GOVERNMENT OF THE PUNJAB
ORANGE LINE METRO TRAIN TIMELINES
NATIONAL ENGINEERING SERVICES
PAKISTAN (PVT) LIMITED
THE PUNJAB METRO BUS AUTHORITY
June 2015
1
Introduction
• Total Length = 27.1 km
• Elevated Viaduct = 25.4 km
• Cut & Cover Section = 1.71 km
• Elevated Stations = 24
• Underground Stations = 2
• Date of Commencement of Project = Date of Advance Payment to CR-NORINCO = 1-8-2015
2
Timelines for Orange Line …. Contd.
3
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
1
Info about Survey + Geotech Requirements from CR-
NORINCO
CR-NORINCO 0.5 months
from contract signing date
(21.4.15)
7-5-2015
(received)
---- ----
2 Preparation of EIA Report NESPAK 0.5 months
from contract signing date
(21.4.15)
7-5-2015
(already submitted)
---- ----
3
Preparation and Approval of main PC-1 (Based on preliminary
design)
NESPAK / PMA 0.75 months
from contract signing date
(21.4.15)
15-5-2015
(already approved)
---- ----
4
Preparation of second PC-1 for Misc. Items (Based on
estimated costs)
NESPAK 1.25 months
from contract signing date
(21.4.15)
30-5-2015
(submitted to PMA)
---- ----
5 Prequalification of Civil Contractors LDA 1 month after approval of PC-1 15-6-2015 ---- ----
6 Topographic Survey NESPAK 1 month
from info received from CR-
NORINCO
7-6-2015
(already submitted)
---- ----
7 Information about Underground Utilities LDA 15-6-2015
8 Preparation of Utility Relocation Plans
LDA/WASA/
SNGPL/LESCO
30-6-2015
9 Geotech Investigation NESPAK 1.5 months
from info received from CR-
NORINCO
21-6-2015
(already submitted)
---- ----
Timelines for Orange Line …. Contd.
4
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
10
Info about Land Acquisition and Relocation of Facilities
from CR-NORINCO
CR-NORINCO 0.5 months
from topographic survey
and utility plan submission
7-7-2015 ---- ----
11 Time for Public Hearing after EIA Report submission EPA 2.0 months
from EIA Report
Submission
7-7-2015 ---- ----
12
Concept Design of Civil and E&M works by CR-
NORINCO
CR-NORINCO 0.5 months from commencement date 15-8-2015 ---- 30-6-2015
13 Review and Approval of Civil and E&M Concept Design NESPAK 1.5 months from commencement date 15-9-2015 ---- 7-7-2015
14 Preliminary Design of Viaduct NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
15 Preliminary Design of Cut & Cover Section NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
16 Preliminary Design of Elevated Stations NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
17 Preliminary Design of Underground Stations NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
Timelines for Orange Line …. Contd.
5
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
18 Preliminary Design of Depots / Stabling Yards NESPAK
0.5 - 2.0
months
from commencement
date
30-9-2015 ---- 10-7-2015
19 Preliminary Design of Substation NESPAK
0.5 - 2.0
months
from commencement
date
30-9-2015 ---- 10-7-2015
20
Preliminary Civil Design and layout drawings
submission to CR-NORINCO
NESPAK 2 months
from commencement
date
30-9-2015 ---- 10-7-2015
21
Requirements of E&M from Contractor for Detailed Civil
Design
CR-NORINCO 3 months
from commencement
date
30-10-2015 ---- 13-7-2015
22 Preparation of Tender Design for Civil-works and Tender NESPAK / LDA 0.5 months
after E&M info from CR-
NORINCO
