The Case Studies for Project Control Platform
Copenhagen, November 24th 2016
Maurizio M. Granata – Business Development Executive
EMIA – Materials, Costs, & Project Execution Solutions
day
ON BEHALF OF …
COMMON CHALLENGES
CLIENTS COMMON ANSWER
The Case Studies for Project Control Platform
Your Menu today
1
2
3
A FEW EVIDENCES …4
Q & A5
On Behalf of …
Main menu
Welcome on Behalf of …….
Your common challenges
Main menu
Projects Correlation between Size & Performance
$$$,$$$,$$$
$$$,$$$
$$$
ProjectBudget
ProjectPerformance
IPA Independent Project Analysis study of over 18,000 projects
More Projects challenges
Exception Rule
Large Capital investments that are completed on Schedule and within their Budgets are probably the
Exception rather then the Rule – and even when completed many fail to meet expected revenue targets.
Better forecasting for
Large Capital Projects
Bent Flyvbjerg, Massimo
Garbuio, & Dan Lovallo
McKinsey & Company
i
i
i
i
ii ii ii i
i
i
i
i
Data Sources
Analysis and
Decisions
More Projects challenges
?
Access Navigate Understand
Macro-Level Comprehensive Accurate
…… Room to Improve
Source: EcoSys Customer Internal Survey
Clients Common Answer
Main menu
Customer Story: Technip
11
Customer Story: Jacobs
12
Case Study Marathon Petroleum
Solution:
• New Enterprise System for optimizing Project
Investments on both CapEX and OpEx
• All Investments initiatives
• Portfolios,
• Project Controls,
• Shutdown & Turnaround Management
• All sites
• Consolidate Enterprise Best Practices
• Rapid implementation & deployment
Benefits:
• Centralized Visibility and standardized work processes
• $11 M per year savings from better project governance
• Project Management staff 55% more productive on both Turnaround
& small plant improvements
• $1.5 M per year IT maintenance cost savings
Business Challenge:
• Each Refinery set their control
practices
• Extensive use of
• In-house solutions
• Spreadsheets
• and manual work
• Different ERP integrations
Case Study Los Angeles Department of Water & Power
Business Challenge:
• Lengthy procedures to capture and
reconcile project control data
• Understanding project status not
smooth process
• Project performance missed what-if
scenario analysis
• No Consistent WBS & Milestones
• Not efficient Resource handling
• Slow manual based Reporting
Solution:
• New Capital planning & Reporting
hub integrating several data sources
• Automate data sharing and reporting
• Develop performance metrics
Benefits:
• Significant improvements in project performance visibility
provided greater control
• Analysis and Forecast comparisons to improve decisions
• Meet regulatory deadlines
Case Study Houston Airport System
Business Challenge:
• Lack of consistent:
• Capital Program Planning and
Funding
• Project Cost Management
• Reporting
Solution:
• capital program planning and funding
• contract and project setup
• grant management, design and construction
management including:
• change management
• cost management
• invoicing, document management
• workflow and forms management
Benefits:
• The principal Program Management dashboard and reporting solution
• Supporting stakeholders across HAS in Planning, Design, and
Construction Division, Finance, and the IT Capital Projects PMO Office
Case Study Bechtel
Solution:
• New Enterprise platform integrating proprietary
project control best-practices to deliver optimal
financial results
• Only platform that can embed Bechtel's robust and
proprietary processes with NO needs for costly
software customization
• Bechtel regularly recommends EcoSys EPC to its
customers as the best-in-class solution
Benefits:
• Enhanced Visibility into margin forecasts and early warning of overruns
• More productive PM stuff with a modern system and process automations
• Replaced 3 disparate in-house systems for project controls, EVM, and project
reporting, resulting in sizeable IT cost savings
• EcoSys pitched as key differentiator in competitive bids, reinforcing Bechtel’s
reputation as industry leader in processes and tools
• More rapid support of client requirements by internal staff
Business Challenge:
• Replacing highly-mature but
outdated internally-developed tool
• Integrating with:
• Oracle eBusiness ERP,
• Intergraph Smart Plant
Materials,
• custom In-house solutions
Co-Starring
A few evidences
Main menu
Bring Value to your Enterprise Projects Control Efforts
Before
[Common Practice]
Source: Internal study by Technip
After
PROJECT
BUDGET
Kr. 250.000.000
+
+
Kr.12.500.000
Cost for Overruns
Kr.1.500.000
Costs for Delays and
Extended Duration
POTENTIAL
SAVINGS
Ideal savings for On Time &
On Budget Delivery
Kr.14.000.000
Improved Construction performance
Kr. 1.462.500 1.5% on Construction Budget
Effective Change Management
Kr. 877.500 0.9% on Construction
Budget
Other Indirect & Direct execution Costs Savings
Kr. 1.540.000 1.1% on Engineering &
Construction
Average Potential Savings
Additional
Potential savings
Kr. 3.880.000
7.15%
Total savings
Kr. 17.880.000
-kr. 2,000,000.00
-kr. 1,000,000.00
kr. 0.00
kr. 1,000,000.00
kr. 2,000,000.00
kr. 3,000,000.00
kr. 4,000,000.00
kr. 5,000,000.00
kr. 6,000,000.00
kr. 7,000,000.00
kr. 8,000,000.00
Time 0 H1 H2 H3 H4
Time - Phased NPV
NPV Implementation & Maintenance
Eliminate Waste,
Drive Cost
Savings
Increase
Efficiency
Maximise
Visibility and
Control
Leverage
Increasing Value
Industry Best
Practices
Re-use Data
Ensure Data
Integrity
Analysis &
Forecast
Integrate &
Share work
processes
Projects
Driven
Business
Drive
To Successful
Business
Projects
Driven
Business
Q & A
Main menu
Maurizio M. GRANATA
Mob. +39 348 2727834
email maurizio.granata@intergraph.com
Skype MMGRANATA
On LinkedIn include
The Future of Engineering Today
The Case Studies for Project Control Platform
Thank you

