PLANEJAMENTO
PROJETO EVEREST
EUROFARMA AGOSTO
S95 – 11/09/2021
SMS
PROJETO EVEREST
MOMENTO SMS
Tema: Teste da Sirene
SEGURANÇA DO TRABALHO
Acidentes
CPT
Acidentes
SPT
4 0
OCORRÊNCIAS
ACIDENTE DE TRABALHO - 2021
Dias sem ocorrências de
acidentes SPT / CPT
46 (11.09.21)
OCORRÊNCIAS NA SEMANA
ACIDENTES / INCIDENTES
1
OPORTUNIDADES
DE MELHORIA
POSITIVA
0 0
OBSERVAÇÕES DE SMS
OMINI
OMINI
0
Ago/21 Acum.
Projeto
00 00
00 00
00 04
01 13
43* -
SEGURANÇA DO TRABALHO
* Informações até 04.09.2021
(OMINI, LV OECI)
DATA DO INCIDENTE 08/08/2021
HORÁRIO DO INCIDENTE 17h40’
LOCAL DO INCIDENTE Entre Hormonais e Cefalosporinicos
DESCRIÇÃO DO INCIDENTE O motorista estava realizando manobra de marcha ré, quando
o sol refletiu no retrovisor e ao perceber a trasseira do
caminhão já havia ultrapassado o talude.
AÇÃO CORRETIVAS:
DDS;
Continuidade do cronograma de treinamento
de direção defensiva;
Identificação de sinaleiros para cada
equipamento;
Continuidade de melhoria da sinalização.
SEGURANÇA DO TRABALHO
SEGURANÇA DO TRABALHO
1- Continuidade na manutenção da organização, arrumação e limpeza;
2- Instalação de caixa de sugestões;
3- Continuidade da sinalização das periferias contra risco de queda;
4- Verificação das proteção de vergalhões ou dobra;
5- Inspeção de máquinas e equipamentos (branco);
1
2
3
4 5
SEGURANÇA DO TRABALHO
6- Mapa de Risco;
7-Instalação de placa de orientação;
8- Continuidade na organização do depósito de vergalhões;
9- Treinamento da equipe de segurança; NR’s, PAE.
6
8
7
9
SAÚDE OCUPACIONAL
ENFERMAGEM
MÉDICO
0
63757
65
3
ATENDIMENTOS
Notas:
1- Atendimentos médicos incluem: Atendimentos
gerais, ocupacionais, urgência e emergência e covid-19.
2- Atendimentos de enfermagem incluem:
Atendimentos gerais, ocupacionais, urgência e
emergência covid-19 e aferições de pressão arterial.
SAÚDE OCUPACIONAL
Confirmado
Suspeitos
5 1
COVID19
AFERIÇÕES DE TEMPERATURA
2.231
SAÚDE OCUPACIONAL
1. Treinamento Promoção de Saúde - Hipertensão Arterial
2. Treinamento Primeiros Socorros – Integração
3. Ação COVID-19 / Uso das plaquinhas no refeitório para zeladores
1
2
3
MEIO AMBIENTE
1. Coleta e destinação de resíduos de madeira, resíduos de construção civil, não reciclável;
2. Coleta e destinação de efluentes;
3. Coleta e destinação de resíduos de metais para reciclagem;
4. Melhorias de segurança nas caixas de sedimentação do lava rodas.
2
3
4
1
MEIO AMBIENTE
Planejamento
PROJETO EVEREST
Semana 95
MONTAGEM DE SEGUNDO TRAMO - PENICILÍNICOS
AVANÇO NA MONTAGEM DE PRÉ-MOLDADOS - ALMOXARIFADO
AVANÇO DA MONTAGEM DE STEEL DECK NÍVEL 25.50 – SÓLIDOS 1
MONTAGEM DE VIGAS METÁLICAS NÍVEL 25.50 – HORMONAIS
ÍNDICES DE PRÉ-MOLDADOS NA SEMANA
OCIOSIDADES
FORMA: 48M³ (DUAS FORMAS DE PILARES E UMA DE ESCADA)
AGUARDANDO LIBERAÇÃO DE PROJETO
TIPO QUANTIDADE (UND) VOLUME (m³)
PILARES 12 106,39
VIGAS 30 126,34
LAJES 35 188,92
ESCADA 0 0,00
TOTAL 77 421,65
FABRICAÇÃO
TIPO QUANTIDADE (UND) VOLUME (m³)
PILARES 12 132,85
VIGAS 15 128,17
LAJES 74 373,92
LAJES ALV. 12 16,08
ESCADA 0 0,00
TOTAL 113 651,02
MONTAGEM
HISTOGRAMA DE MÃO DE OBRA
S-94 S-95 S-96
Elemento Quant. Semana: 30/08 à 05/09 06/09 à 12/09 13/09 à 19/09
59 PREVISTO
56 REAL 1
TENDÊNCIA 1
118 PREVISTO
118 REAL 0 0
TENDÊNCIA
225 PREVISTO 9 15 8
219 REAL 0 6
TENDÊNCIA 2 6
404 PREVISTO 3 1
392 REAL 1 0
TENDÊNCIA 3 1
12 PREVISTO
12 REAL
TENDÊNCIA
759 PREVISTO 12 16 8
741 REAL 1 6 0
TENDÊNCIA 5 7 0
59 PREVISTO
22 REAL 2 2
TENDÊNCIA
126 PREVISTO
21 REAL 3 2
z TENDÊNCIA
239 PREVISTO
34 REAL 0 0
TENDÊNCIA
427 PREVISTO 7 11 10
352 REAL 2 0
TENDÊNCIA 3 3
12 PREVISTO
0 REAL
TENDÊNCIA
804 PREVISTO 7 11 10
407 REAL 5 2 0
TENDÊNCIA 3 3 0
Lajes
Escadas
TOTAL_CEFALOSPORÍNICOS
FABRICAÇÃO DE PRÉ-MOLDADOS / SAPATAS
Vigas
Lajes
Escadas
TOTAL_PENICILÍNICOS
PENICILÍNICOS
SÓLIDOS
HORMONAIS
Pilares
Vigas
Sapatas
Sapatas
Pilares
CEFALOSPORÍNICOS
86 PREVISTO
11 REAL
TENDÊNCIA
138 PREVISTO 8 9 9
41 REAL 7 5
TENDÊNCIA 8 9
504 PREVISTO 16 15 20
46 REAL 0 7
TENDÊNCIA 28 30
PREVISTO
REAL
TENDÊNCIA
PREVISTO
REAL
TENDÊNCIA
642 PREVISTO 24 24 29
87 REAL 7 12 0
TENDÊNCIA 36 39 0
63 PREVISTO 10 10 1
61 REAL 7 6
TENDÊNCIA 9
90 PREVISTO 9 10 10
38 REAL 3 5
TENDÊNCIA 7 7
213 PREVISTO 18 12 8
170 REAL 31 17
TENDÊNCIA 25 24
512 PREVISTO 33 23 30
338 REAL 42 35
TENDÊNCIA 30 30
PREVISTO
REAL
TENDÊNCIA
815 PREVISTO 60 45 48
546 REAL 76 57 0
TENDÊNCIA 62 61 0
TOTAL_GERAL_PRÉ.MOLD 3020 PREVISTO 103 96 95
TOTAL_GERAL_PRÉ.MOLD 1781 REAL 89 77 0
TOTAL_GERAL_TENDÊNCIA TENDÊNCIA 106 110 0
Vigas
Lajes Alveolares
Escadas
TOTAL_ESPINHA CENTRAL
Lajes
ARMAZÉM DE UTILIDADES
Escadas
Sapatas
Pilares
ESPINHA CENTRAL
TOTAL_ARMAZÉM DE UTILIDADES
Sapatas
Pilares
Vigas
S-94 S-95 S-96
Elemento Quant. Semana: 30/08 à 05/09 06/09 à 12/09 13/09 à 19/09
SÓLIDOS 1 4
HORMONAIS 7
118 PREVISTO 4 6 6
69 REAL 8 8
TENDÊNCIA 6 6
225 PREVISTO 6 5 6
94 REAL 13 3
TENDÊNCIA 12 5
404 PREVISTO 28 20 15
174 REAL 13 29
TENDÊNCIA 8 15
79 PREVISTO
38 REAL 26 12
TENDÊNCIA
PREVISTO
