SlideShare uma empresa Scribd logo
1 de 16
Contract Transitions -
Responsibility Notes for the Incumbent

                      - Tracy Dorsey/PMP

                   PM Challenge 2012
                       Feb 22nd-23rd
Background

General Timeline

   • Transition Environment (Staff, Support companies, Customers/Projects)

   • Core Transition Responsibilities



General message – We should all care and help ensure successful contract transitions. It’s not
just the successors responsibility

‘Parental Style Mindset’ – Release your tasks, projects and transitioning staff as if you were
sending them off to college. Well equipped and knowing that you want them to succeed.
Personal Experience
• Began working in 1984 at GSFC since 1989 Employed by SGT Inc.
• Masters – Space Systems Engineering
• Held many roles supporting NASA – Currently Program Manager
  MSES IIA contract at Goddard Space Flight Center

Stinger Ghaffarian Technologies
• Founded in 1994; Headquartered in Greenbelt, MD
• 1,600 employees: engineers, scientists, IT professionals
• Key Customers
     – NASA                             – NOAA
        – Goddard Space Flight          – Department of                                  IT 24%
          Center                           Transportation
        – Ames Research Center          – Air Force Space         Engineering 61%
        – Glenn Research Center            Command                                         Science 5%
                                                                                      Program
        – Stennis Space Center          – USGS                                      M anagement
        – Langley Research Center                                                       10%
        – Johnson Space Center
        – Kennedy Space Center
Timing
  • Contracts generally turn over every 5 -7 years
  • Transitions will not be in alignment with supported Projects
  • Procurement schedules generally won’t be fixed
     Variables: Procurement delays, protest, etc.

Contractor and Staffing Mix
  • Some transitions and contracts can be very large and complicated
  • Uncertainties of employees through the process
  • Most likely new mixture of contractors on succession vehicle
  • Incumbent contractor is likely pursuing the follow-on contract in some fashion

For the purposes of this presentation – it’s assumed the incumbent will transition
 follow-on the contract to a successor contractor
CONTINUITY OF SERVICES (JAN 1991)
(a) The Contractor recognizes that the services under this contract are vital to the Government and must be
continued without interruption and that, upon contract expiration, a successor, either the Government or
another contractor, may continue them. The Contractor agrees to—
(1) Furnish phase-in training; and (2) Exercise its best efforts and cooperation to effect an orderly and efficient
transition to a successor.
(b) The Contractor shall, upon the Contracting Officer’s written notice, (1) furnish phase-in, phase-out services
for up to 90 days after this contract expires and (2) negotiate in good faith a plan with a successor to
determine the nature and extent of phase-in, phase-out services required. The plan shall specify a training
program and a date for transferring responsibilities for each division of work described in the plan, and shall be
subject to the Contracting Officer’s approval. The Contractor shall provide sufficient experienced personnel
during the phase-in, phase-out period to ensure that the services called for by this contract are maintained at
the required level of proficiency.
(c) The Contractor shall allow as many personnel as practicable to remain on the job to help the successor
maintain the continuity and consistency of the services required by this contract. The Contractor also shall
disclose necessary personnel records and allow the successor to conduct on-site interviews with these
employees. If selected employees are agreeable to the change, the Contractor shall release them at a
mutually agreeable date and negotiate transfer of their earned fringe benefits to the successor.
(d) The Contractor shall be reimbursed for all reasonable phase-in, phase-out costs (i.e., costs incurred within
the agreed period after contract expiration that result from phase-in, phase-out operations) and a fee (profit)
not to exceed a pro rata portion of the fee (profit) under this contract.
(End of clause)
Stage 1
  • Phase 1) Proposal Development and Submissions
      Varied timeframes as companies pursue opportunities approaching release
      Synopsis, Industry Day(s), RFI, customer visits, Draft RFP, RFP
  • Phase 2) Board Assessments
      6-9 months
  • Phase 3) Award Announcement and contract start
      Unprotested transition could start immediately (after the debriefs)


Stage 2
  • Phase 4) Transition
      30, 45, 60 and 90 variations (for bulk of contracts)


Stage 3
  • Phase 5) Contract Execution by Successor
      Dependent on opportunity (5-8 years)
 Phase 1: Proposal Development and Submission

   Stressors:
     – Proposal input, writing and reviewing demands
     – Project timelines don’t change due to proposal schedule
     – Current operating team may not be teammates on follow-on efforts
        » Information, working styles and visibility practices may be adjusted near the end
          of an executing contract.