Mais conteúdo relacionado

Mais procurados

Avoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAvoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAconex
 
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...Aconex
 
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...Aconex
 
Aconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performanceAconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performanceAconex
 
"Show me the ROI" – concrete results from process improvement
"Show me the ROI" – concrete results from process improvement"Show me the ROI" – concrete results from process improvement
"Show me the ROI" – concrete results from process improvementAconex
 
Digital transformation webinar amer slideshare
Digital transformation webinar amer slideshareDigital transformation webinar amer slideshare
Digital transformation webinar amer slideshareAconex
 
Unlocking Engineering and Construction performance webinar apac slideshare
Unlocking Engineering and Construction performance webinar apac slideshareUnlocking Engineering and Construction performance webinar apac slideshare
Unlocking Engineering and Construction performance webinar apac slideshareAconex
 
Keeping your project on track - Webinar, September 2016
Keeping your project on track - Webinar, September 2016Keeping your project on track - Webinar, September 2016
Keeping your project on track - Webinar, September 2016Aconex
 
Deliver Reliable Power Projects - Webinar June 16 2015
Deliver Reliable Power Projects - Webinar June 16 2015Deliver Reliable Power Projects - Webinar June 16 2015
Deliver Reliable Power Projects - Webinar June 16 2015Aconex
 
Achieve competitive advantage through innovative process management
Achieve competitive advantage through innovative process managementAchieve competitive advantage through innovative process management
Achieve competitive advantage through innovative process managementAconex
 
Best practices to predictably meet your project budget
Best practices to predictably meet your project budgetBest practices to predictably meet your project budget
Best practices to predictably meet your project budgetAconex
 
Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015
Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015
Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015Aconex
 
Global Trends in Delivery Projects
Global Trends in Delivery ProjectsGlobal Trends in Delivery Projects
Global Trends in Delivery ProjectsAconex
 
