilian Power Sector
overview
 About us
 Brazilian strategy to develop key
infrastructure projects
 Impact and value
ANEEL Board of Directors Open
Sessions
› Decisions are made by the Board of Directors (5)
› Board sessions are open to the public participation and is
transmitted live over the web
› Cases are distributed to each Director by lottery
› Case settling relies on technical and legal analyses
99
Topics
 Brazilian tidbits and Brazilian Power Sector
overview
 About us
 Brazilian strategy to develop key
infrastructure projects
 Impact and value
1010
Infrastructure governance cycle
1. Evaluation of
infrastructure
needs
2. Decision and
prioritization
3. Project preparation
4. Auctioning
5. Executive project and
licensing
6. Construction
operation and
maintenance
1111
Topics
 Brazilian tidbits and Brazilian Power Sector
overview
 About us
 Brazilian strategy to develop key
infrastructure projects
 Impact and value
1212
Value for Money
“How much is too much?”
Economics Efficiency
Can we get equivalent
infrastructure for less
money?
Can we get the same results
while saving money and
time depending on how we
manage the process?
Would savings regarding the economics and efficiency of the Project risk
its effectiveness and sustainability?
1313
Sustainability trail
Goal
 GHG emissions
 Renewable
sources
 Distributed
generation
 Power losses
Pathway (Long Term Plan)
Resources and
technology
availability
Budget
constraints
Regulation
Subsidies
Strategic
Projects
Externalities (Global and Local)
Life Time Analysis
Environmental
 Economic
 Social
Jobs
Health
Mitigation and
Compensation
Execution
Assurance of
project
commitments
Accountability
Secure
stakeholders
acceptance and
approval
1414
Learning by Doing
But we deal with uncertainty and
sometimes we need to get back
on trail and try harder
To do that we need stakeholders
support
Again, accountability appears as a
key concept
1515
Impact and value – Transmission
Good Economics
Since 1999 the Brazilian Government has been conducting
auctions to contract transmission services from greenfield
projects. The auctions procure long term contracts (30 years)
and define the transmission services to be delivered and the
construction time line.
Applicants need to meet certain criteria in order to be accepted
for participation in the auctions. This design intends to ensure
that the project offered will meet environmental, technical and
economic requirements of quality .
Bidders with the lowest proposed prices are the winners.
1616
1.0
7.7
0.8
2.2
3.5
6.1
5.0
3.0
1.7
13.9
4.5
2.5
7.0
10.5 10.2
13.3 13.3
30.6
0
5
10
15
20
25
30
35
Investment in Billions of (R$)
Concessions Granted and Expected till the end of 2016* - present
value
(*assumes all contracts signed)
1717
Impact and value – Transmission
Low Efficiency
% of projects with delays for each required
phase.
With delay
Early start
In time
Unknown
1818
8/28/2013 - Last Major Disturbance
taken place in the Interconnected Grid.
Load Loss: ~11GW
Cut off Consummers : 17.5 million
Fault Clearance Time: 4 hours
Cause: Fire
Impact and value – Transmission
Good Effectiveness
Availability of transmission lines in the last 5 years (%)
Load Restoration in the Northeast
1919
Scope
 General goals
 Governance arrangement
 Budget (funding and
finance)
Public Policy
Major Risks
 Unrealistic goals
 Bad governance
 Insufficient resources
Risk-Bearing
 Government
 Society
Scope
 Strategic Projects
 Pricing and Timing
 Previous License
 Stakeholders support
Planning
Major Risks
 Social and Environmental
feasibility
 Stakeholders support
(not in my backyard!)
Risk-Bearing
 Government
 Society
2020
Scope
 Contract design
 Auction design
Auctioning
Major Risks
 Collusion
 Bidless Auctions
 Winner’s Curse
Risk-Bearing
 Government
 Society
 Winner (Entrepreneur)
Scope
 Executive Project
 Final Licenses
 Construction
 Project Compliance
Construction
Major Risks
 Licensing delay
 Exchange rate
 Capital cost
 Bad Project
 New Environmental
Agency requirements
(studies and mitigation
measures)
 Weather
Risk-Bearing
 Government
 Society
 Entrepreneur
2121
Scope
 Power Capacity
 Energy Generation
 Transmissions Services
Operation
Major Risks
 Inflation
 Non concatenation
(generation and
transmission)
 Blackout (bad planning)
 Bad performance
 Market exposure
Risk-Bearing
 Consumer
 Entrepreneur
2222
SGAN – Quadra 603
Módulos “I” e “J”
CEP: 70.830-110 /Brasília – DF
Tel.: 55 (61) 2192-8604
tiago@aneel.gov.br
Thank you!