   On contract (Incumbent) Responsibilities
     – Ensure current work continues at a high level (technical and management)
     – Increase communications with staff – technical and management level flows.
       Contract performance should never be compromised
     – Ensure follow-on contract teaming arrangements don’t adversely affect ongoing
       contract performance
Phase 2: Board Assessments

   Stressors:
     – Hallway rumors, expectations, realities of contract ending, employee uncertainties



    On Contract Responsibilities
     – Continue communications to executing team, continue to stress focus on assigned
       task and commitments.
     – In most cases technical incumbent team will not be adversely impacted by a
       transition – convey the message.
     – Begin to refine preparatory documents that will be needed for transition
         » Task lists, staffing list, property list, ITAR documents and critical project
           schedules.
         » Have a checklist for every task, work with your NASA Technical Monitors
 Phase 3: Award Announcements

   Stressors
     – Realities of contract ending are cemented
     – Employee uncertainties have peaked if communications have been lagging

    On Contract Responsibilities
     – Meet with your current COTR/CO and make sure everyone is on the same page with
       regard to the transition
     – Generate a proposed schedule for phase out activities
     – Work with your current Civil Servant Task monitors
        » Descopes and expectations
        » Task continuations on succession vehicle (lose visibility but you still have
          obligations to your current staff. Is everyone getting picked up on the follow-on
          vehicle)
        » Realize and help staffers manage change (Internally and/or attending open
          houses of successor)
Phase 4 On Contract Responsibilities


  • The Transition

    Stressors:
      – Employee uncertainties, some early staff movements are realistic to
        assume
      – Continue efforts to ensure no interruptions in work or performance
      – Maintain trust with current customers through the last day
      – Follow-on contract may not be straight forward succession
Civil Servant Team                                     Incumbent Contractor Team
(most likely will consist of)                                Program Manager
     Contract Manager or owner                              Business Manager
     Contracting Officer (CO)                               Contracts Manager
     Contracting Officer's Technical                        Corporate assigned Transition Manager
      Representative (COTR)
     Resource Analyst (RA)
     Representatives from other Major-Use
      Organizations
     Chief Information Officer's (CIO)
      Information Technology (IT) Personnel
     Security Personnel
                                                         • Execute transition to governments satisfaction
• Entity ensures the governments best interest is
                                                         • Execute transition consistent with FAR 52.237-
  maintained and serves as official executer of
                                                           3 – Continuity of Services (JAN 1991)
  the transition
• Should work very closely with incumbent in
  ensuring a readiness posture for the transition.
  A close relationship will usually yield the most
  effective set of information and possibilities for
  a smooth transition.
 On Contract Responsibilities and more elements

 Schedule a meeting with the govt, your transition manager and the successor
    • Handle requests as appropriate (i.e. current support, contractor team mix, meet weekly)
 Finalize Inventory for everything on contract task
    • Staffers, subcontracts, equipment, badges
    • Readdress and Review critical schedules or milestones
    • Document and prepare to disposition all technical equipment, intellectual property,
      software, data, licenses and customized scripts that will be transferred.
 Identify all contractor-owned technical equipment, intellectual property, software, data, and
  end items that must be removed from NASA facilities and ensure the government understands
 Establish a definite check-out procedure for all incumbent contractor employees, technical
  equipment, intellectual property, software, data, and end items that reside on or at a
  government facility.
 Facilitate subcontract phase out procedures
    • Dependent on size of contract this could be a large effort
 On Contract Responsibilities and more elements

       Task monitors to need access dependencies which might cause some tasks not to transition on day
        one
         – Large procurement in process, TAA’s, Critical phase of a projects
         – All successor transition teams aren’t equal
         – Understand your existing task values as it relates to EAC
            » Government will need to obligate funding to new vehicle