Benefits of a Company-wide Project Management Platform - Webinar, July 2016
Benefits of a Company-wide Project Management Platform - Webinar, July 2016Benefits of a Company-wide Project Management Platform - Webinar, July 2016
Benefits of a Company-wide Project Management Platform - Webinar, July 2016Aconex
 
Real estate analyst kpi
Real estate analyst kpiReal estate analyst kpi
Real estate analyst kpiferascajom
 
Real estate analyst kpi
Real estate analyst kpiReal estate analyst kpi
Real estate analyst kpiwriretuqe
 
5 methods session 2 webinar slideshare systems co
5 methods session 2 webinar slideshare systems co5 methods session 2 webinar slideshare systems co
5 methods session 2 webinar slideshare systems coAconex
 
Electrical inspector kpi
Electrical inspector kpiElectrical inspector kpi
Electrical inspector kpiqewtiret
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Aconex
 
GTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityGTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityDiana Nash
 

Mais procurados (20)

Avoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAvoid the risk and streamline your project controls
Avoid the risk and streamline your project controls
 
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
 
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
 
Aconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performanceAconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performance
 
"Show me the ROI" – concrete results from process improvement
"Show me the ROI" – concrete results from process improvement"Show me the ROI" – concrete results from process improvement
"Show me the ROI" – concrete results from process improvement
 
Digital transformation webinar amer slideshare
Digital transformation webinar amer slideshareDigital transformation webinar amer slideshare
Digital transformation webinar amer slideshare
 
Unlocking Engineering and Construction performance webinar apac slideshare
Unlocking Engineering and Construction performance webinar apac slideshareUnlocking Engineering and Construction performance webinar apac slideshare
Unlocking Engineering and Construction performance webinar apac slideshare
 
Keeping your project on track - Webinar, September 2016
Keeping your project on track - Webinar, September 2016Keeping your project on track - Webinar, September 2016
Keeping your project on track - Webinar, September 2016
 
Deliver Reliable Power Projects - Webinar June 16 2015
Deliver Reliable Power Projects - Webinar June 16 2015Deliver Reliable Power Projects - Webinar June 16 2015
Deliver Reliable Power Projects - Webinar June 16 2015
 
Achieve competitive advantage through innovative process management
Achieve competitive advantage through innovative process managementAchieve competitive advantage through innovative process management
Achieve competitive advantage through innovative process management
 
Best practices to predictably meet your project budget
Best practices to predictably meet your project budgetBest practices to predictably meet your project budget
Best practices to predictably meet your project budget
 
Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015
Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015
Cutting Approval Cycles from 30 Days to Ten - Webinar, September 29, 2015
 
Global Trends in Delivery Projects
Global Trends in Delivery ProjectsGlobal Trends in Delivery Projects
Global Trends in Delivery Projects
 
Benefits of a Company-wide Project Management Platform - Webinar, July 2016
Benefits of a Company-wide Project Management Platform - Webinar, July 2016Benefits of a Company-wide Project Management Platform - Webinar, July 2016
Benefits of a Company-wide Project Management Platform - Webinar, July 2016
 
Real estate analyst kpi
Real estate analyst kpiReal estate analyst kpi
Real estate analyst kpi
 
Real estate analyst kpi
Real estate analyst kpiReal estate analyst kpi
Real estate analyst kpi
 
5 methods session 2 webinar slideshare systems co
5 methods session 2 webinar slideshare systems co5 methods session 2 webinar slideshare systems co
5 methods session 2 webinar slideshare systems co
 
Electrical inspector kpi
Electrical inspector kpiElectrical inspector kpi
Electrical inspector kpi
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 
GTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityGTC_Energy Services_Mexico City
GTC_Energy Services_Mexico City
 

Destaque (20)

Astroz
AstrozAstroz
Astroz
 
Transitividade verbal
Transitividade verbalTransitividade verbal
Transitividade verbal
 
