SlideShare uma empresa Scribd logo
1 de 37
Baixar para ler offline
Konstantinos Seferoglou, Civil (Geotechnical) Engineer, M.Sc.
Isabella Vassilopoulou, Dr. Civil (Structural) Engineer
Fragiskos Chrysohoidis, Engineering Geologist M.Sc., DIC
Petros Fortsakis, Dr. Civil (Geotechnical) Engineer
Georgios Prountzopoulos, Dr. Civil (Geotechnical) Engineer
Konstantinos Nikas, Civil (Geotechnical) Engineer, M.Sc.
Building a bridge over an active landslide
Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
2
CONTENTS
• INTRODUCTION
• TEMPORARY INFRASTRUCTURE PROJECTS
• INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM
• DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
• THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
3
In 2003 a major landslide destroyed a
highway in southern Greece causing a
mass displacement of about 6.000.000m3.
INTRODUCTION
Major landslide event
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
4
An arched steel bridge was designed
over the active landslide creating
geotechnical and structural challenges
during the construction.
2003
2013 2016
INTRODUCTION
Bridge project
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
5
INTRODUCTION
Bridge project
The 390m long bridge consisted of an access part made of prestressed concrete between the
northern abutment and the pier with total length 130m and an arched part with suspended steel
deck of 260m between the pier and the southern abutment.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
6
Landslide limits
INTRODUCTION
Bridging an active landslide
The arch was designed to bridge over the landslide, which was active and moved downstream at an
average rate of about 1.5-2.0mm/month. The rate of movement increased dramatically during the
winter rainfalls, exceeding for short periods of time, 30mm/month.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
7
• INTRODUCTION
• TEMPORARY INFRASTRUCTURE PROJECTS
• INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM
• DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
• THE BRIDGE UNDER CONSTRUCTION
TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
8
TEMPORARY INFRASTRUCTURE PROJECTS
Construction of the pier and the concrete part of the superstructure
The V-shaped supporting struts, forming the pier, was constructed first. The 55m part of the deck
followed, ensuring the stability of the pier. The 130m access concrete bridge was completed, with
the construction of the 75m part of the deck between the pier and the abutment, using heavy duty
PERI bridge-type scaffolding and founded with piles on adverse surface morphology and soil
conditions.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
9
Landslide limits
TEMPORARY INFRASTRUCTURE PROJECTS
Construction of the arch
During the construction period, it was required to use the landslide body as a foundation ground to
support 16 steel towers up to 60m high. The towers aimed at heavy lifting and final assembly at
height of the steel arch parts. At the same time, the heavy highway traffic was deviated to pass on
top of the slide body.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
10
Landslide limits
TEMPORARY INFRASTRUCTURE PROJECTS
Foundation of the towers
The foundation of the towers consisted of piles connected with pile-caps. Between the pile-caps
concrete slabs on ground and small temporary bridges on pile systems were also constructed,
which were used for the assembling/welding of the arch and deck segments. Most of the deep
foundation and the supporting structures were built in the active landslide where the evolving
movements were observed.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
11
Infrastructure for the erection of the steel arches
TEMPORARY INFRASTRUCTURE PROJECTS
Southern
Abutment
Temporary traffic
Pilewall to retain the
temporary road
Assembly
towers ΜΤ
Assembly piers
Π1Δ-Π7Δ
Assembly
slabs/bridges
Assembly piers
Π1Α-Π7Α
Assembly
slabs on
ground
Middle pier
strut
Landslide limits and
movement
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
12
• INTRODUCTION
• TEMPORARY INFRASTRUCTURE PROJECTS
• INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM
• DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
• THE BRIDGE UNDER CONSTRUCTION
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
13
4 optical targets for surface movements
26 optical targets for movements of pier foundation
6 optical targets for movements of the pile wall
4 automated permanent inclinometers
3 automated permanent piezometers
7 conventional inclinometers
conventional piezometers
Geotechnical instruments
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
14
Automated Monitoring - Schematic Function
Data Logger & Modem
Scheduled Readings
(i.e. every 4 hours)
Readings
downloaded to
