FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE
FMEP-P-0750 Rev. No. 2Subject:
DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS
Page 1 of 5
SAIC FREDERICK
A Division of Science Applications International Corporation
1.0 PURPOSE
To provide the details of collecting and verifying subcontractor work on a daily basis.
2.0 GENERAL
It is essential, for good subcontractor job control, to maintain current and cumulative records of the daily activities,
and that all related information, as listed herein, is to be placed into the Daily Progress Report (Exhibit A). In
addition, these Daily Progress Reports will be reviewed for accuracy by the assigned SAIC Representative who will
document independent observations into the Daily COTR Log (Exhibit B).
3.0 PROCEDURE
3.1 Responsibilities
The responsibilities of the various parties are identified below.
3.1.1 Science Applications International Corporation (SAIC)/Contracting Officers Technical Representative
(COTR)
(a) The assigned SAIC Representative shall ensure that the subcontractor prepares, and submits for review by the
assigned SAIC Representative, the Daily Progress Report by noon of the next working day.
(b) The assigned SAIC Representative shall verify the accuracy and completeness of the Subcontractor’s Daily
Progress Report and acknowledge same on their Daily COTR Log. The Daily Progress Report shall not be marked
by the SAIC Representative.
(c) The assigned SAIC Representative shall prepare a Daily COTR Log that will address disagreements with the
subcontractor prepared Daily Progress Report and include a summary of observations and instructions not included
in the Daily Progress Report.
3.1.2 Subcontractor
The subcontractor shall submit the original of the Daily Progress Report to the SAIC Representative for logging and
filing into the project files, and forward a copy of the Daily Progress Report to the contract specialist.
3.2 Requirements
3.2.1. The requirements associated with the Daily Progress Report are identified below.
(a) The Daily Progress Report is a SAIC document and is included as Exhibit A.
(b) The Daily Progress Report is an important historical document that records the subcontractor’s day-to-day
operations, and can be used, as a basic reference, to determine the exact progress of the work at any given time. In
FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE
FMEP-P-0750 Rev. No. 2Subject:
DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS
Page 2 of 5
SAIC FREDERICK
A Division of Science Applications International Corporation
the event of a claim or dispute, the details of events in the Daily Progress Report may become of paramount
importance.
(c) The Daily Progress Report should be generated electronically or may be completed manually using Exhibit A. If
the reports are manually prepared, they shall be prepared and signed with permanent ink and shall contain no
erasures or alterations with correction fluid. If changes are necessary, strike through the part to be removed so that it
is readable. Initial and date any changes.
(d) The Daily Progress Report shall be concise and factual since they are considered as “records kept during the
regular course of business”. These reports are admissible, normally, as evidence to prove the truth of such
statements contained therein, without the original author appearing and testifying in person.
(e) Opinions shall not be expressed in the Daily Progress Report.
(f) The amount of detail in the Daily Progress Report will vary with the amount of activity and complexity of the
work.
(g) Other activity reports should be referenced in the Daily Progress Report. These may include (but not be limited
to) such reports as:
• Welding Reports
• Force Reports
• Quantity Reports and Surveillance Inspections Reports
• Safety Reports
• Field Inspection Reports
• Hot Work Permits
(h) Each day, from mobilization to demobilization, shall be covered by a Daily Progress Report. If no work is
performed on the weekend, a separate Daily Progress Report is not required for each day of the weekend, providing
that the Daily Progress Report for the next regular work day contains a statement such as: “No work was performed
on (day) and (day) and includes the actual dates.
(i) If work is not performed for a number of days, one Daily Progress Report may be prepared stating the dates
covered by the report.
3.3 3.2.1.1 Daily Progress Report Details
The details associated with the Daily Progress Report are identified below.
FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE
FMEP-P-0750 Rev. No. 2Subject:
DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS
Page 3 of 5
SAIC FREDERICK
A Division of Science Applications International Corporation
3.3.1 3.2.1.1.1 Work Shift
The shift and the starting and ending times shall be indicated.
3.3.2 3.2.1.1.2 Forces and Equipment
Records shall be kept of the number of workers by craft and the major equipment on site. Equipment moved on or
off site since the last report shall be indicated. Any down equipment and the downtime, if it can be established, shall
be indicated.
3.3.3 3.2.1.1.3 Description of Work Performed Today - Progress
(a) A brief description of the work being performed shall be entered, indicating the area, location, etc.
(b) The progress made relative to the subcontractor’s plan shall be indicated, noting the initiation and completion for
any major item of work.
(c) Major items of material received on and/or removed from the site shall be recorded.
(d) When the subcontractor ceases work for a period of time, or returns to work after a period of time away from the
job, this shall be so noted with appropriately detailed comments.
3.3.4 3.2.1.1.4 Special Comments
(a) Work stoppage, interruptions, delays, or potential delays.
(b) All alleged delays shall be accurately described, including actions taken to rectify the situation with the
responsible parties identified and any action dates needed.
(c) In recording information on such delays, stoppages, and interruptions, the following listed items should be
considered:
• Was it unavoidable?
• Was it actual or potential?
• What was the cause?
• What was the productivity result?
• How much time was lost – craft and work hours?
• What equipment was affected or idled?
FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE
FMEP-P-0750 Rev. No. 2Subject:
DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS
Page 4 of 5
SAIC FREDERICK
A Division of Science Applications International Corporation
3.3.5 3.2.1.1.5 Weather
Any unusual weather conditions shall be described, indicating if weather affected the subcontractor’s operation.
3.3.6 3.2.1.1.6 Surveillance
A record shall be kept of such items as:
(a) Unusual field conditions.
(b) Unsatisfactory work.
.
(c) Tests and inspections performed and results (satisfactory or unsatisfactory). If unsatisfactory, identify the actions
that were taken to remedy the situation.
3.3.7 3.2.1.1.7 Accidents
Any accidents, injuries, or safety violations shall be recorded.
3.3.8 3.2.1.1.8 Instructions
Instructions given to the subcontractor shall be recorded, listing the name of the person and the time given. Any
action taken shall also be indicated.
3.3.9 3.2.1.1.9 Conflicts
When conflicts occur, the following shall be recorded:
• The problem.
• Who discovered and reported it?
• Who was informed?
• What steps were taken to resolve the conflict, i.e., was RFI issued?
• What was the resolution?
3.3.10 3.2.1.1.10 Meetings Held
Make note of any meetings held on site.
3.2.2 Requirements associated with the Daily COTR Log are identified below.
FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE
FMEP-P-0750 Rev. No. 2Subject:
DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS
Page 5 of 5
SAIC FREDERICK
A Division of Science Applications International Corporation
(a) Daily COTR Logs will be prepared for each visit day of construction. If for some reason the COTR did not
visit the site on a particular day of construction, the reason for non-visit and pertinent observations as to
events occurring during period of absence will be included in the Daily COTR Log for the next subsequent
visit day.
(b) The Daily COTR Log should be generated electronically or may be completed manually using Exhibit B.
(c) Daily COTR Logs should be prepared on the day that the site was visited and shall be sequentially
numbered.
(d) Daily COTR Logs will be identified by a project name, work order number, Subcontractor name and
contract number.
(e) All changes to Daily COTR Log entries made after the initial entry is made will be made by striking
through the original entry in a manner which does not obliterate the original entry, and providing the
initials of the person making the change and date the change was made.
(f) Dates will be recorded in the month/day/year format. Time will be recorded in the 24-hour (military) clock
format (e.g. 1500 hours rather than 3:00 p.m.).
(g) The PM will periodically review Daily COTR Logs to insure their completeness, accuracy, legibility,
consistency, and clarity. The schedule for these periodic reviews shall be left to the PM to establish but
shall not be less frequent than monthly.
_____________________________________
FMEP-P-0750 Exhibits
Exhibit A-Daily Progress Report (2 pages)
Exhibit B-COTR DAILY LOG (1page)

