SlideShare uma empresa Scribd logo
1 de 194
DEEP FOUNDTION
Jyoti Khatiwada Anischit
This part is also useful for site investigation
DEEP FOUNDATION
DEFINITION
 If the depth of a foundation is greater than its
width, the foundation is known as deep
foundation.
 In deep foundation the depth to width ratio is
usually greater than 4 to 5.
 Deep foundations as compare to Shallow
foundations distribute the load of the super structure
vertically rather than laterally.
 Deep foundations are provided when the expected
loads from superstructure cannot be supported on
shallow foundations.
Examples of Deep Foundations
 Pile foundations
 Pier foundations
 Wells or
Caissons foundations.
WHEN IT IS USED?
 In cases where
 The strata of good bearing capacity is not available near the ground
 The space is restricted to allow for spread footings
 In these cases the foundation of the structure has to be taken
deep with the purpose of attaining a bearing stratum which is
suitable and which ensures stability and durability of a structure.
 The bearing stratum is not the only case. There may be many
other cases. For example, the foundation for a bridge pier must
be placed below the scour depth, although suitable bearing
stratum may exist at a higher level.
TYPES OF DEEP FOUNDATION
Deep foundation is classified into following types:
• Pile foundation
• Well foundation
• Caisson foundation
Pile Foundations
 Pile foundations are the part of a structure used to
carry and transfer the load of the structure to the
bearing ground located at some depth below ground
surface.
 The main components of the foundation
1. The piles 2. The pile caps
CONT’D
 Piles are long and slender
members which transfer
the load to deeper soil or
rock of high bearing
capacity avoiding
shallow soil of low
bearing capacity.
 Pile caps are thick slabs
used to tie a group of
piles together to support
and transmit column
loads to the piles.
Pile Foundations
 Where Used :
 stratum of required bearing capacity is at greater depth
 steep slopes are encountered
 Compressible soil or water-logged soil or soil of made-up type
 Examples: Piles are used for foundation for buildings, trestle-bridges
and water front installations (piers, docks etc ).
Types of Piles Based on Function
Classification based on Function or Use
1. End Bearing Piles
2. Skin Friction Piles
3. Compaction Piles
4. Driven Piles
5. Auger cast Piles
Types of Piles (cont’d)
End Bearing Piles
 Driven into the ground until a
hard stratum is reached.
 Acts as pillars supporting the
super-structure and transmitting
the load to the ground.
 Piles, by themselves do not
support the load, rather acts as
a medium to transmit the load
from the foundation to the
resisting sub-stratum.
Types of Piles (cont’d)
Skin Friction Piles (Floating Piles)
 Piles are driven at a site where soil is
weak or soft to a considerable depth
and it is not economical or rather
possible to rest the bottom end of the
pile on the hard stratum,
 Load is carried by the friction developed
between the sides of the pile and the
surrounding ground ( skin friction).
 The piles are driven up to such a depth
that skin friction developed at the sides
of the piles equals the load coming on
the piles.
 The load carrying capacity of friction pile
can be increased by-
 increasing diameter of the pile
 driving the pile for larger depth
 grouping of piles
 making surface of the pile rough
Types of Piles (cont’d)
Anchor Piles
 Piles are used to provide anchorage against horizontal pull from sheet
piling wall or other pulling forces.
Compaction piles:
 When piles are driven in granular soil with the aim of increasing the
bearing capacity of the soil, the piles are termed as compaction piles.
Types of Piles (cont’d)
Driven piles:
 Driven piles are deep foundation
elements driven to a design
depth. If penetration of dense soil
is required, pre drilling may be
required for the pile to penetrate
to the design depth. Types
include timber, pre-cast concrete,
steel H-piles, and pipe piles.
Types of Piles (cont’d)• Auger cast piles
Auger cast piles, are deep foundation
elements that are cast-in-place, using
a hollow stem auger with continuous
flights. The auger is then slowly
extracted, removing the drilled
soil/rock.. Reinforcing steel is then
lowered into the wet concrete or
grout. The auger is drilled into the
soil or rock to design depth. The
technique has been used to support
buildings, tanks, towers and bridges.
Well foundations
 Well foundations are
being used in India
from very early days.
Taj Mahal was built on
such foundations. Wells
are also type of deep
foundations. The main
difference between a
well and a pile
foundation is that,
while a pile is flexible
like a beam under
horizontal loads, the
well undergoes rigid
body movement under
such loads.
Types of Well Foundation
Wells have different
shapes and accordingly
they are named as
• Circular Wells
• Dumb bell
• Double-D Wells
• Double Octagonal Wells
• Single and Double
Rectangular Wells
• Multiple Dredged Holed
Wells
LOADS FOR WELL FOUNDATION DESIGN
The following loads are considered for the
analysis and design of well foundation:
1.Dead load
2.Live load
3.Buoyancy
4.Wind load
5.Horizontal force due to water current
6.Centrifugal forces
7.Longitudinal forces
8.Seismic forces
9.Horizontal shear forces at bearings due
to longitudinal forces and seismic forces
10.Forces due to tilt and shift.
TYPES OF FOUNDATION
Caissons
Caisson foundation is also known as
pier foundation.
Caisson is a cylinder or hollow box
that is sunk into the ground to a
specified depth by auguring a deep
hole into the strata. The cylinder or
box is then back filled with
concrete, thus creating the
foundation.
This type of foundation is most
often used when constructing
bridge piers and other such
foundations that will be beneath
bodies of water since the caissons
can be floated to the correct
locations and then sunk in place
using concrete.
Why To Use a Caisson Foundation
• This type of foundation will keep the soils
underneath the building or structure from moving
vertically. Since soil will settle over time, the
building or structure on top of the soil will also
settle. This can cause major structural damage.
Since a caisson foundation is drilled into the earth
and large concrete t filled cylinders are placed
within the ground rather than on top, the
settlement of the soil will not cause many
difficulties for the building or structure.
Types of Caissons
• Box caissons are watertight
boxes that are constructed
of heavy timbers and open
at the top. They are
generally floated to the
appropriate location and
then sunk into place with a
masonry pier within it.
• Excavated caissons are just
as the name suggests,
caissons that are placed
within an excavated site.
These are usually cylindrical
in shape and then back filled
with concrete.
Types of Caissons (cont’d)
• Floating caissons are also
known as floating docks and
are prefabricated boxes that
have cylindrical cavities.
• Open caissons are small
cofferdams that are placed
and then pumped dry and
filled with concrete. These
are generally used in the
formation of a pier.
• Pneumatic caissons are
large watertight boxes or
cylinders that are mainly
used for under water
construction.
Careful study of loads to be transmitted from
columns of super structure and soil profile.
Objective :
oTo identify type of pile
oTo determine load carrying capacity of
individual pile
Only one type of pile below different columns
For large projects two or three sizes may be
adopted
1. IDENTIFYING STRONG BEARING
LAYER FOR LOCATING THE PILE TIP
• Study soil profile
• Look for strong bearing layer
IF STRONG BEARING LAYER IS FOUND
• Locate pile tip, a few meters, in
• Pile becomes ‘end bearing pile’
• Easy to conduct settlement analysis
IF NO STRONG BEARING LAYER IS FOUND
• Pile should be friction pile.
• Pile derives its capacity from both, end
bearing & friction.
• Select two pile lengths as deep as possible.
2. SELECTION OF PILE
Choice of pile depends on
Length
Width
Material ( concrete, steel, wood)
Cross-section (square, circular, tubular)
Installation procedure (driven, bored)
Feasibility of construction
Feasibility of noise and vibration
3. RANGE OF PILE LENGTH &
DIAMETERS
LENGTH :
• Usually 10 – 30 m
• Offshore application 70 – 100 m
WIDTH/DIAMETERS :
• Usually 0.3 – 0.75 m
• Drilled piles 1 – 2.5 m
• Micropiles 0.15 m
4. AXIAL CAPACITY ANALYSIS
Pile type – selected
Range of dimensions – chosen
Estimate the axial capacity
One of the procedures is ‘Pile Load Test’
5. SETTLEMENT ANALYSIS
• For piles, not resting on strong bearing
capacity, settlement analysis is conducted.
6. RESULTS & RECOMMENDATIONS
Presented in tabular form.
In selecting from the options available, two factors
are given :
Large sized but fewer number of piles, hence
installation time is less.
3 piles (min. number) can support only lightly
loaded columns, for heavier loads, increase the
pile group.
ADVANTAGES OF DIFFERENT METHODS
OF DEEP FOUNDATION
DRILLED PIER FOUNDATIONS
Advantages
1.Pier of any length and size can be constructed
at the site
2. Construction equipment is normally mobile and
construction can proceed rapidly
3. Inspection of drilled holes is possible because of
the larger diameter of the shafts
4.The drilled pier is applicable to a wide variety of
soil conditions
5.Changes can be made in the design criteria
during the progress of a job
7.Ground vibration that is normally associated with
driven piles is absent in drilled pier construction
8.Bearing capacity can be increased.
Disadvantages
1. Installation of drilled piers needs a
careful supervision and quality control of all
the materials used in the construction
2. The method is cumbersome. It needs
sufficient storage space for all the
materials used in the construction.
Augered Piles
Advantages……
1.Limited risk of damage to adjacent foundations or underground
utilities from ground displacement or densification of loose sands, as
can occur with displacement piles.
2.CFA piles can be installed with little vibrations or noise.
3.Should problems occur during pile construction, it is relatively simple
to re–drill and install the pile at the same location, thereby eliminating
the need to redesign the pile group or the pile caps.
4.A reliable flow meter can be used to monitor and record penetration /
uplift per revolution, auger depth, concrete supply per increment of
auger uplift during placing, and injection pressure at the auger head.
.
Disadvantage
1.If the appropriate installation procedures are not followed exactly the
pile formed may be of poor and/or inconsistent quality and load
carrying capacity.
2.The most critical factor for the CFA system is still its reliance on
operator performance, which may result in a pile of poor quality and
reduced load carrying capacity. Thus, it is vitally important that
experienced personnel install the piles.
3.To ensure success it is vital to give due care to every stage of the field
installation procedure, including drilling of the hole, casting of the shaft,
extraction of the auger and the placement of the reinforcement.
Driven concrete pile
ADVANTAGES……..
1.Driven concrete pile foundations are applicable under most
ground conditions.
2.Concrete piles are usually inexpensive compared with other
types of deep foundations.
3.The procedure of pile installation is straightforward; piles can
be produced in mass production either on site or in a
manufacture factory, and the cost for materials is usually much
less than steel piles.
4.Proxy coating can be applied to reduce negative skin friction
along the pile.
5.Pile driving can densify loose sand and reduce liquefaction
potential within a range of up to three diameters surrounding
the pile.
DISADVANTAGES……
1.Pile driving produces noise pollution and causes disturbance
to the adjacent structures.
2. Driving of concrete piles also requires large overhead
space.
3.Piles may break during driving and impose a safety hazard.
4.Piles that break underground cannot take their design
loads, and will cause damage to the structures if the broken
pile is not detected and replaced.
5. End-bearing capacity of a pile is not reliable if the end of a
pile is smashed.
DRIVEN WOODEN PILE
ADVANTAGES……
1.The piles are easy to handle
2.Relatively inexpensive where
timber is plentiful.
3.Sections can be joined together
and excess length easily removed.
1.The piles will rot above the ground water level. Have a limited
bearing capacity.
2.Can easily be damaged during driving by stones and boulders.
3.The piles are difficult to splice and are attacked by marine borers in
salt water.
DISADVANTAGES
DRILLED SHAFT METHOD
ADVANTAGES…….
1.The length and size of the foundations can be
tailored easily.
2. Disturbance to the nearby structures is small
compared with other types of deep foundations.
3.Drilled shafts can be constructed very close to
existing structures and can be constructed under
low overhead conditions. Therefore,
4. drilled shafts are often used in many seismic
retrofit projects.
DISADVANTAGES
1. Drilled shafts may be difficult to install under
certain ground conditions such as soft soil, loose
sand, sand under water, and soils with boulders.
2. Drilled shafts will generate a large volume of soil
cuttings and fluid and can be a mess. Disposal of
the cuttings is usually a concern for sites with
contaminated soils.
3. Drilled shaft foundations are usually comparable
with or more expensive than driven piles.
APPLICTION OF DEEP FOUNDATION
A
deep foundation installation for
a bridge in Napa,
California, United States.
APPLICTION OF DEEP FOUNDATION
Pile driving operations in the
Port ofTampa, Florida, United
States.
APPLICTION OF DEEP FOUNDATION
Sheet piles are used to restrain
soft soil above the bedrock in
this excavation
APPLICTION OF DEEP FOUNDATION
Adfreeze Piles supporting a
building in Barrow, Alaska,
United States
APPLICTION OF DEEP FOUNDATION
Sheet piling, by a bridge, was
used to block a canal in New
Orleans, United States
after Hurricane Katrinadamaged
it
APPLICTION OF DEEP FOUNDATION
Cutaway illustration. Deep
inclined (battered) pipe piles
support a precast segmented
skyway where upper soil layers
are weak muds.
• DEFORMABILITY MODULUS OF JOINTED
ROCKS, LIMITATION OF EMPIRICAL
METHODS, AND INTRODUCING A NEW
ANALYTICAL APPROACH
• Introduction
• The commission of Terminology, symbols and graphic
representation of the International Society for Rock
Mechanics ISRM ) ISRM, 1975 )
• Modulus of elasticity or Young’s modulus (E) : The ratio of
stress to corresponding strain below the proportionality
limit of a material.
• Modulus of deformation of a rock mass (Em) : The ratio of
stress (p) to corresponding strain during loading of a rock
mass, including elastic and inelastic behavior
• Modulus of elasticity of a rock mass (Eem) : The ratio of
stress (p) to corresponding strain during loading of a rock
mass, including only the elastic behavior
Conclusion On Deformability
• Deformability modulus is a stress dependent
parameter and increases as applied stress
increases.
• All well-known empirical formulations do not
consider this property of deformability modulus.
• A new procedure is proposed to quantify the
stress dependency of deformability modulus.
Plane of weakness
• Discontinuity Orientation
• Dip - Angle of Steepest Inclination of Plane,
Measured Below Horizontal (two digits 00 to 90)
• Dip Direction (Dip Azimuth) - Azimuth of the Line
of Dip (three digits 000 to 360)
• Strike - Azimuth of a Horizontal Line (90 Degrees
to Dip Direction) - Unsuitable for Rock Slope
Engineering
Discontinuity Spacing
• Measure True Spacing in Surface Mapping
• Range:
• Extremely close spacing (<20 mm)
• Extremely wide spacing (>6000 mm)
• Line Mapping or Coreholes: Use Terzaghi
Correction for True Spacing
Persistence
• Document Visible or Inferred Length
• -Range:
• Very low (<1 m)
• Very high (>20 m)
• Document Termination of Joints (0, 1, 2)
• Statistical Estimates of Length Distribution
Persistence cannot be Measured in Core
IMPORTANCE OF JOINTS IN
TERMS OF ROCK MECHNICS
JYOTI KHATIWADA
INTRODUCTION
• In geology, a joint is a fracture dividing rock into two sections that have
not moved away from each other. A joint sees little or no displacement.
• As Earth crust is full of joints, therefore their study and importance is very
significance.
• joints are important not only in understanding the local and
regional geology and geomorphology, but also are important in
development of natural resources, the safe design of structures, and
environmental protection. Joints have a profound control on weathering
and erosion of bedrock. As a result, they exert a strong control on how
topography and morphology of landscapes develop.
• Importance of joints in engineering and geological
applications include:
1. In rock mass classification
2. foundation strength
3. Geohydrology/ Natural circulation of fluids
4. Petroleum and mineral deposition
5. Studying mechanical properties of rock masses
6. Mining and quarry operational feasibility
7. Toxic waste/ risk
1. IN ROCK MASS
CLASSIFICATION
a. In determination of RQD (Rock Quality
Designation)
b. In determination of block size.
c. In determination of RMR (Rock Mass Rating)
d. In determination of rock quality ( Q system)
• In determination of RQD (Rock Quality
Designation):
In many cases the degree of jointing is the most important
factor for the stability of rock masses. The volumetric joint
count (Jv) is a simple measure of the degree of jointing. It
takes into account all the occurring joints and fractures and is
easily calculated from standard joint descriptions. The (Jv) has
been used by engineering geologists in Norway for several
years and it has been a useful tool in the description and
classification of rock masses. The paper describes the
procedure for the calculation of the (Jv) and it shows how the
joint spacings are included in the measure.
RQD = 115 - 3.3 Jv.
Jv = Joint volumetric count
• In determination of block size:
Block size =
If 𝐽 𝑛 = 0, block size tends to infinite, it represents
continuity i.e. ground is made up of rock.
If 𝐽 𝑛 is more, ground is moving towards fractured
ground.
Hence joints are very important parameter affecting
geotechnical behavior of ground.
𝑅𝑄𝐷
𝐽 𝑛
• In determination of RMR (Rock Mass Rating):
RMR is determined as an algebraic sum of six
parameters given below:
1. Rock quality designation
2. Joint spacing
3. Joint condition
4. Joint orientation
5. Ground water condition
6. UCS of rock material.
RMR = RRQD + RJOINT SPACING + RJOINT CONDITION + RORIENTATION + RGROUND
WATER CONDITION + RUCS
RMR
Rock
quality
0 - 20 Very Poor
21 - 40 Poor
41 - 60 Fair
61 - 80 Good
81 - 100 Very good
• In determination of rock quality ( Q system):
• The Q-system for rock mass classification is developed by
Barton, Lien, and Lunde. It expresses the quality of the rock mass
in the so-called Q-value, on which are based design and support
recommendations for underground excavations.
• The Q-value is determined with
𝑹𝑸𝑫
𝑱 𝒏
represents block size
𝑱 𝒓
𝑱 𝒂
represents shear strength
𝑱 𝒓
𝑱 𝒂
represents condition or nature of rock
• Jw is the measure of water pressure which has an adverse effect
on the shear strength of joint due to reduction in effective normal
stress.
𝑸 =
𝑹𝑸𝑫
𝑱 𝒏
×
𝑱 𝒓
𝑱 𝒂
×
𝑱 𝒘
𝑺𝑹𝑭
OTHER IMPORTANCE :
• Joints often impart a well-develop fracture-induced
permeability to bedrock. As a result, joints strongly
influence, even control, the natural circulation
(geohydrology) of fluids.
• groundwater and pollutants within aquifers, petroleum in
reservoirs, and hydrothermal circulation at depth, within
bedrock. Thus, joints are important to the economic and
safe development of petroleum, hydrothermal, and
groundwater resources and the subject of intensive
research relative to the development of these resources.
• Also, regional and local joint systems exert a very strong control on
how ore-forming (hydrothermal) fluids, consisting largely of  H2O, CO2,
and NaCl, that formed most of Earth's ore deposits circulated within the
Earth crust. As a result, understanding their genesis, structure,
chronology, and distribution is an important part of finding and
profitably developing ore deposits of various types.
• Finally, joints often form discontinuities that may have a large influence
on the mechanical behavior (strength, deformation, etc.) of soil and rock
masses in, for example, tunnel, foundation, or slope construction.
• As a result, joints are an important part of geotechnical engineering in
practice and research
Footing
Definition
Footings are structural members used to support
columns and walls and to transmit and distribute
their loads to the soil in such a way that the load
bearing capacity of the soil is not exceeded,
excessive settlement, differential settlement,or
rotation are prevented and adequate safety
against overturning or sliding is maintained.
Types of Footing
Wall footings are used to
support structural walls that
carry loads for other floors
or to support nonstructural
walls.
Types of Footing
Isolated or single footings
are used to support single
columns. This is one of the
most economical types of
footings and is used when
columns are spaced at
relatively long distances.
Types of Footing
Combined footings usually
support two columns, or
three columns not in a row.
Combined footings are used
when tow columns are so
close that single footings
cannot be used or when one
column is located at or near
a property line.
Types of Footing
Cantilever or strap footings
consist of two single
footings connected with a
beam or a strap and support
two single columns. This
type replaces a combined
footing and is more
economical.
Types of Footing
Continuous footings
support a row of three or
more columns. They have
limited width and continue
under all columns.
Types of Footing
Rafted or mat foundation
consists of one footing
usually placed under the
entire building area. They
are used, when soil bearing
capacity is low, column
loads are heavy single
footings cannot be used,
piles are not used and
differential settlement must
be reduced.
Types of Footing
Pile caps are thick slabs
used to tie a group of piles
together to support and
transmit column loads to the
piles.
Distribution of Soil Pressure
When the column load P is
applied on the centroid of the
footing, a uniform pressure is
assumed to develop on the soil
surface below the footing area.
However the actual distribution of
the soil is not uniform, but
depends on may factors especially
the composition of the soil and
degree of flexibility of the footing.
Distribution of Soil Pressure
Soil pressure distribution in
cohesionless soil.
Soil pressure distribution in
cohesive soil.
Design Considerations
Footings must be designed to carry the column loads
and transmit them to the soil safely while satisfying
code limitations.
The area of the footing based on the allowable
bearing soil capacity
Two-way shear or punching shear.
One-way bearing
Bending moment and steel reinforcement required
*
*
*
*
Design Considerations
Footings must be designed to carry the column loads
and transmit them to the soil safely while satisfying
code limitations.
Bearing capacity of columns at their base
Dowel requirements
Development length of bars
Differential settlement
*
*
*
*
Size of Footing
The area of footing can be determined from the
actual external loads such that the allowable soil
pressure is not exceeded.
 