server in txt
format
Programmed
spreadsheet
collects
downloaded
data
Data elaborated,
analyzed and
graphs for each
instrument is
created
automatically
Alarm SMS is released in
case the movements exceed
the limits (TSAKONA
ALARM)
Extra readings and
evaluation performed,
instruction for contingency
measures provided.
The updated spreadsheet
is uploaded on a shared
cloud server and provides
the evaluation of the
developments at least
every 4 hours.
Monthly reports
submitted
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
15
Main conclusions drawn from monitoring results
• A seasonal variation of the rate of movement of the slide was noted related to rainfall.
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
16
• A seasonal variation of the rate of movement of the slide was noted related to rainfall.
• Differences of the rate of movement were observed among the various monitoring locations
(13 - 40mm/year). Factors influencing the rate are the depth of the sliding surface and the
inclination of the bedrock surface.
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
Main conclusions drawn from monitoring results
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
17
Main conclusions drawn from monitoring results
Sliding surface
(zone)
Characteristic section
Bedrock surface
Bridge Axis
Temporary
highway traffic
Position of piers foundation
Pile wall
Sliding zone
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
• A seasonal variation of the rate of movement of the slide was noted related to rainfall.
• Differences of the rate of movement were observed among the various monitoring locations
(13 - 40mm/year). Factors influencing the rate are the depth of the sliding surface and the
inclination of the bedrock surface.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
18
Main conclusions drawn from monitoring results
• Deep movements (inclinometric readings) and surface movements (optical targets movements)
were in good agreement.
Location of readings
Depth of
sliding zone
Mean total annual
movement
Sliding zone Τ4-ΚΝ1 and Τ4-ΚΝ2 15-20m 27mm
Optical targets on pile wall Μ2, Μ3, Μ4 18-22m 25mm
Optical targets on pile caps Π2Α, Π3Α, Π4Α 18-20m 29mm
Optical targets on pile caps Π2Δ, Π3Δ, Π4Δ 30-34m 34mm
Sliding zone ΚΛ5 and ΚΛ6 35-40m 32mm
Comparison of Deep Vs Surface movements (28/03/13÷7/03/14)
• For the design of the projects a two years construction period was assumed and the proposed
design movement (transverse to the bridge axis) was 30mm/year and for the longitudinal
direction a total differential movement between temporary piers of about 15mm/year was
considered.
INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
• A seasonal variation of the rate of movement of the slide was noted related to rainfall.
• Differences of the rate of movement were observed among the various monitoring locations
(13 - 40mm/year). Factors influencing the rate are the depth of the sliding surface and the
inclination of the bedrock surface.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
19
• INTRODUCTION
• TEMPORARY INFRASTRUCTURE PROJECTS
• INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM
• DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
• THE BRIDGE UNDER CONSTRUCTION
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
20
Design of the towers foundation
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
The most challenging of the required temporary infrastructure, was the design of the foundation of
the 14 steel piers used for the heavy lifting final assembly at height, of the 36m parts of the arch
pair. The demanding stability within a moving mass, combined with the very tight accuracy
requirements of the arch welding activities and the significant loads transferred to the ground,
comprised the technical framework for the design of these works.
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
21
• Two years of arch construction
• 30mm/year max horizontal movement
• Temporary structures – low cost
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Assumptions
Design Criteria
• Not possible to stabilize the landslide
• Safety of the temporary traffic of the
highway
• Safe erection of the arch
• Stability and tight accuracy for the
welding activities
Aim
• Floating piles in the sliding mass
(depth 8m-22m)
• Piles in the rock for depth of sliding
mass smaller than 5m
• Deep foundation with pile groups
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
22
Piers foundation design methodology
• As the major concern was the influence of the landslide movements on the bending moments
and shear forces on each pile group, it was decided to use initially a 3D (ABAQUS) model as a
guide for the geotechnical assessments. The excitation due to soil mass movements was