15-11-2015 ---- 15-7-2015
23 Evaluation and Award of Civil Contract LDA / NESPAK 0.5 months after Tender 30-11-2015 ---- 7-8-2015
24
Final Civil Design and provision of drawings to CR-
NORINCO
NESPAK 5 months
from commencement
date
30-12-2015 ---- 30-10-2015
25
Detailed design of E&M system furnished by CR-
NORINCO
CR-NORINCO 10 months
from commencement
date
30-5-2016 ---- 30-12-2015
Timelines for Orange Line …. Contd.
6
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
26
Construction of the sections from the throat area to
building at Depot and Stabling Yard
LDA / NESPAK 10 months from commencement date 30-5-2016 ---- 15-3-2016
27 Review and approval of detailed design of E&M system NESPAK 11 months from commencement date 30-6-2016 ---- 30-1-2016
28
Provision of Civil-works in sections for Track Laying
Base
LDA / NESPAK 8.5 months after award of civil contract 15-8-2016 ---- 21-5-2016
29
Start of Construction of the track laying base by CR-
NORINCO
CR-NORINCO
12.5
months
from commencement date 15-8-2016 ---- 21-5-2016
30
Completion of Construction of buildings and other
sections at Depot and Stabling Yard
LDA / NESPAK
13 months
9 months
from commencement date
after award of civil contract
30-8-2016 ---- 30-5-2016
31 Completion of Cut and Cover with subgrade works LDA / NESPAK
14.5
months
10.5
months
from commencement date
after award of civil contract
15-10-2016 ---- 30-6-2016
32 Provision of External 132KV Power Supply by Employer PMA / LDA 15 months from commencement date 30-10-2016 ---- 30-6-2016
33
Completion of Construction of Cast-in-situ U-type girder
and continuous girder **
LDA / NESPAK
16.5
months
12.5
months
from commencement date
after award of civil contract
15-12-2016 15-10-2016 15-7-2016
Timelines for Orange Line …. Contd.
7
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
34 Completion of Construction of Stations ** LDA / NESPAK
18.5
months
14.5
months
from commencement date
after award of civil contract
15-2-2017 15-10-2016 15-7-2016
35 Completion of Erection of U-type Girders ** LDA / NESPAK
19 months
15 months
from commencement date
after award of civil contract
28-2-2017 30-10-2016 30-7-2016
36
Provision of working conditions for other E&M system according to
interface table requirement (Power Supply Signaling Telecom AFC
PSD & APG HVAC Escalator & Elevator Fire Fighting Water Supply
& Drainage Illumination BAS FAS FES Depot & Stabling Yard
equipment)
LDA / NESPAK
12TH
- 19TH
months
from commencement date
1-8-2016 to
30-3-2017
----
15-5-2016 to
30-11-2016
37 Track Laying ** CR-NORINCO 23 months from commencement date 30-6-2017 30-3-2017 30-12-2016
38
Installation of Power Supply System, Communication,
Signaling, and other E&M Systems **
CR-NORINCO 24 months from commencement date 30-7-2017 30-4-2017 30-1-2017
39 Testing and Commissioning CR-NORINCO 27 months from commencement date 30-10-2017 30-7-2017 23-3-2017
** Critical Activities : Time saved here, if possible will advance the project completion date.
Time for
Completion
27 months
Time for
Completion
24 months
Planned / Agreed time for Civil-Works = 6 months to 15 months
Expedited time for Civil-Works = 6 months to 11 months
High Accelerated for Civil-Works = 6 months to 10.5 months
Time for
Completion
20.75 months
Inauguration
March 23, 2017