pressuresoilallowable
weight-selfincludingloadTotal
footingofArea 
footingofarea
u
u
P
q 
Strength design requirements
Two-Way Shear (Punching Shear)
For two-way shear in slabs (& footings) Vc is smallest of
long side/short side of column
concentrated load or reaction area<2
length of critical perimeter around the
column
where, bc =
b0 =
ACI 11-35
dbfV 0c
c
c
4
2









b
When b >2 the allowable Vc is reduced.
Design of two-way shear
Assume d.
Determine b0:
b0 = 4(c+d) for square columns
where one side = c
b0 = 2(c1+d) +2(c2+d) for
rectangular columns of sides c1
and c2.
1
2
Design of two-way shear
The shear force Vu acts at a
section that has a length
b0 = 4(c+d) or 2(c1+d) +2(c2+d)
and a depth d; the section is
subjected to a vertical downward
load Pu and vertical upward
pressure qu.
3
 
   columnsrrectangulafor
columnssquarefor
21uuu
2
uuu
dcdcqPV
dcqPV


Design of two-way shear
Allowable
Let Vu=fVc
4
dbfV 0cc 4ff 
0c
u
4 bf
V
d
f

If d is not close to the assumed d,
revise your assumptions
Design of one-way shear
For footings with bending action
in one direction the critical
section is located a distance d
from face of column
dbfV 0cc 2ff 
Design of one-way shear
The ultimate shearing force at
section m-m can be calculated








 d
cL
bqV
22
uu
If no shear reinforcement is to
be used, then d can be checked
Design of one-way shear
bf
V
d
2 c
u
f