       Additional Notes
         – Training – Certification information where appropriate (if any key records held outside of Satern)
         – IT Security (Badge transfer process – some badges may not be transferred)
         – Clearances (Transfers may have to occur- corp and Govt. security need to be involved)
         – ITAR and TAA (3-6 month process)
         – Property (GFE listing)
         – Final task reports
             » add element to final monthly (disposition all deliverables and property held under task order)
Phase 5 On Contract Responsibilities

  • Contract Execution by Successor
    Stressors:
      – You and your Business Manager are the only ones left 

    Responsibilities
      – Complete any remaining final task reports
      – Final 533’s, Close up trailing costs and invoice processing
      – Execute any remaining tasks due lagging issues (ie ITAR, Critical schedules or
        government’s convenience)
Transition Environment is complex
  • (Staff, Support companies, Customers, Projects)

Transition Elements and Core Responsibilities

Make it a success and everybody wins in a variety of ways
•   Thanks (Shelley Johnson/SGT and MSES Management Team)

•   Questions, Comments ?

•   Contact Information for follow-up questions and other inquiries:

         Tracy Dorsey
         tdorsey@sgt-in.com
         SGT Inc.
         7515 Mission Drive
         Suite 300
         Lanham, Md. 20706
         (Office) 301-464-7557 / (Cell) 301-526-6621

Mais conteúdo relacionado

Mais procurados

Bizier.brenda
Bizier.brendaBizier.brenda
Bizier.brenda
NASAPMC
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
NASAPMC
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalley
NASAPMC
 
Stephen.book
Stephen.bookStephen.book
Stephen.book
NASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
NASAPMC
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.j
NASAPMC
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
NASAPMC
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
NASAPMC
 
Hyatt.mark
Hyatt.markHyatt.mark
Hyatt.mark
NASAPMC
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brian
NASAPMC
 
Sally godfreyheatherrarick
Sally godfreyheatherrarickSally godfreyheatherrarick
Sally godfreyheatherrarick
NASAPMC
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paul
NASAPMC
 
Risk.panel handout
Risk.panel handoutRisk.panel handout
Risk.panel handout
NASAPMC
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
NASAPMC
 

Mais procurados (20)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Bizier.brenda
Bizier.brendaBizier.brenda
Bizier.brenda
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalley
 
Stephen.book
Stephen.bookStephen.book
Stephen.book
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.j
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
 
Symons
SymonsSymons
Symons
 
Hyatt.mark
Hyatt.markHyatt.mark
Hyatt.mark
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brian
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
Sally godfreyheatherrarick
Sally godfreyheatherrarickSally godfreyheatherrarick
Sally godfreyheatherrarick
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paul
 
Risk.panel handout
Risk.panel handoutRisk.panel handout
Risk.panel handout
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
 

Destaque

Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
NASAPMC
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvin
NASAPMC
 
David.dean.john.michalic
David.dean.john.michalicDavid.dean.john.michalic
David.dean.john.michalic
NASAPMC
 
Pedro.ribeiro
Pedro.ribeiroPedro.ribeiro
Pedro.ribeiro
NASAPMC
 
Hatfieldskip
HatfieldskipHatfieldskip
Hatfieldskip
NASAPMC
 
Chmielewski.arthur
Chmielewski.arthurChmielewski.arthur
Chmielewski.arthur
NASAPMC
 
Darryl.mitchell
Darryl.mitchellDarryl.mitchell
Darryl.mitchell
NASAPMC
 
Crocker lori
Crocker loriCrocker lori
Crocker lori
NASAPMC
 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deans
NASAPMC
 
Richarde summers
Richarde summersRicharde summers
Richarde summers
NASAPMC
 
Ronnie goodin ethics
Ronnie goodin ethicsRonnie goodin ethics
Ronnie goodin ethics
NASAPMC
 
Robert odlerobert.cox
Robert odlerobert.coxRobert odlerobert.cox
Robert odlerobert.cox
NASAPMC
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
NASAPMC
 
