SlideShare uma empresa Scribd logo
1 de 24
Baixar para ler offline
RECOMMISSIONING PROCEDURE
AFTER CAPITAL
OVERHAUL OF BOILER
By
Manohar Tatwawadi
+91 9372167165
09/08/2019 total output power solutions 1
OBJECTIVES
Recommissioning of the boiler after capital overhaul aims at
following objectives.:-
1. Preparation of the equipments for reliable and trouble free
operation. This may involve.
A. Inspection, pre operational checking and preparation
of the equipment for satisfactory trial.
B. Trial run, initial operation and performance
monitoring and
C. Problem analysis and solution.
2. Compiling and creation of equipment performance data for
future reference and comparison.
09/08/2019 total output power solutions 2
OBJECTIVES
3. Checking of all interlocks of the equipment and confirming the
operation of relays as per the protection provided and
tripping of the equipment accordingly.
4. Some of the equipment or subsystem of the boiler like
auxiliaries, coal handling plant, ash handling plant, service and
instrument compressors, electrical systems are overhauled by
different agencies. For successful commissioning of the steam
generator all these equipment should be made ready at
appropriate stage of boiler commissioning. This involves
effective coordination between the operation and
maintenance staff.
09/08/2019 total output power solutions 3
ACTIVITIES
• Broadly, the activities during recommissioning of
a boiler can be divided into following different
stages.
 Planning and Preparation.
 Inspection and checks.
 Trial run of equipments.
 Trial run of boiler and setting parameters for
operation regimes.
 Performance Testing.
09/08/2019 total output power solutions 4
Planning and Preparation
• Planning for recommissioning of the unit should start atleast 8
to 10 days prior to completion of the overhaul of the unit.
• Scope of work and clear demarkation should be there
regarding responsibilities of different section/ agencies i.e.
mechanical, electrical, Testing, I and C, operation and
maintenance etc.
• To facilitate smooth recommissioning, proper coordination
should be there among various sections/ agencies for trial
run, testing, activities like chemical cleaning, steam blowing
and other commissioning activities.
• For effective monitoring, a PERT chart or a bar chart of
commissioning activities should be prepared. This can be
done after ascertaining the planned dates of activities and
readiness of requisite inputs like power, water, fuel,
lubricants, service facilities and trained personnel.
09/08/2019 total output power solutions 5
Inspection and
Recommissioning Checks
• The first important recommissioning activity at site is the
inspection and checking of equipment.
• Generally this activity is meant to ensure overhaul of the
equipment completion, compliance of critical dimensions,
tolerances, removal of unwanted material and access for
inspection.
• All the air and gas duct should be checked for completeness
of work, correct supporting, expansion provision wherever
required and proper flanged and welded connections.
• The complete system should be cleaned of all debris.
Proper application of insulation to minimise heat loss and
to ensure human safety should also be checked.
09/08/2019 total output power solutions 6
Steam Drum
• The steam drum should be checked for correct fit
up of internals and cleanliness.
• All safety valve nozzles, water column nozzles,
vent nozzles, pressure gauge nozzles, down
comer nozzles etc. should be checked for any
obstruction.
• The drum should be free to expand in all the
required directions.
• The water level gauge and water level instrument
connection should be strictly as per drawing.
09/08/2019 total output power solutions 7
Superheater, Reheater,
Desuperheater and Economiser
• Cleanliness is the one of the prime requirement
in this area.
• The assemblies should be checked for transverse
and longitudinal spacing. Any misalignment
should be corrected.
• Supports, expansion clearances, correct
installation of cooled and uncooled spacers gas
baffles etc. should be checked.
• The thermocouples for temperature
measurement should be checked for correct
location and installation.
09/08/2019 total output power solutions 8
Waterwalls and Buckstays
• All the waterwalls and other areas subjected to
expansion movement should be checked up for
any tie up with structural steel. Adequate
expansion clearances and guiding must be
provided.
• Correct location of instrument tapping points
should be checked. For measurement of
verification of thermal expansion of boiler,
indicators should be mounted at the required
location.
09/08/2019 total output power solutions 9
Waterwalls and Buckstays
• The buckstays system should be checked for
correct installation and insulation filling wherever
required. Corner connection and intersection
between vertical and horizontal buckstays, front
and rear pass buckstays should be checked for
proper arrangement.
• The bottom ash hoppers may be checked for any
possible spray or splashing of water on to the
waterwall tubes. Water seal plates should be
checked for expansion clearances and adequacy.
09/08/2019 total output power solutions 10
Hangers and Support
• All hangers of the boiler, headers, ducts and
piping should be checked up for correct
location.
• Loading spring compression in case of spring
type hangers should be strictly as per design.
• Both the spring and constant load hangers
should have adequate expansion range.
09/08/2019 total output power solutions 11
Safety valves
• The hydrostatic test plug to safety valves must
be removed prior to firing the unit.
• After hydrostatic testing all the valves should
be cleaned, assembled and made ready for
setting.
• The safety valve vent pipes should be properly
supported with adequate expansion around
the drip pan.
• Drains of adequate size must be provided.
09/08/2019 total output power solutions 12
Rotating Equipment
• The rotating equipment including fans, airheaters and
pulverisers should be completely checked as per O & M
manuals.
• Gaps and clearances inside the mill, air heater and all