If no shear reinforcement is to
be used, then d can be checked,
assuming Vu = fVc
Flexural Strength and Footing reinforcement
2
y
u
s










a
df
M
A
f
The bending moment in each
direction of the footing must be
checked and the appropriate
reinforcement must be
provided.
Flexural Strength and Footing reinforcement
bf
Af
a
85.0 c
sy

Another approach is to
calculated Ru = Mu / bd2 and
determine the steel percentage
required r . Determine As then
check if assumed a is close to
calculated a
Flexural Strength and Footing reinforcement
The minimum steel percentage
required in flexural members is
200/fy with minimum area and
maximum spacing of steel bars
in the direction of bending
shall be as required for
shrinkage temperature
reinforcement.
Flexural Strength and Footing reinforcement
The reinforcement in one-way
footings and two-way footings
must be distributed across the
entire width of the footing.
1
2
directionshortinentreinforcemTotal
widthbandinentReinforcem


b
footingofsideshort
footingofsidelong
b
where
Bearing Capacity of Column at Base
The loads from the column act on the footing at the base
of the column, on an area equal to area of the column
cross-section. Compressive forces are transferred to the
footing directly by bearing on the concrete. Tensile
forces must be resisted by reinforcement, neglecting any
contribution by concrete.
Bearing Capacity of Column at Base
Force acting on the concrete at the base of the column
must not exceed the bearing strength of the concrete
 1c1 85.0 AfN f
where f = 0.7 and
A1 =bearing area of column
Bearing Capacity of Column at Base
The value of the bearing strength may be multiplied by a
factor for bearing on footing when the
supporting surface is wider on all sides than the loaded
area.
0.2/ 12 AA
The modified bearing
strength
 
 1c2
121c2
85.02
/85.0
AfN
AAAfN
f
f


Dowels in Footings
A minimum steel ratio r = 0.005 of the column section
as compared to r = 0.01 as minimum reinforcement for
the column itself. The number of dowel bars needed is
four these may be placed at the four corners of the
column. The dowel bars are usually extended into the
footing, bent at the ends, and tied to the main footing
reinforcement. The dowel diameter shall not =exceed
the diameter of the longitudinal bars in the column by
more than 0.15 in.
Development length of the Reinforcing Bars
The development length for compression bars was
given
but not less than
Dowel bars must be checked for proper
development length.
cbyd /02.0 fdfl 
in.8003.0 by df
Differential Settlement
Footing usually support the following loads
Dead loads from the substructure and superstructure
Live load resulting from material or occupancy
Weight of material used in backfilling
Wind loads
General Requirements for Footing Design
A site investigation is required to determine the
chemical and physical properties of the soil.
Determine the magnitude and distribution of
loads form the superstructure.
Establish the criteria and the tolerance for the
total and differential settlements of the structure.
1
2
3
General Requirements for Footing Design
Determine the most suitable and economic type
of foundation.
Determine the depth of the footings below the
ground level and the method of excavation.
Establish the allowable bearing pressure to be
used in design.
4
5
6
General Requirements for Footing Design
Determine the pressure distribution beneath the
footing based on its width
Perform a settlement analysis.
7
8
EFFECT OF DISCONTINUTY STRIKE & DIP
ORIENTATION IN EXPLORATION/TUNNELING
STRIKE PERPENDICULAR
TO TUNNEL AXIS
STRIKE PARALLEL TO TUNNEL AXIS
Drive with dip: Dip 45-
90°
Drive with dip: Dip 20-45° Dip 45-90° Dip 20-45°
Very favorable Favorable Very favorable Fair
Drive against dip: Dip
45-90°
Drive against dip: Dip 20-
45°
Dip 0-20° , Irrespective of strike angle
Fair Unfavorable Fair
TOWER OF PISA, ITALY
MAIN FACTORS AFFECTING THE ROCK QUALITY
 Topography of area
 Types Soil/rock on Surface as well as Subsurface.
 Degree of weathering
 Number of Joint sets
 Spacing between joints
 Cavity
 Filling material
 Dewatering/ ground water inflow
 Direction and amount of Dip and strike
METHODS OF STUDY THE ROCK QUALITY
• A number of Geotechnical parameters govern condition of Rock mass and
the nature of its discontinuities. Main two are:-
• (1) RMR (2) Q SYSTEM
• (1) RMR (Rock Mass rating):
• Bieniawski (1973), proposed RMR system, also know as ‘Geomechanics
Classification” for jointed rock masses. Many modifications has undergone time to
time.
• Five basic parameters considered for RMR: STRENGTH OF ROCK, RQD (Rock Quality
Designation), SPACING OF JOINTS, CONDITION OF JOINTS & GROUND WATER
CONDITION.
• Final RMR value related to five classes of rock mass i.e. ‘very good’, ‘good’’, ‘fair’,
‘poor’, ‘very poor’ rock.
METHODS OF STUDY THE ROCK QUALITY
 Q- SYSTEM (ROCK MASS QUALITY)
 Proposed by Basedon in 1974, based on the study of 200 tunnel case histories.
 The rock quality Q is determined by estimating six parameters. These are RQD, JOINT
SET NUMBER (Jn), JOINT ROUGHNESS NUMBER (Jr), JOINT ALTERATION NUMBER (Ja)
AND STRESS REDUCTION FACTOR (SRF).
 Q= (RQD/Jn) x (Jr/Ja) X (Jw/SRF) (Barton et. al. 1974)
 The numerical value Q ranges from 0.001 (for exceptionally poor quality squeezing
ground) to 1000 (for exceptionally good quality rock which is practically unjointed).
 Q-value is divided into 9 categories of rock quality which are related to support
requirement depending upon excavation span and intended use of excavation.
SURFACE/SUBSURFACE INVESTIGATION
INVESTIGATIONS
FIELD INVESTIGATIONS LABOURATURY INVESTIGATIONS
(A) Geotechnical (a) Physical properties of Soil & Rock
(B) Hydrological (b) Geomechanical Properties
(C) Geophysical (c ) Petrological studies of rock & soil
(D) Construction material
Main Field tests are Drilling, Pit excavation, Deformability test (Goodman Jack Test &
Hydro Fracture test), Load bearing capacity test (Plate Load Test), Water Percolation
test (permeability test), Earth resistivity test, Seismic reflection test (know the
subsurface fault/ shear zone), aggregate test , topographical studies etc.
Studies of Satellite imageries is very useful to understand the topography,
geomorphology of area.
• On the basis of RMR and Q Value, geologist
suggest supporting system in excavated
rock/soil.
• On the basis of geotechnical & geologist
report project designer has fixed the structure
design and remedies measures.
RESULTS
CAREER IN ENGINEERING GEOLOGY
• Infrastructure Projects as Hydro Power Plant,
Tunnels for railway/transport, Canal, Dam,
reservoir, highways, bridges, buildings, water
treatment plant, land use, environmental studies
etc.
• For Mine and Quarry excavations, mine
reclamation.
• For coastal engineering, sand replenishment, sea
cliff stability, water front development.
• For offshore drilling platform, sub sea pipeline
and cables etc.
TUNNELING
• Jyoti Anischit
INTRODUCTION
A tunnel is an underground passageway, completely
enclosed except for openings for egress, commonly at each
end.
A tunnel may be for road traffic,road
traffic,canal,hydroelectric station,sewer etc.
The Delaware Aqueduct in New York USA is the longest
tunnel, of any type, in the world at 137 km (85 mi)
REQUIRMENTS OF
TUNNEL
 IT IS VERY USEFUL WHERE BRIDGE FAIL TO FULFILL REQUIRMENTS
LIKE IN SEA ,IN URBAN AREA ,AND IN MOUNTAINS.
 EFFICIENT COPARED TO BRIDGES.