Mais conteúdo relacionado

Mais procurados

Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Thomas Ingrey
 
Biskra 460 MW SCPP_Algeria
Biskra 460 MW SCPP_AlgeriaBiskra 460 MW SCPP_Algeria
Biskra 460 MW SCPP_AlgeriaErdal Berkay
 
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...ATIF HUSSAIN
 
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...ATIF HUSSAIN
 
Digital logic and verilog
Digital logic and verilogDigital logic and verilog
Digital logic and verilogRoshni Uppala
 

Mais procurados (11)

Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014
 
Biskra 460 MW SCPP_Algeria
Biskra 460 MW SCPP_AlgeriaBiskra 460 MW SCPP_Algeria
Biskra 460 MW SCPP_Algeria
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Roberto Guevara-CV
Roberto Guevara-CVRoberto Guevara-CV
Roberto Guevara-CV
 
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
 
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...
 
Digital logic and verilog
Digital logic and verilogDigital logic and verilog
Digital logic and verilog
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
Delivering a breakthrough rail project by Bill Henry
Delivering a breakthrough rail project by Bill HenryDelivering a breakthrough rail project by Bill Henry
Delivering a breakthrough rail project by Bill Henry
 
Authorities ici
Authorities iciAuthorities ici
Authorities ici
 

Destaque

What is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - OverviewWhat is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - Overviewuvahidy
 
Project Sheet-PSPC
Project Sheet-PSPCProject Sheet-PSPC
Project Sheet-PSPCAzmat Mazhar
 
Eia coal convying at PIBT Port Qasim by NESPAK
Eia coal convying at PIBT Port Qasim by NESPAKEia coal convying at PIBT Port Qasim by NESPAK
Eia coal convying at PIBT Port Qasim by NESPAKzubeditufail
 
PR consultancies in pakistan
PR consultancies in pakistanPR consultancies in pakistan
PR consultancies in pakistanWajeeha Azam
 
Effect of local market access on diets consumption and nutitional indicators ...
Effect of local market access on diets consumption and nutitional indicators ...Effect of local market access on diets consumption and nutitional indicators ...
Effect of local market access on diets consumption and nutitional indicators ...ExternalEvents
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITEDWater Birds (Ali)
 
Transportation & communication OF PAKISTAN PPT
Transportation & communication OF PAKISTAN PPTTransportation & communication OF PAKISTAN PPT
Transportation & communication OF PAKISTAN PPTABDUL SAMAD
 
Mass transit system
Mass transit systemMass transit system
Mass transit systemAsjad Khuram
 
Road sector in India
Road sector in IndiaRoad sector in India
Road sector in Indiasharifishere
 
1. classification of urban roads 28 jun
1. classification of urban roads 28 jun1. classification of urban roads 28 jun
1. classification of urban roads 28 junPrathamesh Kulkarni
 
Civil Engineering – Oldest Yet A Highly Sought After Career Choice in India
Civil Engineering – Oldest Yet A Highly Sought After Career Choice in IndiaCivil Engineering – Oldest Yet A Highly Sought After Career Choice in India
Civil Engineering – Oldest Yet A Highly Sought After Career Choice in IndiaAnkur Tandon
 

Destaque (19)

What is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - OverviewWhat is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - Overview
 
Project Sheet-PSPC
Project Sheet-PSPCProject Sheet-PSPC
Project Sheet-PSPC
 
KPRRP Sheets
KPRRP SheetsKPRRP Sheets
KPRRP Sheets
 
cv
cvcv
cv
 
Presentation
PresentationPresentation
Presentation
 
umesh dangi
umesh dangiumesh dangi
umesh dangi
 
Eia coal convying at PIBT Port Qasim by NESPAK
Eia coal convying at PIBT Port Qasim by NESPAKEia coal convying at PIBT Port Qasim by NESPAK
Eia coal convying at PIBT Port Qasim by NESPAK
 
PR consultancies in pakistan
PR consultancies in pakistanPR consultancies in pakistan
PR consultancies in pakistan
 
Pakistan
PakistanPakistan
Pakistan
 
Effect of local market access on diets consumption and nutitional indicators ...
Effect of local market access on diets consumption and nutitional indicators ...Effect of local market access on diets consumption and nutitional indicators ...
Effect of local market access on diets consumption and nutitional indicators ...
 
Metro bus project
Metro bus projectMetro bus project
Metro bus project
 
Design of National Highway-13
Design of National Highway-13Design of National Highway-13
Design of National Highway-13
 
Introduction to drr 2013
Introduction to drr 2013Introduction to drr 2013
Introduction to drr 2013
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
Transportation & communication OF PAKISTAN PPT
Transportation & communication OF PAKISTAN PPTTransportation & communication OF PAKISTAN PPT
Transportation & communication OF PAKISTAN PPT
 
Mass transit system
Mass transit systemMass transit system
Mass transit system
 
Road sector in India
Road sector in IndiaRoad sector in India
Road sector in India
 
1. classification of urban roads 28 jun
1. classification of urban roads 28 jun1. classification of urban roads 28 jun
1. classification of urban roads 28 jun
 
Civil Engineering – Oldest Yet A Highly Sought After Career Choice in India
Civil Engineering – Oldest Yet A Highly Sought After Career Choice in IndiaCivil Engineering – Oldest Yet A Highly Sought After Career Choice in India
Civil Engineering – Oldest Yet A Highly Sought After Career Choice in India
 