introduced using a real profile of the movements as it was depicted from the monitoring data.
External loading from the superstructure was also added.
• The 3D guide-model was then used to calibrate 2D geotechnical models (PLAXIS) for each one of
the 14 piers, which led to the assessment of bending and shear increase due to the soil
movement, considering in each case the local morphology of the sliding surface and the local
profile of the soil mass movement.
• Finally, the results of the geotechnical analyses provided the required data to feed more detailed
3D structural analysis (SOFiSTiK), used for the optimization of the dimensioning and required
reinforcement of each structural element of the foundation.
Phase 1: Analysis with the
detailed 3D FE «guide-
model»
Phase 2: Calibration of the
geotechnical 2D FE model
with the «guide-model»
Phase 3: Geotechnical analysis of 2D FE
models adjusted to the local morphology
and loadings for each pair of piers
Phase 4: Calibration of the
structural 3D FE model with
the «guide-model»
Phase 5: Structural design of 3D FE models and reinforcement
optimization for each pier. Extra calculations for contingency hypotheses
of shallow failure planes as well as anchoring of the pile groups
DESIGN OF INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
23
Phase 1: 3D geotechnical analysis (guide-model, ABAQUS)
Step 1 Step 2 Step 3 Step 5
Transverse slope movement
Step 4
The slope movement practically
led to a uniform movement of the
soil above the failure plane,
causing small increase of bending,
shear and axial internal forces of
the piles. (ΔN=+3.4%, ΔQ=4.2%,
ΔM=37.5%)
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
24
Phase 2: 2D geotechnical analyses (PLAXIS)
Model calibration
PLAXIS ABAQUS
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
25
Π1 Π2 Π3
Π4 Π5 Π6 Π7
Phase 3: 2D geotechnical analyses for each pair of piers (PLAXIS)
Earth pressure and
soil spring values
calculated to be
fed into structural
models in Phase 4.
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
26
Phase 4: 3D structural analyses (SOFiSTiK)
Model calibration and design
SOFiSTiK ABAQUS
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
27
• Local shallow failure plane developed introducing a 15mm transverse movement.
Anchoring is also activated in this case.
Contingency working hypotheses
Phase 5: 3D structural analyses (SOFiSTiK)
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
28
• Contingency anchoring of the pile caps in case the movements exceeded the
predicted values or the tolerance of the superstructure during the erection of the
steel arches
Location of contingency
anchoring on the pile cap
Contingency working hypotheses
Phase 5: 3D structural analyses (SOFiSTiK)
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
29
Design of the temporary towers foundation
• Self weight
• Loads from the temporary towers
• Loads from the slabs/bridges
• Earth pressures (static and seismic)
• Seismic action α=0.08g (temporary project)
• Soil movements 15mm (Local shallow failure planes at the piers Π2Δ – Π5Δ)
• Forces from anchoring
Comparison of piles internal forces due to static and seismic load combinations
(SOFiSTiK) with the corresponding ones due to the soil movement (PLAXIS)
Small differences were observed up to 3% for the axial forces and 6% for the
bending moments. Hence, for the piles of piers Π2Δ – Π5Δ an increase of the
required reinforcement was considered up to 10%.
Phase 5: 3D structural analyses (SOFiSTiK)
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
30
• INTRODUCTION
• TEMPORARY INFRASTRUCTURE PROJECTS
• INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM
• DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
• THE BRIDGE UNDER CONSTRUCTION
DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
31
THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
32
THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
33
THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
34
THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
35
THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
36
THE BRIDGE UNDER CONSTRUCTION
Building a bridge over an active landslide. Geotechnical and Structural Challenges
ODOTECHNIKI Ltd, Athens, Greece
37
Contractor: TERNA S.A. (Initially J/V TERNA S.A. –
ALPINE BAU)
Structural design of the Tsakona bridge: DOMI S.A.
Geotechnical and foundation design of the Tsakona bridge: EDAFOS S.A.
Design of infrastructure projects and construction consulting: ODOTECHNIKI Ltd
Design of heavy lifting scaffolding: PERI Formwork Scaffolding Engineering
Steel fabrication and erection: EMEK S.A.
Consulting support on optimization of ABAQUS by Prof. I. Anastasopoulos and K. Tzivakos, Civil Engineers.
DESIGN AND CONSTRUCTION TEAM