 IN WAR TIME IT IS MUCH DIFFICULT TO DESTROY A TUNNEL BUT
DESTRUCTION OF BRIDGE IS TOO EASY.
 LOTS OF LAND AND TIME IS SAVED.
MAIN PURPOSES
1.IN ROAD TRAFFICS
2.IN SEWERS
3.IN MININGS
4.IN RAIL TRAFFICS
5.IN HYDROELECTRIC
STATIONS etc.
The process for bored tunnelling involves all or some of the
following operations:
• Probe drilling (when needed)
• Grouting (when needed)
• Excavation (or blasting)
• Supporting
• Transportation of muck
• Lining or coating/sealing
• Draining
• Ventilation
PROBE DRILLING
• This type of drilling is done in order to find out
suitable method for drilling .
• It consist of drilling in sample, by various method to
find most suitable .
• It is necessary part of all drilling operation .
GROUTING
• It is the process of providing additional support to
drilled mine.
• It is done by a liquid called grout ,consist of water
,cement ,color tint and sometime fine gravel .
• Good surface is achieved .
EXCAVATION
• Excavation is the digging and recording of
artifacts at an archaeological site.
• It is necessary to know the archaeological
importance of a site before digging .
• This is performed by experts in a scientific way.
• Many governments grants permission for
tunneling after finding a go certificate in
excavation.
SUPPORTING
• After initial mining , tunnel need supports for
further processing .
• For the sake of life a perfect planning is needed
for support.
• In ancient time timber and masonry were the
main methods.
• Today support is provided by injecting final pipe
or building it completely before further
tunneling
Transportation of muck
• In ancient time transportation was done by
steam engine and by Manual transport.
• Today it is done by modern methods and
process is automatic .
• TBMs are also come with proper arrangment for
the transport of muck.
LINING OR COATING
• Lining of proper material is done by modern
methods like polishing ,painting to prevent wear and
tear and corrosion.
• Very necessary part where corrosive metals are being
used.
DRAINING
• Draining is the process to remove the water or other
liquid from working site .
• Very important where water level is very high.
• Pumps and pipes are used for this purpose.
VENTILATION
• Proper ventilation is required for safety of workers.
• This is done by proper checking of oxygen and other
parameters .
• Proper installations for exit of hazardous gasses
coming out from tunneling .
tunnel construction methods:
• Classical methods
• Cut-and-cover
• Drill and blast
• Tunnel boring machines (TBMs)
• Immersed tunnels
• Tunnel jacking
• Other methods .
Classical Methods
 Among the classical methods are the
Belgian, English, German, Austrian,
Italian and American systems. These
methods had much in common with
early mining methods and were used
until last half of the 19th century.
 Excavation was done by hand or
simple drilling equipment.
 Supports were predominantly timber,
and transportation of muck was done
on cars on narrow gauge tracks and
powered by steam.
 Progress was typically in multiple
stages i.e. progress in one drift, then
support, then drift in another drift,
and so on.
 The lining would be of brickwork.
These craft-based methods are no
longer applicable, although some of
their principles have been used in
combination up to present day.
Nevertheless some of the world’s
great tunnels were built with these
methods.
The English method (crown-bar method, figure
left) started from a central top heading
which allowed two timber crown bars to be
hoisted into place, the rear ends supported
on a completed length of lining, the forward
ends propped within the central heading.
Development of the heading then allowed
additional bars to be erected around the
perimeter of the face with boards between
each pair to exclude the ground. The system
is economical in timber, permits
construction of the arch of the tunnel in
full-face excavation, and is tolerant of a
wide variety of ground conditions, but
depends on relatively low ground pressures.
 The Austrian (cross-bar) method required a
strongly constructed central bottom
heading upon which a crown
heading was constructed. The
timbering for full-face excavation
was then heavily braced against the
central headings, with longitudinal
poling boards built on timber bars
carried on each frame of timbering.
As the lining advanced, so was the
timbering propped against each
length to maintain stability. The
method was capable of withstanding
high ground pressures but had high
demand for timber.
• The German method (core-leaving method) provided a series of box headings
within which the successive sections of the side walls of the tunnel were
built from the footing upwards, thus a forerunner of the system of multiple
drifts. The method depends on the central dumpling being able to resists
without excessive movement pressure transmitted from the side walls, in
providing support to the top 'key' heading prior to completion of the arch
and to ensuring stability while the invert arch is extended in sections.
• The Belgian system (underpinning or flying arch method) started from the
construction of a top heading, propped approximately to the level of the
springing of the arch for a horseshoe tunnel. This heading was then extended
to each side to permit construction of the upper part of the arch, which was
extended by under- pinning, working from side headings. The system was
only practicable where rock loads were not heavy.
• The first sizeable tunnel in soft ground was the Tronquoy tunnel on the St
Quentin canal in France in 1803, where the method of construction, based
on the use of successive headings to construct sections of the arch starting
from the footing, was a forerunner to the German system described above.
Road headers
Cut and Cover Method
CUT & COVER METHOD
The principal problem to be solved in connection with this
construction method is to how to maintain surface traffic,
with the least disturbance during the construction period.
One method is to restrict traffic to a reduced street width,
another to direct traffic to a bypassing street.
 Another way of supporting the sidewalls of open trenches is
to substitute sheet-pile walls by concrete curtain walls cast
under bentonite slurry (ICOS method), and using steel
struts. This is especially a requisite in narrower streets
trimmed with old sensitive buildings with their foundation
plane well above the bottom level of the pit. This type of
trench wall becomes a requirement for maintenance of
surface traffic due to the anticipation of vibration effects
potentially harmful to the stability of buildings with
foundations lying on cohesionless soils.
DRILL AND BLAST
1.Before the advent of tunnel boring
machines, drilling and blasting was the only
economical way of excavating long tunnels through
hard rock, where digging is not possible.
2.Even today, the method is still used in the
construction of tunnels.
HOW DRILL AND BLAST IS BEING DONE.
Mechanical Drilling and Cutting-Crushing Strength of rock
TBM
• In various size Tunnel Boring Machines(TBM)
are used for drilling a vast type of tunnels .
• Transportation of muck , supporting and all
other actions are done automatically.
• Very useful in boring tunnel where all other
methods fail.
• A main method in use in now a days.
IMMERSED TUNNELS
1.THIS TYPE OF TUNNELS ARE PARTLY OR
WHOLLY ARE UNDERWATWER.
2.THEY DO NOT BLOCK THE ROOT FOR
SHIPS SO THERE IS NO PROBLEM OF
CONGESSION OF TRAFFIC AS IN CASE OF
BRIDGES OVER RIVERS OR SEAS.
TUNNEL JACKING
1.IT IS A PROCESS TO MAKE TUNNELS IN
ALREADY EXISTING BOADIES SUCH AS
ROADS ,RAILWAYS.
2.IN THIS METHOD ESPECIALLY MADE PIPES
ARE PUSHED BY A HYDRAULIC RAM IN
GROUND .
3.MAXIMUM DIAMETER OF TUNNEL BY
THIS METHOD IS AROUND 2.4 METER.
The choice of tunnelling method may be dictated by:
• geological and hydrological conditions,
• cross-section and length of continuous tunnel,
• local experience and time/cost considerations
(what is the value of time in the project),
• limits of surface disturbance, and many others
factors.
• Tunnel methods .
• Required speed of construction.
• Shape of tunnel.
• Managing the risk of variations in ground quality
THE OTHER SIDE
• Beside of many security measures , tunnelling is still
not full proof.
• Failure of automatic system will cause deadly results
as depicted in Hollywood flick Die Hard 4.0.
• High cost than bridges , but more fruitful from
previous.
NATM
NATM
NEW AUSTRIAN TUNNELING METHOD
By
ADIL BIN AYOUB
41-CE-13
B.Tech
CIVIL ENGINEERING
School of Engineering & Technology, BGSBU
Rajouri J&K
HISTORY OF NATM
• The term New Austrian Tunneling Method
Popularly Known as NATM got its name from
Salzburg (Austria).
• It was first used by Mr. Rabcewicz in 1962. It got
world wise recognition in1964.
• The first use of NATM in soft ground tunnel in
Frankfurt (Europe) metro in 1969.
DEFINITION OF NATM
• The New Austrian Tunneling Method is a
support method to stabilize the tunnel
perimeter by means of sprayed concrete
,anchors and other support and uses monitoring
too control stability.
• Main idea is to use the geological stress of the
surrounding rock mass to stabilize the tunnel
itself
BROAD PRINCIPLES OF NATM
• Mobilization of the strength of rock mass
• Shotcrete protection
• Measurements and monitoring
• Primary Lining
• Closing of invert
• Rock mass classification
MOBILIZATION OF STRENGTH
OF ROCK MASS
SHOTCRETE
PROTECTION
MEASUREMENTS AND
MONITORING
PRIMARY LINING
Wire mesh and steel ribs
CLOSING OF INVERT
ROCK MASS CLASSIFICATION
WHY NATM
• Flexibility to adopt different excavation
geometries and very large cross sections.
• Flexibility to install additional support measures,
rock bolts, dowels, steel ribs if required.
• Easy to install a waterproof membrane.
• Easy to install primary support, i.e. shotcrete.
SUMMARY OF THE PROCEDURE
IN NATM
• SHOTCRETING AT THE EXCAVATED AREA(PRIMARY
LINING)
• PLACING OF THE WIREMESH ALONG THE FACEOF THE
TUNNEL
• ERECTION OF THE LATTICE GIRDER ALONG THE FACE OF
THE TUNNEL
• PERTICULAR TYPE OF ROCKBOLTING
• SHOTCRETING THE WHOLE ARRENGEMENT(SECONDARY
LINING)
CONCEPT OF 3D MONITORING
• 3D MONITORING IS NEW TECHNIQUE USING FOR TAKING
THE RIGHT ALIGNMENT OF THE TUNNEL
• OPTICAL TARGETS ARE USED FOR DETRMINIG THE
COORDINATES FOR MEASUREMENTS
• THE COORDINATES SHOULD BE CHECKED DAILY
• IT IS NECESSARY FOR THE TUNNEL AS BY IT WE KNOW
ANY DISPLACEMENT AND WRONG ALIGNMENTS
General
Optical Target
WHERE NATM IS USING IN
INDIA
• PRESENTLY IT IS USING WIDLELY IN
KASHMIR RAILWAY PROJECT
• THEY ARE USING IT IN THEIR TUNNELS
LIKE IN PIR PANJAL TUNNEL , T-74R, T-
48 ETC
NATM approach of design and execution of the tunneling in soft ground is
advantageous and scientific way in comparision to the old way of tunneling. This
system monitors rock mass deformation and design the support system with
reference to the rock mass type .
CONCLUSION
Rock Slope Stability Analysis
• A variety of engineering activities require
excavation of rock cuts.
• In civil engineering, projects include
transportation systems such as highways and
railways, dams for power production and
water supply, and industrial and urban
development.
Fig 1: Rock slope in Hong Kong supported with tensioned rock anchors
and reinforced concrete reaction blocks, and shotcrete.
• Figure 1 is a rock cut, with a face angle of about
60◦, supported with tensioned anchors
incorporating reinforced concrete bearing pads
about 1m2 that distribute the anchor load on the
face.
• The face is also covered with shotcrete to prevent
weathering and loosening between the bolts.
• Water control measures include drain holes
through the shotcrete and drainage channels on
the benches and down the face to collect surface
run-off.
• The support is designed to both ensure long-term
stability of the overall slope, and minimize rock
falls that could be a hazard to traffic.
Principles of Rock Slope Engineering
• The design of rock cuts for civil projects such as
highways and railways is usually concerned with
details of the structural geology.
• That is, the orientation and characteristics (such
as length, roughness and infilling materials) of the
joints, bedding and faults that occur behind the
rock face.
• For example, Figure 2 shows a cut slope in shale
containing smooth bedding planes that are
continuous over the full height of the cut and dip
at an angle of about 50° towards the highway.
Figure 2: Cut face coincident with continuous, low friction bedding planes
in shale on Trans Canada Highway near Lake Louise, Alberta.
• Since the friction angle of these
discontinuities is about 20–25°, any attempt
to excavate this cut at a steeper angle than
the dip of the beds would result in blocks of
rock sliding from the face on the beds; the
steepest unsupported cut that can be made is
equal to the dip of the beds.
• However, as the alignment of the road
changes so that the strike of the beds is at
right angles to the cut face (right side of
photograph), it is not possible for sliding to
occur on the beds, and a steeper face can be
excavated.
• For many rock cuts on civil projects, the
stresses in the rock are much less than the
rock strength so there is little concern that
fracturing of intact rock will occur.
• Therefore, slope design is primarily concerned
with the stability of blocks of rock formed by
the discontinuities.
• Intact rock strength, which is used indirectly in
slope design, relates to the shear strength of
discontinuities and rock masses, as well as
excavation methods and costs.
Shear Strength of Discontinuities
• If geological mapping and/or diamond drilling
identify discontinuities on which shear failure
could take place, it will be necessary to
determine the friction angle and cohesion of the
sliding surface in order to carry out stability
analyses.
• The investigation program should also obtain
information on characteristics of the sliding
surface that may modify the shear strength
parameters.
• Important discontinuity characteristics include
continuous length, surface roughness, and the
thickness and characteristics of any infilling, as
well as the effect of water on the properties of
the infilling.
Definition of Cohesion and Friction Angle
• In rock slope design, rock is assumed to be a
Coulomb material in which the shear strength
of the sliding surface is expressed in terms of
the cohesion (c) and the friction angle (φ)
(Coulomb, 1773).
• Assume a number of test samples were cut
from a block of rock containing smooth,
planar discontinuity.
• Furthermore, the discontinuity contains a
cemented infilling material such that a tensile
force would have to be applied to the two
halves of the sample in order to separate
them.
Fig 3 (a) Shear test of discontinuity
• Each sample is subjected to a force at right
angles to the discontinuity surface (normal
stress, σ), and a force is applied in the direction
parallel to the discontinuity (shear stress, τ)
while the shear displacement (δs) is measured
(Figure 3 (a)).
• For a test carried out at a constant normal
stress, a typical plot of the shear stress against
the shear displacement is shown in Figure 3 (b).
Fig 3 (b): plot of shear displacement vs shear stress
• At small displacements, the specimen behaves
elastically and the shear stress increases linearly with
displacement.
• As the force resisting movement is overcome, the
curve become non-linear and then reaches a maximum
that represents the peak shear strength of the
discontinuity.
• Thereafter, the stress required to cause displacement
decreases and eventually reaches a constant value
termed the residual shear strength.
• If the peak shear strength values from tests carried out
at different normal stress levels are plotted, a
relationship shown in Figure 3 (c) is obtained; this is
termed a Mohr diagram (Mohr, 1900).
Fig 3(c): Mohr plot of peak strength
• The features of this plot are;
• first, it is approximately linear and the slope of
the line is equal to the peak friction angle φp of
the rock surface.
• Second, the intercept of the line with the shear
stress axis represents the cohesive strength c of
the cementing material.
• This cohesive component of the total shear
strength is independent of the normal stress, but
the frictional component increases with
increasing normal stress.
• Based on the relationship illustrated on Figure 3
(c), the peak shear strength is defined by the
equation.
• Friction Angle: The angle of internal friction is measure
of the ability of a material (could be rock or soil or
whatever) to withstand a shear stress.
• Cohesion: The force of attraction that holds molecules
of a given substance together.
OR
The sticking together of particles of the same substance.
Mohr plot of peak and residual strength is shown in Fig 3
(d).
Fig 3 (d): Mohr plot of peak and residual strength.
.
.

