Deconstructing the Big Dig: Lessons Learned from the Country’s
                      Largest Mega Project
          NASA PM Challenge 2010 Above and Beyond, Galveston, Texas
                                 Presented By:
           Virginia A. Greiman, Assistant Professor, Boston University




© 2009 V. Greiman


                                 Used with permission
Presentation of Research
     Literature review of cost escalation on mega
     projects and comparison to Big Dig

     Detailed analysis of cost and schedule data over life
     of project

     Presentation of techniques for analyzing data

     Discussion of lessons learned

     Recommendations for mega project managers


© 2009 V. Greiman
Existing Literature
     Focus on causes of mega project cost
     increases

     Techniques for estimating costs

     Governance and support mechanisms

     Frameworks used in different countries

     Little comparative research on strategies and
     methodologies for cost estimation
     management
© 2009 V. Greiman
Why Study Mega Projects? R & D
             Laboratories
     Major driver of economic development and globalization

     Largest Investment of Capital Worldwide

     Output of Technology and Innovation

     Critical cause of poverty is lack of access to infrastructure

     Resolution of political, legal and financial challenges

     Absence of research on cost estimation management

     Interdisciplinary

© 2009 V. Greiman
Transportation Research Board
     In 2006, the Transportation Research Board’s
     Final Report for Cost Estimation and
     Management for Highway Projects, identified
     eight strategies to address cost escalation,
     and linked these strategies to 18 different
     causes of cost escalation on highway
     projects in the United States. Notably, the
     research concluded that most efforts in cost
     estimation have focused on creating tools to
     improve cost estimates with less emphasis
     on tools for cost estimation management.
      (Anderson et. al. 2006).
© 2009 V. Greiman
Why the Big Dig?

     I-90 Never Finished in 1952

     10-14 Hours of Gridlock Per Day

     Accident Rate Four Times National Average

     Rapidly Deteriorating Structure

     Improve Regional Network

     Economic Stimulation

     Environmental Improvements
© 2009 V. Greiman
© 2009 V. Greiman
© 2009 V. Greiman
Project Structure
   State Funding                         Public        Government
                                        Relations/       Agency   Community    Regulatory
                                                                                            Joint Venture
                                         Media          Interests  Interests   And Audit


                                     Federal Funding                           Board of Directors
Project Financing
TIF, GANS, GOBs
                                                                                     SHAREHOLDERS
                                                                                       (Taxpayers)
                                               58%                100%
                                      42%
                      Professional
                        Services                                         Insurance


           Input                             Project Company                        Output:
    Labor and Materials                       (CA/T Project)                    Infrastructure
                                                                               and Technology
                                                                                     Right of
                  Technology
                                                                                     Way Con-
                                  Design        Construction                          tracts
                                                                    Operating &
                                 Contracts       Contracts          Maintenance
 1CA/T Project Structure”
                                                                     Contract

  © 2009 V. Greiman
Project Organization
                           Central Artery / Tunnel Project



            Interface                                                   MTA Chairman

           MTA Positions


                    MTA                                                 MTA Project                                                          MTA General
                 Headquarters                                            Director                                                             Counsel

                                                                                                                                                 Legal
                                                                        B/PB Program
Quality
                                                                          Manager
                Risk
             Management
                                                                                                                                               Claims &
                                                        Design                                                       Construction
                                                                                                                                               Changes
                 Public
              Information          Design Chiefs                 Design Mgmt.
                                                                                               Construction                          Construction
                                     Geotech                                       Human        Services                             Management
                 Fiscal                                          Area    Area
                                                                                  Resources
                                     Civil/Structural
                                                                                                 Tech Support
                                                             P.E.        P.E.         Safety                                 Area   Area     Area        Area
                                     Bridge
                                                                                                   Lab
              Accounting             Architecture            P.E.        P.E.                                                R.E.   R.E.      R.E.       R.E.
                                                                                   Cost &
                                     IPCS                    P.E.        P.E.     Schedule           Experts -               R.E.   R.E.      R.E.       R.E.
                Internal                                                                           Means/Methods
                Controls             Traffic Engr.
                                                             P.E.        P.E.                                                R.E.   R.E.      R.E.       R.E.
                                                                                      Metals
                                     Traffic Mgmt.                                                 Closeout/Training
              Procurement                                                                                                    R.E.   R.E.      R.E.       R.E.
                                     Environmental