Mais conteúdo relacionado

Mais procurados (9)

State work
State workState work
State work
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Petronas procedures and guidelines for planning and budgeting
Petronas procedures and guidelines for planning and budgetingPetronas procedures and guidelines for planning and budgeting
Petronas procedures and guidelines for planning and budgeting
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
1. MDB Unit 1
1. MDB Unit 11. MDB Unit 1
1. MDB Unit 1
 
Petronas procedures and guidelines for finance
Petronas procedures and guidelines for financePetronas procedures and guidelines for finance
Petronas procedures and guidelines for finance
 
Causal Analysis w b tie
Causal Analysis w b tieCausal Analysis w b tie
Causal Analysis w b tie
 
Fgd data sheets
Fgd data sheetsFgd data sheets
Fgd data sheets
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 

Semelhante a Procedures

Tpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareTpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareRajiva Gupta
 
Guidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontarioGuidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontariojameschisholm
 
PSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdfPSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdfromuloac
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyasPMI_IREP_TP
 
Amendments_ERDMP_08.02.2021_Petroleum.pdf
Amendments_ERDMP_08.02.2021_Petroleum.pdfAmendments_ERDMP_08.02.2021_Petroleum.pdf
Amendments_ERDMP_08.02.2021_Petroleum.pdfDivakarDhande2
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013leo040490
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015HaGun Gunawan
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
TECHNICAL WRITER DAY TO DAY JOB FLOW - Complete
TECHNICAL WRITER DAY TO DAY JOB FLOW - CompleteTECHNICAL WRITER DAY TO DAY JOB FLOW - Complete
TECHNICAL WRITER DAY TO DAY JOB FLOW - CompleteBahrun Sahib
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTNur Ain Samsudin
 

