Design Concepts &
                                         Implementation Plan




RiverFIRST:
A Park Design Proposal and Implementation Framework
for the Minneapolis Upper Riverfront




DRAFT
RiverFIRST Guiding Principles
21st Century Challenges
The Minneapolis Riverfront Development Initiative provides a chance                                     habitats. RiverFirst is guided by similar principles that embrace the notion    Park, but also includes the depth of the river and all points in between.
to consider how the Minneapolis park system can protect the national                                    that cities evolve over time and must be allowed to accommodate changes in      Understanding the nuanced difference in surface shape and features of
ecological heritage of the Minneapolis Riverfront and the Mississippi River,                            environmental, social, and economic climates.                                   this landscape creates opportunities for multiple-scaled combinations of
foster community health, support economic opportunity and prepare                                                                                                                       submerged, emergent, riparian, and meadow upland. This sensibility has
Minneapolis with resilient and sustainable eco-infrastructure for generations                           Design Principles                                                               the potential to guide an urbanistic strategy toward built form that results in
to come. There are 21st Century challenges that are global in nature and                                RiverFirst is based on four design principles. The first, Go with the Flow,      buildings that optimize orientation for natural light, energy harvesting, and
local in impact. Mississippi River access may increase in value as energy costs                         reflects the dynamic characteristic of the river itself and becomes a model      stormwater management.
rise and warming climates reduce winter port closures. Greenhouse gas                                   for other systems such as public access, mobility, and energy infrastructure.
emissions need to be controlled. Storm water systems must be adapted to                                 This principle is based less on the addition of the physical characteristics    The third principle, Both/And, addresses the unlikely juxtaposition of the
account for increasing uncertainty in local climate variability. Urban growth                           that are common to planning but rather on a subtractive approach that           Mississippi River to its immediate surroundings, in particular the Northside
must be accommodated. RiverFirst considers these challenges as the                                      exposes the underlying nature of a place, sometimes literally unearthing        industrial district which has suffered through neglect and a weak economy.




  AFT
means to enable a blue & green way of life to flourish in Minneapolis and to                             existing conditions in an effort to recover its identity. The daylighting of    Both/And provides the groundwork for a condition where two seemingly




DR
attract the brightest creative minds to live in Minneapolis.                                            buried stormwater systems is an example where the act of excavation not         conflicting circumstances can be allowed to co-exist, even be strengthened
                                                                                                        only points to the significance of a tributaries relationship to the river but   by the others presence.
The Mississippi is still a working place for industry, but current economic
                                                                                                        simultaneous remediates or cleans the stormwater before entering the river.     Finally, Park Plus, reflects the contemporary role that cities must play to
opportunity is hindered by the dislocated relationship between Minneapolis
                                                                                                        The effect provides measurable benefits including increased visibility of the    address the challenges of the 21st Century. Parks today are expected to
and its river. A planning strategy that prioritizes the Mississippi, that puts
                                                                                                        river and thus security, and reduced park maintenance.                          exceed our normal understanding of a park as a social gathering space rather
it first, is intended to renew the river’s strength and diversity as a living
ecosystem. In doing so, the physical, societal and economic health of the                               Where Go with the Flow reflects mobility and access, the second principle,       it must play a role in reducing energy consumption through environmental
city is placed first. RiverFirst is guided by the dynamics of the river. Water                           Design with Topography, is more physical in nature. The great range of          stewardship, minimizing maintenance costs, and providing places that
carves and erodes to form the river that supports and sustains diverse                                  geographic diversity begins not only with the site’s highest point, Farview     support health and safety.




                                                          DOWNTOWN
                                                              MINNEAPOLIS

                                                                                           SAINT PAUL
                                                           CHAIN OF LAKES




                                                                            LAKE NOKOMIS




    REGIONAL MOBILITY                                                                                     SHIPPING LANES                                                                 SHIPPING LANES
    Minneapolis Context                                                                                   Minneapolis Context                                                            Minneapolis Context
         Grand Rounds               Existing Parks                                                             Key Text                                                                       Key Text

         Riverfirst Connector       Riverfirst Parkland                                                        Key Text                                                                       Key Text
         Proposed Regional Trails                                                                              Key Text                                                                       Key Text
         Parks Regional Trails                                                                                                                                                                Key Text

         State, Federal Trails




Extended regional trail system                                                                          Mississippi River Nutritional run-off                                           Mississippi global transportation links



8
Loops                                                                             Moisture Gradients
                      The north-south Trail System connects with east-west pedestrian walkways          Landscape is created by the varying interactions of soil and water. Much of
Phase 1 Loops         (Knot Bridges) in a series of recreational River Loop circuits that link North    the RiverFirst effort concerns putting seasonal stream and river water back in
Phase 2 Connections
                      and Northeast Neighborhoods. In so doing, sections of the river can be            contact with riverbanks and uplands that have been cut off by piped outfalls,
                      encircled and begin to create a series of interconnected “rooms” each with        bulwarks and embankments. The more we can increase these soil / water
                      a specific urban and natural character. This simple idea has great strength        contacts in terms of length, area, and varying saturation conditions, the
                      as a means of orientation and breaking down a river that is regional in scale     greater the species diversity and ecosystem resilience can be created. These
                      to something in neighborhood sized chunks. The trail system will have the         varying levels of new moisture in the soil – from constant saturation to drier
                      most flexibility and variety in terms of routes when options for crossing the      fast-draining uplands will largely determine the ecosystem types we see in
                      river are positioned within a five minute walk. One could imagine a series         this river reach in the coming years. So not only the plants but the associated,
                      of linked rubber bands stretched around each room along with the idea             interrelated food web of amphibians, insects, birds, and mammals that
                      that these flexible loops can also be expanded to take in the entire 5 ½           depend on them are fundamentally organized by moisture gradients in the
                      miles of riverfront and northward beyond. In the same way, loops can and          soil. Historically, along this stretch of the Mississippi we had the possibility
                      should expand into both the Northside and Northeast neighborhoods so              of highly varied ecosystems in close proximity due to the river’s varying
                      they are flexibly joined to the river based system. The result is a flexible,       encounters with shorelines, tributaries, and islands. Of course numerous
                      web-like circulation structure that can organize movement over a significant       alterations to the channel have reduced this condition. RiverFirst is working
                      area of the city. Five minute pedestrian loops can then be joined onto large      carefully with topography and day-lighted storm flows to dramatically expand
                      intermodal systems like the Prairie Loop Shuttle that encircles the entire site   the topographic, hydrologic, and consequently, small scale ecological
                      using Railroad rights-of-ways.                                                    diversity throughout this reach.




                                      DRAFT


                                                                                                                                                                                      9
Guiding Principles Urban Ecology




                                                                                                                                                                                                                                                                                                leucocephalus




                                                                                                                                                                                                                                                                                                                                                                                                    Lontra canadensis
                                                                                                                                                                                                                                                                                                Haliaeetus
                                                                                                                                                 Vulpes vulpes
                                                                                    Spilogale putorius




                                                                                                                                                                                                                                                  Pandion haliaetus
                                                                                                                                                                                              Circus cyaneus




                                                                                                                                                                                                                                                                                                                                           Ondatra zibethicus




                                                                                                                                                                                                                                                                                                                                                                                                                                               Aegolius funereus
                                   Foodweb
                                   97 Species of Greatest Conservation Need




                                                                                                                                                                                                                                                                                  Micropterus




                                                                                                                                                                                                                                                                                                                                                                                                                        Dendroica
                                                                                                                                                                                                                                                                                                                                                                                Aythya affinis




                                                                                                                                                                                                                                                                                                                                                                                                                        cerulea
                                                                                                         Sorex palustris
                                   (SGCN) are known or predicted to occur




                                                                                                                                                                                                                      Pseudacris
                                                                                    Phenacomys




                                                                                                                                                                                                                                                                                                                                                                                                                                                                   Pipistrellus
                                                                                                                                                                                                                                         maculosus
                                   within the Riverfirst site. This food web




                                                                                                                                                                                                                                         Necturus




                                                                                                                                                                                                                                                                                                                                  Morone
                                                                                                                                                                                 Megaceryle
                                   examines a small collection of those SGCN




                                                                                                                                                                                 alcyon
                                   and illustrates the necessity for biodiversity
                                   in order to achieve conservation goals and
                                   create a renewed urban ecology.




                                                                                                                                                                                                                                                                                                                Plethobasus




                                                                                                                                                                                                                                                                                                                                                                                                Orconectes
                                                                                    Formicinae




                                                                                                                                                                             Cicindela




                                                                                                                                                                                                                                   Ophiogo
                                                                                                                           Ceraclea




                                                                                                                                                                                                                                                                                                                                                                Dendroc
                                                                                                                                                                                                                                   -mphys




                                                                                                                                                                                                                                                                        Erynnis




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      Glycera
                                                                                                                                                                                                                                                                                                                                                                -touns




                                                                                                                                                                                                                                                                                                                                                                                                                                     Pimoa
                                                                                                                                                                                                               Apis
                                     AFT


                                                                                    Vernonia
                                   DR



                                                                                                                                                                 Morchella




                                                                                                                                                                                                                                                                                                                                                                Phytoplankton




                                                                                                                                                                                                                                                                                                                                                                                                                                    Solidago
                                                                                                                                                                                                                                                                                                                              Sagittaria
                                                                                                                                      Viburnum




                                                                                                                                                                                                                           Aster




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  Solidago
                                                                                                                                                                                                                                                                                                                                                                                                            Spartina
                                                                                                                                                                                                                                                                      Asclepias
                                                                                                                                                                                                                                        Liatris
                                   Regional Corridors                                                                                                                                                                              Urban Ecology Corridor
                                   Green-Regional Natural Resource/                                                                                                                                                                Source Habitat                                                                                                          Urban Fabric                                                                             River Habitat
                                   Areas Significant Ecological Areas/
                                   Wetlands and Wet Areas (MMCD)
                                   Green Lines-Trails
                                   Blue-Water Bodies
                                   Purple Arrows-Flyway and
                                   Terrestrial Corridors




                                   150 years ago, this reach of the Mississippi was a focus of diverse biological                                                                                                                  The physical result is tree-like in nature, with the Mississippi itself as the main
                                   activity ranging from bacteria in the soil to the dead plants they break down,                                                                                                                  trunk and tributary corridors as some of the key structural branches – such as
                                   to the insects, amphibians, snakes, birds, and mammals that consume each                                                                                                                        Shingle Creek to the north, Basset Creek and other to southwest connecting
                                   other in a complex food chain. This vast interrelated system relies upon a                                                                                                                      on to the Chain of Lakes and beyond, and a new proposed natural corridor
                                   healthy river and tributaries and generous riverine areas of moist and often                                                                                                                    to Columbia Park to the Northeast. Once a rich habitat with Sandy Lake at
                                   saturated soils to support it in place. The more mobile species also rely on                                                                                                                    its core, this current golf course has the potential for restoration as a lake
                                   the river and related corridors to facilitate movement as they seek shelter and                                                                                                                 and wetland complex. This crucial piece of ecological real estate can also
                                   food over a wider range. Urban interventions, especially in this reach, have                                                                                                                    function as a future Central Park of Minneapolis as its urban margins increase
                                   fragmented every aspect of the system creating a “missing link” not only                                                                                                                        in density over the next 20 years. I-94, like most urban highways is laced with
                                   in the Grand Rounds but in the Mississippi Flyway and terrestrial corridors.                                                                                                                    endless swaths of open soil which lay sterile and create another blockage in
                                   In everything it does, RiverFirst seeks to reverse this disconnection and                                                                                                                       the system of habitat and natural species cover. This could be transformed
                                   fragmentation through specific measures concerning renewing the natural                                                                                                                          into diverse urban forest by cultivating every available embankment and sliver
                                   hydrology within urban conditions, increasing areas native landscape types,                                                                                                                     of residual land with native trees.
                                   and cultivating natural attractors for species that may be in decline or have
                                   left the area entirely.