Mais conteúdo relacionado

Mais procurados

Geotechnical Engineering-I [Lec #2: Introduction-2]
Geotechnical Engineering-I [Lec #2: Introduction-2]Geotechnical Engineering-I [Lec #2: Introduction-2]
Geotechnical Engineering-I [Lec #2: Introduction-2]Muhammad Irfan
 
Slope stability question answers
Slope stability question answersSlope stability question answers
Slope stability question answersJyoti Khatiwada
 
Effect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionEffect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionSailish Cephas
 
Lecture 1 introduction & properties of soil
Lecture 1  introduction & properties of soilLecture 1  introduction & properties of soil
Lecture 1 introduction & properties of soilDr.Abdulmannan Orabi
 
Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240Wajahat Ullah
 
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Muhammad Irfan
 
Geotechnical investigation for road work
Geotechnical investigation for road workGeotechnical investigation for road work
Geotechnical investigation for road workRakesh Meena
 
Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]Muhammad Irfan
 
Soil exploration methods and soil investigation report
Soil exploration  methods and soil investigation reportSoil exploration  methods and soil investigation report
Soil exploration methods and soil investigation reportAnjana R Menon
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration TestMohd. Ikhwan
 

Mais procurados (20)

Lecture 2 bearing capacity
Lecture 2 bearing capacityLecture 2 bearing capacity
Lecture 2 bearing capacity
 
Geotechnical Engineering-I [Lec #2: Introduction-2]
Geotechnical Engineering-I [Lec #2: Introduction-2]Geotechnical Engineering-I [Lec #2: Introduction-2]
Geotechnical Engineering-I [Lec #2: Introduction-2]
 
Slope stability question answers
Slope stability question answersSlope stability question answers
Slope stability question answers
 
Engineering properties of soil
Engineering properties of soilEngineering properties of soil
Engineering properties of soil
 
Effect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its preventionEffect of expansive soils on buildings and its prevention
Effect of expansive soils on buildings and its prevention
 
Subsurface Investigation
Subsurface InvestigationSubsurface Investigation
Subsurface Investigation
 
Soil slope stability
Soil slope stabilitySoil slope stability
Soil slope stability
 
Lecture 1 introduction & properties of soil
Lecture 1  introduction & properties of soilLecture 1  introduction & properties of soil
Lecture 1 introduction & properties of soil
 
Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240Lecture 11 Shear Strength of Soil CE240
Lecture 11 Shear Strength of Soil CE240
 
Rock mechanics
Rock mechanicsRock mechanics
Rock mechanics
 
importance of geology in civil
importance of geology in civil importance of geology in civil
importance of geology in civil
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
 
Geotechnical investigation for road work
Geotechnical investigation for road workGeotechnical investigation for road work
Geotechnical investigation for road work
 
Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]Geotechnical Engineering-I [Lec #1: Introduction]
Geotechnical Engineering-I [Lec #1: Introduction]
 
Basics of soil mechanics
Basics of soil mechanics   Basics of soil mechanics
Basics of soil mechanics
 
Geotechnical site investigation
Geotechnical site investigationGeotechnical site investigation
Geotechnical site investigation
 
Soil exploration methods and soil investigation report
Soil exploration  methods and soil investigation reportSoil exploration  methods and soil investigation report
Soil exploration methods and soil investigation report
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 
Engineering Geology Lecture 1
Engineering Geology Lecture 1Engineering Geology Lecture 1
Engineering Geology Lecture 1
 

Destaque

Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3Jyoti Khatiwada
 
Rock mechanics for engineering geology part 1
Rock mechanics for engineering geology part 1Rock mechanics for engineering geology part 1
Rock mechanics for engineering geology part 1Jyoti Khatiwada
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)S M Rahat Rahman
 
Geophysical methods brief summary
Geophysical methods brief summaryGeophysical methods brief summary
Geophysical methods brief summaryJyoti Khatiwada
 
Engineering Geology (Civil Engineering Applications)
Engineering Geology (Civil Engineering Applications)Engineering Geology (Civil Engineering Applications)
Engineering Geology (Civil Engineering Applications)GAURAV. H .TANDON
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATIONaframawal
 
Soil mechanics question answers
Soil mechanics question answersSoil mechanics question answers
Soil mechanics question answersJyoti Khatiwada
 
To determine the particle size distribution of soil by hydrometer method
To determine the particle size distribution of soil by hydrometer methodTo determine the particle size distribution of soil by hydrometer method
To determine the particle size distribution of soil by hydrometer methodJyoti Khatiwada
 
Index properties of rocks
Index properties of rocksIndex properties of rocks
Index properties of rocksAli Wassan
 
Rock Socket Piling
Rock Socket PilingRock Socket Piling
Rock Socket PilingJim McMullan
 
CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150
CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150
CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150CS Unitec
 
Using A Circular Saw
Using A Circular SawUsing A Circular Saw
Using A Circular Sawswampfoxoz
 
1. How to build a shed foundation
1. How to build a shed foundation1. How to build a shed foundation
1. How to build a shed foundationicreatablesseo
 
Analysis and-design-of-shallow-and-deep-foundations-lc-reese
Analysis and-design-of-shallow-and-deep-foundations-lc-reeseAnalysis and-design-of-shallow-and-deep-foundations-lc-reese
Analysis and-design-of-shallow-and-deep-foundations-lc-reeseJose Carlos Calisto da Silva
 
To determine dry density of soil by core cutter method
To determine dry density of soil by core cutter methodTo determine dry density of soil by core cutter method
To determine dry density of soil by core cutter methodJyoti Khatiwada
 

Destaque (20)

Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3Rock mechanics for engineering geology part 3
Rock mechanics for engineering geology part 3
 
Rock mechanics for engineering geology part 1
Rock mechanics for engineering geology part 1Rock mechanics for engineering geology part 1
Rock mechanics for engineering geology part 1
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Geophysical methods brief summary
Geophysical methods brief summaryGeophysical methods brief summary
Geophysical methods brief summary
 
Engineering Geology (Civil Engineering Applications)
Engineering Geology (Civil Engineering Applications)Engineering Geology (Civil Engineering Applications)
Engineering Geology (Civil Engineering Applications)
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Soil mechanics question answers
Soil mechanics question answersSoil mechanics question answers
Soil mechanics question answers
 
To determine the particle size distribution of soil by hydrometer method
To determine the particle size distribution of soil by hydrometer methodTo determine the particle size distribution of soil by hydrometer method
To determine the particle size distribution of soil by hydrometer method
 
Index properties of rocks
Index properties of rocksIndex properties of rocks
Index properties of rocks
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Rock Socket Piling
Rock Socket PilingRock Socket Piling
Rock Socket Piling
 
CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150
CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150
CS Unitec Pnuematic Cut Off Concrete Saws Schematic: CSH 125 & 150
 
Using A Circular Saw
Using A Circular SawUsing A Circular Saw
Using A Circular Saw
 
Yashar Pourang Portfolio
Yashar Pourang Portfolio Yashar Pourang Portfolio
Yashar Pourang Portfolio
 
Report on excavation
Report on excavationReport on excavation
Report on excavation
 
1. How to build a shed foundation
1. How to build a shed foundation1. How to build a shed foundation
1. How to build a shed foundation
 
Analysis and-design-of-shallow-and-deep-foundations-lc-reese
Analysis and-design-of-shallow-and-deep-foundations-lc-reeseAnalysis and-design-of-shallow-and-deep-foundations-lc-reese
Analysis and-design-of-shallow-and-deep-foundations-lc-reese
 
To determine dry density of soil by core cutter method
To determine dry density of soil by core cutter methodTo determine dry density of soil by core cutter method
To determine dry density of soil by core cutter method
 

Semelhante a Rock mechanics for engineering geology (part 2)

Semelhante a Rock mechanics for engineering geology (part 2) (20)

Deep foundation.types and design
Deep foundation.types and designDeep foundation.types and design
Deep foundation.types and design
 
Pile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdfPile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdf
 