Mais conteúdo relacionado

Mais procurados

Design and analysis of flexible pavement docx
Design and analysis of flexible pavement docxDesign and analysis of flexible pavement docx
Design and analysis of flexible pavement docxDevesh Chaurasia
 
Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasShantanu Patil
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part IISachin Kulkarni
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its typesprathiekraj1
 
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]Muhammad Irfan
 
Strengthening and Widening of road (P.W.D)(Summer Training)
Strengthening and Widening of road (P.W.D)(Summer Training)Strengthening and Widening of road (P.W.D)(Summer Training)
Strengthening and Widening of road (P.W.D)(Summer Training)Arif Siddiqui
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavementAglaia Connect
 
Report on Widening and Construction of Roads
Report on Widening and Construction of RoadsReport on Widening and Construction of Roads
Report on Widening and Construction of RoadsSanjeev B
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...
EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...
EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...IAEME Publication
 
Widening and Strengthening of Roads Final Report
Widening and Strengthening of Roads Final ReportWidening and Strengthening of Roads Final Report
Widening and Strengthening of Roads Final ReportNaresh Anumandla
 
Airfield design methods
Airfield design methodsAirfield design methods
Airfield design methodsBhavya Jaiswal
 
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Muhammad Irfan
 
Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1GARRE RAVI KUMAR
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 

Mais procurados (20)

Design and analysis of flexible pavement docx
Design and analysis of flexible pavement docxDesign and analysis of flexible pavement docx
Design and analysis of flexible pavement docx
 
Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly Areas
 
DESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENTDESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENT
 
Geotechnical engineering ppt 0719
Geotechnical engineering ppt 0719Geotechnical engineering ppt 0719
Geotechnical engineering ppt 0719
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its types
 
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
Geotechnical Engineering-II [Lec #6: Stress Distribution in Soil]
 
Strengthening and Widening of road (P.W.D)(Summer Training)
Strengthening and Widening of road (P.W.D)(Summer Training)Strengthening and Widening of road (P.W.D)(Summer Training)
Strengthening and Widening of road (P.W.D)(Summer Training)
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
 
Report on Widening and Construction of Roads
Report on Widening and Construction of RoadsReport on Widening and Construction of Roads
Report on Widening and Construction of Roads
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...
EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...
EXPERIMENTAL INVESTIGATION ON CALIFORNIA BEARING RATIO FOR MECHANICALLY STABI...
 
Widening and Strengthening of Roads Final Report
Widening and Strengthening of Roads Final ReportWidening and Strengthening of Roads Final Report
Widening and Strengthening of Roads Final Report
 
Airfield design methods
Airfield design methodsAirfield design methods
Airfield design methods
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
 
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
 
Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
response spectra
response spectraresponse spectra
response spectra
 

Semelhante a BRIDGING OVER A LANDSLIDE

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Mihalis presentation final 10092011
Mihalis presentation final 10092011Mihalis presentation final 10092011
Mihalis presentation final 10092011ILIAS MICHALIS
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecturegefyra-rion
 
Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"Dr. Ezzat Elsayed Gomaa
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011ILIAS MICHALIS
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsIRJET Journal
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsIRJET Journal
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructionsVinay Vb
 
Mohammad S. Alshakhatreh - Geotechnical / Grouting
Mohammad S. Alshakhatreh - Geotechnical / Grouting Mohammad S. Alshakhatreh - Geotechnical / Grouting
Mohammad S. Alshakhatreh - Geotechnical / Grouting MohammedAlshakhatreh
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifaSUNILPRASAD68
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005gefyra-rion
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptxSubratDash37
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 

Semelhante a BRIDGING OVER A LANDSLIDE (20)

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Mihalis presentation final 10092011
Mihalis presentation final 10092011Mihalis presentation final 10092011
Mihalis presentation final 10092011
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecture
 
Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011
 
Pecker aci2003
Pecker aci2003Pecker aci2003
Pecker aci2003
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
KONSTANTINOS SEFEROGLOU CV_2016
KONSTANTINOS SEFEROGLOU CV_2016KONSTANTINOS SEFEROGLOU CV_2016
KONSTANTINOS SEFEROGLOU CV_2016
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Summer training
Summer  trainingSummer  training
Summer training
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Mohammad S. Alshakhatreh - Geotechnical / Grouting
Mohammad S. Alshakhatreh - Geotechnical / Grouting Mohammad S. Alshakhatreh - Geotechnical / Grouting
Mohammad S. Alshakhatreh - Geotechnical / Grouting
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifa
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
PROJECTS index updated
PROJECTS index updatedPROJECTS index updated
PROJECTS index updated
 