10
Mobility




                                                                                                                                                                                                                                                               DRAFT
                        13                                                            17
                                                                                       6
                        5




                              9
                              3

                                                             3.5 mi




                                                                                       9
                                                                                           3
                              9


                                                                                                                                                                                                                                                            Mobility Scales
                              3



                                                                                                     10                                         32
                                                                                                                                                                                                                                                            City Source                    Users                         River Loop
                                                                                                     3
                             22
                                                                         1.8 mi



                                                                                                                                       10
                                    9                                                                     12

                                    2                                                                     4


                                                                       1.2 mi


                         5                                                                                                       888

                                                                                                               15

                                                                      1.3 mi
                                                                                                                5




                             14                                                        0.6 mi


                              5




                                                        16
                                                             6
                                                                                                                                            7
                                                                                                                                                3
        19
                                        LOOP
                                                                                                                        1.8 mi
                                                                                                                                                                          The RiverFirst proposal incorporates new and existing transportation              The new Cedar lake Bike trail links the River with Target Field, improving
                                                                                                                                                                          initiatives to create a sustainable, multi-modal and interconnected               suburban and regional public access to the river on the Hiawatha LRT, the
                                                                                                                                                                          public transportation system for commuting, recreation, and mobility in           North Star and future Central, Southwest, and Bottineau LRT lines. Existing
                                                                                                                                                                          Minneapolis. The Minneapolis Flyway, a comprehensive new North-South              train rail lines are retained to facilitate sustainable transportation logistics
                                                                       16                       55
                                                                                  7                                                                          16           pedestrian and bicycle Park Trail System, is linked with a East-West Knot         for a new eco-business innovation district that can benefit in the future
                                                                                                                9
                                                                                                                    3                                                     Bridge pedestrian and bicycle paths supported by the exiting foundations of       from renewable Minnesota wind energy and locally generated solar energy
                              6                    18
                                                                                                                                                                          City and County bridges.                                                          on Parklands. Residents form North and Northeast Neighborhoods will
                                                                                                                                       7                                                                                                                    be able to walk, bike or take a clean electric shuttle to work. Nice Ride
                                                                                                                                                                          Access to the Trail System is provided by existing Bus routes, the proposed       stations and public kayak launching sites at the Urban Boat Builder’s facility
                                                                                                                                                                          clean electric bus Prairie Loop route and a series of new bridge crossings        on 28th Avenue North and Scherer Park increase the public accessibility of
MOBILITY
                                                                                                                                 0 500’ 1000’        2000’        4000’   over I-94 that connect the North Neighbourhoods with the River. Pedestrian        the RiverFirst multi-modal transportation initiative and create a world class
     Parkland                Prairie Loop
                             Hiawatha Light Rail
                                                                                       Trail Connection
                                                                                       Secondary Connection
                                                                                                                                                                          connection improvements to Dowling Street, 34th Avenue North (Perkins Hill        recreational and bike commuting network.
     Tree Cover
     Trails                  Metro Transit                                             Interstate Highway                                                                 and City View School), Lowry and Broadway are proposed to compliment the
     Proposed Connection     NorthStar Commuter Rail                                   Nice Ride Station
                                                                                                                                                                          central RiverFirst connecting feature, an overpass that links Farview Park, the
     Recreation Loops        Rail                                                      Proposed Nice Ride Station
                                                                                                                                                                          City’s historic high point, with the River.




                                                                                                                                                                                                                                                                                                                                           11
Guiding Principles Green Networks


                                                           RIVER TALK WiFi Network




                                                                                  17
               13
                                                                                   6
               5




                                     9
                                     3




                            13                                                             10
                            5                                                                 3




                                                                                                       15
                                                                                                       5                                       Sea Turtle App      Locavore              Love Fresh       National Geographic
                                                                                                                                                                   Green Market Finder   iPhone App       Bird App

                                 14

                                 5


                                                                                                                          7
                                                                                                                          3


                                                                                                                                               The RiverFirst proposal leverages the development of Riverfront                   Neighbourhoods with significant new urban agriculture resources, including
                                                    LOOP
                                                                                                                                               Parkland to improve the health of the River and the health of the City            native edibles, that build upon existing community gardens, Farmer’s Markets
                                                                                                                                               and its Neighbourhoods. At the larger urban scale, RiverFirst creates and         and sustainable organic and slow food establishments.
                                                                                                                                               interconnects a series of synergistic Green Networks that are comprised
                                                                                                                                                                                                                                 The Green Networks combine to build a large, diverse constituency of
                                                                   16
                                                                        7
                                                                                                                                               of sustainable bike routes and pedestrian trails, existing Neighbourhood
                                                                                                                                                                                                                                 citizens who are informed about health, community based food, recreation
                                                                                                                                               based community gardens and local food initiatives, new civic clean energy
                                                                                                                                                                                                                                 and the benefits of a sustainable River. New initiatives are envisioned, such
                                                                                                   9
                                                                                                   3
                                                                                                                                               resources and the WiFI River Talk network, providing public outreach and
                                                                                                                                                                                                                                 as the development of sustainable consumer products: 1% RiverFirst clean
                                                                                                                                               education on local conservation. Renewable energy in Parklands provides
                                                                                                                                                                                                                                 road salt and natural lawn fertilizer products to raise public awareness of how
                                                                                                                                               clean power for charging electric vehicles and on shore power (OSP) for
                                                                                                                                                                                                                                 everyday consumer practices can improve River ecology and community
                                                                                                                                               green industry, reducing future energy cost risks, noise and emissions.
 INFORMATION + ENERGY NETWORKS
                                                                                                                0 500’ 1000’   2000’   4000’
                                                                                                                                                                                                                                 health far beyond the Minneapolis Riverfront.




                                                                                                                                                                                                                                              AFT
      Existing Parkland                  Prarie Loop Terminal               RiverTalk Usage                                                    RiverFirst Parklands create significant new opportunities for urban agriculture,
                                         Trail Connections                  Community Garden
                                                                                                                                               help provide for municipal food security and expand neighbourhood access




                                                                                                                                                                                                                                            DR
      Developed Parkland
      Trails                             WiFi Repeater                      CSA Drop Off
      Proposed Connection                Prarie Loop                        Local Produce Market                                               to healthy food and nutrition in ways that build communities and local
      Photovoltaic Energy                Interstate Highway                 Riverfirst Urban Agriculture Building
                                                                                                                                               business enterprises. Together the RiverFirst Green Network systems link




12
Water




                                                                                                         Watershed – Impaired Waters                                                        Stormwater Flows
                           8
                                                                                                         Hg –                                                                               Rainfall                                                  River Outfall
                                                                                                         Mercury
     17                                                                           12

                                                                                                         PCB –                                                                                                   Current: Pipe System
                                                                                                         Polychlorinated
                                                                                                         bipehyls
                                                                                    19

     22                                                                                                  FC –
                                                                                                         Fecal Coliforum

                                                                                                         PFOS –
                                                                             41
                                                                                                         Perfluoroctane                                                                                           Proposed: Riverfirst
                                                                                                         Sulfinate

                                                                                                         T–
                                                                                                         Turbidity
31                                                             96
               29
                                                                                                         NaCl –
                                                                                                         Sodium Chloride



                                                                    84
                                                                                                         The basis of RiverFirst lies in restoring the relationship of land to water, the   RiverFirst proposes a system of bio-filtration opportunities including a new
                                                                                                         notion of B’dote in Native American cultures, where every joining of waters        20 acre wetland at the current barge port that can receive and clean large
                                      53
                                                                                                         has a sacred and also practical status in that these moments of hydrologic         quantities of north side storm flows while also creating rich and diverse new
                                                                                                         connections maintain the heath of the overall tree-like system. As ”limbs”         emergent ecosystem based on what had previously existed there. A stair-
                                                                                                         have become severed and polluted over the years the natural function of            step series of biofiltratrion terraced gardens along Dowling also provides
                                                                                                         these tributaries has been lost. The watersheds which feed this reach of the       an environment for cultivating native “crops” such as American lotus and
                      67                                                                                 Mississippi now contribute a range of urban pollutants including mercury,          Arrowhead which historically fed Native Americans and waterfowl. At the
                                                                                                         PCB’s, and most importantly salt from roadways. Reversing this trend requires      Northeast side, existing parks provide a starting point for a series of new
                                                                                                         a system-wide solution within each watershed. But the zone along the river         storm water ravines and seasonal creeks which gently slope from Marshall
                                                                                                         where piped outfalls occur is a fundamental place to start transforming the        St. to the river, allowing both people and water new access to the shoreline.
                                                                                                         current hard infrastructure into a “soft” one where storm flows are brought         These measures provide a powerful starting point within each watershed in
                                                                                                         to the surface wherever feasible to be naturally cleansed by riparian corridors    terms of treating pollutants at their most concentrated, but also create a new
                                                                                                         and wetland features cultivated with bio-filtering species.                         visibility for a natural hydrology that will support new urban ecosystems.
STORM WATER
                                                                         0 500’ 1000’    2000’   4000’
          Parkland                         Watershed Regions




                                                                                                                             AFT
          Stormwater Outfall
          Hidden Stormwater Outfall




                                                                                                                           DR
          Industrial Outfall
          Stormwater Drainage




                                                                                                                                                                                                                                                                       13
Guiding Principles Emergent / Meadow




DRAFT



      Urban                                                      Urban
                   Meadow                               Upland
                                  Emergent   Riparian


14
Riparian / Upland




                                                                                                                                                                                                                    DRAFT




Meadow                                                               Emergent                                                                Riparian                                                               Upland
This iconic habitat zone starts at the edge of the twin cities and   This zone of shallow water is often manipulated by the rivers           This dynamic zone needs bank stability since anthropogenic             Where the moisture regime changes a diverse canopy of timber
stretches to the south and west of the state. These landscapes       force and sedimentation; a multitude of rushes, sedges, and             forces have increased the stress of wave action and decreased          emerges, layered with a myriad of sub-canopy and ground-layer
are dominated by grasses;a perfect habitat for small mammals         grasses scatter refuge for the river’s wildlife inhabitants. A living   natural flood plains. Defined by drastic topographical changes           vegetation, providing a rich habitat for fringe species that “go
and their predators. Typically the topography is flat with slight     machine that absorbs flood waters, with the ability to filter             from scrouring, this zone is a key link between land and river as it   to” the river for food and reproduction needs. This zone provides
depressions and gentle slopes.                                       pollutants, these waters team with insects, reptiles, and fish.          provides the opportunity to increase habitat and biodiversity.         essential habitat buffering to urban adjacencies.

                                                                                                                                                                                                                                                                                 15
Overall Plan First Steps and Future Growth
                             Introduction
                             The planning strategy to develop the 5 ½ mile stretch of riverfront and adjacent urban             5–10 Year Vision
                             upland along the Mississippi is to prioritize five strategic implementation sites that              The 5 –10 year Vision includes the further growth of projects that have been implemented in
                             over a 0 – 5 year timeframe together establish a framework for future visions outlined             the 0 – 5 year plan and introduces new areas for development. For example, the Farview Park
                             in two further phases, a 5 –10 year and 10 – 20 year plan. In the near term, a system of           Extension strengthens its connection from Northside through the addition of a two-block
                             north to south riverfront trails are complimented by east to west bridges that establish a         land bridge that spans I-94 and extends the landscape of Farview Park down the hill toward
                             network of circulation and access opportunities to the Mississippi River and its adjacent          the river. 27th Ave North, lost over decades of industrial development, is restored as a walk-
                             neighborhoods. Site specific demonstration sites create anchors at strategic locations              street and lined by rain gardens that bring stormwater from Farview Park to the river. The
                             along the river that establish the foundation for a vision for the Mississippi that will           Farview Park Extension culminates in the redevelopment of the City-managed Trash Transfer
                             support the region’s neighborhoods that are rich with cultural and ethnic diversity, artistic      facility for use as a river-oriented enterprise and educational/interpretive experience such as
                             production, and multi-scaled industrial business served by freeway, rail, and barge.               a boat builder. This 12-block sector from Farview Park to the river becomes the core of a new
                                                                                                                                Eco-Business District that serves as a model for others to follow.
                             0 – 5 Year Strategic Implementation Plan
                             The first intervention is a 6 mile Riverfront Trail System from Plymouth Bridge to Camden           To extend the recreational and community energy created at Scherer Park, a mix of
                             Bridge and back down to Boom Island. This system of trails includes a series of floating            recreational enterprise uses such as a café, pavilion and museum would be developed in
                             Biohaven Islands that are dedicated wildlife sanctuaries intended to reintroduce and support       the area around the Marina at Boom Island. At the Northside Wetlands Park the Upper
                             riverfront habitats. The Riverfront Trail System is a continuous trail and bikeway proposal that   Harbor Terminal port facility is replaced by park space, a renovated Cold Storage Building,
                             will use existing public parkland as well as private property requiring access through either      and structures for public amenities, solar arrays, and areas to store dredge spoils.This first
                             the purchase of land or easement agreements. As a result of active industries along the            large scale project north of Lowry will serve as a prototype for future developments.
                             Northside, riverfront trails are proposed to be elevated allowing industries to operate while      The 5 –10 Year Vision introduces a new area of development—the Northeast Riverfront
                             the public enjoys park amenities and wildlife habitats. In the event that easements are not        Park which proposes to utilize MPRB-owned parcels to create stormwater mitigation by
                             possible an interim bikeway is proposed along 2nd Ave N thus providing a link between the          regrading parkland at existing outfall locations.
                             riverfront trails that terminate north of Broadway Bridge and North Mississippi Park.