Set four
Set fourSet four
Set four
 
Anexo circular 081 enams 2009 2010.dominio esperado 7 - 2[1]
Anexo circular 081 enams 2009 2010.dominio esperado 7 - 2[1]Anexo circular 081 enams 2009 2010.dominio esperado 7 - 2[1]
Anexo circular 081 enams 2009 2010.dominio esperado 7 - 2[1]
 
Resultados
ResultadosResultados
Resultados
 
8
88
8
 
Marina fernandes
Marina fernandesMarina fernandes
Marina fernandes
 
Fefsedfg
FefsedfgFefsedfg
Fefsedfg
 
Testing
TestingTesting
Testing
 
Observatory guest house website
Observatory guest house websiteObservatory guest house website
Observatory guest house website
 
Avicola
AvicolaAvicola
Avicola
 
Center Stage
Center StageCenter Stage
Center Stage
 
3
33
3
 
Nabou Photography
Nabou PhotographyNabou Photography
Nabou Photography
 
Páginas de Veríssimo
Páginas de VeríssimoPáginas de Veríssimo
Páginas de Veríssimo
 
Caleb
CalebCaleb
Caleb
 
Slideshare video
Slideshare videoSlideshare video
Slideshare video
 
Factos juridicos
Factos juridicosFactos juridicos
Factos juridicos
 
B ag
B agB ag
B ag
 
Tipos de desenvolvimento
Tipos de desenvolvimentoTipos de desenvolvimento
Tipos de desenvolvimento
 

Semelhante a The Case Studies for Project Control Platform - Maurizio M. Granata Business Development Manager Intergraph PP&M

Paperless Document Control
Paperless Document ControlPaperless Document Control
Paperless Document Controlp6academy
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptp6academy
 
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 20165 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016Aconex
 
Strategic Modeling: Right Strategic Decisions Aligned with Operating Plans a...
Strategic Modeling:  Right Strategic Decisions Aligned with Operating Plans a...Strategic Modeling:  Right Strategic Decisions Aligned with Operating Plans a...
Strategic Modeling: Right Strategic Decisions Aligned with Operating Plans a...Joseph Alaimo Jr
 
OpenWorld: 4 Real-world Cloud Migration Case Studies
OpenWorld: 4 Real-world Cloud Migration Case StudiesOpenWorld: 4 Real-world Cloud Migration Case Studies
OpenWorld: 4 Real-world Cloud Migration Case StudiesDatavail
 
Case study businessone (en) 1.0
Case study  businessone (en) 1.0Case study  businessone (en) 1.0
Case study businessone (en) 1.0BIcasestudy
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Softchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost GovernanceSoftchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost GovernanceSoftchoice Corporation
 
Leading practices in Project Planning
Leading practices in Project PlanningLeading practices in Project Planning
Leading practices in Project PlanningAlithya
 
Sameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project ManagementSameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project ManagementSameer Mitter
 
Developing a Modernization Strategy: Evaluating the Options by Chris Koppe
Developing a Modernization Strategy: Evaluating the Options by Chris KoppeDeveloping a Modernization Strategy: Evaluating the Options by Chris Koppe
Developing a Modernization Strategy: Evaluating the Options by Chris KoppeFresche Solutions
 
ETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEightETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEightComit Projects Ltd
 
BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...
BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...
BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...Garth Knudson
 
Modernizing Your Finance Team With Technology
Modernizing Your Finance Team With TechnologyModernizing Your Finance Team With Technology
Modernizing Your Finance Team With TechnologyWorkiva
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentCenter for Energy and Environment
 
Increase your resource capacity without hiring ppt
Increase your resource capacity without hiring pptIncrease your resource capacity without hiring ppt
Increase your resource capacity without hiring pptp6academy
 

Semelhante a The Case Studies for Project Control Platform - Maurizio M. Granata Business Development Manager Intergraph PP&M (20)

CM.pptx
CM.pptxCM.pptx
CM.pptx
 
Cost Management
Cost ManagementCost Management
Cost Management
 
Paperless Document Control
Paperless Document ControlPaperless Document Control
Paperless Document Control
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
 
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 20165 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
 
Strategic Modeling: Right Strategic Decisions Aligned with Operating Plans a...
Strategic Modeling:  Right Strategic Decisions Aligned with Operating Plans a...Strategic Modeling:  Right Strategic Decisions Aligned with Operating Plans a...
Strategic Modeling: Right Strategic Decisions Aligned with Operating Plans a...
 