Mais conteúdo relacionado

Mais procurados

RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -
RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -
RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -energydialog
 
Long-term energy scenarios for the clean energy transition: possible engageme...
Long-term energy scenarios for the clean energy transition: possible engageme...Long-term energy scenarios for the clean energy transition: possible engageme...
Long-term energy scenarios for the clean energy transition: possible engageme...IEA-ETSAP
 
The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...
The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...
The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...OECD Governance
 
Issues in Public Private Partnership in India
Issues in Public Private Partnership in India Issues in Public Private Partnership in India
Issues in Public Private Partnership in India IPPAI
 
Hot topics on public private partnerships
Hot topics on public private partnershipsHot topics on public private partnerships
Hot topics on public private partnershipsSamuel Elusoji
 
Developing Climate Friendly Economies in Central Asia
Developing Climate Friendly Economies in Central AsiaDeveloping Climate Friendly Economies in Central Asia
Developing Climate Friendly Economies in Central AsiaCIFOR-ICRAF
 
Financing Suppportes NAMAs
Financing Suppportes NAMAsFinancing Suppportes NAMAs
Financing Suppportes NAMAsCIFOR-ICRAF
 
Saudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projectsSaudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projectsIbrahim Al-Hudhaif
 
CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...
CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...
CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...OECD Environment
 
Enabling Factors, Part III, Capacity building | Lena Klockemann, GIZ
Enabling Factors, Part III, Capacity building | Lena Klockemann, GIZEnabling Factors, Part III, Capacity building | Lena Klockemann, GIZ
Enabling Factors, Part III, Capacity building | Lena Klockemann, GIZNAP Global Network
 
Making the demand side more investable 12 9 17-2
Making the demand side more investable 12 9 17-2Making the demand side more investable 12 9 17-2
Making the demand side more investable 12 9 17-2Steven Fawkes
 
PPP for regional development - Lee MIZELL, Consultant
PPP for regional development - Lee MIZELL, ConsultantPPP for regional development - Lee MIZELL, Consultant
PPP for regional development - Lee MIZELL, ConsultantOECD Governance
 
Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018Audrey Mwala
 
CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...
CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...
CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...OECD Environment
 
Accelerating Investment in Energy Efficiency
Accelerating Investment in Energy Efficiency Accelerating Investment in Energy Efficiency
Accelerating Investment in Energy Efficiency Steven Fawkes
 

Mais procurados (20)

RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -
RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -
RISK MITIGATION - KEY TO CHEAPER RENEWABLE ENERGY -
 
Long-term energy scenarios for the clean energy transition: possible engageme...
Long-term energy scenarios for the clean energy transition: possible engageme...Long-term energy scenarios for the clean energy transition: possible engageme...
Long-term energy scenarios for the clean energy transition: possible engageme...
 
Source Presentation to AIIB
Source Presentation to AIIBSource Presentation to AIIB
Source Presentation to AIIB
 
The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...
The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...
The governance of mega infrastructure projects - Juliane JANSEN, OECD Secreta...
 
Issues in Public Private Partnership in India
Issues in Public Private Partnership in India Issues in Public Private Partnership in India
Issues in Public Private Partnership in India
 
Ford Foundation - The Just City by Amy Kenyon at GIB Summit
Ford Foundation - The Just City by Amy Kenyon at GIB SummitFord Foundation - The Just City by Amy Kenyon at GIB Summit
Ford Foundation - The Just City by Amy Kenyon at GIB Summit
 
Hot topics on public private partnerships
Hot topics on public private partnershipsHot topics on public private partnerships
Hot topics on public private partnerships
 
Developing Climate Friendly Economies in Central Asia
Developing Climate Friendly Economies in Central AsiaDeveloping Climate Friendly Economies in Central Asia
Developing Climate Friendly Economies in Central Asia
 
Innovative Financing Mechnisms and Tools
Innovative Financing Mechnisms and ToolsInnovative Financing Mechnisms and Tools
Innovative Financing Mechnisms and Tools
 
Financing Suppportes NAMAs
Financing Suppportes NAMAsFinancing Suppportes NAMAs
Financing Suppportes NAMAs
 
Saudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projectsSaudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projects
 
CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...
CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...
CCXG Global Forum March 2018, Transparency of CB and TT support – a Swiss pe...
 