bearings must be checked and adjusted.
• Correct direction of rotation and proper alignment with
the drive should be ensured.
• The suction vanes, filters, strainers, guides must be
ensured to be clean and dust free.
• Lubricating system, oil with oil pumps must be ensured
to be working and all permits must be closed.
09/08/2019 total output power solutions 13
Trial Run of the Equipment
• Normally before trial run of equipments, service
facilities like power, cooling water and lubricants
must be made available.
• Prior to trial run of the equipment, trial run of the
drive unit (electric motor) need to be taken in the
un-coupled condition. Motor’s protection and
interlocks should be tested.
• After successful trial run of drive, the equipment
be coupled and trial run in coupled condition be
taken.
09/08/2019 total output power solutions 14
Trial Run of the Equipment
• Trial run of the rotating equipment must be
individually done.
• During trial run, equipment should be carefully
observed for any unusual noise, abnormal
vibrations or undue bearing temperature rise.
Any defect noticed should be immediately
attended.
• A record of trial run including vibrations bearing
temp, starting current, no load current etc should
be maintained for future reference.
09/08/2019 total output power solutions 15
Safety Valve Setting Procedure
• The safety valve in the Boiler to be floated and set to operate
at the required pressure. This is done to ensure the
availability of the safety valves for pressure release in times of
necessity and also to check the adequacy of the venting
system.
• During safety valve setting, the Boiler steam pressure will be
raised to the maximum value of the setting.
• Before commencing floating, all the precommissioning checks
and servicing of the valves should have been completed.
• The boiler pressure is gradually raised at much lower rate to
facilitate measuring of waterwall and other pressure part
expansions.
09/08/2019 total output power solutions 16
Safety Valve Setting Procedure
• After measuring the expansion at operating pressure, all the
safety valves are gagged except the one to be floated and
when the boiler pressure is around 10% lower than the set
value, the valve is warmed up and eased by hand popping.
• Then the pressure is gradually raised. When the safety valve
floats, the pressure is noted down using a calibrated gauge
and the firing is stopped.
• As the boiler pressure decays, the safety valve resetting
pressure is also noted.
09/08/2019 total output power solutions 17
Safety Valve Setting Procedure
• Any adjustment required for setting the lifting
pressure, blow down is done as per the safety valve O
& M manual. Then the firing is restarted and pressure
raised. The procedure is repeated till the safety valve
lifting pressure and blow down are within acceptable
limits. The above procedure is repeated for all safety
valves. If floating is started from the valve set at
highest pressure and proceeded in the order of
decreasing set pressure, gagging of already floated
safety valves will not be normally required.
• Before declaring the completion of this activity, gags
from all the safety valves should be removed and
recorded.
09/08/2019 total output power solutions 18
FILLING OF BOILER
– While filling the boiler with water, following care
should be taken.
• DM water only should be used to reduce
corrosion and deposition.
• The temperature of water fed should be within
allowable limit compared to the temperature of
metal to reduce thermal stresses. Temperature
difference within 50 0C is generally considered as
safe.
• Keep all the vents open while filling such that no
air pocket is formed.
09/08/2019 total output power solutions 19
Hydraulic Testing of Boiler
Precautions to be taken during a Hydraulic Test.
• If the test is to be conducted above the operating
pressure, the safety valves are to be gagged.
• Only D.M. water treated with volatile chemicals such
as Hydrazine, Ammonia and proper P. H. value as per
the chemist should be used.
• Use water at ambient temperature but above 25 0C
• Check the supports and arrest all spring loaded
hangers to take up the additional load due to water.
09/08/2019 total output power solutions 20
Hydraulic Test… Precautions
• Keep the boiler outlet valves tightly closed. Ensure
that water should not enter the Turbine.
• Arrest the hangers of pipe line.
• If the Boiler is to be kept idle after the hydraulic
testing, pressure parts are to be preserved by wet
method or nitrogen blanketing.
• Ensure that the safety valve gagging (or Hydraulic
test plug) is removed after completion of Hydraulic
test.
09/08/2019 total output power solutions 21
TRIAL OPERATION OF BOILER
• After completing the Re-commissioning activities
satisfactorily, Boiler is ready for Trial Operation.
• At this time, all facilities and inputs for loading the unit and
putting into regular service should be ready.
• Same time, the Turbine, Generator and complete electrical
transmission system must be ready.
• Before trial run of the Boiler, general inspection of all
equipment is carried out. All rotating equipment is checked
for proper lubrication and smooth operation.
• Dampers and valves one checked for proper operation.
• The complete Instrumentation and control must be checked
for proper functioning.
• The boiler is then lighted up in accordance with operation and
maintenance instructions as per the light-up programme
09/08/2019 total output power solutions 22
Performance Testing
• On successful completion of trial run of the boiler it is
declared ready for further full load operation.
• If at this stage there are some minor pending points or
problems which do not affect the safe operation of the
unit, the concerned agency may be asked to attend the
problem at the next available opportunity.
• When the unit is fully loaded and the performance is
found satisfactory, then performance testing of the unit
can be carried out to find out the improvement after
carrying out the capital overhaul.
09/08/2019 total output power solutions 23
09/08/2019 total output power solutions 24