OpenWorld: 4 Real-world Cloud Migration Case Studies
OpenWorld: 4 Real-world Cloud Migration Case StudiesOpenWorld: 4 Real-world Cloud Migration Case Studies
OpenWorld: 4 Real-world Cloud Migration Case Studies
 
Case Study- BusinessOne
Case Study- BusinessOneCase Study- BusinessOne
Case Study- BusinessOne
 
Case study businessone (en) 1.0
Case study  businessone (en) 1.0Case study  businessone (en) 1.0
Case study businessone (en) 1.0
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Softchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost GovernanceSoftchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost Governance
 
Leading practices in Project Planning
Leading practices in Project PlanningLeading practices in Project Planning
Leading practices in Project Planning
 
Sameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project ManagementSameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project Management
 
Developing a Modernization Strategy: Evaluating the Options by Chris Koppe
Developing a Modernization Strategy: Evaluating the Options by Chris KoppeDeveloping a Modernization Strategy: Evaluating the Options by Chris Koppe
Developing a Modernization Strategy: Evaluating the Options by Chris Koppe
 
ETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEightETDP 2015 D2 Next Generation Bim - InEight
ETDP 2015 D2 Next Generation Bim - InEight
 
BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...
BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...
BizFlow - BPM at Jardine Lloyd Thompson for Sales, Document Handling, Custome...
 
ch07.ppt
ch07.pptch07.ppt
ch07.ppt
 
Modernizing Your Finance Team With Technology
Modernizing Your Finance Team With TechnologyModernizing Your Finance Team With Technology
Modernizing Your Finance Team With Technology
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the Envrinment
 
Increase your resource capacity without hiring ppt
Increase your resource capacity without hiring pptIncrease your resource capacity without hiring ppt
Increase your resource capacity without hiring ppt
 

Último

How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxssuserf63bd7
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.aruny7087
 

Último (14)

How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 

The Case Studies for Project Control Platform - Maurizio M. Granata Business Development Manager Intergraph PP&M