Dfi2005 pecker
Dfi2005 peckerDfi2005 pecker
Dfi2005 pecker
 

BRIDGING OVER A LANDSLIDE

  • 1. Konstantinos Seferoglou, Civil (Geotechnical) Engineer, M.Sc. Isabella Vassilopoulou, Dr. Civil (Structural) Engineer Fragiskos Chrysohoidis, Engineering Geologist M.Sc., DIC Petros Fortsakis, Dr. Civil (Geotechnical) Engineer Georgios Prountzopoulos, Dr. Civil (Geotechnical) Engineer Konstantinos Nikas, Civil (Geotechnical) Engineer, M.Sc. Building a bridge over an active landslide Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece
  • 2. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 2 CONTENTS • INTRODUCTION • TEMPORARY INFRASTRUCTURE PROJECTS • INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM • DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS • THE BRIDGE UNDER CONSTRUCTION
  • 3. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 3 In 2003 a major landslide destroyed a highway in southern Greece causing a mass displacement of about 6.000.000m3. INTRODUCTION Major landslide event
  • 4. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 4 An arched steel bridge was designed over the active landslide creating geotechnical and structural challenges during the construction. 2003 2013 2016 INTRODUCTION Bridge project
  • 5. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 5 INTRODUCTION Bridge project The 390m long bridge consisted of an access part made of prestressed concrete between the northern abutment and the pier with total length 130m and an arched part with suspended steel deck of 260m between the pier and the southern abutment.
  • 6. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 6 Landslide limits INTRODUCTION Bridging an active landslide The arch was designed to bridge over the landslide, which was active and moved downstream at an average rate of about 1.5-2.0mm/month. The rate of movement increased dramatically during the winter rainfalls, exceeding for short periods of time, 30mm/month.
  • 7. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 7 • INTRODUCTION • TEMPORARY INFRASTRUCTURE PROJECTS • INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM • DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS • THE BRIDGE UNDER CONSTRUCTION TEMPORARY INFRASTRUCTURE PROJECTS
  • 8. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 8 TEMPORARY INFRASTRUCTURE PROJECTS Construction of the pier and the concrete part of the superstructure The V-shaped supporting struts, forming the pier, was constructed first. The 55m part of the deck followed, ensuring the stability of the pier. The 130m access concrete bridge was completed, with the construction of the 75m part of the deck between the pier and the abutment, using heavy duty PERI bridge-type scaffolding and founded with piles on adverse surface morphology and soil conditions.
  • 9. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 9 Landslide limits TEMPORARY INFRASTRUCTURE PROJECTS Construction of the arch During the construction period, it was required to use the landslide body as a foundation ground to support 16 steel towers up to 60m high. The towers aimed at heavy lifting and final assembly at height of the steel arch parts. At the same time, the heavy highway traffic was deviated to pass on top of the slide body.
  • 10. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 10 Landslide limits TEMPORARY INFRASTRUCTURE PROJECTS Foundation of the towers The foundation of the towers consisted of piles connected with pile-caps. Between the pile-caps concrete slabs on ground and small temporary bridges on pile systems were also constructed, which were used for the assembling/welding of the arch and deck segments. Most of the deep foundation and the supporting structures were built in the active landslide where the evolving movements were observed.
  • 11. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 11 Infrastructure for the erection of the steel arches TEMPORARY INFRASTRUCTURE PROJECTS Southern Abutment Temporary traffic Pilewall to retain the temporary road Assembly towers ΜΤ Assembly piers Π1Δ-Π7Δ Assembly slabs/bridges Assembly piers Π1Α-Π7Α Assembly slabs on ground Middle pier strut Landslide limits and movement
  • 12. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 12 • INTRODUCTION • TEMPORARY INFRASTRUCTURE PROJECTS • INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM • DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS • THE BRIDGE UNDER CONSTRUCTION INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
  • 13. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 13 4 optical targets for surface movements 26 optical targets for movements of pier foundation 6 optical targets for movements of the pile wall 4 automated permanent inclinometers 3 automated permanent piezometers 7 conventional inclinometers conventional piezometers Geotechnical instruments INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