Semelhante a Activities - Presentation (NESPAK) v1.6

Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614Tejas Kale
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDFClement Seong
 
altaf resume work preparation
altaf resume work preparationaltaf resume work preparation
altaf resume work preparationAltaf Tanwar
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptSrikanthTirluka1
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptAkdDeshmukh
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadiumSLIIT, Sri Lanka
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plantsPrashant Alekar
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)Baig Ali
 

Semelhante a Activities - Presentation (NESPAK) v1.6 (20)

10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
ICI FINAL REPORT
ICI FINAL REPORTICI FINAL REPORT
ICI FINAL REPORT
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
altaf resume work preparation
altaf resume work preparationaltaf resume work preparation
altaf resume work preparation
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.ppt
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
june'15
june'15june'15
june'15
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plants
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 

Activities - Presentation (NESPAK) v1.6

  • 1. GOVERNMENT OF THE PUNJAB ORANGE LINE METRO TRAIN TIMELINES NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LIMITED THE PUNJAB METRO BUS AUTHORITY June 2015 1
  • 2. Introduction • Total Length = 27.1 km • Elevated Viaduct = 25.4 km • Cut & Cover Section = 1.71 km • Elevated Stations = 24 • Underground Stations = 2 • Date of Commencement of Project = Date of Advance Payment to CR-NORINCO = 1-8-2015 2
  • 3. Timelines for Orange Line …. Contd. 3 Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months) PLANNED / AGREED DATES EXPEDITED DATES HIGH ACCELERATION DATES 1 Info about Survey + Geotech Requirements from CR- NORINCO CR-NORINCO 0.5 months from contract signing date (21.4.15) 7-5-2015 (received) ---- ---- 2 Preparation of EIA Report NESPAK 0.5 months from contract signing date (21.4.15) 7-5-2015 (already submitted) ---- ---- 3 Preparation and Approval of main PC-1 (Based on preliminary design) NESPAK / PMA 0.75 months from contract signing date (21.4.15) 15-5-2015 (already approved) ---- ---- 4 Preparation of second PC-1 for Misc. Items (Based on estimated costs) NESPAK 1.25 months from contract signing date (21.4.15) 30-5-2015 (submitted to PMA) ---- ---- 5 Prequalification of Civil Contractors LDA 1 month after approval of PC-1 15-6-2015 ---- ---- 6 Topographic Survey NESPAK 1 month from info received from CR- NORINCO 7-6-2015 (already submitted) ---- ---- 7 Information about Underground Utilities LDA 15-6-2015 8 Preparation of Utility Relocation Plans LDA/WASA/ SNGPL/LESCO 30-6-2015 9 Geotech Investigation NESPAK 1.5 months from info received from CR- NORINCO 21-6-2015 (already submitted) ---- ----
  • 4. Timelines for Orange Line …. Contd. 4 Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months) PLANNED / AGREED DATES EXPEDITED DATES HIGH ACCELERATION DATES 10 Info about Land Acquisition and Relocation of Facilities from CR-NORINCO CR-NORINCO 0.5 months from topographic survey and utility plan submission 7-7-2015 ---- ---- 11 Time for Public Hearing after EIA Report submission EPA 2.0 months from EIA Report Submission 7-7-2015 ---- ---- 12 Concept Design of Civil and E&M works by CR- NORINCO CR-NORINCO 0.5 months from commencement date 15-8-2015 ---- 30-6-2015 13 Review and Approval of Civil and E&M Concept Design NESPAK 1.5 months from commencement date 15-9-2015 ---- 7-7-2015 14 Preliminary Design of Viaduct NESPAK 0.5 - 2.0 months from commencement date 30-9-2015 ---- 10-7-2015 15 Preliminary Design of Cut & Cover Section NESPAK 0.5 - 2.0 months from commencement date 30-9-2015 ---- 10-7-2015 16 Preliminary Design of Elevated Stations NESPAK 0.5 - 2.0 months from commencement date 30-9-2015 ---- 10-7-2015 17 Preliminary Design of Underground Stations NESPAK 0.5 - 2.0 months from commencement date 30-9-2015 ---- 10-7-2015