Enabling Factors, Part III, Capacity building | Lena Klockemann, GIZ
Enabling Factors, Part III, Capacity building | Lena Klockemann, GIZEnabling Factors, Part III, Capacity building | Lena Klockemann, GIZ
Enabling Factors, Part III, Capacity building | Lena Klockemann, GIZ
 
Making the demand side more investable 12 9 17-2
Making the demand side more investable 12 9 17-2Making the demand side more investable 12 9 17-2
Making the demand side more investable 12 9 17-2
 
PPP for regional development - Lee MIZELL, Consultant
PPP for regional development - Lee MIZELL, ConsultantPPP for regional development - Lee MIZELL, Consultant
PPP for regional development - Lee MIZELL, Consultant
 
Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018
 
CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...
CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...
CCXG Global Forum March 2018 Summary Slides Breakout Groups 4 and 5 by Hugh S...
 
Accelerating Investment in Energy Efficiency
Accelerating Investment in Energy Efficiency Accelerating Investment in Energy Efficiency
Accelerating Investment in Energy Efficiency
 
GIB2015_Solid Standards and Ratings_Schneider_Roos
GIB2015_Solid Standards and Ratings_Schneider_RoosGIB2015_Solid Standards and Ratings_Schneider_Roos
GIB2015_Solid Standards and Ratings_Schneider_Roos
 
GIB2015_Solid Standards and Ratings_Georgoulias
GIB2015_Solid Standards and Ratings_GeorgouliasGIB2015_Solid Standards and Ratings_Georgoulias
GIB2015_Solid Standards and Ratings_Georgoulias
 

Destaque

Mobilising support & resources for infrastructure strategies - Philip Davies,...
Mobilising support & resources for infrastructure strategies - Philip Davies,...Mobilising support & resources for infrastructure strategies - Philip Davies,...
Mobilising support & resources for infrastructure strategies - Philip Davies,...OECD Governance
 
The Italian Infrastructure Framework - Gabriele Pasquini, Italy
The Italian Infrastructure Framework - Gabriele Pasquini, ItalyThe Italian Infrastructure Framework - Gabriele Pasquini, Italy
The Italian Infrastructure Framework - Gabriele Pasquini, ItalyOECD Governance
 
Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...
Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...
Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...OECD Governance
 
A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...
A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...
A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...OECD Governance
 
Mobilising support and resources for infrastructures strategies - "Logros y d...
Mobilising support and resources for infrastructures strategies - "Logros y d...Mobilising support and resources for infrastructures strategies - "Logros y d...
Mobilising support and resources for infrastructures strategies - "Logros y d...OECD Governance
 
Mexico City new international airport - Frederico Patino, Mexico
Mexico City new international airport - Frederico Patino, MexicoMexico City new international airport - Frederico Patino, Mexico
Mexico City new international airport - Frederico Patino, MexicoOECD Governance
 
Transparency & Integrity - Petter Matthews, United Kingdom
Transparency & Integrity - Petter Matthews, United KingdomTransparency & Integrity - Petter Matthews, United Kingdom
Transparency & Integrity - Petter Matthews, United KingdomOECD Governance
 
Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...
Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...
Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...OECD Governance
 
Project Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United KingdomProject Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United KingdomOECD Governance
 
Crossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United KingdomCrossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United KingdomOECD Governance
 

Destaque (10)

Mobilising support & resources for infrastructure strategies - Philip Davies,...
Mobilising support & resources for infrastructure strategies - Philip Davies,...Mobilising support & resources for infrastructure strategies - Philip Davies,...
Mobilising support & resources for infrastructure strategies - Philip Davies,...
 
The Italian Infrastructure Framework - Gabriele Pasquini, Italy
The Italian Infrastructure Framework - Gabriele Pasquini, ItalyThe Italian Infrastructure Framework - Gabriele Pasquini, Italy
The Italian Infrastructure Framework - Gabriele Pasquini, Italy
 
Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...
Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...
Key Challenges in Infrastructure Governance -- A US Perspective - Elaine Buck...
 
A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...
A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...
A systemic approach to Infrastructure Governance - Daniel Wiener, Global Infr...
 