                             The second intervention is the 26th Ave N Greenway Extension and improvements to 28th              10 – 20 Year Vision
                             Ave N which establishes an initial implementation for the plan’s long-term vision to extend        The longer range 10 – 20 Year Vision is to create opportunities within the framework of
                             Farview Park to the river through this area’s industrial district.                                 the plan for added development that reinforces both the RiverFirst initiative and City of
                                                                                                                                Minneapolis redevelopment goals. The plan attempts to preserve the city grid framework
                             The third intervention, the Scherer Park District, develops the 11-acre Scherer Brothers           and introduce new and innovative programs that are responsive to environmental
                             property recently acquired by the MPRB for public park land along with development that            stewardship and provides opportunities for a mix of creative industries, commercial
                             includes a mix of uses to support an energized park. The plan for Scherer Park includes            amenities, and residential growth. Clusters of development are encouraged at east-west
                             restoration of Halls Island and the narrow river channel between Halls Island and the              corridors such as Plymouth, Broadway, Lowry, Dowling, and 41st Street N at north-south
                             Scherer site. The plan would create roughly an 7 acre park and 4 acres of development on           intersections such as 2nd Avenue N and Marshall Avenue.
                             the Scherer site. This third intervention also includes establishment of Sheridan Park and
                             development of new residential housing adjacent to the Grainbelt Brewery .                         Finally, the Spirit Island site, located where the former Spirit Island once existed just below
                                                                                                                                Saint Anthony Falls and obliterated during the construction of the lock and dam system,




 RAFT
                             The fourth intervention is the Northside Wetlands Park, currently the site of the City of          is included as a central piece of the RiverFirst project. Once a sacred ground for the native
                             Minneapolis’ Upper Harbor Terminal. This project proposes to create a 25 acre wetland              Dakota community, it is the intention of the RiverFirst proposal to establish a process that




D
                             on a portion of the 48-acre site currently used as a materials handling facility for coal, steel   will lead to the celebration of Spirit Island as a gesture that marks a commitment to a much
                             coil, and dredge spoils from the river. This 0 – 5 year plan proposes to consolidate the port      deeper cross-cultural understanding so important to the life of our city.
                             facility to the northern end of the site making space for the wetlands project.
                                                                                                                                Ultimately, it is the vision of RiverFirst to transform the 3-mile stretch of Northside industrial
                             Downtown Gateway Park, the fifth intervention, provides a destination downtown park                 land as a place where both ecologically-responsible business industries and mixed use
                             adjacent to the Central Library as well as reestablishment of an open space link between           developments can co-exist and that share a common interest in preserving the health of
                             Gateway Park, Nicollet Mall and the Mississippi River.                                             the Mississippi River providing a bridge to it from communities such as Northside that
                                                                                                                                previously have had no access to its riverbanks. The RiverFirst plan provides riverfront
                                                                                                                                park land with trails, bikeways, bridges, and walkable streets that support and help foster
                                                                                                                                strategic development opportunities that take advantage of the areas proximity to a
                                                                                                                                growing downtown Minneapolis, the diverse Northside and Northeast neighborhoods to
                                                                                                                                the east and west, and unique parks to the north.

 16
0 – 5 Year Implementation Plan     5–10 Year Vision   10 – 20 Year Vision




                                 DRAFT


                                                                            17
Priority Project 0 – 5 Years                                                                                         Riverfront Trail System: Plymouth to BNSF Trail Loop
                               1. Scherer Park
                               2. Boom Island marina
                               3. Restored Hall Island
                               4. Plymouth Knot bridge




                                                                                                                AFT
                               5. Sheridan Park and Development
                               6. Broadway Knot Bridge




                                                                                                              DR
                               7. Biohaven Island
                               8. BNSF Pedestrian Bridge and Third Rail Cafe
                               9. Riverside Commons Park




                               Named after the Mississippi Flyway, one of the world’s most significant north-                       Access to the Trail System is from city streets, bike trails and bus lines as
                               south bird migration routes, this proposed public Trail System will provide                         well as from the proposed Prairie Loop clean electric bus line. When the
                               six miles of new, Riverfront recreational trails for pedestrians, bicyclists and                    Flyway Trail System crosses over land owned by existing industry, it bridges
                               x-country skiers. The north-south Trail System connects with east-west                              over operational areas. Representatives of all industrial land owners were
                               pedestrian walkways (Knot Bridges) in a series of recreational River Loop                           contacted by the Design Team to discuss and develop criteria for the Trail
                               circuits that link North and Northeast Neighbourhoods.                                              System. By creating a public presence along the riverfront, the Minneapolis
                                                                                                                                   Flyway trail system will jumpstart the RiverFirst Parklands and create the
                               Site lighting, grouping cyclists and pedestrians with appropriate lane ways,                        connective ‘glue’ to link Downtown and Neighborhoods with the River and
                               open view corridors, WiFi access through the proposed River Talk network                            with existing and new Parklands. The trail system can be implemented in a
                               and convenient vehicular and pedestrian Trail access points will help to                            series of cost effective modular segments that can be constructed over time.
                               ensure public safety as the riverfront develops. The Trail System can serve
                               as a 21st century model for new operational efficiencies in bio-remediated
                               storm water irrigation, modular construction, and low maintenance solar
                               powered snow melting systems.




                                                         Plymouth to Broadway is the first and most easily achievable loop
                                                         in the system of loops moving northward with no special bridging
                                                         required N-S
                                                         BNSF bridge link requires a major acquisition of strategic rail
                                                         bridge still in marginal use
                                                         BNSF link would allow major bike traffic on 26th St. to connect to
                                                         major routes on NE side
                                                         Graco river frontage already in process of easement creation
                                                         Park at Riverside condos creates screening of residents from
                                                         industrial activity and new acoustic green living plant wall park in at
                                                         “triangle” creates cleft for storm water collection




18
Riverfront Trail System: BNSF to Lowry Loop
                                              1. BNSF Pedestrian Bridge and Third Rail Cafe
                                              2. Edgewater Park
                                              3. New Ravine Trail
                                              4. Gluek Park
                                              5. New Ravine Trail
                                              6. Biohaven Island
                                              7. Children’s Art Camp
                                              8. Lowry Bridge
                                              9. Flyway Bridge
                                              10. 26th St. Bike Route




                                              The Minneapolis Flyway Trail System serves the City and Parks as a                                    Preliminary Development Budget
                                              comprehensive riparian conservation spine. The Trail System provides a rich                           A preliminary budget of $62,088,122 has been estimated for the Riverfront
                                              range of landscape habitat to support endangered cornerstone species.                                 Trail System that includes costs for the N 26th Avenue Greenway extension
                                              Naturally cleansed storm water is integrated along the Trail System in small                          and improvements to N 28th Avenue. Trail sites along the riverfront that are
                                              scale bridge crossing points that allow natural drainage as well as animals                           private property will require both easements and fee acquisition resulting in
                                              to move freely underneath to sustain species and habitat movement. The                                additional development costs that are not reflected in the total capital cost.
                                              Trail System provides an armature for the re-establishment of the historic                            This budget will be refined prior to Board action in December 2011.
                                              riverbank canopy, which in turn supports pollinator and food web species for
                                              Warbler, Fly Catchers, Bireos, Oriels and other migrating species, as well as
                                              supporting river cleaning mollusks and fish that sustain Heron, Osprey, and
                                              Eagles. The Conservation Strategy unifies the form, material expression and
                                              public experience of the Trail System. Constructed sustainably of reclaimed
                                              wood modules, with low maintenance recycled rubber walking surfaces, the
                                              Trail System allows bio-diversity to return to the river and flourish over time.




                                                                        East side – through trail shifts to Marshall with various “eyebrows” where bikes
                                                                        and pedestrians loop to the river’s edge.
                                                                        Ravines allow gently sloped flows of people and day-lighted storm to river’s edge
                                                                        Lowry crossing engages with and modifies construction in-progress
                                                                        West side has three of most challenging trail connections – under BNSF,
                                                                                                                                                                          DRAFT
                                                                        over 2 different active barge docks using Flyway bridges
                                                                        Easement and land acquisition at these locations among most strategic
                                                                        for long term success of Grand Rounds
                                                                        Interim fall-back location at Pacific St.
                                                                        Below-bridge space at west end of Lowry developed as park and possible
                                                                        commercial along with remodeled storm water detention




                                                                                                                                                                                                                               19
Priority Project 0 – 5 Years                                                                                                                                                                   Riverfront Trail System: Wetlands Marshall Loop
                                         1. Marshall Terrace Park




                                                                                                                                                                    AFT
                        12               2. New ravine trail




                                                                                                                                                                  DR
                                         3. East side urban farm
                                         4. Excel Plant
                                         5. New wetlands park
                                         6. Remodeled Cold Storage Bldg.
                                         7. Remodeled Grain Elevator
                                         8. Amphitheater Slope
                                         9. Photo-voltaic Arrival Canopy w/ pavilions
                                         10. Biofiltration wetland gardens
                                         11. Park “Rooms”
                11                       12. Biohaven Island




                10

            9



                    8


        7
                             4
                                                                                                                                                                                                                                        Prefabricated wood-based structures allow for rapid istallation


                                                                                        Thickened structure for torsional sti ness

            6
                                                                                                      Walking surface
                                                                                                                                           Form slopes outward for weather protection
                                                                                                                              Handrail




                                     3
                                                               Laminated engineered wood layers




                                                                            Thickened wood structure for bending sti ness



                                                                                                                     Bridge pier support                                                Engineering concept illustrating the use of laminated wood and method of prefabrication for the Flyway Bridge



                                                                          East Side—“eyebrow” system stops at Excel with no riverfront access allowable
                5                                                         Marshall “through-way” continues uninterrupted to St. Anthony Parkway.
                                                                          Easement parcels east of Marshall opposite Excel can be developed as urban farming
                                                                          to continue park sensibility around Excel
                                                                          West side riverfront trail enters its richest moment looping around new wetland park
                                                                          Thru-bikes kept to rear of Port property along rail corridor
                                 1                                        Key connection and highway bridge at 34rth St. from North side neighborhood to new park
                                                                          Trail ascends to the top of the existing cold storage building on sloping landforms
                                                                          North of existing cold storage building “Ridge trail” follows the crest of new dredge fill
                                                                          landforms against the rail lines—“shoreline trail” follows water’s edge

                             2




20
Riverfront Trail System: Camden North Mississippi Loop
                                              1. Canadian Pacific Bridge
                                              2. Biohaven Island
                                              3. North Mississippi Park
                                              4. Shingle Creek
                                              5. Existing Boat Launch
                                              6. Rail Bridge Undercrossing




                                                                                                                                              Bicycle Path, Dupont Maryland



           3




                                                       DRAFT
                                                                                                                                              Bicycle path, Copenhagen, Denmark


               5
                          2




                                                                         Completing vital connections to North Mississippi Park and to
                                                                         Shingle Creek Grand Rounds link
                                                                         Knot bridge or Camden bridge walkway essential to complete
                      6                                                  the loop
                              1                                          Canadian Pacific bridge not available for any pedestrians or bikes
                                                                         but connecting under on west side is crucial connection and brings
                                                                         existing boat ramp into the rest of the park
                                                                         Connection to Shingle Creek can be made via highway
                                                                         undercrossing for the creek

                                                                                                                                              American River Bike Trail, Sacramento CA




                                                                                                                                                                                         21
Priority Project 0 – 5 Years                                                                                                                                       Riverfront Trail System: Knot Bridges
                                                                                      Separation of bridge deck above abut-
                                                         Steel arch                     ments used to create a torsion tube

                                                                          Brace support frame ties cantilevered
                                               Support cables
                                                                               bridge back to bridge abutment


                               Steel frame provides rigidity
                                 for cantilevered steel deck




                                                                                                                              Horizontal force
                                                                                                                              tied back to abutment




                                                                                                                              Vertical force
                                                                                                                              directly transferred

                                           Existing Bridge Structure   Concrete extensions on existing abutments




                               Engineering sketch illustrating Knot Bridge
                               structural concept




                               Reclaimed BN/SF Bridge looking east toward the
                               Third Rail Cafe