  • 14. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 14 Automated Monitoring - Schematic Function Data Logger & Modem Scheduled Readings (i.e. every 4 hours) Readings downloaded to server in txt format Programmed spreadsheet collects downloaded data Data elaborated, analyzed and graphs for each instrument is created automatically Alarm SMS is released in case the movements exceed the limits (TSAKONA ALARM) Extra readings and evaluation performed, instruction for contingency measures provided. The updated spreadsheet is uploaded on a shared cloud server and provides the evaluation of the developments at least every 4 hours. Monthly reports submitted INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
  • 15. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 15 Main conclusions drawn from monitoring results • A seasonal variation of the rate of movement of the slide was noted related to rainfall. INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM
  • 16. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 16 • A seasonal variation of the rate of movement of the slide was noted related to rainfall. • Differences of the rate of movement were observed among the various monitoring locations (13 - 40mm/year). Factors influencing the rate are the depth of the sliding surface and the inclination of the bedrock surface. INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM Main conclusions drawn from monitoring results
  • 17. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 17 Main conclusions drawn from monitoring results Sliding surface (zone) Characteristic section Bedrock surface Bridge Axis Temporary highway traffic Position of piers foundation Pile wall Sliding zone INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM • A seasonal variation of the rate of movement of the slide was noted related to rainfall. • Differences of the rate of movement were observed among the various monitoring locations (13 - 40mm/year). Factors influencing the rate are the depth of the sliding surface and the inclination of the bedrock surface.
  • 18. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 18 Main conclusions drawn from monitoring results • Deep movements (inclinometric readings) and surface movements (optical targets movements) were in good agreement. Location of readings Depth of sliding zone Mean total annual movement Sliding zone Τ4-ΚΝ1 and Τ4-ΚΝ2 15-20m 27mm Optical targets on pile wall Μ2, Μ3, Μ4 18-22m 25mm Optical targets on pile caps Π2Α, Π3Α, Π4Α 18-20m 29mm Optical targets on pile caps Π2Δ, Π3Δ, Π4Δ 30-34m 34mm Sliding zone ΚΛ5 and ΚΛ6 35-40m 32mm Comparison of Deep Vs Surface movements (28/03/13÷7/03/14) • For the design of the projects a two years construction period was assumed and the proposed design movement (transverse to the bridge axis) was 30mm/year and for the longitudinal direction a total differential movement between temporary piers of about 15mm/year was considered. INSTRUMENTATION – MONITORING – EARLY WARNING SYSTEM • A seasonal variation of the rate of movement of the slide was noted related to rainfall. • Differences of the rate of movement were observed among the various monitoring locations (13 - 40mm/year). Factors influencing the rate are the depth of the sliding surface and the inclination of the bedrock surface.
  • 19. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 19 • INTRODUCTION • TEMPORARY INFRASTRUCTURE PROJECTS • INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM • DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS • THE BRIDGE UNDER CONSTRUCTION DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 20. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 20 Design of the towers foundation DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS The most challenging of the required temporary infrastructure, was the design of the foundation of the 14 steel piers used for the heavy lifting final assembly at height, of the 36m parts of the arch pair. The demanding stability within a moving mass, combined with the very tight accuracy requirements of the arch welding activities and the significant loads transferred to the ground, comprised the technical framework for the design of these works.
  • 21. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 21 • Two years of arch construction • 30mm/year max horizontal movement • Temporary structures – low cost DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS Assumptions Design Criteria • Not possible to stabilize the landslide • Safety of the temporary traffic of the highway • Safe erection of the arch • Stability and tight accuracy for the welding activities Aim • Floating piles in the sliding mass (depth 8m-22m) • Piles in the rock for depth of sliding mass smaller than 5m • Deep foundation with pile groups
