Mais conteúdo relacionado Semelhante a LiamBaines_Construction_FACADES (20) LiamBaines_Construction_FACADES2. PLAN LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
Joint project, however this
document contains my Indi-
vidual contribution; facade
design.
Typical ground floor plan
and core layout for the office
block.
West, South and East Ele-
vations are all to have Alu-
cobond facades, while the
North Elevation is to make
maximum use of the sunlight
with a glass curtain wall.
3. GSEducationalVersion
+3,700
2 Ground Floor
+3,700
2 Ground Floor
+7,400
3 1st Floor
+7,400
3 1st Floor
+11,100
4 2nd Floor
+11,100
4 2nd Floor
+14,800
5 3rd Floor
+14,800
5 3rd Floor
+18,500
6 4th Floor
+18,500
6 4th Floor
+22,200
7 5th Floor
+22,200
7 5th Floor
+25,900
8 6th Floor
+25,900
8 6th Floor
+29,600
9 7th Floor
+29,600
9 7th Floor
+33,300
10 8th Floor
+33,300
10 8th Floor
+37,000
11 9th Floor
+37,000
11 9th Floor
1 North Elevation 1:200
NORTH ELEVATION LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
Curtain Wall facade
with opaque glass
along the slab and
column segments.
Allows deepest light
penetration into the
office block.
4. GSEducationalVersion
1 2 3 4 5
+3,700
Ground Floor
+3,700
Ground Floor
+7,400
1st Floor
+7,400
1st Floor
+11,100
2nd Floor
+11,100
2nd Floor
+14,800
3rd Floor
+14,800
3rd Floor
+18,500
4th Floor
+18,500
4th Floor
+22,200
5th Floor
+22,200
5th Floor
+25,900
6th Floor
+25,900
6th Floor
+29,600
7th Floor
+29,600
7th Floor
+33,300
8th Floor
+33,300
8th Floor
+37,000
9th Floor
+37,000
9th Floor
1 West Elevation 1:200
WEST ELEVATION LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
Alucobond facade
with windows above
desk height, and
Alucobond Cassette
System along the
slab and column seg-
ments.
5. GSEducationalVersion
1 Alucobond Detail 1:50
2 Section AA 1:50
Selected 600x600mm
20mm Ceiling tile w/
selected Aluminium
suspended ceiling grid
Alucabond cassette
System
R2.8 Fibreglass
Insulation
90x45 H1.2 timber
framing construction
600x600mm Cast
Insitu RC column w/
steel reinforcing to
Engineers design
10mm Membrane
to top of ecoply
Carpet
75mm RC topping w/
reinforcing as per
engineers design
Stresscrete 200mm RC
precast plank floor system
w/20mm H3.2 plywood
infill
Selected 600x600mm
20mm Ceiling tile w/
selected Aluminium
suspended ceiling grid
Thermosash 40mm double
glazing
Commercial
Aluminium window
Joinery
R2.8 Fibreglass Insulation
Ecoply Rigid Air Barrier
90x45 H1.2 timber framing
construction
Alucobond casette
system over 7mm
Ecoply Rigid Air
Barrier w/
proprietary tape.
The Ecoply barrier
is fixed to 90x45
H1.2 timber
framing w/R2.8
fibreglass
insulation. The
timber framing is
then fixed to RC
concrete
construction w/
M16 Bolts
2/ 10mm GIB Fyreline wall
lining
7mm Ecoply rigid
air barrier
R2.8 fibreglass
insulation
90x45 H1.2 timber
framing @ 600mm
ctrs w/ dwangs @
800mm vertical
centres
600x600mm Cast Insitu RC
column w/ steel reinforcing
to Engineers design
Thermosash 40mm
double glazing
Commercial
Aluminium window
Joinery
ALUCOBOND DETAIL LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
6. GSEducationalVersion
1 Curtainwall Detail 1:50
2 Section BB 1:50
Selected 600x600mm
20mm Ceiling tile w/
selected Aluminium
suspended ceiling grid
600x600mm Cast
Insitu RC column w/
steel reinforcing to
Engineers design
Carpet
75mm RC topping w/
reinforcing as per
engineers design
Stresscrete 200mm RC
precast plank floor system
w/20mm H3.2 plywood
infill
Selected 600x600mm
20mm Ceiling tile w/
selected Aluminium
suspended ceiling grid
Thermosash 40mm double
glazing
Thermosash
curtain facade
system suspended
in front of slab on
10mm mild steel
bracket attaching
vertical mullions to
the slab
Frosted glazing on
slab layer
600x600mm Cast Insitu RC
column w/ steel reinforcing
to Engineers design
Thermosash curtain
wall stick system w/
double glazing
Aluminium facade
system window
Joinery
Frosted glazing on
slab layer
Fire safing
CURTAIN WALL DETAIL LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014