                               Marsupial Bike and Pedestrian Bridge Milwaukee



                               The RIVERFIRST Trail System initiative is designed to create new synergies
                                                                                                                                                      DRAFT
                                                                                                                                                      and solid state lighting systems. Efficient pathway lighting is envisioned to
                               between existing City and County Bridges and a set of proposed water                                                   enhance public safety and create a beautiful new bridge profile on existing
                               remediation and ecological conservation assets. Knot Bridges are designed                                              bridges without creating light spill.
                               to be supported from the existing foundations of bridge structures, and
                                                                                                                                                      The Knot Bridge system creates an unprecedented ease of access to move
                               provide needed pedestrian linkages with the north-south river Trail System.
                                                                                                                                                      along North South park trails and East West across neighbourhoods that
                               The Knot Bridges tie or “knot together” roadway and the River Trail levels,                                            have been historically separated by the River. Knot Bridges, together with
     T                         providing the “missing links” in section that connect the disparate heights                                            the River Trail System complete the series of connective River loops that link
                               of existing bridge roadways with the lower natural river bank topography.                                              the Parklands, Neighbourhoods and Downtown. Together, The Knot Bridges
                               Natural land grading is used to make the Knot bridges handicap accessible.                                             and River Trails Systems create a comprehensive recreational and sustainable
                               On each bridge crossing, Plymouth Bridge (slated for repairs), Broadway                                                commuter biking system for the City of Minneapolis.
                               Bridge, BNSF Railway Bridge, the new Lowry Bridge (under construction)
                               and the Camden Bridge the RiverFirst vision provides a bridge specific                                                  Preliminary Development Budget
                               design strategy to implement dedicated bike lanes and pedestrian pathways.                                             A conceptual development cost of $18,320,584 has been estimated for Knot
                               Knot Bridges are constructed of lightweight steel members with a low                                                   Bridges at the Plymouth, Broadway, and Camden Bridges and includes the
                               maintenance recycled rubber decking. The Knot Bridges support the clean                                                repurposing of the BN/SF Bridge as a bike and pedestrian trail. This budget
                               energy equipment needed for the solar powered WiFi River Talk network                                                  will be refined prior to Board action in December 2011.


22
Riverfront Trail System: Biohaven Islands




                                                                                                                                    Floating Island Remidiation, Chippewa
                                                                                                                                    Flowage, Northern Wisconson




                                                                                                                                    20,000 SF Floating Island, Montana,
                                                                                                                                    US Army Corp of Engineers


                                                                                                                                       R
                                                                                                                                       I
                                                                                                                                       P
                                                                                                                                       A
                                                                                                                                       R
                                                                                                                                       I
                                                                                                                                       A
                                                                                                                                       N
                                                                                                                                   S
                                                                                                                                   P   W




                                                       AFT
                                                                                                                                   E   E
                                                                                                                                       T
Species List:                                                                                                                      C   L




                                                     DR
                                                                                                                                   I   A
                                                                                                                                       N
Acorus calamus                  Carex vulpinoidea                Lobelia siphilitica            Sagittaria latifolia               E   D
Allium canadense                Boltonia asteroides              Lysimachia quadrifolia         Scirpus atrovirens                 S
Anemone canadensis              Chelone glabra                   Lythrium alatum                Scirpus cyperinus                      U
Asclepias incarnata             Elymus virginicus                Pedicularis lanceolata         Solidego riddellii                     P
                                                                                                                                       L
Aster novae-angliae             Eupatorieum perfoliatum          Phlox divaricata               Verbena hastata                        A
Aster umbellatus                Iris versicolor                  Pycnanthemum virginianum       Vernonia fasciculata                   N
                                                                                                                                       D
Calamagrostis canadensis        Juncus effuses                   Rudbeckia hirta                Veronicastrum virginicum
Caltha palustris                Leersia oryzoides                Rudbeckia subtomentosa         Zizia aurea
Carex hystericina               Liatris ligulistylis             Thalictrum dasycarpum                                                      YEAR 1                          2                        3                            4                           5
                                                                                                                                                                                    BIODIVERSITY OVER TIME


A system of floating Biohaven Islands, anchored on existing downstream                   water. The River Talk WiFI network, integrated in the Knot Bridges, supports the        A pair of Biohaven Islands offers the river a bio-remediation capacity that can
bridge pier foundations, creates a conservation feature that can be viewed              Biohaven experience by provides educational conservation information to the             absorb 32 kg/day of phosphors or about (1681 gallons) of dish soap per day,
from the pedestrian Knot Bridges along the River Trail. Biohaven Islands                public that can be accessed through a mobile phone.                                     based on the new Minnesota regulation of .5% max phosphates in detergent.
provide bio-remediation to cleanse river water and provide more than 7 acres                                                                                                    636.63 kg of nitrates per day can be naturally removed by the planted root
                                                                                        RiverFirst uses soft engineering principles and the natural buoyancy of the             systems. Each day, the Islands would have the capacity to bio-remediate the
of protected riparian habitat for migrating birds and endangered species.
                                                                                        river. Instead of costly hard and resistive structures, buoyancy is provided            nitrate content of about 224 twenty five lb bags of lawn fertilizer.
These include native mussels, blanding turtle, osprey, logger head strike and
                                                                                        by innovative and locally fabricated fiber foam made of 100% recycled PET
karner blue butterfly. Biohaven islands can be adopted and supported by local
                                                                                        (water bottle plastics). Soil and gravel are placed atop the island to provide          Preliminary Development Budget
organizations or corporations as special sites for native berries and plantings.
                                                                                        a nutrient medium for plants and shrubs. Islands are tethered fixed anchors
                                                                                                                                                                                A conceptual development cost of $12,188,880 has been estimated for 6 clusters
People who walk along the Trail System Loops will have the experience of being          outside of the existing Navigation Channel. A hinge connection allows the
                                                                                                                                                                                of Biohaven Islands that run from the west side of the Broadway Bridge to the
able to pause at the mid-point of the River and observe native vegetation, bird         downstream island to shift slightly, accommodating different water levels and
                                                                                                                                                                                west side of the Canadian Pacific Railroad Bridge.facing North Mississippi Park.
and wildlife activities. Kayakers will be able to experience the Biohavens from the     allowing sunlight down to the river bed below.
                                                                                                                                                                                This budget will be refined prior to Board action in December 2011.



                                                                                                                                                                                                                                                            23
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal
Design Concepts & Implementation Plan - Draft RiverFIRST Proposal

Mais conteúdo relacionado

Mais procurados

River front development principles - draft
River front development principles - draftRiver front development principles - draft
River front development principles - draftNehal Elhagene
 
River front development
River front developmentRiver front development
River front developmentBismi S
 
Riverfront development
Riverfront developmentRiverfront development
Riverfront developmentmisschand
 
CARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENTCARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENTOmkar Nandavadekar
 
Sabarmati riverfront case study for development of yamuna riverfront agra
Sabarmati riverfront case study for development of yamuna riverfront agraSabarmati riverfront case study for development of yamuna riverfront agra
Sabarmati riverfront case study for development of yamuna riverfront agradeeksha sharma
 
Riverfront development Case study Hoshangabad Thesis
Riverfront development  Case study Hoshangabad Thesis Riverfront development  Case study Hoshangabad Thesis
Riverfront development Case study Hoshangabad Thesis Praveen Mukati
 
River - Front Development with 2 Examples
River - Front Development with 2 ExamplesRiver - Front Development with 2 Examples
River - Front Development with 2 ExamplesRohit Kumar Singh
 
Sabarmati riverfront
Sabarmati riverfrontSabarmati riverfront
Sabarmati riverfrontshiv404
 
Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...
Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...
Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...KatthyLucas2100
 
Action Plan for the Central Delaware: 2008-2018
Action Plan for the Central Delaware: 2008-2018Action Plan for the Central Delaware: 2008-2018
Action Plan for the Central Delaware: 2008-2018Wallace Roberts & Todd
 
Urban design sabarmati
Urban design sabarmatiUrban design sabarmati
Urban design sabarmatiSyam M
 
Varanasi Riverfront Development
Varanasi Riverfront DevelopmentVaranasi Riverfront Development
Varanasi Riverfront DevelopmentBeda Choudhury
 
IRJET- A Sustainable Approach for Urban Riverfront Development
IRJET-  	  A Sustainable Approach for Urban Riverfront DevelopmentIRJET-  	  A Sustainable Approach for Urban Riverfront Development
IRJET- A Sustainable Approach for Urban Riverfront DevelopmentIRJET Journal
 
Creating the Waterfront City of the Future
Creating the Waterfront City of the FutureCreating the Waterfront City of the Future
Creating the Waterfront City of the FutureCity of Annapolis
 
PPD 531 Council for Watershed
PPD 531 Council for WatershedPPD 531 Council for Watershed
PPD 531 Council for Watershedkvon15
 
Kuching waterfront-tales-of-three-cities1
Kuching waterfront-tales-of-three-cities1Kuching waterfront-tales-of-three-cities1
Kuching waterfront-tales-of-three-cities1Andrew Law
 

Mais procurados (20)

River front development principles - draft
River front development principles - draftRiver front development principles - draft
River front development principles - draft
 
River front development
River front developmentRiver front development
River front development
 
Riverfront development
Riverfront developmentRiverfront development
Riverfront development
 
CARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENTCARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENT
 
Sabarmati riverfront case study for development of yamuna riverfront agra
Sabarmati riverfront case study for development of yamuna riverfront agraSabarmati riverfront case study for development of yamuna riverfront agra
Sabarmati riverfront case study for development of yamuna riverfront agra
 
Tlp ravi forum
Tlp ravi forumTlp ravi forum
Tlp ravi forum
 
Riverfront development Case study Hoshangabad Thesis
Riverfront development  Case study Hoshangabad Thesis Riverfront development  Case study Hoshangabad Thesis
Riverfront development Case study Hoshangabad Thesis
 
River - Front Development with 2 Examples
River - Front Development with 2 ExamplesRiver - Front Development with 2 Examples
River - Front Development with 2 Examples
 
Sabarmati riverfront
Sabarmati riverfrontSabarmati riverfront
Sabarmati riverfront
 
Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...
Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...
Waterfront Master Planning | Urban Waterfronts and Marinas Services | Moffatt...
 
Action Plan for the Central Delaware: 2008-2018
Action Plan for the Central Delaware: 2008-2018Action Plan for the Central Delaware: 2008-2018
Action Plan for the Central Delaware: 2008-2018
 
Urban design sabarmati
Urban design sabarmatiUrban design sabarmati
Urban design sabarmati
 
CMAA Riverwalk Presentation
CMAA Riverwalk PresentationCMAA Riverwalk Presentation
CMAA Riverwalk Presentation
 
Varanasi Riverfront Development
Varanasi Riverfront DevelopmentVaranasi Riverfront Development
Varanasi Riverfront Development
 
IRJET- A Sustainable Approach for Urban Riverfront Development
IRJET-  	  A Sustainable Approach for Urban Riverfront DevelopmentIRJET-  	  A Sustainable Approach for Urban Riverfront Development
IRJET- A Sustainable Approach for Urban Riverfront Development
 
Creating the Waterfront City of the Future
Creating the Waterfront City of the FutureCreating the Waterfront City of the Future
Creating the Waterfront City of the Future
 
Srfdc
SrfdcSrfdc
Srfdc
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
 
PPD 531 Council for Watershed
PPD 531 Council for WatershedPPD 531 Council for Watershed
PPD 531 Council for Watershed
 
Kuching waterfront-tales-of-three-cities1
Kuching waterfront-tales-of-three-cities1Kuching waterfront-tales-of-three-cities1
Kuching waterfront-tales-of-three-cities1
 

Destaque

Sabarmati Riverfront development project
Sabarmati Riverfront development projectSabarmati Riverfront development project
Sabarmati Riverfront development projectNoopur Raval
 
2012 11-30 RiverFirst dnr-usace presentation
2012 11-30 RiverFirst dnr-usace presentation2012 11-30 RiverFirst dnr-usace presentation
2012 11-30 RiverFirst dnr-usace presentationRiverFirst Initiative
 
Switchard Park Master Plan | Design Workshop
Switchard Park Master Plan | Design WorkshopSwitchard Park Master Plan | Design Workshop
Switchard Park Master Plan | Design WorkshopRundellErnstberger
 
2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou
2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou
2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam OuWater, Land and Ecosystems (WLE)
 
RIWC_PARA_A131 Universal Design in a Park
RIWC_PARA_A131 Universal Design in a ParkRIWC_PARA_A131 Universal Design in a Park
RIWC_PARA_A131 Universal Design in a ParkMarco Muscroft
 
