Poor project cost estimates are more than
embarrassing...
But good communication and corporate culture can help
avoid cost blow outs
The New Zealand Herald recently cited SkyCity managing director Nigel
Morrison saying cost over-runs and 'design improvements' had seen the bill for
the Auckland convention centre blow out from an original budget of $402 million
to between $470 million and $530 million.
Further afield, the Berlin airport is an even more dramatic example of a project
cost increase – one that cost Berlin's mayor his job, and German tax payers a
lot of money. The original cost estimate for this new airport was about €2 billion.
Construction started in 2006 and the airport was meant to open in 2012. At the
time of writing, the airport still hasn’t been completed and the costs to
completion are now estimated at €5.4 billion.
While these are only two examples, research supports the suggestion that cost
estimates are typically inaccurate (AACE International Transactions, Estimate
Accuracy: Dealing with Reality, by John K Hollmann, 2012).
But before we examine the issue further, it’s worth briefly reminding ourselves
of what a ‘project’ is. Let's keep it simple and say a project is a one off activity
with a defined start and end. This definition alone suggests that since projects
are 'one off' activities, no two projects will be the same. As they don't come off
an assembly line, project costs can’t usually be predicted by looking at the last
1000 or so and coming up with a number that will remotely resemble the final
cost.
This article is not about project delivery, scope management, risk
management or team selection. It focuses only on a small, albeit
important part of a project - the cost estimate.
So why do we keep getting it wrong? It’s not a recent phenomenon. It’s also not
limited to projects in one particular industry or just large projects. In fact, some
work into the success factors of delivering projects has suggested that smaller
projects suffer even more from poor delivery, including inaccurate budgets, as
they usually receive less attention than larger ones.
These are high level observations. Some practitioners may argue that each
project is different and there are numerous reasons why projects don’t come in
on budgeted. However, even when scope is tightly controlled, numerous other
factors can contribute to project outturn costs being different to the original cost
estimate.
At a glance
Cost estimation -
how many projects
do you know that
have come in on
budget?
Cost estimation – March 2015 coffey.com
Understanding possible cost outcomes
Let's look at the following two statements:
1. Project cost estimates are usually communicated in the form of a single
dollar value.
2. History tells us it is unlikely that a project cost estimate will be accurate.
One solution to the problem can essentially be based on the above two
statements - rather than communicating a single value, project cost estimates
should communicate a likely range of cost outcomes including lower and upper
bounds for the project cost (not just adding contingency).
If you’re the project client and presented with a cost estimate that states a
single number, no matter how much detail has gone into it, history suggests
that the final project cost is more than likely to be different, even if it includes a
contingency. We recommend you ask for a range of likely cost outcomes
instead. While this may seem obvious, it’s our experience that very few
organisations develop cost estimates which communicate at least three data
points:
3. The value at which there is a 50% chance of the project coming in above
this cost and a 50% chance of it coming in below this cost (known as the
P50 estimate).
4. The value at which there is only a 10% chance of the project coming in at a
lower cost (known as the P10 estimate), i.e. the lower bound.
5. The value at which there is a 90% chance of the project coming in at a
lower cost (known as the P90 estimate), i.e. the upper bound.
Cost estimation – March 2015 coffey.com
If a project is at an early stage, with little knowledge of the details, it’s
impossible to develop an accurate cost estimate as there’s simply not enough
detail known about the project. As a result, you’d expect the lower and upper
bound to be far apart. As the project concept is developed towards
implementation, more detail is known and the cost estimate can be improved
upon. Therefore, the range of cost outcomes will become narrower as the upper
and lower bounds will move closer to the midpoint. However, even during the
implementation phase, a range of cost outcomes are still possible.
For a moment let's consider this issue from a procurement perspective. Few
tenders require bidders to communicate the anticipated cost as a range of likely
outcomes. You could argue that this isn’t usually in the interest of the client, as
tenders requesting a fixed price seek to allocate the cost risk with the
contractor. But most projects are tendered before every detail has been
defined, and it’s not unusual for contractors to take advantage of this and bid
low, only to submit multiple variations later, as project details are becoming
clearer. So a fixed price bid doesn’t eliminate the cost risk after all. In fact, a
fixed price is little more than an indication of the minimum cost of the project.
And if you look at history you’ll likely find that the project cost is often
significantly more by the time it’s completed.
Of course there’s no guarantee that the three values (P10, P50 and P90) are
more accurate than a single value. However, if nothing else it raises awareness
with both the project team and the project client that costs cannot be predicted
accurately. Providing a range of potential outcomes should trigger the right
conversations between project stakeholders.
Communication and culture
We’re all prone to wishful thinking. And few people like a doomsayer.
Recognising these facts is important when considering cost estimates. It’s our
experience that the majority of project feasibility assessments, including
financial affordability, take on a life of their own as the project team develops a
sense of ownership with a project. In other words, when people become
involved in a project they develop a sense of association, often resulting in a
poor representation of the real project viability at the concept phase. It takes
courage to fess up and express what is likely to be perceived as a negative or
opposing viewpoint, and many organisations don’t have an appropriate level of
appreciation for this. External peer reviews should help with this issue.
However, in our experience the above points still apply, and of course an
external peer reviewer doesn't have the same in-depth knowledge of the project
as the project team.
We suggest that an organisational or corporate culture where staff feedback is
valued, won’t only provide operational benefits in terms of productivity, staff
retention and other metrics, but will also enable those projects which have a
better chance of coming in on budget, on schedule and to quality expectations
being sent to management for approval.
We do support an external peer reviewer be engaged. However, to ensure the
external peer reviewer relationship with the project team doesn’t unduly
influence the reviewers’ approach or outcome, it’s important they be engaged
by the executive leadership team or the Board.
Cost estimation – March 2015 coffey.com
There are of course many other issues to consider when delivering projects to a
budget. This includes scope management and a thorough project risk analysis.
However, when you’re presented with a project cost estimate, ask for a range of
likely cost outcomes, not just a point estimate. And in terms of improving cost
estimate accuracy and project delivery in the long term, seek to develop an
organisational culture which values honest opinion.
Coffey helps clients to deliver projects, from concept to completion. We
recognise that each project is different, and we tailor our solutions to reflect this.
We can help you and your team develop and deliver projects, including the
preparation and communication of a robust cost estimate, and ultimately help
you deliver a project that you and your organisation can be proud of.
For more information please contact Markus Benter-Lynch at Markus.Benter-
Lynch@coffey.com.
If you would prefer not to receive further client insights from Coffey, click here to unsubscribe from
any further marketing communications.
Cost estimation – March 2015 coffey.com