Semelhante a Procedures (20)

MAINTENANCE
MAINTENANCEMAINTENANCE
MAINTENANCE
 
Tpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareTpqma r5 to upload in slide share
Tpqma r5 to upload in slide share
 
Guidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontarioGuidance on ems regulatory requirements in ontario
Guidance on ems regulatory requirements in ontario
 
PSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdfPSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdf
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyas
 
Amendments_ERDMP_08.02.2021_Petroleum.pdf
Amendments_ERDMP_08.02.2021_Petroleum.pdfAmendments_ERDMP_08.02.2021_Petroleum.pdf
Amendments_ERDMP_08.02.2021_Petroleum.pdf
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Ad2 2009
Ad2 2009Ad2 2009
Ad2 2009
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
Dg sets final2013
Dg sets final2013Dg sets final2013
Dg sets final2013
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Engineering SOP
Engineering SOPEngineering SOP
Engineering SOP
 
SOP ENGINEERING
SOP ENGINEERINGSOP ENGINEERING
SOP ENGINEERING
 
SOP Engg operationl
SOP Engg operationl  SOP Engg operationl
SOP Engg operationl
 
HSE Temporary works management plan
HSE Temporary works management planHSE Temporary works management plan
HSE Temporary works management plan
 
TECHNICAL WRITER DAY TO DAY JOB FLOW - Complete
TECHNICAL WRITER DAY TO DAY JOB FLOW - CompleteTECHNICAL WRITER DAY TO DAY JOB FLOW - Complete
TECHNICAL WRITER DAY TO DAY JOB FLOW - Complete
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 