Topeka River Front Park Concept
Topeka River Front Park Concept Topeka River Front Park Concept
Topeka River Front Park Concept John Campos
 
Park Design for Community Health & Wellbeing
Park Design for Community Health & WellbeingPark Design for Community Health & Wellbeing
Park Design for Community Health & WellbeingDekker/Perich/Sabatini
 
Proposed Saint Mutien Fashion School
Proposed Saint Mutien Fashion SchoolProposed Saint Mutien Fashion School
Proposed Saint Mutien Fashion Schoolinstitutesed
 
An Evening Walk @ Tmn Jaya Recreational Park
An Evening Walk @ Tmn Jaya Recreational ParkAn Evening Walk @ Tmn Jaya Recreational Park
An Evening Walk @ Tmn Jaya Recreational ParkPoh Lin Lim
 
NostalgicOutdoors™- Acadia National Park- Green Outdoors Activities
NostalgicOutdoors™- Acadia National Park- Green Outdoors ActivitiesNostalgicOutdoors™- Acadia National Park- Green Outdoors Activities
NostalgicOutdoors™- Acadia National Park- Green Outdoors ActivitiesNostalgicOutdoors™
 
Eiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakeshEiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakeshLokesh Saini
 
Hyatt Regency Jacksonville Riverfront
Hyatt Regency Jacksonville RiverfrontHyatt Regency Jacksonville Riverfront
Hyatt Regency Jacksonville Riverfrontndemars
 
Concept Plans for the Park
Concept Plans for the ParkConcept Plans for the Park
Concept Plans for the ParkCity of Arvada
 
Designing for waterfront resilience in Hudson Riverfront communities
Designing for waterfront resilience in Hudson Riverfront communitiesDesigning for waterfront resilience in Hudson Riverfront communities
Designing for waterfront resilience in Hudson Riverfront communitiesLibby Zemaitis
 
Colorado Riverfront Project - Stacy Beaugh, Tamarisk Coalition
Colorado Riverfront Project - Stacy Beaugh, Tamarisk CoalitionColorado Riverfront Project - Stacy Beaugh, Tamarisk Coalition
Colorado Riverfront Project - Stacy Beaugh, Tamarisk Coalitionrshimoda2014
 
Preview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City CouncilPreview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City Councilpublicinvolvement
 

Destaque (20)

Sabarmati Riverfront development project
Sabarmati Riverfront development projectSabarmati Riverfront development project
Sabarmati Riverfront development project
 
2012 11-30 RiverFirst dnr-usace presentation
2012 11-30 RiverFirst dnr-usace presentation2012 11-30 RiverFirst dnr-usace presentation
2012 11-30 RiverFirst dnr-usace presentation
 
Switchard Park Master Plan | Design Workshop
Switchard Park Master Plan | Design WorkshopSwitchard Park Master Plan | Design Workshop
Switchard Park Master Plan | Design Workshop
 
2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou
2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou
2016 GMekong Forum - S08 - Macro-invertebrate Sampling on the Nam Ou
 
RIWC_PARA_A131 Universal Design in a Park
RIWC_PARA_A131 Universal Design in a ParkRIWC_PARA_A131 Universal Design in a Park
RIWC_PARA_A131 Universal Design in a Park
 
Topeka River Front Park Concept
Topeka River Front Park Concept Topeka River Front Park Concept
Topeka River Front Park Concept
 
Melaleuca
MelaleucaMelaleuca
Melaleuca
 
Park Design for Community Health & Wellbeing
Park Design for Community Health & WellbeingPark Design for Community Health & Wellbeing
Park Design for Community Health & Wellbeing
 
Proposed Saint Mutien Fashion School
Proposed Saint Mutien Fashion SchoolProposed Saint Mutien Fashion School
Proposed Saint Mutien Fashion School
 
An Evening Walk @ Tmn Jaya Recreational Park
An Evening Walk @ Tmn Jaya Recreational ParkAn Evening Walk @ Tmn Jaya Recreational Park
An Evening Walk @ Tmn Jaya Recreational Park
 
NostalgicOutdoors™- Acadia National Park- Green Outdoors Activities
NostalgicOutdoors™- Acadia National Park- Green Outdoors ActivitiesNostalgicOutdoors™- Acadia National Park- Green Outdoors Activities
NostalgicOutdoors™- Acadia National Park- Green Outdoors Activities
 
Eiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakeshEiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakesh
 
Hyatt Regency Jacksonville Riverfront
Hyatt Regency Jacksonville RiverfrontHyatt Regency Jacksonville Riverfront
Hyatt Regency Jacksonville Riverfront
 
Concept Plans for the Park
Concept Plans for the ParkConcept Plans for the Park
Concept Plans for the Park
 
Milwaukie Riverfront Park Project - Herrigal
Milwaukie Riverfront Park Project - HerrigalMilwaukie Riverfront Park Project - Herrigal
Milwaukie Riverfront Park Project - Herrigal
 
Designing for waterfront resilience in Hudson Riverfront communities
Designing for waterfront resilience in Hudson Riverfront communitiesDesigning for waterfront resilience in Hudson Riverfront communities
Designing for waterfront resilience in Hudson Riverfront communities
 
PM tools and techniques
PM tools and techniquesPM tools and techniques
PM tools and techniques
 
Port of New Orleans: Riverfront Development Issues
Port of New Orleans: Riverfront Development IssuesPort of New Orleans: Riverfront Development Issues
Port of New Orleans: Riverfront Development Issues
 
Colorado Riverfront Project - Stacy Beaugh, Tamarisk Coalition
Colorado Riverfront Project - Stacy Beaugh, Tamarisk CoalitionColorado Riverfront Project - Stacy Beaugh, Tamarisk Coalition
Colorado Riverfront Project - Stacy Beaugh, Tamarisk Coalition
 
Preview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City CouncilPreview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City Council
 

Semelhante a Design Concepts & Implementation Plan - Draft RiverFIRST Proposal

Upper Riverfront Map+Timeline Presentation (24-25 May 2011)
Upper Riverfront Map+Timeline Presentation (24-25 May 2011)Upper Riverfront Map+Timeline Presentation (24-25 May 2011)
Upper Riverfront Map+Timeline Presentation (24-25 May 2011)RiverFirst Initiative
 
Aaron Elswick-Portfolio 2015
Aaron Elswick-Portfolio 2015Aaron Elswick-Portfolio 2015
Aaron Elswick-Portfolio 2015Aaron Elswick
 
PSPD Newletter Spring 2011
PSPD Newletter Spring 2011PSPD Newletter Spring 2011
PSPD Newletter Spring 2011Pratt CMFM
 
Pspd Newsletter Spring 2011
Pspd Newsletter   Spring 2011Pspd Newsletter   Spring 2011
Pspd Newsletter Spring 2011Pratt CMFM
 
CA: San Francisco: Low Impact Design Toolkit for Stormwater
CA: San Francisco: Low Impact Design Toolkit for StormwaterCA: San Francisco: Low Impact Design Toolkit for Stormwater
CA: San Francisco: Low Impact Design Toolkit for StormwaterSotirakou964
 
Wtershed management
Wtershed managementWtershed management
Wtershed managementGhassan Hadi
 
superfund poster final final final
superfund poster final final finalsuperfund poster final final final
superfund poster final final finalEugene Peck
 
Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...
Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...
Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...Rodelon Ramos
 
For distribution RiverFIRST Letter From Diane Hofstede 9.7.11
For distribution RiverFIRST Letter From Diane Hofstede 9.7.11For distribution RiverFIRST Letter From Diane Hofstede 9.7.11
For distribution RiverFIRST Letter From Diane Hofstede 9.7.11Mill City Times
 
Lower Macungie Township Environmental Analysis
Lower Macungie Township Environmental AnalysisLower Macungie Township Environmental Analysis
Lower Macungie Township Environmental AnalysisMichael Metz
 
Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...
Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...
Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...ChokManalo
 
Water Sensitive Urban Design
Water Sensitive Urban DesignWater Sensitive Urban Design
Water Sensitive Urban DesignElisa Sutanudjaja
 
Options for the environmental future of the River Murray
Options for the environmental future of the River MurrayOptions for the environmental future of the River Murray
Options for the environmental future of the River MurrayUniversity of Adelaide
 
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualitySotirakou964
 
Kathryn Little Portfolio
Kathryn Little PortfolioKathryn Little Portfolio
Kathryn Little Portfoliokzl5000
 

Semelhante a Design Concepts & Implementation Plan - Draft RiverFIRST Proposal (20)

Upper Riverfront Map+Timeline Presentation (24-25 May 2011)
Upper Riverfront Map+Timeline Presentation (24-25 May 2011)Upper Riverfront Map+Timeline Presentation (24-25 May 2011)
Upper Riverfront Map+Timeline Presentation (24-25 May 2011)
 
Aaron Elswick-Portfolio 2015
Aaron Elswick-Portfolio 2015Aaron Elswick-Portfolio 2015
Aaron Elswick-Portfolio 2015
 
PSPD Newletter Spring 2011
PSPD Newletter Spring 2011PSPD Newletter Spring 2011
PSPD Newletter Spring 2011
 
Pspd Newsletter Spring 2011
Pspd Newsletter   Spring 2011Pspd Newsletter   Spring 2011
Pspd Newsletter Spring 2011
 
CA: San Francisco: Low Impact Design Toolkit for Stormwater
CA: San Francisco: Low Impact Design Toolkit for StormwaterCA: San Francisco: Low Impact Design Toolkit for Stormwater
CA: San Francisco: Low Impact Design Toolkit for Stormwater
 
Wtershed management
Wtershed managementWtershed management
Wtershed management
 
superfund RSM final
superfund RSM finalsuperfund RSM final
superfund RSM final
 
superfund poster final final final
superfund poster final final finalsuperfund poster final final final
superfund poster final final final
 
Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...
Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...
Daylighting the Amorsolo Creek - Participatory Design and the Revival of an U...
 
Green infrastructure: Reconnecting Agriculture and Communities
Green infrastructure: Reconnecting Agriculture and CommunitiesGreen infrastructure: Reconnecting Agriculture and Communities
Green infrastructure: Reconnecting Agriculture and Communities
 
For distribution RiverFIRST Letter From Diane Hofstede 9.7.11
For distribution RiverFIRST Letter From Diane Hofstede 9.7.11For distribution RiverFIRST Letter From Diane Hofstede 9.7.11
For distribution RiverFIRST Letter From Diane Hofstede 9.7.11
 
Lower Macungie Township Environmental Analysis
Lower Macungie Township Environmental AnalysisLower Macungie Township Environmental Analysis
Lower Macungie Township Environmental Analysis
 
Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...
Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...
Flood Mitigation through Green Infrastructure: Proposed Urban Design Interven...
 
Alala
AlalaAlala
Alala
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
Claire Robinson
Claire RobinsonClaire Robinson
Claire Robinson
 
Water Sensitive Urban Design
Water Sensitive Urban DesignWater Sensitive Urban Design
Water Sensitive Urban Design
 
Options for the environmental future of the River Murray
Options for the environmental future of the River MurrayOptions for the environmental future of the River Murray
Options for the environmental future of the River Murray
 
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water QualityNY: A Green Infrastructure Approach - Onondaga Creek Water Quality
NY: A Green Infrastructure Approach - Onondaga Creek Water Quality
 
Kathryn Little Portfolio
Kathryn Little PortfolioKathryn Little Portfolio
Kathryn Little Portfolio
 

Mais de RiverFirst Initiative

Finance Strategy: Initial Findings (May 2013)
Finance Strategy: Initial Findings (May 2013)Finance Strategy: Initial Findings (May 2013)
Finance Strategy: Initial Findings (May 2013)RiverFirst Initiative
 
Executive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsExecutive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsRiverFirst Initiative
 
RiverFirst Schematic Design: Mid-term Presentation
RiverFirst Schematic Design: Mid-term PresentationRiverFirst Schematic Design: Mid-term Presentation
RiverFirst Schematic Design: Mid-term PresentationRiverFirst Initiative
 
Themes Emerge from Funding Strategy Research
Themes Emerge from Funding Strategy ResearchThemes Emerge from Funding Strategy Research
Themes Emerge from Funding Strategy ResearchRiverFirst Initiative
 
Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)
Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)
Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)RiverFirst Initiative
 
Appendices - Draft RiverFIRST Proposal
Appendices - Draft RiverFIRST ProposalAppendices - Draft RiverFIRST Proposal
Appendices - Draft RiverFIRST ProposalRiverFirst Initiative
 