REAL
TENDÊNCIA
747 PREVISTO 38 31 27
375 REAL 60 52 0
TENDÊNCIA 26 26 0
90 PREVISTO 10 6 9
30 REAL 2 4 0
TENDÊNCIA 1
213 PREVISTO 7 12 18
52 REAL 16 12 0
TENDÊNCIA 14 7
512 PREVISTO 25 35 40
150 REAL 35 45 0
TENDÊNCIA 30 20
PREVISTO
REAL
TENDÊNCIA
815 PREVISTO 42 53 67
232 REAL 53 61 0
TENDÊNCIA 45 27 0
138 PREVISTO 4
6 REAL 0
TENDÊNCIA 4
504 PREVISTO 16
REAL 0
TENDÊNCIA 8
1364 PREVISTO
REAL
TENDÊNCIA
PREVISTO
REAL
TENDÊNCIA
2006 PREVISTO 20 0 0
6 REAL 0 0 0
TENDÊNCIA 12 0 0
TOTAL_GERAL_PREVISTO 1562 PREVISTO 100 84 94
TOTAL_GERAL_REAL 613 REAL 124 113 0
TOTAL_GERAL_TENDÊNCIA TENDÊNCIA 71 53 0
TOTAL_ESPINHA CENTRAL
TOTAL_PENICILÍNICOS
Pilar
Viga
Laje
Escadas
TOTAL_ALMOXARIFADO/UTILIDADE
S
Pilar
Viga
Lajes Alveolares
Escadas
Viga
Laje
Escadas
Laje Alv.
ALMOXARIFADO/UTILIDADES
ESPINHA CENTRAL
MONTAGEM DE PRÉ MOLDADOS
PENICILÍNICOS
Pilar
MONTAGEM PRÉ-MOLDADOS - PENICILÍNICOS
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Montagem Semana 06-09 à 11-09-21
Montagem Semana 13-09 à 18-09-21
MONTAGEM PRÉ-MOLDADOS - ALMOXARIFADO
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Montagem Semana 06-09 à 11-09-21
Montagem Semana 13-09 à 18-09-21
SAPATAS - ALMOXARIFADO / UTILIDADES
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
PROGRAMAÇÃO
SEMANA 13/09 À 18/09
EXECUTADO
SEMANA 06/09 À 11/09
SAPATAS – CEFALOSPORÍNICOS
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
PROGRAMAÇÃO
SEMANA 13/09 À 18/09
EXECUTADO
SEMANA 06/09 À 11/09
SÓLIDOS 1 – Estruturas Metálicas El. 8,70
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Montado
Programação
13/09 à 19/09
SÓLIDOS 1 – Steel Deck El. 8,70
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Montado
SÓLIDOS 1 – Estruturas Metálicas El. 25,50
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Montado
SÓLIDOS 1 – Steel Deck El. 25,50
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Realizado
Programação
06/09 à 11/09
HORMONAIS – Estruturas Metálicas El. 8,70
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Montado
HORMONAIS – Estruturas Metálicas El. 25,50
Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21
Programação
13/09 à 19/09
Realizado
PRÓXIMAS ATIVIDADES E PONTOS DE ATENÇÃO
Pontos Críticos:
 Liberação de Projetos Pendentes – ESP e ALM
 Liberação de Projetos de Estrut. "In Loco" - SO1 e HOR
 Liberação de Projeto de Alvenaria Armada – SO1 e HOR
Próximas atividades:
 Fabricação de Pré-Moldados – ALM, PEN, CEF e ESP
 Montagem de Pré-Moldados – ALM e PEN
 Capeamento no Steel Deck El. 8.70 – SO1
 Continuação Montagem de Estruturas Metálicas El. 25.50 – HOR
 Montagem de Steel Deck El. 25.50 – HOR
 Concretagem de Viga “in loco” 8,70 – HOR
 Concretagem de Vigas “in loco” El. 0,00 – PEN
 Escavação e Concretagem de Sapatas – ALM
 Escavação, Contenção dos Porões e Concretagem de Sapatas – CEF
 Execução da estrutura dos elevadores – SO1 e HOR
ENGENHARIA
PROJETO EVEREST
PROJETOS – SÓLIDOS I E HORMONAIS
LIBERADO
NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO
NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO
11/set
EDIFICIO
% PENDÊNCIA
DE
ENGENHARIA
STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA
PRÉ-MOLDADOS ELEV.00
ESTRUTURAS IN LOCO ELEV.00
PRÉ-MOLDADOS ELEV.8,70
PRÉ-MOLDADOS ELEV.16,80
PRÉ-MOLDADOS ELEV.25,50
LAJES E VIGAS IN LOCO EIXO H-I 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE AÇO LIBERAÇÃO DOS PROJETOS. 10/07/2021
ALVENARIA EL -7,40 - 25,50
ALVENARIA ELEVADORES 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE MATERIAL LIBERAÇÃO DOS PROJETOS 10/07/2021
EDIFICIO STATUS PENDÊNCIA IMPACTO AÇÃO
PRÉ-MOLDADOS ELEV.00
ESTRUTURAS IN LOCO ELEV.00
VIGAS IN LOCO ELEV.00
PRÉ-MOLDADOS ELEV.8,70
PRÉ-MOLDADOS ELEV.16,80
LAJES ALVEOLAR
VIGAS IN LOCO VIGAS ELEVADORES
PRÉ-MOLDADOS ELEV.25,50
LAJES E VIGAS IN LOCO EIXO H-I 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE AÇO LIBERAÇÃO DOS PROJETOS 10/07/2021
ALVENARIA EL -7,40 - 25,50
ALVENARIA ELEVADORES 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE MATERIAL LIBERAÇÃO DOS PROJETOS 10/07/2021
HORMONAIS
DESCRIÇÃO
SOLIDOS1
DESCRIÇÃO
PROJETOS – SÓLIDOS I E HORMONAIS
PROJETOS –PENICILÍNICOS E CEFALOSPORÍNICOS
LIBERADO
NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO
NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO
11/set
EDIFICIO
% PENDÊNCIA
DE
ENGENHARIA
STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA
PRÉ-MOLDADOS ELEV.00
PRÉ-MOLDADOS ELEV.8,70
PRÉ-MOLDADOS ELEV.16,80
PRÉ-MOLDADOS ELEV.25,50
COMPLEMENTO DE VIGAS 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE AÇO LIBERAÇÃO DOS PROJETOS 15/07/2021
LAJES E VIGAS IN LOCO EIXO H-I 100% LIBERAÇÃO DOS PROJETOS
EDIFICIO STATUS PENDÊNCIA IMPACTO AÇÃO
PRÉ-MOLDADOS ELEV.00
PILAR 70% NÃO LIBERADO
PILARE ESPINHA (PJ-21) E PILARES ESPECIAIS
PK"-22'; PK"-22"; PJ'-23
ATRASO NA ESPINHA E
OCIOSIDADE NA FÁBRICA
LIBERAÇÃO DOS PROJETOS. FOI ENVIADA LISTA DE PROJETOS EM
APROVAÇÃO E NÃO EMITIDOS.