             Administrative          Rowars                                                      Utility Maint./Cond. T.O.
               Services              Elect./Mech.                                                                                      Contractors
                                                                                                  Special Projects
     © 2009 V. Greiman               Information Tech.
                                                                                                 Maint. of Traffic                              Milestone
                                     Engr. Services                                                                                             Managers
Cost History And Scope Evolution
              The Central
              Artery/Tunnel Budget
              1985-2007 - $12B                                                           14,475 14,625 14,785
                                                                                14,075                           Owners
              Growth from 2.5 B -                                                                                Contingency
              $14.789
                                                           10,468      10,841
                                                                                                                 Inflation




                                                                                         7,886   7,972   8,000
                                                                                 7,658                           Accounting
                                                   7,740                                                         Changes


                                                                        5,810
                                 5,780             5,187    5,597                                                 Scope,
                                                                                                                  Schedule
                                                                                                                  and
                                                                                                                  Pricing
                4,436                    4,317
                                 3,963                                                                            Changes
                         3,708                                                                                    (1982 $)


2,564           3,409

                                                                                                                  Original
                                                                                                                  Scope



1985             1989            1991            1992 APF 1994           1994 2000       2001    2002    2006
                  ICE
 EIS © 2009 V. Greiman           APF             w/NCRC CSU6             CSU6 CSU7       CSU8    CSU8    CSU9
                                                         w/Inflation     1997
                                                                       Rebaseline
Eurotunnel Facts
     Project cost twice as much as original estimates.
     Project finance included a suspension of interest
     payments and conversion of debt to bonds.
     Project risks included a fire that damaged image and
     revenues.
     Enhanced environmental, safety, and security
     demands increased cost.
     Project was initially weakly staffed through
     seconded employees.
     Contracts were less tight than normal for a project
     financing of this size.
Bent Flyvbjerg, Megaprojects and Risk, p. 97-98

© 2009 V. Greiman
Why are Mega Projects Consistently
        Underestimated?
     A review of large public works projects
     over the last century concluded that
     costs are consistently underestimated,
     a phenomenon attributed to the desire
     of the project advocates to have their
     projects approved.
     (Flyvjberg 2002)




© 2009 V. Greiman
Underestimation of Costs is the
       Rule Rather than the Exception!
  “The difference between actual and
  estimated investment cost is often 50-
  100 per cent, and for many projects cost
  overruns end up threatening project
  viability. Underestimation of costs at the
  time of the decision to build is the rule
  rather than the exception for
  transportation infrastructure projects.”
  (Flyvjberg 2002 and 2006)
© 2009 V. Greiman
© 2009 V. Greiman
© 2009 V. Greiman
© 2009 V. Greiman
© 2009 V. Greiman
Jacked Tunnel
                    Process

                    •Jacking Pit Constructed
                    •Freeze Pipes Placed
                    •Ground Frozen over 3-4 mo.
                    •Tunnel Segments built
                    •Tunnels Jacked 3 ft/day




© 2009 V. Greiman
© 2009 V. Greiman
© 2009 V. Greiman
Modification Cause by
                              Volume 13,490
                                 Scope Transfer
                                    Change
                Different Site      695 - 5%
                 Condition
                                                       Design
                2,411 - 18%
                                                     Development
                                                     4,975 - 37%



               3rd Party
               966 - 7%


                                                   Schedule
                                                  Adjustment
                                 Other             372 - 3%
   © 2009 V. Greiman
As of September 30, 2004
CA/T Safety Performance
           Recordable




  Source: CA/T Project Management Monthly Report
© 2009 V. Greiman
Common causes for cost escalation

     Failure to include a cost for inflation in each
     contract and actual rate of inflation greater
     than planned estimate

     Delays in project completion

     Financing shortfalls and interest rates

     Scope changes

     Shortages of materials and labor
© 2009 V. Greiman
More causes for cost escalation