Mais conteúdo relacionado

Mais procurados

steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)Billa ParameswaraRao
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesManohar Tatwawadi
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSManohar Tatwawadi
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection systemSachin Pyasi
 
Auxiliary power consumption reduction
Auxiliary power consumption reductionAuxiliary power consumption reduction
Auxiliary power consumption reductionAmit jangra
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plantManohar Tatwawadi
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protectionanujkumarsingh79
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Manohar Tatwawadi
 
Turbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & WorkingTurbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & WorkingTahoor Alam Khan
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANTSTUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANTRajashekar Gurrala
 
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyAuxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyManohar Tatwawadi
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownAshvani Shukla
 

Mais procurados (20)

Stator water system chemistry
Stator water system chemistryStator water system chemistry
Stator water system chemistry
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONS
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection system
 
Auxiliary power consumption reduction
Auxiliary power consumption reductionAuxiliary power consumption reduction
Auxiliary power consumption reduction
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
Turbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & WorkingTurbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & Working
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANTSTUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
 
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyAuxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 

Semelhante a Recommissioning boiler procedures

171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.pptssuser9e9be71
 
Boiler Maintenance.pptx
Boiler Maintenance.pptxBoiler Maintenance.pptx
Boiler Maintenance.pptxSahalSachu
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintananceAnasMirza10
 
Principals of operation of a thermal power station
Principals of operation of a thermal power stationPrincipals of operation of a thermal power station
Principals of operation of a thermal power stationManohar Tatwawadi
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Fuel gas system of gas production
Fuel gas system of gas productionFuel gas system of gas production
Fuel gas system of gas productionPhyoe Maung Maung
 
resume-4-1.docx (1)
resume-4-1.docx (1)resume-4-1.docx (1)
resume-4-1.docx (1)Thomas Lally
 
A guide for firetube boiler testes
A guide for firetube boiler   testesA guide for firetube boiler   testes
A guide for firetube boiler testesederpitapeva
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
Consolidated power srvc_valves_brochure_0512
Consolidated power srvc_valves_brochure_0512Consolidated power srvc_valves_brochure_0512
Consolidated power srvc_valves_brochure_0512Juan Carlos Elías
 
Energy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class PresentationEnergy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class PresentationTahaUzair2
 
Mastering the Art of Water Heater Installation A Comprehensive Guide.pdf
Mastering the Art of Water Heater Installation A Comprehensive Guide.pdfMastering the Art of Water Heater Installation A Comprehensive Guide.pdf
Mastering the Art of Water Heater Installation A Comprehensive Guide.pdfEco 1 Plumbing LLC
 

Semelhante a Recommissioning boiler procedures (20)

171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Boiler Maintenance.pptx
Boiler Maintenance.pptxBoiler Maintenance.pptx
Boiler Maintenance.pptx
 
