Mohamed Abdalla Hassan Hamed
Msc,MBA,PMP,PQP
Projects Manager
Changes “Variations“ in
Construction Projects .
I am more than glad
to be your speaker for
the next 45 minutes
 MOHAMED ABDALLA
 Projects Manager, Public Speaker
 MSC,MBA, PMP,PQP
 +971508143450
 pm@ace.ae
The construction industry is one of the most
important sectors in United Arab Emirates, So
it is essential to know the ingredients for
success of construction projects in UAE. While
construction project is unique, projects differ
in objectives, size, budget, timeline and
complexity, but we may find some common
features such as changes and risks concerns.
In Construction Field
How many projects we completed without changes?
Agenda
 What is a Change
 Why change occur
 Causes of change
 How PM should lead the change
Change is good or bad ?
Changes
Changes in construction projects can be
defined as any additions or deduction to
project objectives or project scope are
considered to be unplanned changes, whether
they have positive or negative impact on the
project parameters ; cost, time or quality
Why we Focus on changes ?
1- Client / Engineer / Contractor Direct Change ‘’ Variations’’
2- Constructive Changes ‘’ Variations’’
3- Differing Site Conditions
4- Directed Suspension of Work
5- Constructive Suspension of Work
6- Force Majeure
7- Delays
8- Directed Acceleration
9- Constructive Acceleration
10- Termination for Convenience
11- Termination for Default
The most common reasons of Claims / Disputes
Scope
It is the project manager’s duty to balance and
achieve these three often-competing goals.
The Triple Constraint of
Project Management
Scope
The Triple Constraint of
Project Management
When changes can occur ?
During the
planning
Project Lifecycle
Project Lifecycle & Cost of change
Change VS Cost
Change VS Cost
The nature of construction projects is very
complex due to many variables ,Human and
nonhuman factors, as well as construction
project need a long time for execution ,some
of them continue to a several years
Why changes occur ?
Just one
more thing
We still needCan
we add
one
more
thing
But we
need this
We still
need
But we need
this too
Support or Resist changes ?
How to avoid scope creep as a project manager ?
2 3 41
Successful project Manager
How to avoid scope creep as a project manager ?
4
Successful project Manager
How to avoid scope creep as a project manager ?
Say NO if the change is Optional
Change
OptionalMandatory
Stakeholder needsNew regulations
Causes of changes (Variations)
Client Engineer Contractor External
Factors
Causes of changes (Variations)
• inadequate requirements , Funding problems, insufficient project objectives
Client Engineer Contractor External
Factors
Causes of changes (Variations)
Errors or missing in the design , conflict among contract documents , Delay in material or shop drawings approval
Client Engineer Contractor
External
Factors
Causes of changes (Variations)
Poor procurement plan for long lead items, Financial problems
Client Engineer Contractor
External
Factors
Causes of changes (Variations)
Client Engineer Contractor
External
Factors
Changes in Marketplace , Changes in weather conditions
How PM Lead a change
No
Change
Look at the impact of changes
a) Assess the change.
b) Look for options.
c) Change is approved or rejected.
d) Update the status of the change in the change control
system.
2. Identify changes.
7. Manage stakeholder’s expectations by communicating the change
4. Create change request
3. Look at the impact of the change.
1. Prevent the root cause of change. +
+
+
-
+
+
6. Adjust the project management plan, Project Documents, Baselines.
5. Perform Integrated change control
+
-
Steps of the project changes
Change lifecycle
CCB = Change Control Board
Change Goals
● Realistic
● Measurable
● Specific
● Time bound
Smart Goals
● Agreed upon
Changes results in
 Time Variations. (Extension of Time) (EoT)
 Cost Variation. (Additional Cost)
Extension of time Additional Cost
The Flow of Variation resolution
Negotiation DABNegotiation
DAB= Dispute Adjudication Board
See
you
in
Typical sequence of Dispute Events envisaged in
Clause 20
DAB: the persons so named in the contract or other persons appointed
under sub-clause (appointment of the dispute adjudication board)
A
C
E
B
D
Float
Who own The Float ?
6.5 Develop Schedule
One of the most common Dispute ?
6.5.2.2 Critical Path Method (CPM)
Free
Float
Total
Float
A
B
C
D
Client Contractor The project
Who own The Float ?
THANK YOU
FOR ATTENDING THE PRESENTATION
Please don't forget to collect your CPD certificate during
the event from the CPD collection area.

Mais conteúdo relacionado

Mais procurados

Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptssuserb4074f
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 

Mais procurados (20)

Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Fidic
FidicFidic
Fidic
 
fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Construction contract
Construction contract Construction contract
Construction contract
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 

Semelhante a Changes in construction

028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectIRJET Journal
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementChris Hattingh
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementdrdej19
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
Pm expectations duluth
Pm expectations   duluthPm expectations   duluth
Pm expectations duluthBrandon Olson
 
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...SN Panigrahi, PMP
 
Change management
Change managementChange management
Change managementmehak1990
 
Project change management plan template
Project change management plan templateProject change management plan template
Project change management plan templateVivek Srivastava
 
Quality unit 2012
Quality unit 2012 Quality unit 2012
Quality unit 2012 Skript
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxRebeccaEdwards88
 

Semelhante a Changes in construction (20)

TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
Pm expectations duluth
Pm expectations   duluthPm expectations   duluth
Pm expectations duluth
 
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
 
Change management
Change managementChange management
Change management
 
Project change management plan template
Project change management plan templateProject change management plan template
Project change management plan template
 
Quality unit 2012
Quality unit 2012 Quality unit 2012
Quality unit 2012
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
BIM - What the Client wants from Manufacturers #BIM4M2help
BIM - What the Client wants from Manufacturers #BIM4M2helpBIM - What the Client wants from Manufacturers #BIM4M2help
BIM - What the Client wants from Manufacturers #BIM4M2help
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
Change management process 17.01.15
Change management process 17.01.15Change management process 17.01.15
Change management process 17.01.15
 

Último

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 

Último (20)

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 

Changes in construction

  • 1. Mohamed Abdalla Hassan Hamed Msc,MBA,PMP,PQP Projects Manager Changes “Variations“ in Construction Projects .
  • 2. I am more than glad to be your speaker for the next 45 minutes
  • 3.  MOHAMED ABDALLA  Projects Manager, Public Speaker  MSC,MBA, PMP,PQP  +971508143450  pm@ace.ae
  • 4. The construction industry is one of the most important sectors in United Arab Emirates, So it is essential to know the ingredients for success of construction projects in UAE. While construction project is unique, projects differ in objectives, size, budget, timeline and complexity, but we may find some common features such as changes and risks concerns.
  • 5. In Construction Field How many projects we completed without changes?
  • 6. Agenda  What is a Change  Why change occur  Causes of change  How PM should lead the change
  • 7. Change is good or bad ?
  • 8. Changes Changes in construction projects can be defined as any additions or deduction to project objectives or project scope are considered to be unplanned changes, whether they have positive or negative impact on the project parameters ; cost, time or quality
  • 9. Why we Focus on changes ?
  • 10. 1- Client / Engineer / Contractor Direct Change ‘’ Variations’’ 2- Constructive Changes ‘’ Variations’’ 3- Differing Site Conditions 4- Directed Suspension of Work 5- Constructive Suspension of Work 6- Force Majeure 7- Delays 8- Directed Acceleration 9- Constructive Acceleration 10- Termination for Convenience 11- Termination for Default The most common reasons of Claims / Disputes
  • 11. Scope It is the project manager’s duty to balance and achieve these three often-competing goals. The Triple Constraint of Project Management
  • 12. Scope The Triple Constraint of Project Management
  • 13. When changes can occur ? During the planning
  • 14.
  • 16. Project Lifecycle & Cost of change Change VS Cost
  • 18. The nature of construction projects is very complex due to many variables ,Human and nonhuman factors, as well as construction project need a long time for execution ,some of them continue to a several years Why changes occur ?
  • 19. Just one more thing We still needCan we add one more thing But we need this We still need But we need this too
  • 20.
  • 21. Support or Resist changes ?
  • 22. How to avoid scope creep as a project manager ?
  • 23. 2 3 41 Successful project Manager How to avoid scope creep as a project manager ?
  • 24. 4 Successful project Manager How to avoid scope creep as a project manager ? Say NO if the change is Optional
  • 26. Causes of changes (Variations) Client Engineer Contractor External Factors
  • 27. Causes of changes (Variations) • inadequate requirements , Funding problems, insufficient project objectives Client Engineer Contractor External Factors
  • 28. Causes of changes (Variations) Errors or missing in the design , conflict among contract documents , Delay in material or shop drawings approval Client Engineer Contractor External Factors
  • 29. Causes of changes (Variations) Poor procurement plan for long lead items, Financial problems Client Engineer Contractor External Factors
  • 30. Causes of changes (Variations) Client Engineer Contractor External Factors Changes in Marketplace , Changes in weather conditions
  • 31. How PM Lead a change No Change
  • 32. Look at the impact of changes a) Assess the change. b) Look for options. c) Change is approved or rejected. d) Update the status of the change in the change control system. 2. Identify changes. 7. Manage stakeholder’s expectations by communicating the change 4. Create change request 3. Look at the impact of the change. 1. Prevent the root cause of change. + + + - + + 6. Adjust the project management plan, Project Documents, Baselines. 5. Perform Integrated change control + - Steps of the project changes
  • 33. Change lifecycle CCB = Change Control Board
  • 34.
  • 35. Change Goals ● Realistic ● Measurable ● Specific ● Time bound Smart Goals ● Agreed upon
  • 36. Changes results in  Time Variations. (Extension of Time) (EoT)  Cost Variation. (Additional Cost) Extension of time Additional Cost
  • 37. The Flow of Variation resolution Negotiation DABNegotiation DAB= Dispute Adjudication Board See you in
  • 38. Typical sequence of Dispute Events envisaged in Clause 20 DAB: the persons so named in the contract or other persons appointed under sub-clause (appointment of the dispute adjudication board)
  • 39.
  • 41. 6.5 Develop Schedule One of the most common Dispute ? 6.5.2.2 Critical Path Method (CPM) Free Float Total Float A B C D
  • 42. Client Contractor The project Who own The Float ?
  • 43. THANK YOU FOR ATTENDING THE PRESENTATION Please don't forget to collect your CPD certificate during the event from the CPD collection area.