19/08/2021
VIGAS 26% NÃO LIBERADO 19/08/2021
LAJES 21% NÃO LIBERADO 19/08/2021
ESCADA 100% NÃO LIBERADO ESCADA 1 E ESCADA 2 OCIOSIDADE DA FÁBRICA LIBERAÇÃO DOS PROJETOS 19/08/2021
PRÉ-MOLDADOS ELEV.8,70
ESTRUTURA METÁLICA - INSERTS 100% NÃO LIBERADO
PROJETOS DE DETALHES E QUANTIDADES NÃO
EMITIDO
PRODUÇÃO DOS PILARES LIBERAÇÃO DOS PROJETOS 19/08/2021
PRÉ-MOLDADOS ELEV.16,80
PRÉ-MOLDADOS ELEV.25,50
CEFALOSPORINICOS
PENICILINICOS
DESCRIÇÃO
DESCRIÇÃO
PROJETOS –PENICILÍNICOS E CEFALOSPORÍNICOS
202 projetos 87%
13 projetos
6%
16 projetos
7%
PENICILÍNICOS
APROVADO - LO
PARA APROVAÇÃO
NÃO EMITIDO
PROJETOS – ESPINHA CENTRAL PRINCIPAL
LIBERADO
NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO
NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO
11/set
EDIFICIO
% PENDÊNCIA
DE
ENGENHARIA
STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA
PLANTAS, CORTES E DETALHES
BASES E CONTENÇÃO
FUNDAÇÃO 4% PARCIAL
PROJETOS NÃO APROVADOS OU
NÃO EMITIDOS
ATRASO NO PEDIDO DO AÇO E EXECUÇÃO DA ESPINHA
LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES
INFORMADAS PELA GTP 16/01/21
PROJETOS DE ARMAÇÃO LIBERADOS EM 27/01/21. PENDENTE PROJETOS
S1.20X1.20
10/07/2021
CONTENÇÃO 50% NÃO LIBERADO
AGUARDANDO VALIDAÇÃO DO PROJETO
ELABORADO PELA GEOMEC
ATRASO NA EXECUÇÃO DA CONTENÇÃO E FUNDAÇÃO VALIDAR PROJETO ENVIADO PELA OEC / GEOMEC 10/07/2021
PRÉ-MOLDADOS ELEV.-4,40
PILAR 29% PARCIAL PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO E MONTAGEM DOS PILARES
LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES
INFORMADAS PELA GTP 16/01/21. . PROJETOS EMITIDOS EM 01/03,
EXCETO NO TRECHO ADJACENTE À HORMONAIS. PENDENTE PJ21 E PILARES
DOS TRECHOS ENTRE PRÉDIOS. LIBERADOS 22 PILARES 40X40 PORÉM COM
INSERTS NÃO PREVISTOS E COM PROJETOS NÃO LIBERADOS. INSERTS
LIBERADOS 30/06/21
10/07/2021
VIGAS 8% PARCIAL PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO E MONTAGEM DAS VIGAS
LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES
INFORMADAS PELA GTP 16/01/21
24/07/2021
ESTRUTURA METALICA 50% NÃO LIBERADO
INSERTS ESTRUTURA METÁLICA
PENDENTE APROVAÇÃO PROJETOS DE
DETALHES E QUANTIDADES
ATRASO NA COMPRA DO MATERIAL E FABRICAÇÃO DOS
PILARES
LIBERAÇÃO DE PROJETOS 10/07/2021
CAPEAMENTO 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NO PEDIDO DO AÇO LIBERAÇÃO DE PROJETOS 10/07/2021
PRÉ-MOLDADOS ELEV.0,00
VIGAS 7% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 31/07/2021
PRÉ-MOLDADOS ELEV.8,70
VIGAS 15% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 04/09/2021
PRÉ-MOLDADOS ELEV.16,80
VIGAS 9% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 04/09/2021
PRÉ-MOLDADOS ELEV.25,50
VIGAS 2,54% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 04/09/2021
ESPINHA
DESCRIÇÃO
PROJETOS – ESPINHA CENTRAL AMPLIAÇÃO
LIBERADO
NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO
NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO
11/set
EDIFICIO
% PENDÊNCIA
DE
ENGENHARIA
STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA
AMPLIAÇÃO NÃO LIBERADO PROJETOS NÃO EMITIDOS
DATA CONSIDERADA PARA O REPLANEJAMENTO 11/06.
DATA PARA EMISSÃO DOS PROJETOS 11/04. LIBERADOS PROJETOS
PRELIMINARES 14/04. NOVAS DATAS REPLANEJAMENTO 31/08
FUNDAÇÃO 100% NÃO LIBERADO PROJETOS NÃO APROVADOS PLANEJAMENTO, COMPRA DE AÇO E EXECUÇÃO LIBERAÇÃO DE PROJETOS 31/08/2021
PRÉ-MOLDADOS GERAL
PILAR 98% PARCIAL PROJETOS NÃO APROVADOS PLANEJAMENTO, COMPRA DE AÇO E EXECUÇÃO LIBERAÇÃO DE PROJETOS 04/09/2021
VIGA 50% PARCIAL PROJETOS NÃO APROVADOS PLANEJAMENTO, COMPRA DE AÇO E EXECUÇÃO LIBERAÇÃO DE PROJETOS 04/09/2021
IN LOCO
CAPEAMENTO 100%
VIGAS IN LOCO 91%
ESPINHA
DESCRIÇÃO
PROJETOS – ESPINHA CENTRAL PRINCIPAL E AMPLIAÇÃO
223 projetos
72%
36 projetos
12%
49 projetos 16%
ESPINHA CENTRAL
APROVADO - LO
PARA APROVAÇÃO
NÃO EMITIDO
PROJETOS – ADM/LAB E ALM
LIBERADO
NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO
NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO
11/set
EDIFICIO
% PENDÊNCIA
DE
ENGENHARIA
STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA
FUNDAÇÃO 9% NÃO LIBERADO
PROJETOS DE FORMA E ARMAÇÃO LIBERADOS.