Boiler condition survey
Boiler condition surveyBoiler condition survey
Boiler condition survey
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Principals of operation of a thermal power station
Principals of operation of a thermal power stationPrincipals of operation of a thermal power station
Principals of operation of a thermal power station
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Plant start up
Plant start upPlant start up
Plant start up
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Asirvatharavi Mech
Asirvatharavi MechAsirvatharavi Mech
Asirvatharavi Mech
 
Fuel gas system of gas production
Fuel gas system of gas productionFuel gas system of gas production
Fuel gas system of gas production
 
resume-4-1.docx (1)
resume-4-1.docx (1)resume-4-1.docx (1)
resume-4-1.docx (1)
 
A guide for firetube boiler testes
A guide for firetube boiler   testesA guide for firetube boiler   testes
A guide for firetube boiler testes
 
Mech manager
Mech managerMech manager
Mech manager
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
Piping hydrotest
Piping hydrotestPiping hydrotest
Piping hydrotest
 
Consolidated power srvc_valves_brochure_0512
Consolidated power srvc_valves_brochure_0512Consolidated power srvc_valves_brochure_0512
Consolidated power srvc_valves_brochure_0512
 
new_cv-2016
new_cv-2016new_cv-2016
new_cv-2016
 
Energy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class PresentationEnergy Systems & Maintenance - Class Presentation
Energy Systems & Maintenance - Class Presentation
 
Mastering the Art of Water Heater Installation A Comprehensive Guide.pdf
Mastering the Art of Water Heater Installation A Comprehensive Guide.pdfMastering the Art of Water Heater Installation A Comprehensive Guide.pdf
Mastering the Art of Water Heater Installation A Comprehensive Guide.pdf
 

Mais de Manohar Tatwawadi

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Manohar Tatwawadi
 
Green building concepts and good building practices
Green building concepts and good building practicesGreen building concepts and good building practices
Green building concepts and good building practicesManohar Tatwawadi
 
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESCOMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESManohar Tatwawadi
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Manohar Tatwawadi
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plantsManohar Tatwawadi
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stationsManohar Tatwawadi
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSManohar Tatwawadi
 
Environmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsEnvironmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsManohar Tatwawadi
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...Manohar Tatwawadi
 
Fuels and Combustion Equations
Fuels and Combustion EquationsFuels and Combustion Equations
Fuels and Combustion EquationsManohar Tatwawadi
 
Basics of thermal power stations
Basics of thermal power stationsBasics of thermal power stations
Basics of thermal power stationsManohar Tatwawadi
 
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsManohar Tatwawadi
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiencyManohar Tatwawadi
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTManohar Tatwawadi
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATEManohar Tatwawadi
 
Boiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power StationsBoiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power StationsManohar Tatwawadi
 

Mais de Manohar Tatwawadi (20)

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3
 
Green building concepts and good building practices
Green building concepts and good building practicesGreen building concepts and good building practices
Green building concepts and good building practices
 
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESCOMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plants
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPS
 
Environmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsEnvironmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power Stations
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
 
Fuels and Combustion Equations
Fuels and Combustion EquationsFuels and Combustion Equations
Fuels and Combustion Equations
 
Basics of thermal power stations
Basics of thermal power stationsBasics of thermal power stations
Basics of thermal power stations
 
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / Mills
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
 
Swot Analysis
Swot AnalysisSwot Analysis
Swot Analysis
 
Boiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power StationsBoiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power Stations
 

Último

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Último (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Recommissioning boiler procedures