  • 5. Timelines for Orange Line …. Contd. 5 Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months) PLANNED / AGREED DATES EXPEDITED DATES HIGH ACCELERATION DATES 18 Preliminary Design of Depots / Stabling Yards NESPAK 0.5 - 2.0 months from commencement date 30-9-2015 ---- 10-7-2015 19 Preliminary Design of Substation NESPAK 0.5 - 2.0 months from commencement date 30-9-2015 ---- 10-7-2015 20 Preliminary Civil Design and layout drawings submission to CR-NORINCO NESPAK 2 months from commencement date 30-9-2015 ---- 10-7-2015 21 Requirements of E&M from Contractor for Detailed Civil Design CR-NORINCO 3 months from commencement date 30-10-2015 ---- 13-7-2015 22 Preparation of Tender Design for Civil-works and Tender NESPAK / LDA 0.5 months after E&M info from CR- NORINCO 15-11-2015 ---- 15-7-2015 23 Evaluation and Award of Civil Contract LDA / NESPAK 0.5 months after Tender 30-11-2015 ---- 7-8-2015 24 Final Civil Design and provision of drawings to CR- NORINCO NESPAK 5 months from commencement date 30-12-2015 ---- 30-10-2015 25 Detailed design of E&M system furnished by CR- NORINCO CR-NORINCO 10 months from commencement date 30-5-2016 ---- 30-12-2015
  • 6. Timelines for Orange Line …. Contd. 6 Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months) PLANNED / AGREED DATES EXPEDITED DATES HIGH ACCELERATION DATES 26 Construction of the sections from the throat area to building at Depot and Stabling Yard LDA / NESPAK 10 months from commencement date 30-5-2016 ---- 15-3-2016 27 Review and approval of detailed design of E&M system NESPAK 11 months from commencement date 30-6-2016 ---- 30-1-2016 28 Provision of Civil-works in sections for Track Laying Base LDA / NESPAK 8.5 months after award of civil contract 15-8-2016 ---- 21-5-2016 29 Start of Construction of the track laying base by CR- NORINCO CR-NORINCO 12.5 months from commencement date 15-8-2016 ---- 21-5-2016 30 Completion of Construction of buildings and other sections at Depot and Stabling Yard LDA / NESPAK 13 months 9 months from commencement date after award of civil contract 30-8-2016 ---- 30-5-2016 31 Completion of Cut and Cover with subgrade works LDA / NESPAK 14.5 months 10.5 months from commencement date after award of civil contract 15-10-2016 ---- 30-6-2016 32 Provision of External 132KV Power Supply by Employer PMA / LDA 15 months from commencement date 30-10-2016 ---- 30-6-2016 33 Completion of Construction of Cast-in-situ U-type girder and continuous girder ** LDA / NESPAK 16.5 months 12.5 months from commencement date after award of civil contract 15-12-2016 15-10-2016 15-7-2016
  • 7. Timelines for Orange Line …. Contd. 7 Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months) PLANNED / AGREED DATES EXPEDITED DATES HIGH ACCELERATION DATES 34 Completion of Construction of Stations ** LDA / NESPAK 18.5 months 14.5 months from commencement date after award of civil contract 15-2-2017 15-10-2016 15-7-2016 35 Completion of Erection of U-type Girders ** LDA / NESPAK 19 months 15 months from commencement date after award of civil contract 28-2-2017 30-10-2016 30-7-2016 36 Provision of working conditions for other E&M system according to interface table requirement (Power Supply Signaling Telecom AFC PSD & APG HVAC Escalator & Elevator Fire Fighting Water Supply & Drainage Illumination BAS FAS FES Depot & Stabling Yard equipment) LDA / NESPAK 12TH - 19TH months from commencement date 1-8-2016 to 30-3-2017 ---- 15-5-2016 to 30-11-2016 37 Track Laying ** CR-NORINCO 23 months from commencement date 30-6-2017 30-3-2017 30-12-2016 38 Installation of Power Supply System, Communication, Signaling, and other E&M Systems ** CR-NORINCO 24 months from commencement date 30-7-2017 30-4-2017 30-1-2017 39 Testing and Commissioning CR-NORINCO 27 months from commencement date 30-10-2017 30-7-2017 23-3-2017 ** Critical Activities : Time saved here, if possible will advance the project completion date. Time for Completion 27 months Time for Completion 24 months Planned / Agreed time for Civil-Works = 6 months to 15 months Expedited time for Civil-Works = 6 months to 11 months High Accelerated for Civil-Works = 6 months to 10.5 months Time for Completion 20.75 months Inauguration March 23, 2017