PENDENTE PLANTA DE LOCAÇÃO DAS
FUNDAÇÕES
ATRASO NO INÍCIO DA ESCAVAÇÃO
LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES
INFORMADA PELA GTP 16/01/21.
LIBERAÇÃO DOS PROJETOS CONFORME ATA 21.01 PARA DIA 05/02
15/07/2021
PRÉ-MOLDADOS ELEV.00
PILAR 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 15/08/2021
VIGAS 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 15/08/2021
VIGAS IN LOCO 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 31/08/2021
LAJES ALVEOLARES 100% NÃO LIBERADO
AGUARDANDO A LIBERAÇÃO DO PROJETO PARA
EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO
DAS LAJES
ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO
DAS LAJES
LIBERAÇÃO DOS PROJETOS 15/07/2021
CAPEAMENTO 100% 31/08/2021
PRÉ-MOLDADOS ELEV.8,70
VIGAS 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 15/08/2021
VIGAS IN LOCO 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 31/08/2021
LAJES ALVEOLARES 100% NÃO LIBERADO
AGUARDANDO A LIBERAÇÃO DO PROJETO PARA
EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO
DAS LAJES
ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO
DAS LAJES
LIBERAÇÃO DOS PROJETOS 15/07/2021
PRÉ-MOLDADOS ELEV.16,80
LAJES ALVEOLARES 100% NÃO LIBERADO
AGUARDANDO A LIBERAÇÃO DO PROJETO PARA
EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO
DAS LAJES
ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO
DAS LAJES
LIBERAÇÃO DOS PROJETOS 15/07/2021
PRÉ-MOLDADOS ELEV.25,50
LAJES ALVEOLARES 100% NÃO LIBERADO
AGUARDANDO A LIBERAÇÃO DO PROJETO PARA
EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO
DAS LAJES
ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO
DAS LAJES
LIBERAÇÃO DOS PROJETOS 15/07/2021
EDIFICIO STATUS PENDÊNCIA IMPACTO AÇÃO
FUNDAÇÃO
PRÉ-MOLDADOS ELEV.00
PLANTAS E CORTES 45% PARCIAL PROJETOS NÃO EMITIDOS PROGRAMAÇÃO DE MONTAGEM LIBERAÇÃO DOS PROJETOS 10/07/2021
PILARES 0% PARCIAL -
ALTERAÇÃO NA SEQUÊNCIA DE MONTAGEM EM FUNÇÃO
DO ATRASO NA APROVAÇÃO DOS PROJETOS DE FACHADA
-
10/07/2021
VIGAS 14% PARCIAL PROJETOS NÃO EMITIDOS PEDIDO DE AÇO E AJUSTE DAS FORMAS DA FÁBRICA
LIBERAÇÃO DOS PROJETOS. PREMISSA ADITIVO 08/02. PREVISÃO 19/04.
APROVADO 102/208P VIGAS 10/07/2021
LAJES
0% PARCIAL -
ALTERAÇÃO NA SEQUÊNCIA DE MONTAGEM EM FUNÇÃO
DO ATRASO NA APROVAÇÃO DOS PROJETOS DE FACHADA
-
10/07/2021
ADM/LABORATORIO
ALM
DESCRIÇÃO
DESCRIÇÃO
PROJETOS – ADM/LAB E ALM/UTILIDADES
REQUEST FOR INFORMATION – RFI’S NÃO ATENDIDAS
REQUEST FOR INFORMATION – RFI’S PARCIALMENTE ATENDIDAS E ATENDIDAS
PILARES – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
PILAR LIBERADO PARA CONSTRUÇÃO (19)
PILAR SEM PROJETO (27)
PILAR COM PROJETO PRELIMINAR (37)
VIGAS TÉRREO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
VIGA LIBERADA PARA CONSTRUÇÃO
VIGA SEM PROJETO
VIGA COM PROJETO PRELIMINAR
VIGA LIBERADA EM HOLD(2)
VIGAS 1º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS- CEFALOSPORÍNICOS 16/08/2021
LEGENDA
VIGA LIBERADA PARA CONSTRUÇÃO
VIGA SEM PROJETO
VIGA COM PROJETO PRELIMINAR
VIGA LIBERADA EM HOLD(2)
VIGAS 2º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
VIGA LIBERADA PARA CONSTRUÇÃO
VIGA SEM PROJETO
VIGA COM PROJETO PRELIMINAR
VIGA LIBERADA EM HOLD
VIGAS N. 25,50– MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
VIGA LIBERADA PARA CONSTRUÇÃO
VIGA SEM PROJETO
VIGA COM PROJETO PRELIMINAR
VIGA LIBERADA EM HOLD
LAJES TÉRREO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
LAJE LIBERADA PARA CONSTRUÇÃO
LAJE SEM PROJETO
LAJE COM PROJETO PRELIMINAR
LAJE LIBERADA EM HOLD
LAJES 1º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
LAJE LIBERADA PARA CONSTRUÇÃO
LAJE SEM PROJETO
LAJE COM PROJETO PRELIMINAR
LAJE LIBERADA EM HOLD
LAJEA 2º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
LAJE LIBERADA PARA CONSTRUÇÃO
LAJE SEM PROJETO
LAJE COM PROJETO PRELIMINAR
LAJE LIBERADA EM HOLD
LAJEA N. 25,50 – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021
LEGENDA
LAJE LIBERADA PARA CONSTRUÇÃO
LAJE SEM PROJETO
LAJE COM PROJETO PRELIMINAR
LAJE LIBERADA EM HOLD
ANÁLISE DO PERÍODO
Pontos de Atenção Próximas Ações
 Emissão dos projetos pendentes de todos os
prédios;
 Aprovação da locação dos nichos para fixação
dos painéis de fachada do ALM;
 Aprovação do projeto de contenção entre
ESP/LAB e emissão do projeto de contenção
entre ESP/UTI;
 Revisão do projeto de Inserts do ALM e
confirmação das divergências encontradas;
 Definição da solução da estrutura da extração
de fumaça;
 Liberação dos projetos dos pré-moldados de
CEF;
 Emissão dos projetos das estruturas
auxiliares e validação das cargas nas vigas
pré-moldadas;
 Emissão dos projetos estruturais dos
demais painéis pré-moldados de fachada;
 Alteração do projeto do corredor de
visitação na região da escada metálica