Mais conteúdo relacionado

Destaque

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by HubspotMarius Sescu
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTExpeed Software
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsPixeldarts
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthThinkNow
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfmarketingartwork
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024Neil Kimberley
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)contently
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024Albert Qian
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsKurio // The Social Media Age(ncy)
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Search Engine Journal
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summarySpeakerHub
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next Tessa Mero
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentLily Ray
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best PracticesVit Horky
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project managementMindGenius
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...RachelPearson36
 

Destaque (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Cost Estimation 2015

  • 1. Poor project cost estimates are more than embarrassing... But good communication and corporate culture can help avoid cost blow outs The New Zealand Herald recently cited SkyCity managing director Nigel Morrison saying cost over-runs and 'design improvements' had seen the bill for the Auckland convention centre blow out from an original budget of $402 million to between $470 million and $530 million. Further afield, the Berlin airport is an even more dramatic example of a project cost increase – one that cost Berlin's mayor his job, and German tax payers a lot of money. The original cost estimate for this new airport was about €2 billion. Construction started in 2006 and the airport was meant to open in 2012. At the time of writing, the airport still hasn’t been completed and the costs to completion are now estimated at €5.4 billion. While these are only two examples, research supports the suggestion that cost estimates are typically inaccurate (AACE International Transactions, Estimate Accuracy: Dealing with Reality, by John K Hollmann, 2012). But before we examine the issue further, it’s worth briefly reminding ourselves of what a ‘project’ is. Let's keep it simple and say a project is a one off activity with a defined start and end. This definition alone suggests that since projects are 'one off' activities, no two projects will be the same. As they don't come off an assembly line, project costs can’t usually be predicted by looking at the last 1000 or so and coming up with a number that will remotely resemble the final cost. This article is not about project delivery, scope management, risk management or team selection. It focuses only on a small, albeit important part of a project - the cost estimate. So why do we keep getting it wrong? It’s not a recent phenomenon. It’s also not limited to projects in one particular industry or just large projects. In fact, some work into the success factors of delivering projects has suggested that smaller projects suffer even more from poor delivery, including inaccurate budgets, as they usually receive less attention than larger ones. These are high level observations. Some practitioners may argue that each project is different and there are numerous reasons why projects don’t come in on budgeted. However, even when scope is tightly controlled, numerous other factors can contribute to project outturn costs being different to the original cost estimate. At a glance Cost estimation - how many projects do you know that have come in on budget? Cost estimation – March 2015 coffey.com
  • 2. Understanding possible cost outcomes Let's look at the following two statements: 1. Project cost estimates are usually communicated in the form of a single dollar value. 2. History tells us it is unlikely that a project cost estimate will be accurate. One solution to the problem can essentially be based on the above two statements - rather than communicating a single value, project cost estimates should communicate a likely range of cost outcomes including lower and upper bounds for the project cost (not just adding contingency). If you’re the project client and presented with a cost estimate that states a single number, no matter how much detail has gone into it, history suggests that the final project cost is more than likely to be different, even if it includes a contingency. We recommend you ask for a range of likely cost outcomes instead. While this may seem obvious, it’s our experience that very few organisations develop cost estimates which communicate at least three data points: 3. The value at which there is a 50% chance of the project coming in above this cost and a 50% chance of it coming in below this cost (known as the P50 estimate). 4. The value at which there is only a 10% chance of the project coming in at a lower cost (known as the P10 estimate), i.e. the lower bound. 5. The value at which there is a 90% chance of the project coming in at a lower cost (known as the P90 estimate), i.e. the upper bound. Cost estimation – March 2015 coffey.com