  • 1. RECOMMISSIONING PROCEDURE AFTER CAPITAL OVERHAUL OF BOILER By Manohar Tatwawadi +91 9372167165 09/08/2019 total output power solutions 1
  • 2. OBJECTIVES Recommissioning of the boiler after capital overhaul aims at following objectives.:- 1. Preparation of the equipments for reliable and trouble free operation. This may involve. A. Inspection, pre operational checking and preparation of the equipment for satisfactory trial. B. Trial run, initial operation and performance monitoring and C. Problem analysis and solution. 2. Compiling and creation of equipment performance data for future reference and comparison. 09/08/2019 total output power solutions 2
  • 3. OBJECTIVES 3. Checking of all interlocks of the equipment and confirming the operation of relays as per the protection provided and tripping of the equipment accordingly. 4. Some of the equipment or subsystem of the boiler like auxiliaries, coal handling plant, ash handling plant, service and instrument compressors, electrical systems are overhauled by different agencies. For successful commissioning of the steam generator all these equipment should be made ready at appropriate stage of boiler commissioning. This involves effective coordination between the operation and maintenance staff. 09/08/2019 total output power solutions 3
  • 4. ACTIVITIES • Broadly, the activities during recommissioning of a boiler can be divided into following different stages.  Planning and Preparation.  Inspection and checks.  Trial run of equipments.  Trial run of boiler and setting parameters for operation regimes.  Performance Testing. 09/08/2019 total output power solutions 4
  • 5. Planning and Preparation • Planning for recommissioning of the unit should start atleast 8 to 10 days prior to completion of the overhaul of the unit. • Scope of work and clear demarkation should be there regarding responsibilities of different section/ agencies i.e. mechanical, electrical, Testing, I and C, operation and maintenance etc. • To facilitate smooth recommissioning, proper coordination should be there among various sections/ agencies for trial run, testing, activities like chemical cleaning, steam blowing and other commissioning activities. • For effective monitoring, a PERT chart or a bar chart of commissioning activities should be prepared. This can be done after ascertaining the planned dates of activities and readiness of requisite inputs like power, water, fuel, lubricants, service facilities and trained personnel. 09/08/2019 total output power solutions 5
  • 6. Inspection and Recommissioning Checks • The first important recommissioning activity at site is the inspection and checking of equipment. • Generally this activity is meant to ensure overhaul of the equipment completion, compliance of critical dimensions, tolerances, removal of unwanted material and access for inspection. • All the air and gas duct should be checked for completeness of work, correct supporting, expansion provision wherever required and proper flanged and welded connections. • The complete system should be cleaned of all debris. Proper application of insulation to minimise heat loss and to ensure human safety should also be checked. 09/08/2019 total output power solutions 6
  • 7. Steam Drum • The steam drum should be checked for correct fit up of internals and cleanliness. • All safety valve nozzles, water column nozzles, vent nozzles, pressure gauge nozzles, down comer nozzles etc. should be checked for any obstruction. • The drum should be free to expand in all the required directions. • The water level gauge and water level instrument connection should be strictly as per drawing. 09/08/2019 total output power solutions 7
  • 8. Superheater, Reheater, Desuperheater and Economiser • Cleanliness is the one of the prime requirement in this area. • The assemblies should be checked for transverse and longitudinal spacing. Any misalignment should be corrected. • Supports, expansion clearances, correct installation of cooled and uncooled spacers gas baffles etc. should be checked. • The thermocouples for temperature measurement should be checked for correct location and installation. 09/08/2019 total output power solutions 8
  • 9. Waterwalls and Buckstays • All the waterwalls and other areas subjected to expansion movement should be checked up for any tie up with structural steel. Adequate expansion clearances and guiding must be provided. • Correct location of instrument tapping points should be checked. For measurement of verification of thermal expansion of boiler, indicators should be mounted at the required location. 09/08/2019 total output power solutions 9
  • 10. Waterwalls and Buckstays • The buckstays system should be checked for correct installation and insulation filling wherever required. Corner connection and intersection between vertical and horizontal buckstays, front and rear pass buckstays should be checked for proper arrangement. • The bottom ash hoppers may be checked for any possible spray or splashing of water on to the waterwall tubes. Water seal plates should be checked for expansion clearances and adequacy. 09/08/2019 total output power solutions 10
  • 11. Hangers and Support • All hangers of the boiler, headers, ducts and piping should be checked up for correct location. • Loading spring compression in case of spring type hangers should be strictly as per design. • Both the spring and constant load hangers should have adequate expansion range. 09/08/2019 total output power solutions 11
  • 12. Safety valves • The hydrostatic test plug to safety valves must be removed prior to firing the unit. • After hydrostatic testing all the valves should be cleaned, assembled and made ready for setting. • The safety valve vent pipes should be properly supported with adequate expansion around the drip pan. • Drains of adequate size must be provided. 09/08/2019 total output power solutions 12