     Price increases and market changes

     Weak project managers

     Technical and design complexity

     Unexpected events and force majeure


© 2009 V. Greiman
Unique Factors in Big Dig Cost
                  Estimating
   Impact of Long Term Agreement
   Demands of Public Relations
   Subsurface Conditions
   Enormous volume of claims and changes
   Enforcement of safety, quality, budget, and
   schedule
   Management of Political and Regulatory Risk

© 2009 V. Greiman
Unanticipated Site Conditions
     Uncharted utilities

     Obstructions

     Ground water conditions

     Environmental problems

     Archeological discoveries

     Weak soil and hazardous materials

     Design changes

     Change in milestones


© 2009 V. Greiman
Cost History And Scope Evolution

                                                       Environmental / Mitigation
                                                                15%




                                                                            Scope
                                                                         Growth/Claims
                                                                          & Changes
                                                                             15%


     Inflation
       55%




                                                                      Traffic
                                                                       5%


                                                                   Schedule
                                                      Contingency
                                                                  Maintenance
                                                Other     for
                                                                      3%
                                                 5%    Unknowns
                                                          2%


© 2009 V. Greiman
                     Total change from $2.6B to 14.6B = $12.0B
Actual v. Projected Costs Using Actual
               Inflation Rates




© 2009 V. Greiman
Published Inflation Rates




© 2009 V. Greiman
Comparison of 1999 and 2003 Costs




© 2009 V. Greiman
Growth of I-93 Contracts




© 2009 V. Greiman
Lessons Learned
     The importance of calculating inflation
     from the inception of the project

     Monitoring and managing the impact of
     changes

     Critical factors analysis

     Similar factors cut cross all projects
© 2009 V. Greiman
Recommendations
         Study the historical data from mega project
     –         the patterns in the data are valuable indicators of trouble.

     –         Recognize the limitations of the assumptions in
               historical projects with comparable
               characteristics.
         Identify the attributes of the project that will grow
         and change over time.
         Recognize that the accuracy of cost estimates vary
         throughout the project.
         Adopt a baseline for cost control during inception
         and update the baseline when schedule, scope and
         quality change.
© 2009 V. Greiman
More Recommendations!

     Enforce project standards and
     requirements on all project contractors.

     Utilize contingency reserves and
     management reserves solely within the
     framework for which they are
     maintained.


© 2009 V. Greiman
The Most Important Recommendations!
     Establish an open and transparent process!

      – Throughout the project

      – Necessity for accurate and realistic estimation and
        budgeting

     Plot instantaneous data

      – No matter what the accountants say!

      – Every blip is a management decision

     Do your own analysis

      – Use the primary data

© 2009 V. Greiman
References
     Anderson, S., Molenaar, K., Schexnayder, C. (2006, September) Final Report
     for NCHRP Report 574: Guidance for Cost Estimation and Management for
     Highway Project During Planning, Programming, and Preconstruction. National
     Cooperative Highway Research Program, Transportation Research Board of the
     National Academies. 52, 55, 56

     Flyvjberg, B., Holm, M. and Buhl, S. (2002). Underestimating Costs in Public
     Works Projects, Error or Lie?, Journal of the American Planning Association,
     Vol 68, No. 3, American Planning Association, Chicago, Illinois 279-295

     Flyvbjerg B., Bruzelious, N., and Rotherngatter, W., (2006) Megaprojects and
     Risk, Cambridge University Press




© 2009 V. Greiman
Contact Information

                      Virginia A. Greiman
                      Assistant Professor
                       Boston University
                         617-353-6860
                      ggreiman@bu.edu



© 2009 V. Greiman

Mais conteúdo relacionado

Mais procurados

Noneman.steven
Noneman.stevenNoneman.steven
Noneman.steven
NASAPMC
 
Bryson jonathan
Bryson jonathanBryson jonathan
Bryson jonathan
NASAPMC
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
NASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
NASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
NASAPMC
 
Dickerson mark
Dickerson markDickerson mark
Dickerson mark
NASAPMC
 
Alfred mecum
Alfred mecumAlfred mecum
Alfred mecum
NASAPMC
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
NASAPMC
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mike
NASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
NASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
NASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
NASAPMC
 