  • 3. If a project is at an early stage, with little knowledge of the details, it’s impossible to develop an accurate cost estimate as there’s simply not enough detail known about the project. As a result, you’d expect the lower and upper bound to be far apart. As the project concept is developed towards implementation, more detail is known and the cost estimate can be improved upon. Therefore, the range of cost outcomes will become narrower as the upper and lower bounds will move closer to the midpoint. However, even during the implementation phase, a range of cost outcomes are still possible. For a moment let's consider this issue from a procurement perspective. Few tenders require bidders to communicate the anticipated cost as a range of likely outcomes. You could argue that this isn’t usually in the interest of the client, as tenders requesting a fixed price seek to allocate the cost risk with the contractor. But most projects are tendered before every detail has been defined, and it’s not unusual for contractors to take advantage of this and bid low, only to submit multiple variations later, as project details are becoming clearer. So a fixed price bid doesn’t eliminate the cost risk after all. In fact, a fixed price is little more than an indication of the minimum cost of the project. And if you look at history you’ll likely find that the project cost is often significantly more by the time it’s completed. Of course there’s no guarantee that the three values (P10, P50 and P90) are more accurate than a single value. However, if nothing else it raises awareness with both the project team and the project client that costs cannot be predicted accurately. Providing a range of potential outcomes should trigger the right conversations between project stakeholders. Communication and culture We’re all prone to wishful thinking. And few people like a doomsayer. Recognising these facts is important when considering cost estimates. It’s our experience that the majority of project feasibility assessments, including financial affordability, take on a life of their own as the project team develops a sense of ownership with a project. In other words, when people become involved in a project they develop a sense of association, often resulting in a poor representation of the real project viability at the concept phase. It takes courage to fess up and express what is likely to be perceived as a negative or opposing viewpoint, and many organisations don’t have an appropriate level of appreciation for this. External peer reviews should help with this issue. However, in our experience the above points still apply, and of course an external peer reviewer doesn't have the same in-depth knowledge of the project as the project team. We suggest that an organisational or corporate culture where staff feedback is valued, won’t only provide operational benefits in terms of productivity, staff retention and other metrics, but will also enable those projects which have a better chance of coming in on budget, on schedule and to quality expectations being sent to management for approval. We do support an external peer reviewer be engaged. However, to ensure the external peer reviewer relationship with the project team doesn’t unduly influence the reviewers’ approach or outcome, it’s important they be engaged by the executive leadership team or the Board. Cost estimation – March 2015 coffey.com
  • 4. There are of course many other issues to consider when delivering projects to a budget. This includes scope management and a thorough project risk analysis. However, when you’re presented with a project cost estimate, ask for a range of likely cost outcomes, not just a point estimate. And in terms of improving cost estimate accuracy and project delivery in the long term, seek to develop an organisational culture which values honest opinion. Coffey helps clients to deliver projects, from concept to completion. We recognise that each project is different, and we tailor our solutions to reflect this. We can help you and your team develop and deliver projects, including the preparation and communication of a robust cost estimate, and ultimately help you deliver a project that you and your organisation can be proud of. For more information please contact Markus Benter-Lynch at Markus.Benter- Lynch@coffey.com. If you would prefer not to receive further client insights from Coffey, click here to unsubscribe from any further marketing communications. Cost estimation – March 2015 coffey.com