Executive Summary - Draft RiverFIRST Proposal
Executive Summary - Draft RiverFIRST ProposalExecutive Summary - Draft RiverFIRST Proposal
Executive Summary - Draft RiverFIRST ProposalRiverFirst Initiative
 
RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min...
 RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min... RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min...
RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min...RiverFirst Initiative
 
RiverFIRST site design and analysis-book
RiverFIRST site design and analysis-bookRiverFIRST site design and analysis-book
RiverFIRST site design and analysis-bookRiverFirst Initiative
 
Business Planning for a 21st Century Park System
Business Planning for a 21st Century Park SystemBusiness Planning for a 21st Century Park System
Business Planning for a 21st Century Park SystemRiverFirst Initiative
 
TLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 MayTLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 MayRiverFirst Initiative
 
Minneapolis Riverfront Design Competition Siteseeing Youth Engagement
Minneapolis Riverfront Design Competition Siteseeing Youth Engagement Minneapolis Riverfront Design Competition Siteseeing Youth Engagement
Minneapolis Riverfront Design Competition Siteseeing Youth Engagement RiverFirst Initiative
 
Land, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeLand, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeRiverFirst Initiative
 

Mais de RiverFirst Initiative (18)

Finance Strategy: Initial Findings (May 2013)
Finance Strategy: Initial Findings (May 2013)Finance Strategy: Initial Findings (May 2013)
Finance Strategy: Initial Findings (May 2013)
 
Executive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsExecutive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next Steps
 
RiverFirst Schematic Design: Mid-term Presentation
RiverFirst Schematic Design: Mid-term PresentationRiverFirst Schematic Design: Mid-term Presentation
RiverFirst Schematic Design: Mid-term Presentation
 
Themes Emerge from Funding Strategy Research
Themes Emerge from Funding Strategy ResearchThemes Emerge from Funding Strategy Research
Themes Emerge from Funding Strategy Research
 
R1 Steering Committee 2012 10-11
R1 Steering Committee 2012 10-11R1 Steering Committee 2012 10-11
R1 Steering Committee 2012 10-11
 
RiverFirst Vision (Final 2012)
RiverFirst Vision (Final 2012)RiverFirst Vision (Final 2012)
RiverFirst Vision (Final 2012)
 
Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)
Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)
Slideshow: RiverFirst Design and Implementation Plan (presented Sept 2011)
 
Appendices - Draft RiverFIRST Proposal
Appendices - Draft RiverFIRST ProposalAppendices - Draft RiverFIRST Proposal
Appendices - Draft RiverFIRST Proposal
 
Executive Summary - Draft RiverFIRST Proposal
Executive Summary - Draft RiverFIRST ProposalExecutive Summary - Draft RiverFIRST Proposal
Executive Summary - Draft RiverFIRST Proposal
 
RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min...
 RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min... RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min...
RiverFIRST: A Parks Design Proposal and Implementation Framework for the Min...
 
Riverfront Projects Summer 2010
Riverfront Projects Summer 2010Riverfront Projects Summer 2010
Riverfront Projects Summer 2010
 
RiverFIRST site design and analysis-book
RiverFIRST site design and analysis-bookRiverFIRST site design and analysis-book
RiverFIRST site design and analysis-book
 
Business Planning for a 21st Century Park System
Business Planning for a 21st Century Park SystemBusiness Planning for a 21st Century Park System
Business Planning for a 21st Century Park System
 
TLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 MayTLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 May
 
Minneapolis Riverfront Design Competition Siteseeing Youth Engagement
Minneapolis Riverfront Design Competition Siteseeing Youth Engagement Minneapolis Riverfront Design Competition Siteseeing Youth Engagement
Minneapolis Riverfront Design Competition Siteseeing Youth Engagement
 
Stoss video
Stoss videoStoss video
Stoss video
 
Turenscape
TurenscapeTurenscape
Turenscape
 
Land, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeLand, Water, People: New Parks in Practice
Land, Water, People: New Parks in Practice
 

Último

Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)jennyeacort
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girlsssuser7cb4ff
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一lvtagr7
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造kbdhl05e
 
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRCall In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRdollysharma2066
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一Fi L
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Servicejennyeacort
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degreeyuu sss
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubaikojalkojal131
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...Amil baba
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 

Último (20)

Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girls
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造
 
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRCall In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
 