Hurley.robert
Hurley.robertHurley.robert
Hurley.robert
NASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
NASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
NASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
NASAPMC
 
Topousis dennehyfesq
 Topousis dennehyfesq Topousis dennehyfesq
Topousis dennehyfesq
NASAPMC
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
NASAPMC
 

Mais procurados (19)

Noneman.steven
Noneman.stevenNoneman.steven
Noneman.steven
 
Bryson jonathan
Bryson jonathanBryson jonathan
Bryson jonathan
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Ortiz
OrtizOrtiz
Ortiz
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Dickerson mark
Dickerson markDickerson mark
Dickerson mark
 
Alfred mecum
Alfred mecumAlfred mecum
Alfred mecum
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mike
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Hurley.robert
Hurley.robertHurley.robert
Hurley.robert
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Topousis dennehyfesq
 Topousis dennehyfesq Topousis dennehyfesq
Topousis dennehyfesq
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 

Destaque

Love.john
Love.johnLove.john
Love.john
NASAPMC
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
NASAPMC
 
Sweeney.dan
Sweeney.danSweeney.dan
Sweeney.dan
NASAPMC
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegeman
NASAPMC
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
NASAPMC
 
King richardson
King richardsonKing richardson
King richardson
NASAPMC
 
Derleth.james
Derleth.jamesDerleth.james
Derleth.james
NASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
NASAPMC
 
Michael.hazen
Michael.hazenMichael.hazen
Michael.hazen
NASAPMC
 
Thomas.diegelman
Thomas.diegelmanThomas.diegelman
Thomas.diegelman
NASAPMC
 
Dvorak.dan
Dvorak.danDvorak.dan
Dvorak.dan
NASAPMC
 
Dhanu.kothari
Dhanu.kothariDhanu.kothari
Dhanu.kothari
NASAPMC
 

Destaque (13)

Love.john
Love.johnLove.john
Love.john
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 
Sweeney.dan
Sweeney.danSweeney.dan
Sweeney.dan
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegeman
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
 
King richardson
King richardsonKing richardson
King richardson
 
Derleth.james
Derleth.jamesDerleth.james
Derleth.james
 
Hanna
HannaHanna
Hanna
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Michael.hazen
Michael.hazenMichael.hazen
Michael.hazen
 
Thomas.diegelman
Thomas.diegelmanThomas.diegelman
Thomas.diegelman
 
Dvorak.dan
Dvorak.danDvorak.dan
Dvorak.dan
 
Dhanu.kothari
Dhanu.kothariDhanu.kothari
Dhanu.kothari
 

Semelhante a Grieman

xel_062006_kingplant
xel_062006_kingplantxel_062006_kingplant
xel_062006_kingplant
finance26
 
xel_062006_kingplant
xel_062006_kingplantxel_062006_kingplant
xel_062006_kingplant
finance26
 
xel_062006_kingplant
xel_062006_kingplantxel_062006_kingplant
xel_062006_kingplant
finance26
 
Hoffman.ed
Hoffman.edHoffman.ed
Hoffman.ed
NASAPMC
 
Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...
Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...
Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...
johnpolgreen
 
How & Why Architecture & Standards Shape Gov
How & Why Architecture & Standards Shape GovHow & Why Architecture & Standards Shape Gov
How & Why Architecture & Standards Shape Gov
subramanian K
 
Project Excellence Risk Management K
Project Excellence Risk Management KProject Excellence Risk Management K
Project Excellence Risk Management K
SteveSussman
 
Can togaf™ assist_implementation_of_fea_fsam_12_jul10
Can togaf™ assist_implementation_of_fea_fsam_12_jul10Can togaf™ assist_implementation_of_fea_fsam_12_jul10
Can togaf™ assist_implementation_of_fea_fsam_12_jul10
johnpolgreen
 
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hallPutting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
QuestexConf
 
It services are more than technology
It services are more than technologyIt services are more than technology
It services are more than technology
Stuart Rance
 
Taklimat bengkel isp mampu intan v1.2
Taklimat bengkel isp mampu intan v1.2Taklimat bengkel isp mampu intan v1.2
Taklimat bengkel isp mampu intan v1.2
ISP Sektor Awam
 

