Update – Week of
10.18.2010
Current Activities this Week:
Foundations:
Area 4 Field Level – Backfill of foundations for “infill”
area between Column Lines 39-1 is complete.
Concrete Flatwork:
Area 3 Field Level – Concrete for base slab at Cauldron
Club is complete. Field Level Area 3 – Cauldron Club base slab
has been placed.
Masonry:
Area 3 – Masonry pilaster installation at Truck Dock is
ongoing. Area 1, 2, 3 – Masonry installation is ongoing
at Concession Buildings.
Steel:
Area 1, 2, 3 – Canopy decking installation is ongoing.
Area 2 – Concession Building steel truss and decking
installation is nearly complete. Area 1 – Elevator
support steel installation is ongoing for F1.
Area 1 – Masonry and Densglas installation
at Northwest corner of West Building.
Roofing and Sheetmetal:
Area 1, 3 – Canopy gutter installation is complete.
Area 1 – Subgirt installation for metal panels is ongoing
at West Building.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Drywall installation is
is ongoing at Field and Mezzanine Levels
Field Level Area 3 – Masonry pilaster
installation at East Elevation (Truck Dock).
Building the Future
2. Glass:
Area 1 - Curtainwall framing and glass installation is
ongoing at West Building on west, south and east
elevations. South “wing” framing is complete.
MEP Rough-in:
Area 4 – Underground MEP rough-in is ongoing.
West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing. Field Level Area 4 – Structural steel at infill
Plumbing rough-in is ongoing on Suite and area is set and foundations are backfilled.
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Projected Activities occurring next Week:
Concrete Flatwork:
Area 3 Field Level – Prep for Slab-on-Grade at Stair 1
will continue. Area 4 Field Level – Installation of on-grade
seating risers and intermediate stairs will continue.
Area 1 Concourse Level – Placement of topping slabs inside
Concession Buildings will begin. Concourse Level Area 1 – Soffit construction
on SW Concourse Concession Buildings.
Masonry:
Area 3 – Field level masonry installation will continue in
Area C and D. Area 1, 2, 3 – Concourse building
masonry installation will continue.
Steel:
Field Level Area 3 – Misc steel installation that supports
Burnished CMU will begin. Field Level Area 2 - Subroof
installation will continue.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building will continue. Area 1 – Subgirt installation at Mezzanine Level Area 4 – Slab prep is
West Building will continue. ongoing for Mezzanine walkway.
Metal Stud Framing:
Area 1 – Metal stud framing on Field Level will continue.
Area 1 - Drywall installation will continue at Field Level
Building the Future
3. and Mezzanine Level. Drywall installation will begin on
Suite Level.
Glass:
Area 1 – Curtain Framing and Glass installation around West
Building will continue. Curtainwall framing on Suite and
Press Level balconies will continue. Solar Innovations
recessed track will deliver.
Area 1 – Shot of the Field Side of the West
MEP Rough-in: Building looking Northwest.
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels. MEP
rough-in will continue in Main Concourse Buildings.
Area 1 – Shot of the west building showing
the progress of the exterior envelope.
Building the Future
4. Additional Photos:
Field Level Area 2– Swithgear is set in Concourse Level Area 2 – Plumbing carriers
Electrical Service Room 01.20.01. set in Restrooms 03.19.01.
Field Level Area 3 – Emergency Generator is Concourse Level Area 1 – Stair 4 installation
set. is ongoing.
Concourse Level Area 4 – Installation of
metal decking is nearly complete at “infill” Field Level Area 1 – Metal stud framing is
area. ongoing in Wizards Locker room.