GT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptxGT-II-Unit-III-PILE-PartA.pptx
GT-II-Unit-III-PILE-PartA.pptx
 
Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundation
 
deep foundation.ppt
deep foundation.pptdeep foundation.ppt
deep foundation.ppt
 
deep foundation.ppt
deep foundation.pptdeep foundation.ppt
deep foundation.ppt
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
 
POWER POINT PRESENTATION ON pile_foundation_1.ppt
POWER POINT PRESENTATION ON pile_foundation_1.pptPOWER POINT PRESENTATION ON pile_foundation_1.ppt
POWER POINT PRESENTATION ON pile_foundation_1.ppt
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
Pile foundations Case Study Delhi Metro Site Visit
Pile foundations Case Study  Delhi Metro Site VisitPile foundations Case Study  Delhi Metro Site Visit
Pile foundations Case Study Delhi Metro Site Visit
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Building foundation
Building foundationBuilding foundation
Building foundation
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundation
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
 
Chapter 15
Chapter 15Chapter 15
Chapter 15
 
Deep foundation
Deep foundationDeep foundation
Deep foundation
 
Exploring the Benefits of Deep Foundations
Exploring the Benefits of Deep FoundationsExploring the Benefits of Deep Foundations
Exploring the Benefits of Deep Foundations
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
building foundation kagemu SELEMANI
building foundation kagemu SELEMANIbuilding foundation kagemu SELEMANI
building foundation kagemu SELEMANI
 

Mais de Jyoti Khatiwada

Presentation of TU students, 2018 at Ehime University
Presentation of TU students, 2018 at Ehime UniversityPresentation of TU students, 2018 at Ehime University
Presentation of TU students, 2018 at Ehime UniversityJyoti Khatiwada
 
Power point presentation on inclinometers
Power point presentation on inclinometersPower point presentation on inclinometers
Power point presentation on inclinometersJyoti Khatiwada
 
Hydrogeology Introduction with basic terms
Hydrogeology Introduction with basic termsHydrogeology Introduction with basic terms
Hydrogeology Introduction with basic termsJyoti Khatiwada
 
Groundwater Hydrogeology
Groundwater Hydrogeology Groundwater Hydrogeology
Groundwater Hydrogeology Jyoti Khatiwada
 
Drill bit types advantages and disadvantages
Drill bit types advantages and disadvantagesDrill bit types advantages and disadvantages
Drill bit types advantages and disadvantagesJyoti Khatiwada
 
Stress types around excavation opening
Stress types around excavation openingStress types around excavation opening
Stress types around excavation openingJyoti Khatiwada
 
Dam and types of dam with site selection
Dam and types of dam with site selectionDam and types of dam with site selection
Dam and types of dam with site selectionJyoti Khatiwada
 
Similarities between gravity and magnetics and application of different geoph...
Similarities between gravity and magnetics and application of different geoph...Similarities between gravity and magnetics and application of different geoph...
Similarities between gravity and magnetics and application of different geoph...Jyoti Khatiwada
 
Types of groundwater pumps
Types of groundwater pumpsTypes of groundwater pumps
Types of groundwater pumpsJyoti Khatiwada
 
To determine specific gravity of the solids by density bottle method
To determine specific gravity of the solids by density bottle methodTo determine specific gravity of the solids by density bottle method
To determine specific gravity of the solids by density bottle methodJyoti Khatiwada
 
Rock density and porosity lab
Rock density and porosity labRock density and porosity lab
Rock density and porosity labJyoti Khatiwada
 
positive and negative pore pressures.
positive and negative pore pressures.positive and negative pore pressures.
positive and negative pore pressures.Jyoti Khatiwada
 

Mais de Jyoti Khatiwada (20)

Project proposal
Project proposalProject proposal
Project proposal
 
Presentation of TU students, 2018 at Ehime University
Presentation of TU students, 2018 at Ehime UniversityPresentation of TU students, 2018 at Ehime University
Presentation of TU students, 2018 at Ehime University
 
Thesis Proposal example
Thesis Proposal exampleThesis Proposal example
Thesis Proposal example
 
Aggregrates
AggregratesAggregrates
Aggregrates
 
Power point presentation on inclinometers
Power point presentation on inclinometersPower point presentation on inclinometers
Power point presentation on inclinometers
 
Fem 1
Fem 1Fem 1
Fem 1
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Hydrogeology Introduction with basic terms
Hydrogeology Introduction with basic termsHydrogeology Introduction with basic terms
Hydrogeology Introduction with basic terms
 
Groundwater Hydrogeology
Groundwater Hydrogeology Groundwater Hydrogeology
Groundwater Hydrogeology
 
Drill bit types advantages and disadvantages
Drill bit types advantages and disadvantagesDrill bit types advantages and disadvantages
Drill bit types advantages and disadvantages
 
Stress types around excavation opening
Stress types around excavation openingStress types around excavation opening
Stress types around excavation opening
 
Rock failure criteria
Rock failure criteriaRock failure criteria
Rock failure criteria
 
Dam and types of dam with site selection
Dam and types of dam with site selectionDam and types of dam with site selection
Dam and types of dam with site selection
 
Similarities between gravity and magnetics and application of different geoph...
Similarities between gravity and magnetics and application of different geoph...Similarities between gravity and magnetics and application of different geoph...
Similarities between gravity and magnetics and application of different geoph...
 
Types of groundwater pumps
Types of groundwater pumpsTypes of groundwater pumps
Types of groundwater pumps
 
To determine specific gravity of the solids by density bottle method
To determine specific gravity of the solids by density bottle methodTo determine specific gravity of the solids by density bottle method
To determine specific gravity of the solids by density bottle method
 
Rock density and porosity lab
Rock density and porosity labRock density and porosity lab
Rock density and porosity lab
 
positive and negative pore pressures.
positive and negative pore pressures.positive and negative pore pressures.
positive and negative pore pressures.
 
Sediments transport
Sediments transportSediments transport
Sediments transport
 
Sediments loads
Sediments loadsSediments loads
Sediments loads
 

Último

Botany 4th semester series (krishna).pdf
Botany 4th semester series (krishna).pdfBotany 4th semester series (krishna).pdf
Botany 4th semester series (krishna).pdfSumit Kumar yadav
 
COST ESTIMATION FOR A RESEARCH PROJECT.pptx
COST ESTIMATION FOR A RESEARCH PROJECT.pptxCOST ESTIMATION FOR A RESEARCH PROJECT.pptx
COST ESTIMATION FOR A RESEARCH PROJECT.pptxFarihaAbdulRasheed
 
Proteomics: types, protein profiling steps etc.
Proteomics: types, protein profiling steps etc.Proteomics: types, protein profiling steps etc.
Proteomics: types, protein profiling steps etc.Silpa
 
American Type Culture Collection (ATCC).pptx
American Type Culture Collection (ATCC).pptxAmerican Type Culture Collection (ATCC).pptx
American Type Culture Collection (ATCC).pptxabhishekdhamu51
 
Presentation Vikram Lander by Vedansh Gupta.pptx
Presentation Vikram Lander by Vedansh Gupta.pptxPresentation Vikram Lander by Vedansh Gupta.pptx
Presentation Vikram Lander by Vedansh Gupta.pptxgindu3009
 
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43bNightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43bSérgio Sacani
 
Bacterial Identification and Classifications
Bacterial Identification and ClassificationsBacterial Identification and Classifications
Bacterial Identification and ClassificationsAreesha Ahmad
 
❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.
❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.
❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.Nitya salvi
 
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...Monika Rani
 
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 bAsymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 bSérgio Sacani
 
Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...
Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...
Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...Sérgio Sacani
 
GBSN - Microbiology (Unit 2)
GBSN - Microbiology (Unit 2)GBSN - Microbiology (Unit 2)
GBSN - Microbiology (Unit 2)Areesha Ahmad
 
GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)Areesha Ahmad
 
FAIRSpectra - Enabling the FAIRification of Spectroscopy and Spectrometry
FAIRSpectra - Enabling the FAIRification of Spectroscopy and SpectrometryFAIRSpectra - Enabling the FAIRification of Spectroscopy and Spectrometry
FAIRSpectra - Enabling the FAIRification of Spectroscopy and SpectrometryAlex Henderson
 
GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)Areesha Ahmad
 
Pests of cotton_Sucking_Pests_Dr.UPR.pdf
Pests of cotton_Sucking_Pests_Dr.UPR.pdfPests of cotton_Sucking_Pests_Dr.UPR.pdf
Pests of cotton_Sucking_Pests_Dr.UPR.pdfPirithiRaju
 
Botany 4th semester file By Sumit Kumar yadav.pdf
Botany 4th semester file By Sumit Kumar yadav.pdfBotany 4th semester file By Sumit Kumar yadav.pdf
Botany 4th semester file By Sumit Kumar yadav.pdfSumit Kumar yadav
 
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencyHire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencySheetal Arora
 
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdfPests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdfPirithiRaju
 
Conjugation, transduction and transformation
Conjugation, transduction and transformationConjugation, transduction and transformation
Conjugation, transduction and transformationAreesha Ahmad
 

Último (20)

Botany 4th semester series (krishna).pdf
Botany 4th semester series (krishna).pdfBotany 4th semester series (krishna).pdf
Botany 4th semester series (krishna).pdf
 
COST ESTIMATION FOR A RESEARCH PROJECT.pptx
COST ESTIMATION FOR A RESEARCH PROJECT.pptxCOST ESTIMATION FOR A RESEARCH PROJECT.pptx
COST ESTIMATION FOR A RESEARCH PROJECT.pptx
 
Proteomics: types, protein profiling steps etc.
Proteomics: types, protein profiling steps etc.Proteomics: types, protein profiling steps etc.
Proteomics: types, protein profiling steps etc.
 
American Type Culture Collection (ATCC).pptx
American Type Culture Collection (ATCC).pptxAmerican Type Culture Collection (ATCC).pptx
American Type Culture Collection (ATCC).pptx
 
Presentation Vikram Lander by Vedansh Gupta.pptx
Presentation Vikram Lander by Vedansh Gupta.pptxPresentation Vikram Lander by Vedansh Gupta.pptx
Presentation Vikram Lander by Vedansh Gupta.pptx
 
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43bNightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
 
Bacterial Identification and Classifications
Bacterial Identification and ClassificationsBacterial Identification and Classifications
Bacterial Identification and Classifications
 
❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.
❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.
❤Jammu Kashmir Call Girls 8617697112 Personal Whatsapp Number 💦✅.
 
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
Vip profile Call Girls In Lonavala 9748763073 For Genuine Sex Service At Just...
 
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 bAsymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
Asymmetry in the atmosphere of the ultra-hot Jupiter WASP-76 b
 
Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...
Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...
Discovery of an Accretion Streamer and a Slow Wide-angle Outflow around FUOri...
 