  • 13. Rotating Equipment • The rotating equipment including fans, airheaters and pulverisers should be completely checked as per O & M manuals. • Gaps and clearances inside the mill, air heater and all bearings must be checked and adjusted. • Correct direction of rotation and proper alignment with the drive should be ensured. • The suction vanes, filters, strainers, guides must be ensured to be clean and dust free. • Lubricating system, oil with oil pumps must be ensured to be working and all permits must be closed. 09/08/2019 total output power solutions 13
  • 14. Trial Run of the Equipment • Normally before trial run of equipments, service facilities like power, cooling water and lubricants must be made available. • Prior to trial run of the equipment, trial run of the drive unit (electric motor) need to be taken in the un-coupled condition. Motor’s protection and interlocks should be tested. • After successful trial run of drive, the equipment be coupled and trial run in coupled condition be taken. 09/08/2019 total output power solutions 14
  • 15. Trial Run of the Equipment • Trial run of the rotating equipment must be individually done. • During trial run, equipment should be carefully observed for any unusual noise, abnormal vibrations or undue bearing temperature rise. Any defect noticed should be immediately attended. • A record of trial run including vibrations bearing temp, starting current, no load current etc should be maintained for future reference. 09/08/2019 total output power solutions 15
  • 16. Safety Valve Setting Procedure • The safety valve in the Boiler to be floated and set to operate at the required pressure. This is done to ensure the availability of the safety valves for pressure release in times of necessity and also to check the adequacy of the venting system. • During safety valve setting, the Boiler steam pressure will be raised to the maximum value of the setting. • Before commencing floating, all the precommissioning checks and servicing of the valves should have been completed. • The boiler pressure is gradually raised at much lower rate to facilitate measuring of waterwall and other pressure part expansions. 09/08/2019 total output power solutions 16
  • 17. Safety Valve Setting Procedure • After measuring the expansion at operating pressure, all the safety valves are gagged except the one to be floated and when the boiler pressure is around 10% lower than the set value, the valve is warmed up and eased by hand popping. • Then the pressure is gradually raised. When the safety valve floats, the pressure is noted down using a calibrated gauge and the firing is stopped. • As the boiler pressure decays, the safety valve resetting pressure is also noted. 09/08/2019 total output power solutions 17
  • 18. Safety Valve Setting Procedure • Any adjustment required for setting the lifting pressure, blow down is done as per the safety valve O & M manual. Then the firing is restarted and pressure raised. The procedure is repeated till the safety valve lifting pressure and blow down are within acceptable limits. The above procedure is repeated for all safety valves. If floating is started from the valve set at highest pressure and proceeded in the order of decreasing set pressure, gagging of already floated safety valves will not be normally required. • Before declaring the completion of this activity, gags from all the safety valves should be removed and recorded. 09/08/2019 total output power solutions 18
  • 19. FILLING OF BOILER – While filling the boiler with water, following care should be taken. • DM water only should be used to reduce corrosion and deposition. • The temperature of water fed should be within allowable limit compared to the temperature of metal to reduce thermal stresses. Temperature difference within 50 0C is generally considered as safe. • Keep all the vents open while filling such that no air pocket is formed. 09/08/2019 total output power solutions 19
  • 20. Hydraulic Testing of Boiler Precautions to be taken during a Hydraulic Test. • If the test is to be conducted above the operating pressure, the safety valves are to be gagged. • Only D.M. water treated with volatile chemicals such as Hydrazine, Ammonia and proper P. H. value as per the chemist should be used. • Use water at ambient temperature but above 25 0C • Check the supports and arrest all spring loaded hangers to take up the additional load due to water. 09/08/2019 total output power solutions 20
  • 21. Hydraulic Test… Precautions • Keep the boiler outlet valves tightly closed. Ensure that water should not enter the Turbine. • Arrest the hangers of pipe line. • If the Boiler is to be kept idle after the hydraulic testing, pressure parts are to be preserved by wet method or nitrogen blanketing. • Ensure that the safety valve gagging (or Hydraulic test plug) is removed after completion of Hydraulic test. 09/08/2019 total output power solutions 21
  • 22. TRIAL OPERATION OF BOILER • After completing the Re-commissioning activities satisfactorily, Boiler is ready for Trial Operation. • At this time, all facilities and inputs for loading the unit and putting into regular service should be ready. • Same time, the Turbine, Generator and complete electrical transmission system must be ready. • Before trial run of the Boiler, general inspection of all equipment is carried out. All rotating equipment is checked for proper lubrication and smooth operation. • Dampers and valves one checked for proper operation. • The complete Instrumentation and control must be checked for proper functioning. • The boiler is then lighted up in accordance with operation and maintenance instructions as per the light-up programme 09/08/2019 total output power solutions 22
  • 23. Performance Testing • On successful completion of trial run of the boiler it is declared ready for further full load operation. • If at this stage there are some minor pending points or problems which do not affect the safe operation of the unit, the concerned agency may be asked to attend the problem at the next available opportunity. • When the unit is fully loaded and the performance is found satisfactory, then performance testing of the unit can be carried out to find out the improvement after carrying out the capital overhaul. 09/08/2019 total output power solutions 23
  • 24. 09/08/2019 total output power solutions 24