Mobilising support and resources for infrastructures strategies - "Logros y d...
Mobilising support and resources for infrastructures strategies - "Logros y d...Mobilising support and resources for infrastructures strategies - "Logros y d...
Mobilising support and resources for infrastructures strategies - "Logros y d...
 
Mexico City new international airport - Frederico Patino, Mexico
Mexico City new international airport - Frederico Patino, MexicoMexico City new international airport - Frederico Patino, Mexico
Mexico City new international airport - Frederico Patino, Mexico
 
Transparency & Integrity - Petter Matthews, United Kingdom
Transparency & Integrity - Petter Matthews, United KingdomTransparency & Integrity - Petter Matthews, United Kingdom
Transparency & Integrity - Petter Matthews, United Kingdom
 
Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...
Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...
Experiences and Strategy of Infrastructure Development in Japan - Toshio Okaz...
 
Project Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United KingdomProject Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United Kingdom
 
Crossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United KingdomCrossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United Kingdom
 

Semelhante a Impact and Value During and After Construction - Tiago de Barros Correia, Brazil

Clean Energy Finance and Investment Roadmap OECD.pdf
Clean Energy Finance and Investment Roadmap OECD.pdfClean Energy Finance and Investment Roadmap OECD.pdf
Clean Energy Finance and Investment Roadmap OECD.pdfOECD Environment
 
Corporate Presentation CPFL Energia - Março 2016
Corporate Presentation CPFL Energia - Março 2016Corporate Presentation CPFL Energia - Março 2016
Corporate Presentation CPFL Energia - Março 2016CPFL RI
 
Terna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and ValuesTerna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and ValuesTerna SpA
 
2009 07-breaking the-climate_deadlock-cn
2009 07-breaking the-climate_deadlock-cn2009 07-breaking the-climate_deadlock-cn
2009 07-breaking the-climate_deadlock-cnwiriana
 
Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016CPFL RI
 
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...IEA-ETSAP
 
Terna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy TransitionTerna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy TransitionTerna SpA
 
Eni: Integrated Model for Sustainable Energy Resource Development
Eni: Integrated Model for Sustainable Energy Resource DevelopmentEni: Integrated Model for Sustainable Energy Resource Development
Eni: Integrated Model for Sustainable Energy Resource DevelopmentEni
 
CPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATIONCPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATIONCPFL RI
 
Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia  Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia CPFL RI
 
Corporate Presentation CPFL Energia 2020
Corporate Presentation CPFL Energia 2020Corporate Presentation CPFL Energia 2020
Corporate Presentation CPFL Energia 2020CPFL RI
 
Burton brazilian congress april 2015
Burton brazilian congress april 2015Burton brazilian congress april 2015
Burton brazilian congress april 2015Global CCS Institute
 
Corporate presentation cpfl energia agosto 2016
Corporate presentation cpfl energia  agosto 2016Corporate presentation cpfl energia  agosto 2016
Corporate presentation cpfl energia agosto 2016CPFL RI
 
Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se...
 Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se... Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se...
Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se...Smart Villages
 
Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...
Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...
Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...KTN
 
Corporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCorporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCPFL RI
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum PresentationTransGrid AU
 
Institutional Presentation Aug/20
Institutional Presentation Aug/20Institutional Presentation Aug/20
Institutional Presentation Aug/20ersa_ri
 
tisa_esg_briefing_slide_deck_1.pptx
tisa_esg_briefing_slide_deck_1.pptxtisa_esg_briefing_slide_deck_1.pptx
tisa_esg_briefing_slide_deck_1.pptxMendietaPerro
 

Semelhante a Impact and Value During and After Construction - Tiago de Barros Correia, Brazil (20)

Clean Energy Finance and Investment Roadmap OECD.pdf
Clean Energy Finance and Investment Roadmap OECD.pdfClean Energy Finance and Investment Roadmap OECD.pdf
Clean Energy Finance and Investment Roadmap OECD.pdf
 
Corporate Presentation CPFL Energia - Março 2016
Corporate Presentation CPFL Energia - Março 2016Corporate Presentation CPFL Energia - Março 2016
Corporate Presentation CPFL Energia - Março 2016
 
Terna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and ValuesTerna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and Values
 
2009 07-breaking the-climate_deadlock-cn
2009 07-breaking the-climate_deadlock-cn2009 07-breaking the-climate_deadlock-cn
2009 07-breaking the-climate_deadlock-cn
 
Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016
 
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
 
Terna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy TransitionTerna 2017>2021 Enabling Energy Transition
Terna 2017>2021 Enabling Energy Transition
 
Eni: Integrated Model for Sustainable Energy Resource Development
Eni: Integrated Model for Sustainable Energy Resource DevelopmentEni: Integrated Model for Sustainable Energy Resource Development
Eni: Integrated Model for Sustainable Energy Resource Development
 
CPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATIONCPFL ENERGIA_INSTITUTIONAL PRESENTATION
CPFL ENERGIA_INSTITUTIONAL PRESENTATION
 
Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia  Corporate Presentation CPFL Energia
Corporate Presentation CPFL Energia
 
Corporate Presentation CPFL Energia 2020
Corporate Presentation CPFL Energia 2020Corporate Presentation CPFL Energia 2020
Corporate Presentation CPFL Energia 2020
 
Burton brazilian congress april 2015
Burton brazilian congress april 2015Burton brazilian congress april 2015
Burton brazilian congress april 2015
 
Corporate presentation cpfl energia agosto 2016
Corporate presentation cpfl energia  agosto 2016Corporate presentation cpfl energia  agosto 2016
Corporate presentation cpfl energia agosto 2016
 
Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se...
 Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se... Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se...
Edinburgh | May-16 | Energy Storage and Universal Access to Modern Energy Se...
 
Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...
Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...
Overview of Horizon Europe Clusters - Webinar Series | Climate, Energy & Mobi...
 
Sgcp14ellerington
Sgcp14elleringtonSgcp14ellerington
Sgcp14ellerington
 
Corporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCorporate Presentation - CPFL Energia
Corporate Presentation - CPFL Energia
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum Presentation
 
Institutional Presentation Aug/20
Institutional Presentation Aug/20Institutional Presentation Aug/20
Institutional Presentation Aug/20
 
tisa_esg_briefing_slide_deck_1.pptx
tisa_esg_briefing_slide_deck_1.pptxtisa_esg_briefing_slide_deck_1.pptx
tisa_esg_briefing_slide_deck_1.pptx
 

Mais de OECD Governance

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators SlidesOECD Governance
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...OECD Governance
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...OECD Governance
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...OECD Governance
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...OECD Governance
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmOECD Governance
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...OECD Governance
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...OECD Governance
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...OECD Governance
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023OECD Governance
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...OECD Governance
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsOECD Governance
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfOECD Governance
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxOECD Governance
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxOECD Governance
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxOECD Governance
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxOECD Governance
 

Mais de OECD Governance (20)

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators Slides
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and Recommendations
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdf
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptx
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptx
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
 

Último

Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.Christina Parmionova
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 

Último (20)

Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 

Impact and Value During and After Construction - Tiago de Barros Correia, Brazil

  • 1. Tiago de Barros Correia Director February 29, 2016 Paris, France Impact and Value During and After Construction
  • 2. 22 Topics  Brazilian tidbits and Brazilian Power Sector overview  About us  Brazilian strategy to develop key infrastructure projects  Impact and value
  • 3. 33  Total area 8,515 million km2 (83% of Europe)  Total Population – 2015 205 million inhabitants (27% of Europe)  Overall GDP – 2014 U$1,715 billion  Installed capacity 141,631 MW  Peak load 84,958 MW (Feb 2014)  Electricity Consumption per Capita 2,664.15 kWh  Average Energy Consumption Growth Annual Rate 4% BRASIL SUMMARY
  • 4. Electricity Supply Mix 80% of the electricity supply mix is renewable 4,441 plants in operation with a total 141 GW of installed capacity 834 new projects granted, increasing the capacity by 27% (39 GW) by 2021 Fossil Fuel 19% Nuclear 1% Biomass 9% Hydro 65% Wind 6% Solar 0%
  • 5. Transmission Grid 230kV ac 345kV ac 440kV ac 500kV ac 700kV ac 600kV cc 800kV cc 125,644 km of transmission lines Expansion of 10,400 km until 2019 (8%) Auctioning of R$ 30 billion of new Investments only in 2016
  • 6. If our Transmission Grid Were in Europe...
  • 7. 77 Topics  Brazilian tidbits and Brazilian Power Sector overview  About us  Brazilian strategy to develop key infrastructure projects  Impact and value
  • 8. ANEEL Board of Directors Open Sessions › Decisions are made by the Board of Directors (5) › Board sessions are open to the public participation and is transmitted live over the web › Cases are distributed to each Director by lottery › Case settling relies on technical and legal analyses
  • 9. 99 Topics  Brazilian tidbits and Brazilian Power Sector overview  About us  Brazilian strategy to develop key infrastructure projects  Impact and value
  • 10. 1010 Infrastructure governance cycle 1. Evaluation of infrastructure needs 2. Decision and prioritization 3. Project preparation 4. Auctioning 5. Executive project and licensing 6. Construction operation and maintenance
  • 11. 1111 Topics  Brazilian tidbits and Brazilian Power Sector overview  About us  Brazilian strategy to develop key infrastructure projects  Impact and value
  • 12. 1212 Value for Money “How much is too much?” Economics Efficiency Can we get equivalent infrastructure for less money? Can we get the same results while saving money and time depending on how we manage the process? Would savings regarding the economics and efficiency of the Project risk its effectiveness and sustainability?
  • 13. 1313 Sustainability trail Goal  GHG emissions  Renewable sources  Distributed generation  Power losses Pathway (Long Term Plan) Resources and technology availability Budget constraints Regulation Subsidies Strategic Projects Externalities (Global and Local) Life Time Analysis Environmental  Economic  Social Jobs Health Mitigation and Compensation Execution Assurance of project commitments Accountability Secure stakeholders acceptance and approval
  • 14. 1414 Learning by Doing But we deal with uncertainty and sometimes we need to get back on trail and try harder To do that we need stakeholders support Again, accountability appears as a key concept
  • 15. 1515 Impact and value – Transmission Good Economics Since 1999 the Brazilian Government has been conducting auctions to contract transmission services from greenfield projects. The auctions procure long term contracts (30 years) and define the transmission services to be delivered and the construction time line. Applicants need to meet certain criteria in order to be accepted for participation in the auctions. This design intends to ensure that the project offered will meet environmental, technical and economic requirements of quality . Bidders with the lowest proposed prices are the winners.
  • 16. 1616 1.0 7.7 0.8 2.2 3.5 6.1 5.0 3.0 1.7 13.9 4.5 2.5 7.0 10.5 10.2 13.3 13.3 30.6 0 5 10 15 20 25 30 35 Investment in Billions of (R$) Concessions Granted and Expected till the end of 2016* - present value (*assumes all contracts signed)
  • 17. 1717 Impact and value – Transmission Low Efficiency % of projects with delays for each required phase. With delay Early start In time Unknown
  • 18. 1818 8/28/2013 - Last Major Disturbance taken place in the Interconnected Grid. Load Loss: ~11GW Cut off Consummers : 17.5 million Fault Clearance Time: 4 hours Cause: Fire Impact and value – Transmission Good Effectiveness Availability of transmission lines in the last 5 years (%) Load Restoration in the Northeast
  • 19. 1919 Scope  General goals  Governance arrangement  Budget (funding and finance) Public Policy Major Risks  Unrealistic goals  Bad governance  Insufficient resources Risk-Bearing  Government  Society Scope  Strategic Projects  Pricing and Timing  Previous License  Stakeholders support Planning Major Risks  Social and Environmental feasibility  Stakeholders support (not in my backyard!) Risk-Bearing  Government  Society
  • 20. 2020 Scope  Contract design  Auction design Auctioning Major Risks  Collusion  Bidless Auctions  Winner’s Curse Risk-Bearing  Government  Society  Winner (Entrepreneur) Scope  Executive Project  Final Licenses  Construction  Project Compliance Construction Major Risks  Licensing delay  Exchange rate  Capital cost  Bad Project  New Environmental Agency requirements (studies and mitigation measures)  Weather Risk-Bearing  Government  Society  Entrepreneur
  • 21. 2121 Scope  Power Capacity  Energy Generation  Transmissions Services Operation Major Risks  Inflation  Non concatenation (generation and transmission)  Blackout (bad planning)  Bad performance  Market exposure Risk-Bearing  Consumer  Entrepreneur
  • 22. 2222 SGAN – Quadra 603 Módulos “I” e “J” CEP: 70.830-110 /Brasília – DF Tel.: 55 (61) 2192-8604 tiago@aneel.gov.br Thank you!