Semelhante a Grieman (20)

xel_062006_kingplant
xel_062006_kingplantxel_062006_kingplant
xel_062006_kingplant
 
xel_062006_kingplant
xel_062006_kingplantxel_062006_kingplant
xel_062006_kingplant
 
xel_062006_kingplant
xel_062006_kingplantxel_062006_kingplant
xel_062006_kingplant
 
Future of BuildingCycle organisation English
Future of BuildingCycle organisation EnglishFuture of BuildingCycle organisation English
Future of BuildingCycle organisation English
 
20120916 Cv Jpl Referees
20120916 Cv Jpl Referees20120916 Cv Jpl Referees
20120916 Cv Jpl Referees
 
Icon ecpma09
Icon ecpma09Icon ecpma09
Icon ecpma09
 
Hoffman.ed
Hoffman.edHoffman.ed
Hoffman.ed
 
Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...
Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...
Using togaf™ in government_enterprise_architecture_to_describe_the_it_archite...
 
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
 
Project Management Consulting Services
Project Management Consulting ServicesProject Management Consulting Services
Project Management Consulting Services
 
Synthicity final 2013 berkeley
Synthicity final 2013 berkeleySynthicity final 2013 berkeley
Synthicity final 2013 berkeley
 
How & Why Architecture & Standards Shape Gov
How & Why Architecture & Standards Shape GovHow & Why Architecture & Standards Shape Gov
How & Why Architecture & Standards Shape Gov
 
TAI Onsite Staffing
TAI Onsite StaffingTAI Onsite Staffing
TAI Onsite Staffing
 
Project Excellence Risk Management K
Project Excellence Risk Management KProject Excellence Risk Management K
Project Excellence Risk Management K
 
Can togaf™ assist_implementation_of_fea_fsam_12_jul10
Can togaf™ assist_implementation_of_fea_fsam_12_jul10Can togaf™ assist_implementation_of_fea_fsam_12_jul10
Can togaf™ assist_implementation_of_fea_fsam_12_jul10
 
Leanconstructionintrocomprehensive 1214493943663065 8
Leanconstructionintrocomprehensive 1214493943663065 8Leanconstructionintrocomprehensive 1214493943663065 8
Leanconstructionintrocomprehensive 1214493943663065 8
 
Brian Teague New
Brian Teague NewBrian Teague New
Brian Teague New
 
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hallPutting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
 
It services are more than technology
It services are more than technologyIt services are more than technology
It services are more than technology
 
Taklimat bengkel isp mampu intan v1.2
Taklimat bengkel isp mampu intan v1.2Taklimat bengkel isp mampu intan v1.2
Taklimat bengkel isp mampu intan v1.2
 

Mais de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 

Mais de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Último

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Último (20)