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
 

Design Concepts & Implementation Plan - Draft RiverFIRST Proposal

  • 1. Design Concepts & Implementation Plan RiverFIRST: A Park Design Proposal and Implementation Framework for the Minneapolis Upper Riverfront DRAFT
  • 2. RiverFIRST Guiding Principles 21st Century Challenges The Minneapolis Riverfront Development Initiative provides a chance habitats. RiverFirst is guided by similar principles that embrace the notion Park, but also includes the depth of the river and all points in between. to consider how the Minneapolis park system can protect the national that cities evolve over time and must be allowed to accommodate changes in Understanding the nuanced difference in surface shape and features of ecological heritage of the Minneapolis Riverfront and the Mississippi River, environmental, social, and economic climates. this landscape creates opportunities for multiple-scaled combinations of foster community health, support economic opportunity and prepare submerged, emergent, riparian, and meadow upland. This sensibility has Minneapolis with resilient and sustainable eco-infrastructure for generations Design Principles the potential to guide an urbanistic strategy toward built form that results in to come. There are 21st Century challenges that are global in nature and RiverFirst is based on four design principles. The first, Go with the Flow, buildings that optimize orientation for natural light, energy harvesting, and local in impact. Mississippi River access may increase in value as energy costs reflects the dynamic characteristic of the river itself and becomes a model stormwater management. rise and warming climates reduce winter port closures. Greenhouse gas for other systems such as public access, mobility, and energy infrastructure. emissions need to be controlled. Storm water systems must be adapted to This principle is based less on the addition of the physical characteristics The third principle, Both/And, addresses the unlikely juxtaposition of the account for increasing uncertainty in local climate variability. Urban growth that are common to planning but rather on a subtractive approach that Mississippi River to its immediate surroundings, in particular the Northside must be accommodated. RiverFirst considers these challenges as the exposes the underlying nature of a place, sometimes literally unearthing industrial district which has suffered through neglect and a weak economy. AFT means to enable a blue & green way of life to flourish in Minneapolis and to existing conditions in an effort to recover its identity. The daylighting of Both/And provides the groundwork for a condition where two seemingly DR attract the brightest creative minds to live in Minneapolis. buried stormwater systems is an example where the act of excavation not conflicting circumstances can be allowed to co-exist, even be strengthened only points to the significance of a tributaries relationship to the river but by the others presence. The Mississippi is still a working place for industry, but current economic simultaneous remediates or cleans the stormwater before entering the river. Finally, Park Plus, reflects the contemporary role that cities must play to opportunity is hindered by the dislocated relationship between Minneapolis The effect provides measurable benefits including increased visibility of the address the challenges of the 21st Century. Parks today are expected to and its river. A planning strategy that prioritizes the Mississippi, that puts river and thus security, and reduced park maintenance. exceed our normal understanding of a park as a social gathering space rather it first, is intended to renew the river’s strength and diversity as a living ecosystem. In doing so, the physical, societal and economic health of the Where Go with the Flow reflects mobility and access, the second principle, it must play a role in reducing energy consumption through environmental city is placed first. RiverFirst is guided by the dynamics of the river. Water Design with Topography, is more physical in nature. The great range of stewardship, minimizing maintenance costs, and providing places that carves and erodes to form the river that supports and sustains diverse geographic diversity begins not only with the site’s highest point, Farview support health and safety. DOWNTOWN MINNEAPOLIS SAINT PAUL CHAIN OF LAKES LAKE NOKOMIS REGIONAL MOBILITY SHIPPING LANES SHIPPING LANES Minneapolis Context Minneapolis Context Minneapolis Context Grand Rounds Existing Parks Key Text Key Text Riverfirst Connector Riverfirst Parkland Key Text Key Text Proposed Regional Trails Key Text Key Text Parks Regional Trails Key Text State, Federal Trails Extended regional trail system Mississippi River Nutritional run-off Mississippi global transportation links 8
  • 3. Loops Moisture Gradients The north-south Trail System connects with east-west pedestrian walkways Landscape is created by the varying interactions of soil and water. Much of Phase 1 Loops (Knot Bridges) in a series of recreational River Loop circuits that link North the RiverFirst effort concerns putting seasonal stream and river water back in Phase 2 Connections and Northeast Neighborhoods. In so doing, sections of the river can be contact with riverbanks and uplands that have been cut off by piped outfalls, encircled and begin to create a series of interconnected “rooms” each with bulwarks and embankments. The more we can increase these soil / water a specific urban and natural character. This simple idea has great strength contacts in terms of length, area, and varying saturation conditions, the as a means of orientation and breaking down a river that is regional in scale greater the species diversity and ecosystem resilience can be created. These to something in neighborhood sized chunks. The trail system will have the varying levels of new moisture in the soil – from constant saturation to drier most flexibility and variety in terms of routes when options for crossing the fast-draining uplands will largely determine the ecosystem types we see in river are positioned within a five minute walk. One could imagine a series this river reach in the coming years. So not only the plants but the associated, of linked rubber bands stretched around each room along with the idea interrelated food web of amphibians, insects, birds, and mammals that that these flexible loops can also be expanded to take in the entire 5 ½ depend on them are fundamentally organized by moisture gradients in the miles of riverfront and northward beyond. In the same way, loops can and soil. Historically, along this stretch of the Mississippi we had the possibility should expand into both the Northside and Northeast neighborhoods so of highly varied ecosystems in close proximity due to the river’s varying they are flexibly joined to the river based system. The result is a flexible, encounters with shorelines, tributaries, and islands. Of course numerous web-like circulation structure that can organize movement over a significant alterations to the channel have reduced this condition. RiverFirst is working area of the city. Five minute pedestrian loops can then be joined onto large carefully with topography and day-lighted storm flows to dramatically expand intermodal systems like the Prairie Loop Shuttle that encircles the entire site the topographic, hydrologic, and consequently, small scale ecological using Railroad rights-of-ways. diversity throughout this reach. DRAFT 9
  • 4. Guiding Principles Urban Ecology leucocephalus Lontra canadensis Haliaeetus Vulpes vulpes Spilogale putorius Pandion haliaetus Circus cyaneus Ondatra zibethicus Aegolius funereus Foodweb 97 Species of Greatest Conservation Need Micropterus Dendroica Aythya affinis cerulea Sorex palustris (SGCN) are known or predicted to occur Pseudacris Phenacomys Pipistrellus maculosus within the Riverfirst site. This food web Necturus Morone Megaceryle examines a small collection of those SGCN alcyon and illustrates the necessity for biodiversity in order to achieve conservation goals and create a renewed urban ecology. Plethobasus Orconectes Formicinae Cicindela Ophiogo Ceraclea Dendroc -mphys Erynnis Glycera -touns Pimoa Apis AFT Vernonia DR Morchella Phytoplankton Solidago Sagittaria Viburnum Aster Solidago Spartina Asclepias Liatris Regional Corridors Urban Ecology Corridor Green-Regional Natural Resource/ Source Habitat Urban Fabric River Habitat Areas Significant Ecological Areas/ Wetlands and Wet Areas (MMCD) Green Lines-Trails Blue-Water Bodies Purple Arrows-Flyway and Terrestrial Corridors 150 years ago, this reach of the Mississippi was a focus of diverse biological The physical result is tree-like in nature, with the Mississippi itself as the main activity ranging from bacteria in the soil to the dead plants they break down, trunk and tributary corridors as some of the key structural branches – such as to the insects, amphibians, snakes, birds, and mammals that consume each Shingle Creek to the north, Basset Creek and other to southwest connecting other in a complex food chain. This vast interrelated system relies upon a on to the Chain of Lakes and beyond, and a new proposed natural corridor healthy river and tributaries and generous riverine areas of moist and often to Columbia Park to the Northeast. Once a rich habitat with Sandy Lake at saturated soils to support it in place. The more mobile species also rely on its core, this current golf course has the potential for restoration as a lake the river and related corridors to facilitate movement as they seek shelter and and wetland complex. This crucial piece of ecological real estate can also food over a wider range. Urban interventions, especially in this reach, have function as a future Central Park of Minneapolis as its urban margins increase fragmented every aspect of the system creating a “missing link” not only in density over the next 20 years. I-94, like most urban highways is laced with in the Grand Rounds but in the Mississippi Flyway and terrestrial corridors. endless swaths of open soil which lay sterile and create another blockage in In everything it does, RiverFirst seeks to reverse this disconnection and the system of habitat and natural species cover. This could be transformed fragmentation through specific measures concerning renewing the natural into diverse urban forest by cultivating every available embankment and sliver hydrology within urban conditions, increasing areas native landscape types, of residual land with native trees. and cultivating natural attractors for species that may be in decline or have left the area entirely. 10
  • 5. Mobility DRAFT 13 17 6 5 9 3 3.5 mi 9 3 9 Mobility Scales 3 10 32 City Source Users River Loop 3 22 1.8 mi 10 9 12 2 4 1.2 mi 5 888 15 1.3 mi 5 14 0.6 mi 5 16 6 7 3 19 LOOP 1.8 mi The RiverFirst proposal incorporates new and existing transportation The new Cedar lake Bike trail links the River with Target Field, improving initiatives to create a sustainable, multi-modal and interconnected suburban and regional public access to the river on the Hiawatha LRT, the public transportation system for commuting, recreation, and mobility in North Star and future Central, Southwest, and Bottineau LRT lines. Existing Minneapolis. The Minneapolis Flyway, a comprehensive new North-South train rail lines are retained to facilitate sustainable transportation logistics 16 55 7 16 pedestrian and bicycle Park Trail System, is linked with a East-West Knot for a new eco-business innovation district that can benefit in the future 9 3 Bridge pedestrian and bicycle paths supported by the exiting foundations of from renewable Minnesota wind energy and locally generated solar energy 6 18 City and County bridges. on Parklands. Residents form North and Northeast Neighborhoods will 7 be able to walk, bike or take a clean electric shuttle to work. Nice Ride Access to the Trail System is provided by existing Bus routes, the proposed stations and public kayak launching sites at the Urban Boat Builder’s facility clean electric bus Prairie Loop route and a series of new bridge crossings on 28th Avenue North and Scherer Park increase the public accessibility of MOBILITY 0 500’ 1000’ 2000’ 4000’ over I-94 that connect the North Neighbourhoods with the River. Pedestrian the RiverFirst multi-modal transportation initiative and create a world class Parkland Prairie Loop Hiawatha Light Rail Trail Connection Secondary Connection connection improvements to Dowling Street, 34th Avenue North (Perkins Hill recreational and bike commuting network. Tree Cover Trails Metro Transit Interstate Highway and City View School), Lowry and Broadway are proposed to compliment the Proposed Connection NorthStar Commuter Rail Nice Ride Station central RiverFirst connecting feature, an overpass that links Farview Park, the Recreation Loops Rail Proposed Nice Ride Station City’s historic high point, with the River. 11
  • 6. Guiding Principles Green Networks RIVER TALK WiFi Network 17 13 6 5 9 3 13 10 5 3 15 5 Sea Turtle App Locavore Love Fresh National Geographic Green Market Finder iPhone App Bird App 14 5 7 3 The RiverFirst proposal leverages the development of Riverfront Neighbourhoods with significant new urban agriculture resources, including LOOP Parkland to improve the health of the River and the health of the City native edibles, that build upon existing community gardens, Farmer’s Markets and its Neighbourhoods. At the larger urban scale, RiverFirst creates and and sustainable organic and slow food establishments. interconnects a series of synergistic Green Networks that are comprised The Green Networks combine to build a large, diverse constituency of 16 7 of sustainable bike routes and pedestrian trails, existing Neighbourhood citizens who are informed about health, community based food, recreation based community gardens and local food initiatives, new civic clean energy and the benefits of a sustainable River. New initiatives are envisioned, such 9 3 resources and the WiFI River Talk network, providing public outreach and as the development of sustainable consumer products: 1% RiverFirst clean education on local conservation. Renewable energy in Parklands provides road salt and natural lawn fertilizer products to raise public awareness of how clean power for charging electric vehicles and on shore power (OSP) for everyday consumer practices can improve River ecology and community green industry, reducing future energy cost risks, noise and emissions. INFORMATION + ENERGY NETWORKS 0 500’ 1000’ 2000’ 4000’ health far beyond the Minneapolis Riverfront. AFT Existing Parkland Prarie Loop Terminal RiverTalk Usage RiverFirst Parklands create significant new opportunities for urban agriculture, Trail Connections Community Garden help provide for municipal food security and expand neighbourhood access DR Developed Parkland Trails WiFi Repeater CSA Drop Off Proposed Connection Prarie Loop Local Produce Market to healthy food and nutrition in ways that build communities and local Photovoltaic Energy Interstate Highway Riverfirst Urban Agriculture Building business enterprises. Together the RiverFirst Green Network systems link 12
  • 7. Water Watershed – Impaired Waters Stormwater Flows 8 Hg – Rainfall River Outfall Mercury 17 12 PCB – Current: Pipe System Polychlorinated bipehyls 19 22 FC – Fecal Coliforum PFOS – 41 Perfluoroctane Proposed: Riverfirst Sulfinate T– Turbidity 31 96 29 NaCl – Sodium Chloride 84 The basis of RiverFirst lies in restoring the relationship of land to water, the RiverFirst proposes a system of bio-filtration opportunities including a new notion of B’dote in Native American cultures, where every joining of waters 20 acre wetland at the current barge port that can receive and clean large 53 has a sacred and also practical status in that these moments of hydrologic quantities of north side storm flows while also creating rich and diverse new connections maintain the heath of the overall tree-like system. As ”limbs” emergent ecosystem based on what had previously existed there. A stair- have become severed and polluted over the years the natural function of step series of biofiltratrion terraced gardens along Dowling also provides these tributaries has been lost. The watersheds which feed this reach of the an environment for cultivating native “crops” such as American lotus and 67 Mississippi now contribute a range of urban pollutants including mercury, Arrowhead which historically fed Native Americans and waterfowl. At the PCB’s, and most importantly salt from roadways. Reversing this trend requires Northeast side, existing parks provide a starting point for a series of new a system-wide solution within each watershed. But the zone along the river storm water ravines and seasonal creeks which gently slope from Marshall where piped outfalls occur is a fundamental place to start transforming the St. to the river, allowing both people and water new access to the shoreline. current hard infrastructure into a “soft” one where storm flows are brought These measures provide a powerful starting point within each watershed in to the surface wherever feasible to be naturally cleansed by riparian corridors terms of treating pollutants at their most concentrated, but also create a new and wetland features cultivated with bio-filtering species. visibility for a natural hydrology that will support new urban ecosystems. STORM WATER 0 500’ 1000’ 2000’ 4000’ Parkland Watershed Regions AFT Stormwater Outfall Hidden Stormwater Outfall DR Industrial Outfall Stormwater Drainage 13
  • 8. Guiding Principles Emergent / Meadow DRAFT Urban Urban Meadow Upland Emergent Riparian 14
  • 9. Riparian / Upland DRAFT Meadow Emergent Riparian Upland This iconic habitat zone starts at the edge of the twin cities and This zone of shallow water is often manipulated by the rivers This dynamic zone needs bank stability since anthropogenic Where the moisture regime changes a diverse canopy of timber stretches to the south and west of the state. These landscapes force and sedimentation; a multitude of rushes, sedges, and forces have increased the stress of wave action and decreased emerges, layered with a myriad of sub-canopy and ground-layer are dominated by grasses;a perfect habitat for small mammals grasses scatter refuge for the river’s wildlife inhabitants. A living natural flood plains. Defined by drastic topographical changes vegetation, providing a rich habitat for fringe species that “go and their predators. Typically the topography is flat with slight machine that absorbs flood waters, with the ability to filter from scrouring, this zone is a key link between land and river as it to” the river for food and reproduction needs. This zone provides depressions and gentle slopes. pollutants, these waters team with insects, reptiles, and fish. provides the opportunity to increase habitat and biodiversity. essential habitat buffering to urban adjacencies. 15