devido à mudança no projeto;

Mais conteúdo relacionado

Destaque

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Destaque (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Apresentação de Planejamento Reunião Semanal - 16_09_21.pdf

  • 4. SEGURANÇA DO TRABALHO Acidentes CPT Acidentes SPT 4 0 OCORRÊNCIAS ACIDENTE DE TRABALHO - 2021 Dias sem ocorrências de acidentes SPT / CPT 46 (11.09.21) OCORRÊNCIAS NA SEMANA ACIDENTES / INCIDENTES 1 OPORTUNIDADES DE MELHORIA POSITIVA 0 0 OBSERVAÇÕES DE SMS OMINI OMINI 0
  • 5. Ago/21 Acum. Projeto 00 00 00 00 00 04 01 13 43* - SEGURANÇA DO TRABALHO * Informações até 04.09.2021 (OMINI, LV OECI)
  • 6. DATA DO INCIDENTE 08/08/2021 HORÁRIO DO INCIDENTE 17h40’ LOCAL DO INCIDENTE Entre Hormonais e Cefalosporinicos DESCRIÇÃO DO INCIDENTE O motorista estava realizando manobra de marcha ré, quando o sol refletiu no retrovisor e ao perceber a trasseira do caminhão já havia ultrapassado o talude. AÇÃO CORRETIVAS: DDS; Continuidade do cronograma de treinamento de direção defensiva; Identificação de sinaleiros para cada equipamento; Continuidade de melhoria da sinalização. SEGURANÇA DO TRABALHO
  • 7. SEGURANÇA DO TRABALHO 1- Continuidade na manutenção da organização, arrumação e limpeza; 2- Instalação de caixa de sugestões; 3- Continuidade da sinalização das periferias contra risco de queda; 4- Verificação das proteção de vergalhões ou dobra; 5- Inspeção de máquinas e equipamentos (branco); 1 2 3 4 5
  • 8. SEGURANÇA DO TRABALHO 6- Mapa de Risco; 7-Instalação de placa de orientação; 8- Continuidade na organização do depósito de vergalhões; 9- Treinamento da equipe de segurança; NR’s, PAE. 6 8 7 9
  • 9. SAÚDE OCUPACIONAL ENFERMAGEM MÉDICO 0 63757 65 3 ATENDIMENTOS Notas: 1- Atendimentos médicos incluem: Atendimentos gerais, ocupacionais, urgência e emergência e covid-19. 2- Atendimentos de enfermagem incluem: Atendimentos gerais, ocupacionais, urgência e emergência covid-19 e aferições de pressão arterial.
  • 11. SAÚDE OCUPACIONAL 1. Treinamento Promoção de Saúde - Hipertensão Arterial 2. Treinamento Primeiros Socorros – Integração 3. Ação COVID-19 / Uso das plaquinhas no refeitório para zeladores 1 2 3
  • 12. MEIO AMBIENTE 1. Coleta e destinação de resíduos de madeira, resíduos de construção civil, não reciclável; 2. Coleta e destinação de efluentes; 3. Coleta e destinação de resíduos de metais para reciclagem; 4. Melhorias de segurança nas caixas de sedimentação do lava rodas. 2 3 4 1
  • 15. Semana 95 MONTAGEM DE SEGUNDO TRAMO - PENICILÍNICOS AVANÇO NA MONTAGEM DE PRÉ-MOLDADOS - ALMOXARIFADO AVANÇO DA MONTAGEM DE STEEL DECK NÍVEL 25.50 – SÓLIDOS 1 MONTAGEM DE VIGAS METÁLICAS NÍVEL 25.50 – HORMONAIS
  • 16. ÍNDICES DE PRÉ-MOLDADOS NA SEMANA OCIOSIDADES FORMA: 48M³ (DUAS FORMAS DE PILARES E UMA DE ESCADA) AGUARDANDO LIBERAÇÃO DE PROJETO TIPO QUANTIDADE (UND) VOLUME (m³) PILARES 12 106,39 VIGAS 30 126,34 LAJES 35 188,92 ESCADA 0 0,00 TOTAL 77 421,65 FABRICAÇÃO TIPO QUANTIDADE (UND) VOLUME (m³) PILARES 12 132,85 VIGAS 15 128,17 LAJES 74 373,92 LAJES ALV. 12 16,08 ESCADA 0 0,00 TOTAL 113 651,02 MONTAGEM
  • 18. S-94 S-95 S-96 Elemento Quant. Semana: 30/08 à 05/09 06/09 à 12/09 13/09 à 19/09 59 PREVISTO 56 REAL 1 TENDÊNCIA 1 118 PREVISTO 118 REAL 0 0 TENDÊNCIA 225 PREVISTO 9 15 8 219 REAL 0 6 TENDÊNCIA 2 6 404 PREVISTO 3 1 392 REAL 1 0 TENDÊNCIA 3 1 12 PREVISTO 12 REAL TENDÊNCIA 759 PREVISTO 12 16 8 741 REAL 1 6 0 TENDÊNCIA 5 7 0 59 PREVISTO 22 REAL 2 2 TENDÊNCIA 126 PREVISTO 21 REAL 3 2 z TENDÊNCIA 239 PREVISTO 34 REAL 0 0 TENDÊNCIA 427 PREVISTO 7 11 10 352 REAL 2 0 TENDÊNCIA 3 3 12 PREVISTO 0 REAL TENDÊNCIA 804 PREVISTO 7 11 10 407 REAL 5 2 0 TENDÊNCIA 3 3 0 Lajes Escadas TOTAL_CEFALOSPORÍNICOS FABRICAÇÃO DE PRÉ-MOLDADOS / SAPATAS Vigas Lajes Escadas TOTAL_PENICILÍNICOS PENICILÍNICOS SÓLIDOS HORMONAIS Pilares Vigas Sapatas Sapatas Pilares CEFALOSPORÍNICOS
  • 19. 86 PREVISTO 11 REAL TENDÊNCIA 138 PREVISTO 8 9 9 41 REAL 7 5 TENDÊNCIA 8 9 504 PREVISTO 16 15 20 46 REAL 0 7 TENDÊNCIA 28 30 PREVISTO REAL TENDÊNCIA PREVISTO REAL TENDÊNCIA 642 PREVISTO 24 24 29 87 REAL 7 12 0 TENDÊNCIA 36 39 0 63 PREVISTO 10 10 1 61 REAL 7 6 TENDÊNCIA 9 90 PREVISTO 9 10 10 38 REAL 3 5 TENDÊNCIA 7 7 213 PREVISTO 18 12 8 170 REAL 31 17 TENDÊNCIA 25 24 512 PREVISTO 33 23 30 338 REAL 42 35 TENDÊNCIA 30 30 PREVISTO REAL TENDÊNCIA 815 PREVISTO 60 45 48 546 REAL 76 57 0 TENDÊNCIA 62 61 0 TOTAL_GERAL_PRÉ.MOLD 3020 PREVISTO 103 96 95 TOTAL_GERAL_PRÉ.MOLD 1781 REAL 89 77 0 TOTAL_GERAL_TENDÊNCIA TENDÊNCIA 106 110 0 Vigas Lajes Alveolares Escadas TOTAL_ESPINHA CENTRAL Lajes ARMAZÉM DE UTILIDADES Escadas Sapatas Pilares ESPINHA CENTRAL TOTAL_ARMAZÉM DE UTILIDADES Sapatas Pilares Vigas