GBSN - Microbiology (Unit 2)
GBSN - Microbiology (Unit 2)GBSN - Microbiology (Unit 2)
GBSN - Microbiology (Unit 2)
 
GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)
 
FAIRSpectra - Enabling the FAIRification of Spectroscopy and Spectrometry
FAIRSpectra - Enabling the FAIRification of Spectroscopy and SpectrometryFAIRSpectra - Enabling the FAIRification of Spectroscopy and Spectrometry
FAIRSpectra - Enabling the FAIRification of Spectroscopy and Spectrometry
 
GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)
 
Pests of cotton_Sucking_Pests_Dr.UPR.pdf
Pests of cotton_Sucking_Pests_Dr.UPR.pdfPests of cotton_Sucking_Pests_Dr.UPR.pdf
Pests of cotton_Sucking_Pests_Dr.UPR.pdf
 
Botany 4th semester file By Sumit Kumar yadav.pdf
Botany 4th semester file By Sumit Kumar yadav.pdfBotany 4th semester file By Sumit Kumar yadav.pdf
Botany 4th semester file By Sumit Kumar yadav.pdf
 
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencyHire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
 
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdfPests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
 
Conjugation, transduction and transformation
Conjugation, transduction and transformationConjugation, transduction and transformation
Conjugation, transduction and transformation
 

Rock mechanics for engineering geology (part 2)