  • 10. Overall Plan First Steps and Future Growth Introduction The planning strategy to develop the 5 ½ mile stretch of riverfront and adjacent urban 5–10 Year Vision upland along the Mississippi is to prioritize five strategic implementation sites that The 5 –10 year Vision includes the further growth of projects that have been implemented in over a 0 – 5 year timeframe together establish a framework for future visions outlined the 0 – 5 year plan and introduces new areas for development. For example, the Farview Park in two further phases, a 5 –10 year and 10 – 20 year plan. In the near term, a system of Extension strengthens its connection from Northside through the addition of a two-block north to south riverfront trails are complimented by east to west bridges that establish a land bridge that spans I-94 and extends the landscape of Farview Park down the hill toward network of circulation and access opportunities to the Mississippi River and its adjacent the river. 27th Ave North, lost over decades of industrial development, is restored as a walk- neighborhoods. Site specific demonstration sites create anchors at strategic locations street and lined by rain gardens that bring stormwater from Farview Park to the river. The along the river that establish the foundation for a vision for the Mississippi that will Farview Park Extension culminates in the redevelopment of the City-managed Trash Transfer support the region’s neighborhoods that are rich with cultural and ethnic diversity, artistic facility for use as a river-oriented enterprise and educational/interpretive experience such as production, and multi-scaled industrial business served by freeway, rail, and barge. a boat builder. This 12-block sector from Farview Park to the river becomes the core of a new Eco-Business District that serves as a model for others to follow. 0 – 5 Year Strategic Implementation Plan The first intervention is a 6 mile Riverfront Trail System from Plymouth Bridge to Camden To extend the recreational and community energy created at Scherer Park, a mix of Bridge and back down to Boom Island. This system of trails includes a series of floating recreational enterprise uses such as a café, pavilion and museum would be developed in Biohaven Islands that are dedicated wildlife sanctuaries intended to reintroduce and support the area around the Marina at Boom Island. At the Northside Wetlands Park the Upper riverfront habitats. The Riverfront Trail System is a continuous trail and bikeway proposal that Harbor Terminal port facility is replaced by park space, a renovated Cold Storage Building, will use existing public parkland as well as private property requiring access through either and structures for public amenities, solar arrays, and areas to store dredge spoils.This first the purchase of land or easement agreements. As a result of active industries along the large scale project north of Lowry will serve as a prototype for future developments. Northside, riverfront trails are proposed to be elevated allowing industries to operate while The 5 –10 Year Vision introduces a new area of development—the Northeast Riverfront the public enjoys park amenities and wildlife habitats. In the event that easements are not Park which proposes to utilize MPRB-owned parcels to create stormwater mitigation by possible an interim bikeway is proposed along 2nd Ave N thus providing a link between the regrading parkland at existing outfall locations. riverfront trails that terminate north of Broadway Bridge and North Mississippi Park. The second intervention is the 26th Ave N Greenway Extension and improvements to 28th 10 – 20 Year Vision Ave N which establishes an initial implementation for the plan’s long-term vision to extend The longer range 10 – 20 Year Vision is to create opportunities within the framework of Farview Park to the river through this area’s industrial district. the plan for added development that reinforces both the RiverFirst initiative and City of Minneapolis redevelopment goals. The plan attempts to preserve the city grid framework The third intervention, the Scherer Park District, develops the 11-acre Scherer Brothers and introduce new and innovative programs that are responsive to environmental property recently acquired by the MPRB for public park land along with development that stewardship and provides opportunities for a mix of creative industries, commercial includes a mix of uses to support an energized park. The plan for Scherer Park includes amenities, and residential growth. Clusters of development are encouraged at east-west restoration of Halls Island and the narrow river channel between Halls Island and the corridors such as Plymouth, Broadway, Lowry, Dowling, and 41st Street N at north-south Scherer site. The plan would create roughly an 7 acre park and 4 acres of development on intersections such as 2nd Avenue N and Marshall Avenue. the Scherer site. This third intervention also includes establishment of Sheridan Park and development of new residential housing adjacent to the Grainbelt Brewery . Finally, the Spirit Island site, located where the former Spirit Island once existed just below Saint Anthony Falls and obliterated during the construction of the lock and dam system, RAFT The fourth intervention is the Northside Wetlands Park, currently the site of the City of is included as a central piece of the RiverFirst project. Once a sacred ground for the native Minneapolis’ Upper Harbor Terminal. This project proposes to create a 25 acre wetland Dakota community, it is the intention of the RiverFirst proposal to establish a process that D on a portion of the 48-acre site currently used as a materials handling facility for coal, steel will lead to the celebration of Spirit Island as a gesture that marks a commitment to a much coil, and dredge spoils from the river. This 0 – 5 year plan proposes to consolidate the port deeper cross-cultural understanding so important to the life of our city. facility to the northern end of the site making space for the wetlands project. Ultimately, it is the vision of RiverFirst to transform the 3-mile stretch of Northside industrial Downtown Gateway Park, the fifth intervention, provides a destination downtown park land as a place where both ecologically-responsible business industries and mixed use adjacent to the Central Library as well as reestablishment of an open space link between developments can co-exist and that share a common interest in preserving the health of Gateway Park, Nicollet Mall and the Mississippi River. the Mississippi River providing a bridge to it from communities such as Northside that previously have had no access to its riverbanks. The RiverFirst plan provides riverfront park land with trails, bikeways, bridges, and walkable streets that support and help foster strategic development opportunities that take advantage of the areas proximity to a growing downtown Minneapolis, the diverse Northside and Northeast neighborhoods to the east and west, and unique parks to the north. 16
  • 11. 0 – 5 Year Implementation Plan 5–10 Year Vision 10 – 20 Year Vision DRAFT 17
  • 12. Priority Project 0 – 5 Years Riverfront Trail System: Plymouth to BNSF Trail Loop 1. Scherer Park 2. Boom Island marina 3. Restored Hall Island 4. Plymouth Knot bridge AFT 5. Sheridan Park and Development 6. Broadway Knot Bridge DR 7. Biohaven Island 8. BNSF Pedestrian Bridge and Third Rail Cafe 9. Riverside Commons Park Named after the Mississippi Flyway, one of the world’s most significant north- Access to the Trail System is from city streets, bike trails and bus lines as south bird migration routes, this proposed public Trail System will provide well as from the proposed Prairie Loop clean electric bus line. When the six miles of new, Riverfront recreational trails for pedestrians, bicyclists and Flyway Trail System crosses over land owned by existing industry, it bridges x-country skiers. The north-south Trail System connects with east-west over operational areas. Representatives of all industrial land owners were pedestrian walkways (Knot Bridges) in a series of recreational River Loop contacted by the Design Team to discuss and develop criteria for the Trail circuits that link North and Northeast Neighbourhoods. System. By creating a public presence along the riverfront, the Minneapolis Flyway trail system will jumpstart the RiverFirst Parklands and create the Site lighting, grouping cyclists and pedestrians with appropriate lane ways, connective ‘glue’ to link Downtown and Neighborhoods with the River and open view corridors, WiFi access through the proposed River Talk network with existing and new Parklands. The trail system can be implemented in a and convenient vehicular and pedestrian Trail access points will help to series of cost effective modular segments that can be constructed over time. ensure public safety as the riverfront develops. The Trail System can serve as a 21st century model for new operational efficiencies in bio-remediated storm water irrigation, modular construction, and low maintenance solar powered snow melting systems. Plymouth to Broadway is the first and most easily achievable loop in the system of loops moving northward with no special bridging required N-S BNSF bridge link requires a major acquisition of strategic rail bridge still in marginal use BNSF link would allow major bike traffic on 26th St. to connect to major routes on NE side Graco river frontage already in process of easement creation Park at Riverside condos creates screening of residents from industrial activity and new acoustic green living plant wall park in at “triangle” creates cleft for storm water collection 18
  • 13. Riverfront Trail System: BNSF to Lowry Loop 1. BNSF Pedestrian Bridge and Third Rail Cafe 2. Edgewater Park 3. New Ravine Trail 4. Gluek Park 5. New Ravine Trail 6. Biohaven Island 7. Children’s Art Camp 8. Lowry Bridge 9. Flyway Bridge 10. 26th St. Bike Route The Minneapolis Flyway Trail System serves the City and Parks as a Preliminary Development Budget comprehensive riparian conservation spine. The Trail System provides a rich A preliminary budget of $62,088,122 has been estimated for the Riverfront range of landscape habitat to support endangered cornerstone species. Trail System that includes costs for the N 26th Avenue Greenway extension Naturally cleansed storm water is integrated along the Trail System in small and improvements to N 28th Avenue. Trail sites along the riverfront that are scale bridge crossing points that allow natural drainage as well as animals private property will require both easements and fee acquisition resulting in to move freely underneath to sustain species and habitat movement. The additional development costs that are not reflected in the total capital cost. Trail System provides an armature for the re-establishment of the historic This budget will be refined prior to Board action in December 2011. riverbank canopy, which in turn supports pollinator and food web species for Warbler, Fly Catchers, Bireos, Oriels and other migrating species, as well as supporting river cleaning mollusks and fish that sustain Heron, Osprey, and Eagles. The Conservation Strategy unifies the form, material expression and public experience of the Trail System. Constructed sustainably of reclaimed wood modules, with low maintenance recycled rubber walking surfaces, the Trail System allows bio-diversity to return to the river and flourish over time. East side – through trail shifts to Marshall with various “eyebrows” where bikes and pedestrians loop to the river’s edge. Ravines allow gently sloped flows of people and day-lighted storm to river’s edge Lowry crossing engages with and modifies construction in-progress West side has three of most challenging trail connections – under BNSF, DRAFT over 2 different active barge docks using Flyway bridges Easement and land acquisition at these locations among most strategic for long term success of Grand Rounds Interim fall-back location at Pacific St. Below-bridge space at west end of Lowry developed as park and possible commercial along with remodeled storm water detention 19
  • 14. Priority Project 0 – 5 Years Riverfront Trail System: Wetlands Marshall Loop 1. Marshall Terrace Park AFT 12 2. New ravine trail DR 3. East side urban farm 4. Excel Plant 5. New wetlands park 6. Remodeled Cold Storage Bldg. 7. Remodeled Grain Elevator 8. Amphitheater Slope 9. Photo-voltaic Arrival Canopy w/ pavilions 10. Biofiltration wetland gardens 11. Park “Rooms” 11 12. Biohaven Island 10 9 8 7 4 Prefabricated wood-based structures allow for rapid istallation Thickened structure for torsional sti ness 6 Walking surface Form slopes outward for weather protection Handrail 3 Laminated engineered wood layers Thickened wood structure for bending sti ness Bridge pier support Engineering concept illustrating the use of laminated wood and method of prefabrication for the Flyway Bridge East Side—“eyebrow” system stops at Excel with no riverfront access allowable 5 Marshall “through-way” continues uninterrupted to St. Anthony Parkway. Easement parcels east of Marshall opposite Excel can be developed as urban farming to continue park sensibility around Excel West side riverfront trail enters its richest moment looping around new wetland park Thru-bikes kept to rear of Port property along rail corridor 1 Key connection and highway bridge at 34rth St. from North side neighborhood to new park Trail ascends to the top of the existing cold storage building on sloping landforms North of existing cold storage building “Ridge trail” follows the crest of new dredge fill landforms against the rail lines—“shoreline trail” follows water’s edge 2 20
  • 15. Riverfront Trail System: Camden North Mississippi Loop 1. Canadian Pacific Bridge 2. Biohaven Island 3. North Mississippi Park 4. Shingle Creek 5. Existing Boat Launch 6. Rail Bridge Undercrossing Bicycle Path, Dupont Maryland 3 DRAFT Bicycle path, Copenhagen, Denmark 5 2 Completing vital connections to North Mississippi Park and to Shingle Creek Grand Rounds link Knot bridge or Camden bridge walkway essential to complete 6 the loop 1 Canadian Pacific bridge not available for any pedestrians or bikes but connecting under on west side is crucial connection and brings existing boat ramp into the rest of the park Connection to Shingle Creek can be made via highway undercrossing for the creek American River Bike Trail, Sacramento CA 21
  • 16. Priority Project 0 – 5 Years Riverfront Trail System: Knot Bridges Separation of bridge deck above abut- Steel arch ments used to create a torsion tube Brace support frame ties cantilevered Support cables bridge back to bridge abutment Steel frame provides rigidity for cantilevered steel deck Horizontal force tied back to abutment Vertical force directly transferred Existing Bridge Structure Concrete extensions on existing abutments Engineering sketch illustrating Knot Bridge structural concept Reclaimed BN/SF Bridge looking east toward the Third Rail Cafe Marsupial Bike and Pedestrian Bridge Milwaukee The RIVERFIRST Trail System initiative is designed to create new synergies DRAFT and solid state lighting systems. Efficient pathway lighting is envisioned to between existing City and County Bridges and a set of proposed water enhance public safety and create a beautiful new bridge profile on existing remediation and ecological conservation assets. Knot Bridges are designed bridges without creating light spill. to be supported from the existing foundations of bridge structures, and The Knot Bridge system creates an unprecedented ease of access to move provide needed pedestrian linkages with the north-south river Trail System. along North South park trails and East West across neighbourhoods that The Knot Bridges tie or “knot together” roadway and the River Trail levels, have been historically separated by the River. Knot Bridges, together with T providing the “missing links” in section that connect the disparate heights the River Trail System complete the series of connective River loops that link of existing bridge roadways with the lower natural river bank topography. the Parklands, Neighbourhoods and Downtown. Together, The Knot Bridges Natural land grading is used to make the Knot bridges handicap accessible. and River Trails Systems create a comprehensive recreational and sustainable On each bridge crossing, Plymouth Bridge (slated for repairs), Broadway commuter biking system for the City of Minneapolis. Bridge, BNSF Railway Bridge, the new Lowry Bridge (under construction) and the Camden Bridge the RiverFirst vision provides a bridge specific Preliminary Development Budget design strategy to implement dedicated bike lanes and pedestrian pathways. A conceptual development cost of $18,320,584 has been estimated for Knot Knot Bridges are constructed of lightweight steel members with a low Bridges at the Plymouth, Broadway, and Camden Bridges and includes the maintenance recycled rubber decking. The Knot Bridges support the clean repurposing of the BN/SF Bridge as a bike and pedestrian trail. This budget energy equipment needed for the solar powered WiFi River Talk network will be refined prior to Board action in December 2011. 22
  • 17. Riverfront Trail System: Biohaven Islands Floating Island Remidiation, Chippewa Flowage, Northern Wisconson 20,000 SF Floating Island, Montana, US Army Corp of Engineers R I P A R I A N S P W AFT E E T Species List: C L DR I A N Acorus calamus Carex vulpinoidea Lobelia siphilitica Sagittaria latifolia E D Allium canadense Boltonia asteroides Lysimachia quadrifolia Scirpus atrovirens S Anemone canadensis Chelone glabra Lythrium alatum Scirpus cyperinus U Asclepias incarnata Elymus virginicus Pedicularis lanceolata Solidego riddellii P L Aster novae-angliae Eupatorieum perfoliatum Phlox divaricata Verbena hastata A Aster umbellatus Iris versicolor Pycnanthemum virginianum Vernonia fasciculata N D Calamagrostis canadensis Juncus effuses Rudbeckia hirta Veronicastrum virginicum Caltha palustris Leersia oryzoides Rudbeckia subtomentosa Zizia aurea Carex hystericina Liatris ligulistylis Thalictrum dasycarpum YEAR 1 2 3 4 5 BIODIVERSITY OVER TIME A system of floating Biohaven Islands, anchored on existing downstream water. The River Talk WiFI network, integrated in the Knot Bridges, supports the A pair of Biohaven Islands offers the river a bio-remediation capacity that can bridge pier foundations, creates a conservation feature that can be viewed Biohaven experience by provides educational conservation information to the absorb 32 kg/day of phosphors or about (1681 gallons) of dish soap per day, from the pedestrian Knot Bridges along the River Trail. Biohaven Islands public that can be accessed through a mobile phone. based on the new Minnesota regulation of .5% max phosphates in detergent. provide bio-remediation to cleanse river water and provide more than 7 acres 636.63 kg of nitrates per day can be naturally removed by the planted root RiverFirst uses soft engineering principles and the natural buoyancy of the systems. Each day, the Islands would have the capacity to bio-remediate the of protected riparian habitat for migrating birds and endangered species. river. Instead of costly hard and resistive structures, buoyancy is provided nitrate content of about 224 twenty five lb bags of lawn fertilizer. These include native mussels, blanding turtle, osprey, logger head strike and by innovative and locally fabricated fiber foam made of 100% recycled PET karner blue butterfly. Biohaven islands can be adopted and supported by local (water bottle plastics). Soil and gravel are placed atop the island to provide Preliminary Development Budget organizations or corporations as special sites for native berries and plantings. a nutrient medium for plants and shrubs. Islands are tethered fixed anchors A conceptual development cost of $12,188,880 has been estimated for 6 clusters People who walk along the Trail System Loops will have the experience of being outside of the existing Navigation Channel. A hinge connection allows the of Biohaven Islands that run from the west side of the Broadway Bridge to the able to pause at the mid-point of the River and observe native vegetation, bird downstream island to shift slightly, accommodating different water levels and west side of the Canadian Pacific Railroad Bridge.facing North Mississippi Park. and wildlife activities. Kayakers will be able to experience the Biohavens from the allowing sunlight down to the river bed below. This budget will be refined prior to Board action in December 2011. 23