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
 

Grieman

  • 1. Deconstructing the Big Dig: Lessons Learned from the Country’s Largest Mega Project NASA PM Challenge 2010 Above and Beyond, Galveston, Texas Presented By: Virginia A. Greiman, Assistant Professor, Boston University © 2009 V. Greiman Used with permission
  • 2. Presentation of Research Literature review of cost escalation on mega projects and comparison to Big Dig Detailed analysis of cost and schedule data over life of project Presentation of techniques for analyzing data Discussion of lessons learned Recommendations for mega project managers © 2009 V. Greiman
  • 3. Existing Literature Focus on causes of mega project cost increases Techniques for estimating costs Governance and support mechanisms Frameworks used in different countries Little comparative research on strategies and methodologies for cost estimation management © 2009 V. Greiman
  • 4. Why Study Mega Projects? R & D Laboratories Major driver of economic development and globalization Largest Investment of Capital Worldwide Output of Technology and Innovation Critical cause of poverty is lack of access to infrastructure Resolution of political, legal and financial challenges Absence of research on cost estimation management Interdisciplinary © 2009 V. Greiman
  • 5. Transportation Research Board In 2006, the Transportation Research Board’s Final Report for Cost Estimation and Management for Highway Projects, identified eight strategies to address cost escalation, and linked these strategies to 18 different causes of cost escalation on highway projects in the United States. Notably, the research concluded that most efforts in cost estimation have focused on creating tools to improve cost estimates with less emphasis on tools for cost estimation management. (Anderson et. al. 2006). © 2009 V. Greiman
  • 6. Why the Big Dig? I-90 Never Finished in 1952 10-14 Hours of Gridlock Per Day Accident Rate Four Times National Average Rapidly Deteriorating Structure Improve Regional Network Economic Stimulation Environmental Improvements © 2009 V. Greiman
  • 7. © 2009 V. Greiman
  • 8. © 2009 V. Greiman
  • 9. Project Structure State Funding Public Government Relations/ Agency Community Regulatory Joint Venture Media Interests Interests And Audit Federal Funding Board of Directors Project Financing TIF, GANS, GOBs SHAREHOLDERS (Taxpayers) 58% 100% 42% Professional Services Insurance Input Project Company Output: Labor and Materials (CA/T Project) Infrastructure and Technology Right of Technology Way Con- Design Construction tracts Operating & Contracts Contracts Maintenance 1CA/T Project Structure” Contract © 2009 V. Greiman
  • 10. Project Organization Central Artery / Tunnel Project Interface MTA Chairman MTA Positions MTA MTA Project MTA General Headquarters Director Counsel Legal B/PB Program Quality Manager Risk Management Claims & Design Construction Changes Public Information Design Chiefs Design Mgmt. Construction Construction Geotech Human Services Management Fiscal Area Area Resources Civil/Structural Tech Support P.E. P.E. Safety Area Area Area Area Bridge Lab Accounting Architecture P.E. P.E. R.E. R.E. R.E. R.E. Cost & IPCS P.E. P.E. Schedule Experts - R.E. R.E. R.E. R.E. Internal Means/Methods Controls Traffic Engr. P.E. P.E. R.E. R.E. R.E. R.E. Metals Traffic Mgmt. Closeout/Training Procurement R.E. R.E. R.E. R.E. Environmental Administrative Rowars Utility Maint./Cond. T.O. Services Elect./Mech. Contractors Special Projects © 2009 V. Greiman Information Tech. Maint. of Traffic Milestone Engr. Services Managers
  • 11. Cost History And Scope Evolution The Central Artery/Tunnel Budget 1985-2007 - $12B 14,475 14,625 14,785 14,075 Owners Growth from 2.5 B - Contingency $14.789 10,468 10,841 Inflation 7,886 7,972 8,000 7,658 Accounting 7,740 Changes 5,810 5,780 5,187 5,597 Scope, Schedule and Pricing 4,436 4,317 3,963 Changes 3,708 (1982 $) 2,564 3,409 Original Scope 1985 1989 1991 1992 APF 1994 1994 2000 2001 2002 2006 ICE EIS © 2009 V. Greiman APF w/NCRC CSU6 CSU6 CSU7 CSU8 CSU8 CSU9 w/Inflation 1997 Rebaseline
  • 12. Eurotunnel Facts Project cost twice as much as original estimates. Project finance included a suspension of interest payments and conversion of debt to bonds. Project risks included a fire that damaged image and revenues. Enhanced environmental, safety, and security demands increased cost. Project was initially weakly staffed through seconded employees. Contracts were less tight than normal for a project financing of this size. Bent Flyvbjerg, Megaprojects and Risk, p. 97-98 © 2009 V. Greiman
  • 13. Why are Mega Projects Consistently Underestimated? A review of large public works projects over the last century concluded that costs are consistently underestimated, a phenomenon attributed to the desire of the project advocates to have their projects approved. (Flyvjberg 2002) © 2009 V. Greiman