  • 20. S-94 S-95 S-96 Elemento Quant. Semana: 30/08 à 05/09 06/09 à 12/09 13/09 à 19/09 SÓLIDOS 1 4 HORMONAIS 7 118 PREVISTO 4 6 6 69 REAL 8 8 TENDÊNCIA 6 6 225 PREVISTO 6 5 6 94 REAL 13 3 TENDÊNCIA 12 5 404 PREVISTO 28 20 15 174 REAL 13 29 TENDÊNCIA 8 15 79 PREVISTO 38 REAL 26 12 TENDÊNCIA PREVISTO REAL TENDÊNCIA 747 PREVISTO 38 31 27 375 REAL 60 52 0 TENDÊNCIA 26 26 0 90 PREVISTO 10 6 9 30 REAL 2 4 0 TENDÊNCIA 1 213 PREVISTO 7 12 18 52 REAL 16 12 0 TENDÊNCIA 14 7 512 PREVISTO 25 35 40 150 REAL 35 45 0 TENDÊNCIA 30 20 PREVISTO REAL TENDÊNCIA 815 PREVISTO 42 53 67 232 REAL 53 61 0 TENDÊNCIA 45 27 0 138 PREVISTO 4 6 REAL 0 TENDÊNCIA 4 504 PREVISTO 16 REAL 0 TENDÊNCIA 8 1364 PREVISTO REAL TENDÊNCIA PREVISTO REAL TENDÊNCIA 2006 PREVISTO 20 0 0 6 REAL 0 0 0 TENDÊNCIA 12 0 0 TOTAL_GERAL_PREVISTO 1562 PREVISTO 100 84 94 TOTAL_GERAL_REAL 613 REAL 124 113 0 TOTAL_GERAL_TENDÊNCIA TENDÊNCIA 71 53 0 TOTAL_ESPINHA CENTRAL TOTAL_PENICILÍNICOS Pilar Viga Laje Escadas TOTAL_ALMOXARIFADO/UTILIDADE S Pilar Viga Lajes Alveolares Escadas Viga Laje Escadas Laje Alv. ALMOXARIFADO/UTILIDADES ESPINHA CENTRAL MONTAGEM DE PRÉ MOLDADOS PENICILÍNICOS Pilar
  • 21. MONTAGEM PRÉ-MOLDADOS - PENICILÍNICOS Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Montagem Semana 06-09 à 11-09-21 Montagem Semana 13-09 à 18-09-21
  • 22. MONTAGEM PRÉ-MOLDADOS - ALMOXARIFADO Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Montagem Semana 06-09 à 11-09-21 Montagem Semana 13-09 à 18-09-21
  • 23. SAPATAS - ALMOXARIFADO / UTILIDADES Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 PROGRAMAÇÃO SEMANA 13/09 À 18/09 EXECUTADO SEMANA 06/09 À 11/09
  • 24. SAPATAS – CEFALOSPORÍNICOS Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 PROGRAMAÇÃO SEMANA 13/09 À 18/09 EXECUTADO SEMANA 06/09 À 11/09
  • 25. SÓLIDOS 1 – Estruturas Metálicas El. 8,70 Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Montado Programação 13/09 à 19/09
  • 26. SÓLIDOS 1 – Steel Deck El. 8,70 Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Montado
  • 27. SÓLIDOS 1 – Estruturas Metálicas El. 25,50 Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Montado
  • 28. SÓLIDOS 1 – Steel Deck El. 25,50 Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Realizado Programação 06/09 à 11/09
  • 29. HORMONAIS – Estruturas Metálicas El. 8,70 Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Montado
  • 30. HORMONAIS – Estruturas Metálicas El. 25,50 Programação 17.05.21 a 29.05.21 Programação 24.05.21 a 05.06.21 Programação 13/09 à 19/09 Realizado
  • 31. PRÓXIMAS ATIVIDADES E PONTOS DE ATENÇÃO Pontos Críticos:  Liberação de Projetos Pendentes – ESP e ALM  Liberação de Projetos de Estrut. "In Loco" - SO1 e HOR  Liberação de Projeto de Alvenaria Armada – SO1 e HOR Próximas atividades:  Fabricação de Pré-Moldados – ALM, PEN, CEF e ESP  Montagem de Pré-Moldados – ALM e PEN  Capeamento no Steel Deck El. 8.70 – SO1  Continuação Montagem de Estruturas Metálicas El. 25.50 – HOR  Montagem de Steel Deck El. 25.50 – HOR  Concretagem de Viga “in loco” 8,70 – HOR  Concretagem de Vigas “in loco” El. 0,00 – PEN  Escavação e Concretagem de Sapatas – ALM  Escavação, Contenção dos Porões e Concretagem de Sapatas – CEF  Execução da estrutura dos elevadores – SO1 e HOR
  • 33. PROJETOS – SÓLIDOS I E HORMONAIS LIBERADO NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO 11/set EDIFICIO % PENDÊNCIA DE ENGENHARIA STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA PRÉ-MOLDADOS ELEV.00 ESTRUTURAS IN LOCO ELEV.00 PRÉ-MOLDADOS ELEV.8,70 PRÉ-MOLDADOS ELEV.16,80 PRÉ-MOLDADOS ELEV.25,50 LAJES E VIGAS IN LOCO EIXO H-I 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE AÇO LIBERAÇÃO DOS PROJETOS. 10/07/2021 ALVENARIA EL -7,40 - 25,50 ALVENARIA ELEVADORES 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE MATERIAL LIBERAÇÃO DOS PROJETOS 10/07/2021 EDIFICIO STATUS PENDÊNCIA IMPACTO AÇÃO PRÉ-MOLDADOS ELEV.00 ESTRUTURAS IN LOCO ELEV.00 VIGAS IN LOCO ELEV.00 PRÉ-MOLDADOS ELEV.8,70 PRÉ-MOLDADOS ELEV.16,80 LAJES ALVEOLAR VIGAS IN LOCO VIGAS ELEVADORES PRÉ-MOLDADOS ELEV.25,50 LAJES E VIGAS IN LOCO EIXO H-I 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE AÇO LIBERAÇÃO DOS PROJETOS 10/07/2021 ALVENARIA EL -7,40 - 25,50 ALVENARIA ELEVADORES 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE MATERIAL LIBERAÇÃO DOS PROJETOS 10/07/2021 HORMONAIS DESCRIÇÃO SOLIDOS1 DESCRIÇÃO
  • 34. PROJETOS – SÓLIDOS I E HORMONAIS
