Muhammad Ahmed Rana was assigned to work as a Piping Design Engineer for the Barzan Onshore EPC Project from May 5, 2012 to May 8, 2013. The presentation outlines included an overview of the Barzan project, operations of the spoolgen software used for automatic spooling and joint marking, the interface between spoolgen and the CMS construction management system, managing engineering and site revisions through change sheets, revising site spool drawings, and providing field engineering support.
Structural and stability assessment for ex-pit dump toe (final)
Barzan Onshore EPC Project Site Assignment
1. Site Assignment
From 05-May-2012 to 08-May-2013
1
Barzan Onshore EPC Project
Muhammad Ahmed Rana
Piping Design Engineer
Descon Integrated Projects Pvt. Ltd.
2. Presentation Outlines
2
1. Barzan Project Overview
2. Spoolgen Operations
3. CMS and Spoolgen Interface
4. YS/FS Change Sheets
5. Site Drawing’s Revision Work
6. Field Engineering Support
7. Project Pictures
4. 1. Barzan Project Overview
4
Total No. of Lines: 50,300
Total Project Dia Inches: 3,600,000
Total No. of Equipments: 1,100
DESCON Scope
No. of Lines: 10,600
Total Dia Inches 690,000
6. Subcontractors Scope
6
Main Process Trains
• A100, Train 1
• A200, Train 2
Common Process and Main Utilities
• B100
• C100
Common Process and Offsite Utilities
• B200
• C200 & C300
8. Descon Scope Areas
8
Sour Water Area
MEG Regeneration
Condensate Stabilization (Compressor Area)
Flare K.O
Effluent Treatment
Inlet Facilities Area (Slug Catcher)
Cooling Tower Area
Flare
Main Sea Water Line (42”-FRP)
86” Cooling Water Line
11. About Spoolgen
11
Intergraph Software for Automatic Spooling and
Joint Marking
Input File is IDF File generated from PDS or PCF
File generated from SP3D Software
The outputs
CAD Files (Spool drawings for Fabrication)
Weld/Joint Information
Material data for accurate material allocation
Site Assembly/Bolting Information
14. Spool Drawing Preparation and
Issuance
14
Piping Isometric Review and Joint Marking
Preparation of Input Data for Spoolgen Software
Spoolgen Operations (FW Marking, Sheet Split)
Output files Generation (CAD and Text data)
CAD Drawing Along with Data issued to Subcon
Maintaining Index and Issuance Control Sheets
15. Check list and Spoolgen Output
15
Check List Used by JGC
Joint Number Legends
Sample Spool Drawing
Sample Weld Info File
Sample Material File
Sample Assembly File
17. Construction Management System
17
JGC In-house software for complete Construction
Management
CMS
Materal
Control
Test Pack
Control
FS Control
System
Welding
Control
Contruction
Planning
18. 18
3D (PDS etc.)
MACS
REQ
PCOM
ETRS / MTCS
SPOOLGEN
CMS
REQ
PO
Spool Piece wise
Material Data
(LOM)
Weld Joint Data
Assembly Data
PO/Shipping Data
(MSR Data)
E(3D) C(CMS)
Spool
Piece
Dwg
Spool
Dwg
P(PMS)
ISO wise
Material
Data(LOM)
20. YS/FS CHANGE SHEETS
20
Change Sheets Preparation for all Isometrics
(Engineering) Revisions
Automatically generated from CMS
Input for YS is “*.b” files
Input for FS is Manually/Site Mark-up
All spool drawings are updated as per the isometric
revisions
Joint Additions, deletions, and cut and re-welds
YS Revision Check List
Sample YS sheet
YS/FS Tracking Sheet
Finally to DHT for Issuance to Subcon.
22. Site Revisions Work
22
All Changes due to site work other than Engineering
Change
Joint Change Request Form (JCRF)
Shop Fabrication Errors
Site Installation Errors
Joint Category Change
Change due to Construction Sequence (Hydrotesting)
Cut and Re-weld due to RT Failure
Joint added due to Random Pipe Length
Change due to seam Weld orientation
23. Sample Site Revision Drawings
23
Sample 1, Hydro Testing
Sample 2, Change Due To Random Pipe Length
25. Plate Thickness for Hydrotesting
25
Blind for Hydrotesting of 36” Line
Mating Flange = 36” 600# ASME B16.47 Ser. B
Material A36
Design Pressure = 126.3 barg
Blind Thickness as per ASME Sec VIII Comes out to
be 145MM
26. PAD Overlapping with Seam
26
For 52” &56” lines, R.L received 9M instead of
plan 11M
Drawings need to be revised as there were
additional joints
29. FTR (Field Trouble Record) Issuance
29
FTR was issued by Subcon to JGC for any kind
of problem related to Fabrication/installation of
Piping
Sample FTR
34. Spool dwg Hold and Release
34
Spool Fabrication, Installation, Material Issuance,
and every thing got hold for YS Drawings
So if there are many such drawings Shop cannot
proceed Fabrication
Welders/Fabricators can sit idle in severe
conditions if there are too many revisions viz. not
acceptable in any case.
Since all changes are not related to shop
fabrication, so shop can proceed fabrication for
such cases
So, we provided information of spools that shop
can proceed fabrication without any impact by
revision
35. Spool dwg Hold and Release
35
Spool Drawing With Impact on Fabrication
Spool Drawing With No Impact on Fabrication