  • 14. Underestimation of Costs is the Rule Rather than the Exception! “The difference between actual and estimated investment cost is often 50- 100 per cent, and for many projects cost overruns end up threatening project viability. Underestimation of costs at the time of the decision to build is the rule rather than the exception for transportation infrastructure projects.” (Flyvjberg 2002 and 2006) © 2009 V. Greiman
  • 15. © 2009 V. Greiman
  • 16. © 2009 V. Greiman
  • 17. © 2009 V. Greiman
  • 18. © 2009 V. Greiman
  • 19. Jacked Tunnel Process •Jacking Pit Constructed •Freeze Pipes Placed •Ground Frozen over 3-4 mo. •Tunnel Segments built •Tunnels Jacked 3 ft/day © 2009 V. Greiman
  • 20. © 2009 V. Greiman
  • 21. © 2009 V. Greiman
  • 22. Modification Cause by Volume 13,490 Scope Transfer Change Different Site 695 - 5% Condition Design 2,411 - 18% Development 4,975 - 37% 3rd Party 966 - 7% Schedule Adjustment Other 372 - 3% © 2009 V. Greiman As of September 30, 2004
  • 23. CA/T Safety Performance Recordable Source: CA/T Project Management Monthly Report © 2009 V. Greiman
  • 24. Common causes for cost escalation Failure to include a cost for inflation in each contract and actual rate of inflation greater than planned estimate Delays in project completion Financing shortfalls and interest rates Scope changes Shortages of materials and labor © 2009 V. Greiman
  • 25. More causes for cost escalation Price increases and market changes Weak project managers Technical and design complexity Unexpected events and force majeure © 2009 V. Greiman
  • 26. Unique Factors in Big Dig Cost Estimating Impact of Long Term Agreement Demands of Public Relations Subsurface Conditions Enormous volume of claims and changes Enforcement of safety, quality, budget, and schedule Management of Political and Regulatory Risk © 2009 V. Greiman
  • 27. Unanticipated Site Conditions Uncharted utilities Obstructions Ground water conditions Environmental problems Archeological discoveries Weak soil and hazardous materials Design changes Change in milestones © 2009 V. Greiman
  • 28. Cost History And Scope Evolution Environmental / Mitigation 15% Scope Growth/Claims & Changes 15% Inflation 55% Traffic 5% Schedule Contingency Maintenance Other for 3% 5% Unknowns 2% © 2009 V. Greiman Total change from $2.6B to 14.6B = $12.0B
  • 29. Actual v. Projected Costs Using Actual Inflation Rates © 2009 V. Greiman
  • 30. Published Inflation Rates © 2009 V. Greiman
  • 31. Comparison of 1999 and 2003 Costs © 2009 V. Greiman
  • 32. Growth of I-93 Contracts © 2009 V. Greiman
  • 33. Lessons Learned The importance of calculating inflation from the inception of the project Monitoring and managing the impact of changes Critical factors analysis Similar factors cut cross all projects © 2009 V. Greiman
  • 34. Recommendations Study the historical data from mega project – the patterns in the data are valuable indicators of trouble. – Recognize the limitations of the assumptions in historical projects with comparable characteristics. Identify the attributes of the project that will grow and change over time. Recognize that the accuracy of cost estimates vary throughout the project. Adopt a baseline for cost control during inception and update the baseline when schedule, scope and quality change. © 2009 V. Greiman
  • 35. More Recommendations! Enforce project standards and requirements on all project contractors. Utilize contingency reserves and management reserves solely within the framework for which they are maintained. © 2009 V. Greiman
  • 36. The Most Important Recommendations! Establish an open and transparent process! – Throughout the project – Necessity for accurate and realistic estimation and budgeting Plot instantaneous data – No matter what the accountants say! – Every blip is a management decision Do your own analysis – Use the primary data © 2009 V. Greiman
  • 37. References Anderson, S., Molenaar, K., Schexnayder, C. (2006, September) Final Report for NCHRP Report 574: Guidance for Cost Estimation and Management for Highway Project During Planning, Programming, and Preconstruction. National Cooperative Highway Research Program, Transportation Research Board of the National Academies. 52, 55, 56 Flyvjberg, B., Holm, M. and Buhl, S. (2002). Underestimating Costs in Public Works Projects, Error or Lie?, Journal of the American Planning Association, Vol 68, No. 3, American Planning Association, Chicago, Illinois 279-295 Flyvbjerg B., Bruzelious, N., and Rotherngatter, W., (2006) Megaprojects and Risk, Cambridge University Press © 2009 V. Greiman
  • 38. Contact Information Virginia A. Greiman Assistant Professor Boston University 617-353-6860 ggreiman@bu.edu © 2009 V. Greiman