  • 35. PROJETOS –PENICILÍNICOS E CEFALOSPORÍNICOS LIBERADO NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO 11/set EDIFICIO % PENDÊNCIA DE ENGENHARIA STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA PRÉ-MOLDADOS ELEV.00 PRÉ-MOLDADOS ELEV.8,70 PRÉ-MOLDADOS ELEV.16,80 PRÉ-MOLDADOS ELEV.25,50 COMPLEMENTO DE VIGAS 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS COMPRA DE AÇO LIBERAÇÃO DOS PROJETOS 15/07/2021 LAJES E VIGAS IN LOCO EIXO H-I 100% LIBERAÇÃO DOS PROJETOS EDIFICIO STATUS PENDÊNCIA IMPACTO AÇÃO PRÉ-MOLDADOS ELEV.00 PILAR 70% NÃO LIBERADO PILARE ESPINHA (PJ-21) E PILARES ESPECIAIS PK"-22'; PK"-22"; PJ'-23 ATRASO NA ESPINHA E OCIOSIDADE NA FÁBRICA LIBERAÇÃO DOS PROJETOS. FOI ENVIADA LISTA DE PROJETOS EM APROVAÇÃO E NÃO EMITIDOS. 19/08/2021 VIGAS 26% NÃO LIBERADO 19/08/2021 LAJES 21% NÃO LIBERADO 19/08/2021 ESCADA 100% NÃO LIBERADO ESCADA 1 E ESCADA 2 OCIOSIDADE DA FÁBRICA LIBERAÇÃO DOS PROJETOS 19/08/2021 PRÉ-MOLDADOS ELEV.8,70 ESTRUTURA METÁLICA - INSERTS 100% NÃO LIBERADO PROJETOS DE DETALHES E QUANTIDADES NÃO EMITIDO PRODUÇÃO DOS PILARES LIBERAÇÃO DOS PROJETOS 19/08/2021 PRÉ-MOLDADOS ELEV.16,80 PRÉ-MOLDADOS ELEV.25,50 CEFALOSPORINICOS PENICILINICOS DESCRIÇÃO DESCRIÇÃO
  • 36. PROJETOS –PENICILÍNICOS E CEFALOSPORÍNICOS 202 projetos 87% 13 projetos 6% 16 projetos 7% PENICILÍNICOS APROVADO - LO PARA APROVAÇÃO NÃO EMITIDO
  • 37. PROJETOS – ESPINHA CENTRAL PRINCIPAL LIBERADO NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO 11/set EDIFICIO % PENDÊNCIA DE ENGENHARIA STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA PLANTAS, CORTES E DETALHES BASES E CONTENÇÃO FUNDAÇÃO 4% PARCIAL PROJETOS NÃO APROVADOS OU NÃO EMITIDOS ATRASO NO PEDIDO DO AÇO E EXECUÇÃO DA ESPINHA LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES INFORMADAS PELA GTP 16/01/21 PROJETOS DE ARMAÇÃO LIBERADOS EM 27/01/21. PENDENTE PROJETOS S1.20X1.20 10/07/2021 CONTENÇÃO 50% NÃO LIBERADO AGUARDANDO VALIDAÇÃO DO PROJETO ELABORADO PELA GEOMEC ATRASO NA EXECUÇÃO DA CONTENÇÃO E FUNDAÇÃO VALIDAR PROJETO ENVIADO PELA OEC / GEOMEC 10/07/2021 PRÉ-MOLDADOS ELEV.-4,40 PILAR 29% PARCIAL PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO E MONTAGEM DOS PILARES LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES INFORMADAS PELA GTP 16/01/21. . PROJETOS EMITIDOS EM 01/03, EXCETO NO TRECHO ADJACENTE À HORMONAIS. PENDENTE PJ21 E PILARES DOS TRECHOS ENTRE PRÉDIOS. LIBERADOS 22 PILARES 40X40 PORÉM COM INSERTS NÃO PREVISTOS E COM PROJETOS NÃO LIBERADOS. INSERTS LIBERADOS 30/06/21 10/07/2021 VIGAS 8% PARCIAL PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO E MONTAGEM DAS VIGAS LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES INFORMADAS PELA GTP 16/01/21 24/07/2021 ESTRUTURA METALICA 50% NÃO LIBERADO INSERTS ESTRUTURA METÁLICA PENDENTE APROVAÇÃO PROJETOS DE DETALHES E QUANTIDADES ATRASO NA COMPRA DO MATERIAL E FABRICAÇÃO DOS PILARES LIBERAÇÃO DE PROJETOS 10/07/2021 CAPEAMENTO 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NO PEDIDO DO AÇO LIBERAÇÃO DE PROJETOS 10/07/2021 PRÉ-MOLDADOS ELEV.0,00 VIGAS 7% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 31/07/2021 PRÉ-MOLDADOS ELEV.8,70 VIGAS 15% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 04/09/2021 PRÉ-MOLDADOS ELEV.16,80 VIGAS 9% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 04/09/2021 PRÉ-MOLDADOS ELEV.25,50 VIGAS 2,54% NÃO LIBERADO PROJETOS NÃO APROVADOS ATRASO NA FABRICAÇÃO DAS VIGAS LIBERAÇÃO DOS PROJETOS 04/09/2021 ESPINHA DESCRIÇÃO
  • 38. PROJETOS – ESPINHA CENTRAL AMPLIAÇÃO LIBERADO NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO 11/set EDIFICIO % PENDÊNCIA DE ENGENHARIA STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA AMPLIAÇÃO NÃO LIBERADO PROJETOS NÃO EMITIDOS DATA CONSIDERADA PARA O REPLANEJAMENTO 11/06. DATA PARA EMISSÃO DOS PROJETOS 11/04. LIBERADOS PROJETOS PRELIMINARES 14/04. NOVAS DATAS REPLANEJAMENTO 31/08 FUNDAÇÃO 100% NÃO LIBERADO PROJETOS NÃO APROVADOS PLANEJAMENTO, COMPRA DE AÇO E EXECUÇÃO LIBERAÇÃO DE PROJETOS 31/08/2021 PRÉ-MOLDADOS GERAL PILAR 98% PARCIAL PROJETOS NÃO APROVADOS PLANEJAMENTO, COMPRA DE AÇO E EXECUÇÃO LIBERAÇÃO DE PROJETOS 04/09/2021 VIGA 50% PARCIAL PROJETOS NÃO APROVADOS PLANEJAMENTO, COMPRA DE AÇO E EXECUÇÃO LIBERAÇÃO DE PROJETOS 04/09/2021 IN LOCO CAPEAMENTO 100% VIGAS IN LOCO 91% ESPINHA DESCRIÇÃO
  • 39. PROJETOS – ESPINHA CENTRAL PRINCIPAL E AMPLIAÇÃO 223 projetos 72% 36 projetos 12% 49 projetos 16% ESPINHA CENTRAL APROVADO - LO PARA APROVAÇÃO NÃO EMITIDO