James.taylor
James.taylorJames.taylor
James.taylor
NASAPMC
 
Reed simpson
Reed simpsonReed simpson
Reed simpson
NASAPMC
 
Bilbro james
Bilbro jamesBilbro james
Bilbro james
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Gersetenmaier.william l
Gersetenmaier.william lGersetenmaier.william l
Gersetenmaier.william l
NASAPMC
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
NASAPMC
 

Destaque (20)

Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvin
 
David.dean.john.michalic
David.dean.john.michalicDavid.dean.john.michalic
David.dean.john.michalic
 
Pedro.ribeiro
Pedro.ribeiroPedro.ribeiro
Pedro.ribeiro
 
Hatfieldskip
HatfieldskipHatfieldskip
Hatfieldskip
 
Chmielewski.arthur
Chmielewski.arthurChmielewski.arthur
Chmielewski.arthur
 
Darryl.mitchell
Darryl.mitchellDarryl.mitchell
Darryl.mitchell
 
Crocker lori
Crocker loriCrocker lori
Crocker lori
 
Caruso
CarusoCaruso
Caruso
 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deans
 
Richarde summers
Richarde summersRicharde summers
Richarde summers
 
Ronnie goodin ethics
Ronnie goodin ethicsRonnie goodin ethics
Ronnie goodin ethics
 
Robert odlerobert.cox
Robert odlerobert.coxRobert odlerobert.cox
Robert odlerobert.cox
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
James.taylor
James.taylorJames.taylor
James.taylor
 
Reed simpson
Reed simpsonReed simpson
Reed simpson
 
Bilbro james
Bilbro jamesBilbro james
Bilbro james
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Gersetenmaier.william l
Gersetenmaier.william lGersetenmaier.william l
Gersetenmaier.william l
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
 

Semelhante a Tracy dorsey

USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Drone
tkjohns1
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
wkyra78
 
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docxThe Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
todd771
 
OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009
Ian van Vuuren
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
Ricardo Leite
 
Project management plan
Project management planProject management plan
Project management plan
Donny Olson
 

Semelhante a Tracy dorsey (20)

Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Qimonda Pm Foils
Qimonda Pm FoilsQimonda Pm Foils
Qimonda Pm Foils
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Drone
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
The project plan
The project planThe project plan
The project plan
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
 
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docxThe Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
 
Turnaround Project Planner Primer
Turnaround Project Planner PrimerTurnaround Project Planner Primer
Turnaround Project Planner Primer
 
JakeA_resume Oct14
JakeA_resume Oct14JakeA_resume Oct14
JakeA_resume Oct14
 
International Project Management.- Mercedes Benz- Demo
International Project Management.- Mercedes   Benz- DemoInternational Project Management.- Mercedes   Benz- Demo
International Project Management.- Mercedes Benz- Demo
 
OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
 
PERT
PERTPERT
PERT
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project management plan
Project management planProject management plan
Project management plan
 
Best practices for new project commissioning
Best practices for new project commissioningBest practices for new project commissioning
Best practices for new project commissioning
 
Best practices for new project commissioning
Best practices for new project commissioningBest practices for new project commissioning
Best practices for new project commissioning
 
project influnceing
project influnceingproject influnceing
project influnceing
 

Mais de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
NASAPMC
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
NASAPMC
 

Mais de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 

Último

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 

Último (20)

Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 

Tracy dorsey

  • 1. Contract Transitions - Responsibility Notes for the Incumbent - Tracy Dorsey/PMP PM Challenge 2012 Feb 22nd-23rd
  • 2. Background General Timeline • Transition Environment (Staff, Support companies, Customers/Projects) • Core Transition Responsibilities General message – We should all care and help ensure successful contract transitions. It’s not just the successors responsibility ‘Parental Style Mindset’ – Release your tasks, projects and transitioning staff as if you were sending them off to college. Well equipped and knowing that you want them to succeed.
  • 3. Personal Experience • Began working in 1984 at GSFC since 1989 Employed by SGT Inc. • Masters – Space Systems Engineering • Held many roles supporting NASA – Currently Program Manager MSES IIA contract at Goddard Space Flight Center Stinger Ghaffarian Technologies • Founded in 1994; Headquartered in Greenbelt, MD • 1,600 employees: engineers, scientists, IT professionals • Key Customers – NASA – NOAA – Goddard Space Flight – Department of IT 24% Center Transportation – Ames Research Center – Air Force Space Engineering 61% – Glenn Research Center Command Science 5% Program – Stennis Space Center – USGS M anagement – Langley Research Center 10% – Johnson Space Center – Kennedy Space Center
  • 4. Timing • Contracts generally turn over every 5 -7 years • Transitions will not be in alignment with supported Projects • Procurement schedules generally won’t be fixed Variables: Procurement delays, protest, etc. Contractor and Staffing Mix • Some transitions and contracts can be very large and complicated • Uncertainties of employees through the process • Most likely new mixture of contractors on succession vehicle • Incumbent contractor is likely pursuing the follow-on contract in some fashion For the purposes of this presentation – it’s assumed the incumbent will transition follow-on the contract to a successor contractor
  • 5. CONTINUITY OF SERVICES (JAN 1991) (a) The Contractor recognizes that the services under this contract are vital to the Government and must be continued without interruption and that, upon contract expiration, a successor, either the Government or another contractor, may continue them. The Contractor agrees to— (1) Furnish phase-in training; and (2) Exercise its best efforts and cooperation to effect an orderly and efficient transition to a successor. (b) The Contractor shall, upon the Contracting Officer’s written notice, (1) furnish phase-in, phase-out services for up to 90 days after this contract expires and (2) negotiate in good faith a plan with a successor to determine the nature and extent of phase-in, phase-out services required. The plan shall specify a training program and a date for transferring responsibilities for each division of work described in the plan, and shall be subject to the Contracting Officer’s approval. The Contractor shall provide sufficient experienced personnel during the phase-in, phase-out period to ensure that the services called for by this contract are maintained at the required level of proficiency. (c) The Contractor shall allow as many personnel as practicable to remain on the job to help the successor maintain the continuity and consistency of the services required by this contract. The Contractor also shall disclose necessary personnel records and allow the successor to conduct on-site interviews with these employees. If selected employees are agreeable to the change, the Contractor shall release them at a mutually agreeable date and negotiate transfer of their earned fringe benefits to the successor. (d) The Contractor shall be reimbursed for all reasonable phase-in, phase-out costs (i.e., costs incurred within the agreed period after contract expiration that result from phase-in, phase-out operations) and a fee (profit) not to exceed a pro rata portion of the fee (profit) under this contract. (End of clause)
  • 6. Stage 1 • Phase 1) Proposal Development and Submissions  Varied timeframes as companies pursue opportunities approaching release  Synopsis, Industry Day(s), RFI, customer visits, Draft RFP, RFP • Phase 2) Board Assessments  6-9 months • Phase 3) Award Announcement and contract start  Unprotested transition could start immediately (after the debriefs) Stage 2 • Phase 4) Transition  30, 45, 60 and 90 variations (for bulk of contracts) Stage 3 • Phase 5) Contract Execution by Successor  Dependent on opportunity (5-8 years)
  • 7.  Phase 1: Proposal Development and Submission Stressors: – Proposal input, writing and reviewing demands – Project timelines don’t change due to proposal schedule – Current operating team may not be teammates on follow-on efforts » Information, working styles and visibility practices may be adjusted near the end of an executing contract. On contract (Incumbent) Responsibilities – Ensure current work continues at a high level (technical and management) – Increase communications with staff – technical and management level flows. Contract performance should never be compromised – Ensure follow-on contract teaming arrangements don’t adversely affect ongoing contract performance