  • 22. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 22 Piers foundation design methodology • As the major concern was the influence of the landslide movements on the bending moments and shear forces on each pile group, it was decided to use initially a 3D (ABAQUS) model as a guide for the geotechnical assessments. The excitation due to soil mass movements was introduced using a real profile of the movements as it was depicted from the monitoring data. External loading from the superstructure was also added. • The 3D guide-model was then used to calibrate 2D geotechnical models (PLAXIS) for each one of the 14 piers, which led to the assessment of bending and shear increase due to the soil movement, considering in each case the local morphology of the sliding surface and the local profile of the soil mass movement. • Finally, the results of the geotechnical analyses provided the required data to feed more detailed 3D structural analysis (SOFiSTiK), used for the optimization of the dimensioning and required reinforcement of each structural element of the foundation. Phase 1: Analysis with the detailed 3D FE «guide- model» Phase 2: Calibration of the geotechnical 2D FE model with the «guide-model» Phase 3: Geotechnical analysis of 2D FE models adjusted to the local morphology and loadings for each pair of piers Phase 4: Calibration of the structural 3D FE model with the «guide-model» Phase 5: Structural design of 3D FE models and reinforcement optimization for each pier. Extra calculations for contingency hypotheses of shallow failure planes as well as anchoring of the pile groups DESIGN OF INFRASTRUCTURE PROJECTS
  • 23. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 23 Phase 1: 3D geotechnical analysis (guide-model, ABAQUS) Step 1 Step 2 Step 3 Step 5 Transverse slope movement Step 4 The slope movement practically led to a uniform movement of the soil above the failure plane, causing small increase of bending, shear and axial internal forces of the piles. (ΔN=+3.4%, ΔQ=4.2%, ΔM=37.5%) DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 24. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 24 Phase 2: 2D geotechnical analyses (PLAXIS) Model calibration PLAXIS ABAQUS DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 25. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 25 Π1 Π2 Π3 Π4 Π5 Π6 Π7 Phase 3: 2D geotechnical analyses for each pair of piers (PLAXIS) Earth pressure and soil spring values calculated to be fed into structural models in Phase 4. DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 26. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 26 Phase 4: 3D structural analyses (SOFiSTiK) Model calibration and design SOFiSTiK ABAQUS DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 27. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 27 • Local shallow failure plane developed introducing a 15mm transverse movement. Anchoring is also activated in this case. Contingency working hypotheses Phase 5: 3D structural analyses (SOFiSTiK) DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 28. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 28 • Contingency anchoring of the pile caps in case the movements exceeded the predicted values or the tolerance of the superstructure during the erection of the steel arches Location of contingency anchoring on the pile cap Contingency working hypotheses Phase 5: 3D structural analyses (SOFiSTiK) DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 29. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 29 Design of the temporary towers foundation • Self weight • Loads from the temporary towers • Loads from the slabs/bridges • Earth pressures (static and seismic) • Seismic action α=0.08g (temporary project) • Soil movements 15mm (Local shallow failure planes at the piers Π2Δ – Π5Δ) • Forces from anchoring Comparison of piles internal forces due to static and seismic load combinations (SOFiSTiK) with the corresponding ones due to the soil movement (PLAXIS) Small differences were observed up to 3% for the axial forces and 6% for the bending moments. Hence, for the piles of piers Π2Δ – Π5Δ an increase of the required reinforcement was considered up to 10%. Phase 5: 3D structural analyses (SOFiSTiK) DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 30. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 30 • INTRODUCTION • TEMPORARY INFRASTRUCTURE PROJECTS • INSTRUMENTATION, MONITORING AND EARLY WARNING SYSTEM • DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS • THE BRIDGE UNDER CONSTRUCTION DESIGN OF TEMPORARY INFRASTRUCTURE PROJECTS
  • 31. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 31 THE BRIDGE UNDER CONSTRUCTION
  • 32. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 32 THE BRIDGE UNDER CONSTRUCTION
  • 33. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 33 THE BRIDGE UNDER CONSTRUCTION
  • 34. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 34 THE BRIDGE UNDER CONSTRUCTION
  • 35. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 35 THE BRIDGE UNDER CONSTRUCTION
  • 36. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 36 THE BRIDGE UNDER CONSTRUCTION
  • 37. Building a bridge over an active landslide. Geotechnical and Structural Challenges ODOTECHNIKI Ltd, Athens, Greece 37 Contractor: TERNA S.A. (Initially J/V TERNA S.A. – ALPINE BAU) Structural design of the Tsakona bridge: DOMI S.A. Geotechnical and foundation design of the Tsakona bridge: EDAFOS S.A. Design of infrastructure projects and construction consulting: ODOTECHNIKI Ltd Design of heavy lifting scaffolding: PERI Formwork Scaffolding Engineering Steel fabrication and erection: EMEK S.A. Consulting support on optimization of ABAQUS by Prof. I. Anastasopoulos and K. Tzivakos, Civil Engineers. DESIGN AND CONSTRUCTION TEAM