  • 40. PROJETOS – ADM/LAB E ALM LIBERADO NÃO LIBERADO OU PARCIAL/IMPACTO IMEDIATO NÃO LIBERADO OU PARCIAL/IMPACTO PRÓXIMO 11/set EDIFICIO % PENDÊNCIA DE ENGENHARIA STATUS PENDÊNCIA IMPACTO AÇÃO DATA CARTA FUNDAÇÃO 9% NÃO LIBERADO PROJETOS DE FORMA E ARMAÇÃO LIBERADOS. PENDENTE PLANTA DE LOCAÇÃO DAS FUNDAÇÕES ATRASO NO INÍCIO DA ESCAVAÇÃO LIBERAÇÃO DO PEDIDO DO AÇO COM BASE NAS QUANTIDADES INFORMADA PELA GTP 16/01/21. LIBERAÇÃO DOS PROJETOS CONFORME ATA 21.01 PARA DIA 05/02 15/07/2021 PRÉ-MOLDADOS ELEV.00 PILAR 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 15/08/2021 VIGAS 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 15/08/2021 VIGAS IN LOCO 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 31/08/2021 LAJES ALVEOLARES 100% NÃO LIBERADO AGUARDANDO A LIBERAÇÃO DO PROJETO PARA EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO DAS LAJES ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO DAS LAJES LIBERAÇÃO DOS PROJETOS 15/07/2021 CAPEAMENTO 100% 31/08/2021 PRÉ-MOLDADOS ELEV.8,70 VIGAS 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 15/08/2021 VIGAS IN LOCO 100% NÃO LIBERADO PROJETOS NÃO EMITIDOS ATRASO NA FABRICAÇÃO DAS FORMAS E PEÇAS LIBERAÇÃO DOS PROJETOS 31/08/2021 LAJES ALVEOLARES 100% NÃO LIBERADO AGUARDANDO A LIBERAÇÃO DO PROJETO PARA EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO DAS LAJES ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO DAS LAJES LIBERAÇÃO DOS PROJETOS 15/07/2021 PRÉ-MOLDADOS ELEV.16,80 LAJES ALVEOLARES 100% NÃO LIBERADO AGUARDANDO A LIBERAÇÃO DO PROJETO PARA EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO DAS LAJES ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO DAS LAJES LIBERAÇÃO DOS PROJETOS 15/07/2021 PRÉ-MOLDADOS ELEV.25,50 LAJES ALVEOLARES 100% NÃO LIBERADO AGUARDANDO A LIBERAÇÃO DO PROJETO PARA EMISSÃO DO CRONOGRAMA DE FABRICAÇÃO DAS LAJES ATRASO NA ELABORAÇÃO DOS PROJETOS E FABRICAÇÃO DAS LAJES LIBERAÇÃO DOS PROJETOS 15/07/2021 EDIFICIO STATUS PENDÊNCIA IMPACTO AÇÃO FUNDAÇÃO PRÉ-MOLDADOS ELEV.00 PLANTAS E CORTES 45% PARCIAL PROJETOS NÃO EMITIDOS PROGRAMAÇÃO DE MONTAGEM LIBERAÇÃO DOS PROJETOS 10/07/2021 PILARES 0% PARCIAL - ALTERAÇÃO NA SEQUÊNCIA DE MONTAGEM EM FUNÇÃO DO ATRASO NA APROVAÇÃO DOS PROJETOS DE FACHADA - 10/07/2021 VIGAS 14% PARCIAL PROJETOS NÃO EMITIDOS PEDIDO DE AÇO E AJUSTE DAS FORMAS DA FÁBRICA LIBERAÇÃO DOS PROJETOS. PREMISSA ADITIVO 08/02. PREVISÃO 19/04. APROVADO 102/208P VIGAS 10/07/2021 LAJES 0% PARCIAL - ALTERAÇÃO NA SEQUÊNCIA DE MONTAGEM EM FUNÇÃO DO ATRASO NA APROVAÇÃO DOS PROJETOS DE FACHADA - 10/07/2021 ADM/LABORATORIO ALM DESCRIÇÃO DESCRIÇÃO
  • 41. PROJETOS – ADM/LAB E ALM/UTILIDADES
  • 42. REQUEST FOR INFORMATION – RFI’S NÃO ATENDIDAS
  • 43. REQUEST FOR INFORMATION – RFI’S PARCIALMENTE ATENDIDAS E ATENDIDAS
  • 44. PILARES – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA PILAR LIBERADO PARA CONSTRUÇÃO (19) PILAR SEM PROJETO (27) PILAR COM PROJETO PRELIMINAR (37)
  • 45. VIGAS TÉRREO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA VIGA LIBERADA PARA CONSTRUÇÃO VIGA SEM PROJETO VIGA COM PROJETO PRELIMINAR VIGA LIBERADA EM HOLD(2)
  • 46. VIGAS 1º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS- CEFALOSPORÍNICOS 16/08/2021 LEGENDA VIGA LIBERADA PARA CONSTRUÇÃO VIGA SEM PROJETO VIGA COM PROJETO PRELIMINAR VIGA LIBERADA EM HOLD(2)
  • 47. VIGAS 2º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA VIGA LIBERADA PARA CONSTRUÇÃO VIGA SEM PROJETO VIGA COM PROJETO PRELIMINAR VIGA LIBERADA EM HOLD
  • 48. VIGAS N. 25,50– MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA VIGA LIBERADA PARA CONSTRUÇÃO VIGA SEM PROJETO VIGA COM PROJETO PRELIMINAR VIGA LIBERADA EM HOLD
  • 49. LAJES TÉRREO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA LAJE LIBERADA PARA CONSTRUÇÃO LAJE SEM PROJETO LAJE COM PROJETO PRELIMINAR LAJE LIBERADA EM HOLD
  • 50. LAJES 1º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA LAJE LIBERADA PARA CONSTRUÇÃO LAJE SEM PROJETO LAJE COM PROJETO PRELIMINAR LAJE LIBERADA EM HOLD
  • 51. LAJEA 2º PAVIMENTO – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA LAJE LIBERADA PARA CONSTRUÇÃO LAJE SEM PROJETO LAJE COM PROJETO PRELIMINAR LAJE LIBERADA EM HOLD
  • 52. LAJEA N. 25,50 – MAPA SITUAÇÃO DOS PROJETOS – CEFALOSPORÍNICOS 16/08/2021 LEGENDA LAJE LIBERADA PARA CONSTRUÇÃO LAJE SEM PROJETO LAJE COM PROJETO PRELIMINAR LAJE LIBERADA EM HOLD
  • 53. ANÁLISE DO PERÍODO Pontos de Atenção Próximas Ações  Emissão dos projetos pendentes de todos os prédios;  Aprovação da locação dos nichos para fixação dos painéis de fachada do ALM;  Aprovação do projeto de contenção entre ESP/LAB e emissão do projeto de contenção entre ESP/UTI;  Revisão do projeto de Inserts do ALM e confirmação das divergências encontradas;  Definição da solução da estrutura da extração de fumaça;  Liberação dos projetos dos pré-moldados de CEF;  Emissão dos projetos das estruturas auxiliares e validação das cargas nas vigas pré-moldadas;  Emissão dos projetos estruturais dos demais painéis pré-moldados de fachada;  Alteração do projeto do corredor de visitação na região da escada metálica devido à mudança no projeto;