  • 8. Phase 2: Board Assessments Stressors: – Hallway rumors, expectations, realities of contract ending, employee uncertainties  On Contract Responsibilities – Continue communications to executing team, continue to stress focus on assigned task and commitments. – In most cases technical incumbent team will not be adversely impacted by a transition – convey the message. – Begin to refine preparatory documents that will be needed for transition » Task lists, staffing list, property list, ITAR documents and critical project schedules. » Have a checklist for every task, work with your NASA Technical Monitors
  • 9.  Phase 3: Award Announcements Stressors – Realities of contract ending are cemented – Employee uncertainties have peaked if communications have been lagging  On Contract Responsibilities – Meet with your current COTR/CO and make sure everyone is on the same page with regard to the transition – Generate a proposed schedule for phase out activities – Work with your current Civil Servant Task monitors » Descopes and expectations » Task continuations on succession vehicle (lose visibility but you still have obligations to your current staff. Is everyone getting picked up on the follow-on vehicle) » Realize and help staffers manage change (Internally and/or attending open houses of successor)
  • 10. Phase 4 On Contract Responsibilities • The Transition Stressors: – Employee uncertainties, some early staff movements are realistic to assume – Continue efforts to ensure no interruptions in work or performance – Maintain trust with current customers through the last day – Follow-on contract may not be straight forward succession
  • 11. Civil Servant Team Incumbent Contractor Team (most likely will consist of)  Program Manager  Contract Manager or owner  Business Manager  Contracting Officer (CO)  Contracts Manager  Contracting Officer's Technical  Corporate assigned Transition Manager Representative (COTR)  Resource Analyst (RA)  Representatives from other Major-Use Organizations  Chief Information Officer's (CIO) Information Technology (IT) Personnel  Security Personnel • Execute transition to governments satisfaction • Entity ensures the governments best interest is • Execute transition consistent with FAR 52.237- maintained and serves as official executer of 3 – Continuity of Services (JAN 1991) the transition • Should work very closely with incumbent in ensuring a readiness posture for the transition. A close relationship will usually yield the most effective set of information and possibilities for a smooth transition.
  • 12.  On Contract Responsibilities and more elements  Schedule a meeting with the govt, your transition manager and the successor • Handle requests as appropriate (i.e. current support, contractor team mix, meet weekly)  Finalize Inventory for everything on contract task • Staffers, subcontracts, equipment, badges • Readdress and Review critical schedules or milestones • Document and prepare to disposition all technical equipment, intellectual property, software, data, licenses and customized scripts that will be transferred.  Identify all contractor-owned technical equipment, intellectual property, software, data, and end items that must be removed from NASA facilities and ensure the government understands  Establish a definite check-out procedure for all incumbent contractor employees, technical equipment, intellectual property, software, data, and end items that reside on or at a government facility.  Facilitate subcontract phase out procedures • Dependent on size of contract this could be a large effort
  • 13.  On Contract Responsibilities and more elements  Task monitors to need access dependencies which might cause some tasks not to transition on day one – Large procurement in process, TAA’s, Critical phase of a projects – All successor transition teams aren’t equal – Understand your existing task values as it relates to EAC » Government will need to obligate funding to new vehicle  Additional Notes – Training – Certification information where appropriate (if any key records held outside of Satern) – IT Security (Badge transfer process – some badges may not be transferred) – Clearances (Transfers may have to occur- corp and Govt. security need to be involved) – ITAR and TAA (3-6 month process) – Property (GFE listing) – Final task reports » add element to final monthly (disposition all deliverables and property held under task order)
  • 14. Phase 5 On Contract Responsibilities • Contract Execution by Successor Stressors: – You and your Business Manager are the only ones left  Responsibilities – Complete any remaining final task reports – Final 533’s, Close up trailing costs and invoice processing – Execute any remaining tasks due lagging issues (ie ITAR, Critical schedules or government’s convenience)
  • 15. Transition Environment is complex • (Staff, Support companies, Customers, Projects) Transition Elements and Core Responsibilities Make it a success and everybody wins in a variety of ways
  • 16. Thanks (Shelley Johnson/SGT and MSES Management Team) • Questions, Comments ? • Contact Information for follow-up questions and other inquiries: Tracy Dorsey tdorsey@sgt-in.com SGT Inc. 7515 Mission Drive Suite 300 Lanham, Md. 20706 (Office) 301-464-7557 / (Cell) 301-526-6621