  • 1. The Case Studies for Project Control Platform Copenhagen, November 24th 2016 Maurizio M. Granata – Business Development Executive EMIA – Materials, Costs, & Project Execution Solutions
  • 2. day ON BEHALF OF … COMMON CHALLENGES CLIENTS COMMON ANSWER The Case Studies for Project Control Platform Your Menu today 1 2 3 A FEW EVIDENCES …4 Q & A5
  • 3. On Behalf of … Main menu
  • 4. Welcome on Behalf of …….
  • 6. Projects Correlation between Size & Performance $$$,$$$,$$$ $$$,$$$ $$$ ProjectBudget ProjectPerformance IPA Independent Project Analysis study of over 18,000 projects
  • 7. More Projects challenges Exception Rule Large Capital investments that are completed on Schedule and within their Budgets are probably the Exception rather then the Rule – and even when completed many fail to meet expected revenue targets. Better forecasting for Large Capital Projects Bent Flyvbjerg, Massimo Garbuio, & Dan Lovallo McKinsey & Company
  • 8. i i i i ii ii ii i i i i i Data Sources Analysis and Decisions More Projects challenges ? Access Navigate Understand Macro-Level Comprehensive Accurate
  • 9. …… Room to Improve Source: EcoSys Customer Internal Survey
  • 13. Case Study Marathon Petroleum Solution: • New Enterprise System for optimizing Project Investments on both CapEX and OpEx • All Investments initiatives • Portfolios, • Project Controls, • Shutdown & Turnaround Management • All sites • Consolidate Enterprise Best Practices • Rapid implementation & deployment Benefits: • Centralized Visibility and standardized work processes • $11 M per year savings from better project governance • Project Management staff 55% more productive on both Turnaround & small plant improvements • $1.5 M per year IT maintenance cost savings Business Challenge: • Each Refinery set their control practices • Extensive use of • In-house solutions • Spreadsheets • and manual work • Different ERP integrations
  • 14. Case Study Los Angeles Department of Water & Power Business Challenge: • Lengthy procedures to capture and reconcile project control data • Understanding project status not smooth process • Project performance missed what-if scenario analysis • No Consistent WBS & Milestones • Not efficient Resource handling • Slow manual based Reporting Solution: • New Capital planning & Reporting hub integrating several data sources • Automate data sharing and reporting • Develop performance metrics Benefits: • Significant improvements in project performance visibility provided greater control • Analysis and Forecast comparisons to improve decisions • Meet regulatory deadlines
  • 15. Case Study Houston Airport System Business Challenge: • Lack of consistent: • Capital Program Planning and Funding • Project Cost Management • Reporting Solution: • capital program planning and funding • contract and project setup • grant management, design and construction management including: • change management • cost management • invoicing, document management • workflow and forms management Benefits: • The principal Program Management dashboard and reporting solution • Supporting stakeholders across HAS in Planning, Design, and Construction Division, Finance, and the IT Capital Projects PMO Office
  • 16. Case Study Bechtel Solution: • New Enterprise platform integrating proprietary project control best-practices to deliver optimal financial results • Only platform that can embed Bechtel's robust and proprietary processes with NO needs for costly software customization • Bechtel regularly recommends EcoSys EPC to its customers as the best-in-class solution Benefits: • Enhanced Visibility into margin forecasts and early warning of overruns • More productive PM stuff with a modern system and process automations • Replaced 3 disparate in-house systems for project controls, EVM, and project reporting, resulting in sizeable IT cost savings • EcoSys pitched as key differentiator in competitive bids, reinforcing Bechtel’s reputation as industry leader in processes and tools • More rapid support of client requirements by internal staff Business Challenge: • Replacing highly-mature but outdated internally-developed tool • Integrating with: • Oracle eBusiness ERP, • Intergraph Smart Plant Materials, • custom In-house solutions
  • 19. Bring Value to your Enterprise Projects Control Efforts Before [Common Practice] Source: Internal study by Technip After
  • 20. PROJECT BUDGET Kr. 250.000.000 + + Kr.12.500.000 Cost for Overruns Kr.1.500.000 Costs for Delays and Extended Duration POTENTIAL SAVINGS Ideal savings for On Time & On Budget Delivery Kr.14.000.000 Improved Construction performance Kr. 1.462.500 1.5% on Construction Budget Effective Change Management Kr. 877.500 0.9% on Construction Budget Other Indirect & Direct execution Costs Savings Kr. 1.540.000 1.1% on Engineering & Construction Average Potential Savings Additional Potential savings Kr. 3.880.000 7.15% Total savings Kr. 17.880.000 -kr. 2,000,000.00 -kr. 1,000,000.00 kr. 0.00 kr. 1,000,000.00 kr. 2,000,000.00 kr. 3,000,000.00 kr. 4,000,000.00 kr. 5,000,000.00 kr. 6,000,000.00 kr. 7,000,000.00 kr. 8,000,000.00 Time 0 H1 H2 H3 H4 Time - Phased NPV NPV Implementation & Maintenance
  • 22. Industry Best Practices Re-use Data Ensure Data Integrity Analysis & Forecast Integrate & Share work processes
  • 24. Q & A Main menu
  • 25. Maurizio M. GRANATA Mob. +39 348 2727834 email maurizio.granata@intergraph.com Skype MMGRANATA On LinkedIn include The Future of Engineering Today The Case Studies for Project Control Platform Thank you