Procedures

  • 1. FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE FMEP-P-0750 Rev. No. 2Subject: DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS Page 1 of 5 SAIC FREDERICK A Division of Science Applications International Corporation 1.0 PURPOSE To provide the details of collecting and verifying subcontractor work on a daily basis. 2.0 GENERAL It is essential, for good subcontractor job control, to maintain current and cumulative records of the daily activities, and that all related information, as listed herein, is to be placed into the Daily Progress Report (Exhibit A). In addition, these Daily Progress Reports will be reviewed for accuracy by the assigned SAIC Representative who will document independent observations into the Daily COTR Log (Exhibit B). 3.0 PROCEDURE 3.1 Responsibilities The responsibilities of the various parties are identified below. 3.1.1 Science Applications International Corporation (SAIC)/Contracting Officers Technical Representative (COTR) (a) The assigned SAIC Representative shall ensure that the subcontractor prepares, and submits for review by the assigned SAIC Representative, the Daily Progress Report by noon of the next working day. (b) The assigned SAIC Representative shall verify the accuracy and completeness of the Subcontractor’s Daily Progress Report and acknowledge same on their Daily COTR Log. The Daily Progress Report shall not be marked by the SAIC Representative. (c) The assigned SAIC Representative shall prepare a Daily COTR Log that will address disagreements with the subcontractor prepared Daily Progress Report and include a summary of observations and instructions not included in the Daily Progress Report. 3.1.2 Subcontractor The subcontractor shall submit the original of the Daily Progress Report to the SAIC Representative for logging and filing into the project files, and forward a copy of the Daily Progress Report to the contract specialist. 3.2 Requirements 3.2.1. The requirements associated with the Daily Progress Report are identified below. (a) The Daily Progress Report is a SAIC document and is included as Exhibit A. (b) The Daily Progress Report is an important historical document that records the subcontractor’s day-to-day operations, and can be used, as a basic reference, to determine the exact progress of the work at any given time. In
  • 2. FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE FMEP-P-0750 Rev. No. 2Subject: DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS Page 2 of 5 SAIC FREDERICK A Division of Science Applications International Corporation the event of a claim or dispute, the details of events in the Daily Progress Report may become of paramount importance. (c) The Daily Progress Report should be generated electronically or may be completed manually using Exhibit A. If the reports are manually prepared, they shall be prepared and signed with permanent ink and shall contain no erasures or alterations with correction fluid. If changes are necessary, strike through the part to be removed so that it is readable. Initial and date any changes. (d) The Daily Progress Report shall be concise and factual since they are considered as “records kept during the regular course of business”. These reports are admissible, normally, as evidence to prove the truth of such statements contained therein, without the original author appearing and testifying in person. (e) Opinions shall not be expressed in the Daily Progress Report. (f) The amount of detail in the Daily Progress Report will vary with the amount of activity and complexity of the work. (g) Other activity reports should be referenced in the Daily Progress Report. These may include (but not be limited to) such reports as: • Welding Reports • Force Reports • Quantity Reports and Surveillance Inspections Reports • Safety Reports • Field Inspection Reports • Hot Work Permits (h) Each day, from mobilization to demobilization, shall be covered by a Daily Progress Report. If no work is performed on the weekend, a separate Daily Progress Report is not required for each day of the weekend, providing that the Daily Progress Report for the next regular work day contains a statement such as: “No work was performed on (day) and (day) and includes the actual dates. (i) If work is not performed for a number of days, one Daily Progress Report may be prepared stating the dates covered by the report. 3.3 3.2.1.1 Daily Progress Report Details The details associated with the Daily Progress Report are identified below.
  • 3. FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE FMEP-P-0750 Rev. No. 2Subject: DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS Page 3 of 5 SAIC FREDERICK A Division of Science Applications International Corporation 3.3.1 3.2.1.1.1 Work Shift The shift and the starting and ending times shall be indicated. 3.3.2 3.2.1.1.2 Forces and Equipment Records shall be kept of the number of workers by craft and the major equipment on site. Equipment moved on or off site since the last report shall be indicated. Any down equipment and the downtime, if it can be established, shall be indicated. 3.3.3 3.2.1.1.3 Description of Work Performed Today - Progress (a) A brief description of the work being performed shall be entered, indicating the area, location, etc. (b) The progress made relative to the subcontractor’s plan shall be indicated, noting the initiation and completion for any major item of work. (c) Major items of material received on and/or removed from the site shall be recorded. (d) When the subcontractor ceases work for a period of time, or returns to work after a period of time away from the job, this shall be so noted with appropriately detailed comments. 3.3.4 3.2.1.1.4 Special Comments (a) Work stoppage, interruptions, delays, or potential delays. (b) All alleged delays shall be accurately described, including actions taken to rectify the situation with the responsible parties identified and any action dates needed. (c) In recording information on such delays, stoppages, and interruptions, the following listed items should be considered: • Was it unavoidable? • Was it actual or potential? • What was the cause? • What was the productivity result? • How much time was lost – craft and work hours? • What equipment was affected or idled?
  • 4. FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE FMEP-P-0750 Rev. No. 2Subject: DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS Page 4 of 5 SAIC FREDERICK A Division of Science Applications International Corporation 3.3.5 3.2.1.1.5 Weather Any unusual weather conditions shall be described, indicating if weather affected the subcontractor’s operation. 3.3.6 3.2.1.1.6 Surveillance A record shall be kept of such items as: (a) Unusual field conditions. (b) Unsatisfactory work. . (c) Tests and inspections performed and results (satisfactory or unsatisfactory). If unsatisfactory, identify the actions that were taken to remedy the situation. 3.3.7 3.2.1.1.7 Accidents Any accidents, injuries, or safety violations shall be recorded. 3.3.8 3.2.1.1.8 Instructions Instructions given to the subcontractor shall be recorded, listing the name of the person and the time given. Any action taken shall also be indicated. 3.3.9 3.2.1.1.9 Conflicts When conflicts occur, the following shall be recorded: • The problem. • Who discovered and reported it? • Who was informed? • What steps were taken to resolve the conflict, i.e., was RFI issued? • What was the resolution? 3.3.10 3.2.1.1.10 Meetings Held Make note of any meetings held on site. 3.2.2 Requirements associated with the Daily COTR Log are identified below.
  • 5. FACILITIES MAINTENANCE AND ENGINEERING PROCEDURE FMEP-P-0750 Rev. No. 2Subject: DAILY PROGRESS REPORT OF SUBCONTRACTOR OPERATIONS Page 5 of 5 SAIC FREDERICK A Division of Science Applications International Corporation (a) Daily COTR Logs will be prepared for each visit day of construction. If for some reason the COTR did not visit the site on a particular day of construction, the reason for non-visit and pertinent observations as to events occurring during period of absence will be included in the Daily COTR Log for the next subsequent visit day. (b) The Daily COTR Log should be generated electronically or may be completed manually using Exhibit B. (c) Daily COTR Logs should be prepared on the day that the site was visited and shall be sequentially numbered. (d) Daily COTR Logs will be identified by a project name, work order number, Subcontractor name and contract number. (e) All changes to Daily COTR Log entries made after the initial entry is made will be made by striking through the original entry in a manner which does not obliterate the original entry, and providing the initials of the person making the change and date the change was made. (f) Dates will be recorded in the month/day/year format. Time will be recorded in the 24-hour (military) clock format (e.g. 1500 hours rather than 3:00 p.m.). (g) The PM will periodically review Daily COTR Logs to insure their completeness, accuracy, legibility, consistency, and clarity. The schedule for these periodic reviews shall be left to the PM to establish but shall not be less frequent than monthly. _____________________________________ FMEP-P-0750 Exhibits Exhibit A-Daily Progress Report (2 pages) Exhibit B-COTR DAILY LOG (1page)