  • 1. DEEP FOUNDTION Jyoti Khatiwada Anischit This part is also useful for site investigation
  • 3. DEFINITION  If the depth of a foundation is greater than its width, the foundation is known as deep foundation.  In deep foundation the depth to width ratio is usually greater than 4 to 5.  Deep foundations as compare to Shallow foundations distribute the load of the super structure vertically rather than laterally.  Deep foundations are provided when the expected loads from superstructure cannot be supported on shallow foundations.
  • 4. Examples of Deep Foundations  Pile foundations  Pier foundations  Wells or Caissons foundations.
  • 5. WHEN IT IS USED?  In cases where  The strata of good bearing capacity is not available near the ground  The space is restricted to allow for spread footings  In these cases the foundation of the structure has to be taken deep with the purpose of attaining a bearing stratum which is suitable and which ensures stability and durability of a structure.  The bearing stratum is not the only case. There may be many other cases. For example, the foundation for a bridge pier must be placed below the scour depth, although suitable bearing stratum may exist at a higher level.
  • 6. TYPES OF DEEP FOUNDATION Deep foundation is classified into following types: • Pile foundation • Well foundation • Caisson foundation
  • 7. Pile Foundations  Pile foundations are the part of a structure used to carry and transfer the load of the structure to the bearing ground located at some depth below ground surface.  The main components of the foundation 1. The piles 2. The pile caps
  • 8. CONT’D  Piles are long and slender members which transfer the load to deeper soil or rock of high bearing capacity avoiding shallow soil of low bearing capacity.  Pile caps are thick slabs used to tie a group of piles together to support and transmit column loads to the piles.
  • 9. Pile Foundations  Where Used :  stratum of required bearing capacity is at greater depth  steep slopes are encountered  Compressible soil or water-logged soil or soil of made-up type  Examples: Piles are used for foundation for buildings, trestle-bridges and water front installations (piers, docks etc ).
  • 10. Types of Piles Based on Function Classification based on Function or Use 1. End Bearing Piles 2. Skin Friction Piles 3. Compaction Piles 4. Driven Piles 5. Auger cast Piles
  • 11. Types of Piles (cont’d) End Bearing Piles  Driven into the ground until a hard stratum is reached.  Acts as pillars supporting the super-structure and transmitting the load to the ground.  Piles, by themselves do not support the load, rather acts as a medium to transmit the load from the foundation to the resisting sub-stratum.
  • 12. Types of Piles (cont’d) Skin Friction Piles (Floating Piles)  Piles are driven at a site where soil is weak or soft to a considerable depth and it is not economical or rather possible to rest the bottom end of the pile on the hard stratum,  Load is carried by the friction developed between the sides of the pile and the surrounding ground ( skin friction).  The piles are driven up to such a depth that skin friction developed at the sides of the piles equals the load coming on the piles.  The load carrying capacity of friction pile can be increased by-  increasing diameter of the pile  driving the pile for larger depth  grouping of piles  making surface of the pile rough
  • 13. Types of Piles (cont’d) Anchor Piles  Piles are used to provide anchorage against horizontal pull from sheet piling wall or other pulling forces. Compaction piles:  When piles are driven in granular soil with the aim of increasing the bearing capacity of the soil, the piles are termed as compaction piles.
  • 14. Types of Piles (cont’d) Driven piles:  Driven piles are deep foundation elements driven to a design depth. If penetration of dense soil is required, pre drilling may be required for the pile to penetrate to the design depth. Types include timber, pre-cast concrete, steel H-piles, and pipe piles.
  • 15. Types of Piles (cont’d)• Auger cast piles Auger cast piles, are deep foundation elements that are cast-in-place, using a hollow stem auger with continuous flights. The auger is then slowly extracted, removing the drilled soil/rock.. Reinforcing steel is then lowered into the wet concrete or grout. The auger is drilled into the soil or rock to design depth. The technique has been used to support buildings, tanks, towers and bridges.
  • 16. Well foundations  Well foundations are being used in India from very early days. Taj Mahal was built on such foundations. Wells are also type of deep foundations. The main difference between a well and a pile foundation is that, while a pile is flexible like a beam under horizontal loads, the well undergoes rigid body movement under such loads.
  • 17. Types of Well Foundation Wells have different shapes and accordingly they are named as • Circular Wells • Dumb bell • Double-D Wells • Double Octagonal Wells • Single and Double Rectangular Wells • Multiple Dredged Holed Wells
  • 18. LOADS FOR WELL FOUNDATION DESIGN The following loads are considered for the analysis and design of well foundation: 1.Dead load 2.Live load 3.Buoyancy 4.Wind load 5.Horizontal force due to water current 6.Centrifugal forces 7.Longitudinal forces 8.Seismic forces 9.Horizontal shear forces at bearings due to longitudinal forces and seismic forces 10.Forces due to tilt and shift.
  • 19. TYPES OF FOUNDATION Caissons Caisson foundation is also known as pier foundation. Caisson is a cylinder or hollow box that is sunk into the ground to a specified depth by auguring a deep hole into the strata. The cylinder or box is then back filled with concrete, thus creating the foundation. This type of foundation is most often used when constructing bridge piers and other such foundations that will be beneath bodies of water since the caissons can be floated to the correct locations and then sunk in place using concrete.
  • 20. Why To Use a Caisson Foundation • This type of foundation will keep the soils underneath the building or structure from moving vertically. Since soil will settle over time, the building or structure on top of the soil will also settle. This can cause major structural damage. Since a caisson foundation is drilled into the earth and large concrete t filled cylinders are placed within the ground rather than on top, the settlement of the soil will not cause many difficulties for the building or structure.
  • 21. Types of Caissons • Box caissons are watertight boxes that are constructed of heavy timbers and open at the top. They are generally floated to the appropriate location and then sunk into place with a masonry pier within it. • Excavated caissons are just as the name suggests, caissons that are placed within an excavated site. These are usually cylindrical in shape and then back filled with concrete.
  • 22. Types of Caissons (cont’d) • Floating caissons are also known as floating docks and are prefabricated boxes that have cylindrical cavities. • Open caissons are small cofferdams that are placed and then pumped dry and filled with concrete. These are generally used in the formation of a pier. • Pneumatic caissons are large watertight boxes or cylinders that are mainly used for under water construction.
  • 23. Careful study of loads to be transmitted from columns of super structure and soil profile. Objective : oTo identify type of pile oTo determine load carrying capacity of individual pile Only one type of pile below different columns For large projects two or three sizes may be adopted
  • 24. 1. IDENTIFYING STRONG BEARING LAYER FOR LOCATING THE PILE TIP • Study soil profile • Look for strong bearing layer IF STRONG BEARING LAYER IS FOUND • Locate pile tip, a few meters, in • Pile becomes ‘end bearing pile’ • Easy to conduct settlement analysis
  • 25. IF NO STRONG BEARING LAYER IS FOUND • Pile should be friction pile. • Pile derives its capacity from both, end bearing & friction. • Select two pile lengths as deep as possible.
  • 26. 2. SELECTION OF PILE Choice of pile depends on Length Width Material ( concrete, steel, wood) Cross-section (square, circular, tubular) Installation procedure (driven, bored) Feasibility of construction Feasibility of noise and vibration
  • 27. 3. RANGE OF PILE LENGTH & DIAMETERS LENGTH : • Usually 10 – 30 m • Offshore application 70 – 100 m WIDTH/DIAMETERS : • Usually 0.3 – 0.75 m • Drilled piles 1 – 2.5 m • Micropiles 0.15 m
  • 28. 4. AXIAL CAPACITY ANALYSIS Pile type – selected Range of dimensions – chosen Estimate the axial capacity One of the procedures is ‘Pile Load Test’
  • 29. 5. SETTLEMENT ANALYSIS • For piles, not resting on strong bearing capacity, settlement analysis is conducted.
  • 30. 6. RESULTS & RECOMMENDATIONS Presented in tabular form. In selecting from the options available, two factors are given : Large sized but fewer number of piles, hence installation time is less. 3 piles (min. number) can support only lightly loaded columns, for heavier loads, increase the pile group.
  • 31.
  • 32. ADVANTAGES OF DIFFERENT METHODS OF DEEP FOUNDATION DRILLED PIER FOUNDATIONS Advantages 1.Pier of any length and size can be constructed at the site 2. Construction equipment is normally mobile and construction can proceed rapidly 3. Inspection of drilled holes is possible because of the larger diameter of the shafts 4.The drilled pier is applicable to a wide variety of soil conditions 5.Changes can be made in the design criteria during the progress of a job 7.Ground vibration that is normally associated with driven piles is absent in drilled pier construction 8.Bearing capacity can be increased.
  • 33. Disadvantages 1. Installation of drilled piers needs a careful supervision and quality control of all the materials used in the construction 2. The method is cumbersome. It needs sufficient storage space for all the materials used in the construction.
  • 34. Augered Piles Advantages…… 1.Limited risk of damage to adjacent foundations or underground utilities from ground displacement or densification of loose sands, as can occur with displacement piles. 2.CFA piles can be installed with little vibrations or noise. 3.Should problems occur during pile construction, it is relatively simple to re–drill and install the pile at the same location, thereby eliminating the need to redesign the pile group or the pile caps. 4.A reliable flow meter can be used to monitor and record penetration / uplift per revolution, auger depth, concrete supply per increment of auger uplift during placing, and injection pressure at the auger head. .
  • 35. Disadvantage 1.If the appropriate installation procedures are not followed exactly the pile formed may be of poor and/or inconsistent quality and load carrying capacity. 2.The most critical factor for the CFA system is still its reliance on operator performance, which may result in a pile of poor quality and reduced load carrying capacity. Thus, it is vitally important that experienced personnel install the piles. 3.To ensure success it is vital to give due care to every stage of the field installation procedure, including drilling of the hole, casting of the shaft, extraction of the auger and the placement of the reinforcement.
  • 36. Driven concrete pile ADVANTAGES…….. 1.Driven concrete pile foundations are applicable under most ground conditions. 2.Concrete piles are usually inexpensive compared with other types of deep foundations. 3.The procedure of pile installation is straightforward; piles can be produced in mass production either on site or in a manufacture factory, and the cost for materials is usually much less than steel piles. 4.Proxy coating can be applied to reduce negative skin friction along the pile. 5.Pile driving can densify loose sand and reduce liquefaction potential within a range of up to three diameters surrounding the pile.
  • 37. DISADVANTAGES…… 1.Pile driving produces noise pollution and causes disturbance to the adjacent structures. 2. Driving of concrete piles also requires large overhead space. 3.Piles may break during driving and impose a safety hazard. 4.Piles that break underground cannot take their design loads, and will cause damage to the structures if the broken pile is not detected and replaced. 5. End-bearing capacity of a pile is not reliable if the end of a pile is smashed.
  • 38. DRIVEN WOODEN PILE ADVANTAGES…… 1.The piles are easy to handle 2.Relatively inexpensive where timber is plentiful. 3.Sections can be joined together and excess length easily removed.
  • 39. 1.The piles will rot above the ground water level. Have a limited bearing capacity. 2.Can easily be damaged during driving by stones and boulders. 3.The piles are difficult to splice and are attacked by marine borers in salt water. DISADVANTAGES
  • 40. DRILLED SHAFT METHOD ADVANTAGES……. 1.The length and size of the foundations can be tailored easily. 2. Disturbance to the nearby structures is small compared with other types of deep foundations. 3.Drilled shafts can be constructed very close to existing structures and can be constructed under low overhead conditions. Therefore, 4. drilled shafts are often used in many seismic retrofit projects.
  • 41. DISADVANTAGES 1. Drilled shafts may be difficult to install under certain ground conditions such as soft soil, loose sand, sand under water, and soils with boulders. 2. Drilled shafts will generate a large volume of soil cuttings and fluid and can be a mess. Disposal of the cuttings is usually a concern for sites with contaminated soils. 3. Drilled shaft foundations are usually comparable with or more expensive than driven piles.
  • 42. APPLICTION OF DEEP FOUNDATION A deep foundation installation for a bridge in Napa, California, United States.
  • 43. APPLICTION OF DEEP FOUNDATION Pile driving operations in the Port ofTampa, Florida, United States.
  • 44. APPLICTION OF DEEP FOUNDATION Sheet piles are used to restrain soft soil above the bedrock in this excavation
  • 45. APPLICTION OF DEEP FOUNDATION Adfreeze Piles supporting a building in Barrow, Alaska, United States
  • 46. APPLICTION OF DEEP FOUNDATION Sheet piling, by a bridge, was used to block a canal in New Orleans, United States after Hurricane Katrinadamaged it
  • 47. APPLICTION OF DEEP FOUNDATION Cutaway illustration. Deep inclined (battered) pipe piles support a precast segmented skyway where upper soil layers are weak muds.
  • 48. • DEFORMABILITY MODULUS OF JOINTED ROCKS, LIMITATION OF EMPIRICAL METHODS, AND INTRODUCING A NEW ANALYTICAL APPROACH
  • 49. • Introduction • The commission of Terminology, symbols and graphic representation of the International Society for Rock Mechanics ISRM ) ISRM, 1975 ) • Modulus of elasticity or Young’s modulus (E) : The ratio of stress to corresponding strain below the proportionality limit of a material. • Modulus of deformation of a rock mass (Em) : The ratio of stress (p) to corresponding strain during loading of a rock mass, including elastic and inelastic behavior • Modulus of elasticity of a rock mass (Eem) : The ratio of stress (p) to corresponding strain during loading of a rock mass, including only the elastic behavior
  • 50.
  • 51.
  • 52.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57. Conclusion On Deformability • Deformability modulus is a stress dependent parameter and increases as applied stress increases. • All well-known empirical formulations do not consider this property of deformability modulus. • A new procedure is proposed to quantify the stress dependency of deformability modulus.
  • 58. Plane of weakness • Discontinuity Orientation • Dip - Angle of Steepest Inclination of Plane, Measured Below Horizontal (two digits 00 to 90) • Dip Direction (Dip Azimuth) - Azimuth of the Line of Dip (three digits 000 to 360) • Strike - Azimuth of a Horizontal Line (90 Degrees to Dip Direction) - Unsuitable for Rock Slope Engineering
  • 59.
  • 60. Discontinuity Spacing • Measure True Spacing in Surface Mapping • Range: • Extremely close spacing (<20 mm) • Extremely wide spacing (>6000 mm) • Line Mapping or Coreholes: Use Terzaghi Correction for True Spacing
  • 61.
  • 62.
  • 63. Persistence • Document Visible or Inferred Length • -Range: • Very low (<1 m) • Very high (>20 m) • Document Termination of Joints (0, 1, 2) • Statistical Estimates of Length Distribution Persistence cannot be Measured in Core
  • 64.
  • 65.
  • 66.
  • 67.
  • 68.
  • 69.
  • 70.
  • 71.
  • 72.
  • 73.
  • 74.
  • 75. IMPORTANCE OF JOINTS IN TERMS OF ROCK MECHNICS JYOTI KHATIWADA
  • 76. INTRODUCTION • In geology, a joint is a fracture dividing rock into two sections that have not moved away from each other. A joint sees little or no displacement. • As Earth crust is full of joints, therefore their study and importance is very significance. • joints are important not only in understanding the local and regional geology and geomorphology, but also are important in development of natural resources, the safe design of structures, and environmental protection. Joints have a profound control on weathering and erosion of bedrock. As a result, they exert a strong control on how topography and morphology of landscapes develop.
  • 77. • Importance of joints in engineering and geological applications include: 1. In rock mass classification 2. foundation strength 3. Geohydrology/ Natural circulation of fluids 4. Petroleum and mineral deposition 5. Studying mechanical properties of rock masses 6. Mining and quarry operational feasibility 7. Toxic waste/ risk
  • 78. 1. IN ROCK MASS CLASSIFICATION a. In determination of RQD (Rock Quality Designation) b. In determination of block size. c. In determination of RMR (Rock Mass Rating) d. In determination of rock quality ( Q system)
  • 79. • In determination of RQD (Rock Quality Designation): In many cases the degree of jointing is the most important factor for the stability of rock masses. The volumetric joint count (Jv) is a simple measure of the degree of jointing. It takes into account all the occurring joints and fractures and is easily calculated from standard joint descriptions. The (Jv) has been used by engineering geologists in Norway for several years and it has been a useful tool in the description and classification of rock masses. The paper describes the procedure for the calculation of the (Jv) and it shows how the joint spacings are included in the measure. RQD = 115 - 3.3 Jv. Jv = Joint volumetric count
  • 80. • In determination of block size: Block size = If 𝐽 𝑛 = 0, block size tends to infinite, it represents continuity i.e. ground is made up of rock. If 𝐽 𝑛 is more, ground is moving towards fractured ground. Hence joints are very important parameter affecting geotechnical behavior of ground. 𝑅𝑄𝐷 𝐽 𝑛
  • 81. • In determination of RMR (Rock Mass Rating): RMR is determined as an algebraic sum of six parameters given below: 1. Rock quality designation 2. Joint spacing 3. Joint condition 4. Joint orientation 5. Ground water condition 6. UCS of rock material. RMR = RRQD + RJOINT SPACING + RJOINT CONDITION + RORIENTATION + RGROUND WATER CONDITION + RUCS RMR Rock quality 0 - 20 Very Poor 21 - 40 Poor 41 - 60 Fair 61 - 80 Good 81 - 100 Very good
  • 82. • In determination of rock quality ( Q system): • The Q-system for rock mass classification is developed by Barton, Lien, and Lunde. It expresses the quality of the rock mass in the so-called Q-value, on which are based design and support recommendations for underground excavations. • The Q-value is determined with 𝑹𝑸𝑫 𝑱 𝒏 represents block size 𝑱 𝒓 𝑱 𝒂 represents shear strength 𝑱 𝒓 𝑱 𝒂 represents condition or nature of rock • Jw is the measure of water pressure which has an adverse effect on the shear strength of joint due to reduction in effective normal stress. 𝑸 = 𝑹𝑸𝑫 𝑱 𝒏 × 𝑱 𝒓 𝑱 𝒂 × 𝑱 𝒘 𝑺𝑹𝑭
  • 83. OTHER IMPORTANCE : • Joints often impart a well-develop fracture-induced permeability to bedrock. As a result, joints strongly influence, even control, the natural circulation (geohydrology) of fluids. • groundwater and pollutants within aquifers, petroleum in reservoirs, and hydrothermal circulation at depth, within bedrock. Thus, joints are important to the economic and safe development of petroleum, hydrothermal, and groundwater resources and the subject of intensive research relative to the development of these resources.
  • 84. • Also, regional and local joint systems exert a very strong control on how ore-forming (hydrothermal) fluids, consisting largely of  H2O, CO2, and NaCl, that formed most of Earth's ore deposits circulated within the Earth crust. As a result, understanding their genesis, structure, chronology, and distribution is an important part of finding and profitably developing ore deposits of various types. • Finally, joints often form discontinuities that may have a large influence on the mechanical behavior (strength, deformation, etc.) of soil and rock masses in, for example, tunnel, foundation, or slope construction. • As a result, joints are an important part of geotechnical engineering in practice and research
  • 85. Footing Definition Footings are structural members used to support columns and walls and to transmit and distribute their loads to the soil in such a way that the load bearing capacity of the soil is not exceeded, excessive settlement, differential settlement,or rotation are prevented and adequate safety against overturning or sliding is maintained.
  • 86. Types of Footing Wall footings are used to support structural walls that carry loads for other floors or to support nonstructural walls.
  • 87. Types of Footing Isolated or single footings are used to support single columns. This is one of the most economical types of footings and is used when columns are spaced at relatively long distances.
  • 88. Types of Footing Combined footings usually support two columns, or three columns not in a row. Combined footings are used when tow columns are so close that single footings cannot be used or when one column is located at or near a property line.
  • 89. Types of Footing Cantilever or strap footings consist of two single footings connected with a beam or a strap and support two single columns. This type replaces a combined footing and is more economical.
  • 90. Types of Footing Continuous footings support a row of three or more columns. They have limited width and continue under all columns.
  • 91. Types of Footing Rafted or mat foundation consists of one footing usually placed under the entire building area. They are used, when soil bearing capacity is low, column loads are heavy single footings cannot be used, piles are not used and differential settlement must be reduced.
  • 92. Types of Footing Pile caps are thick slabs used to tie a group of piles together to support and transmit column loads to the piles.
  • 93. Distribution of Soil Pressure When the column load P is applied on the centroid of the footing, a uniform pressure is assumed to develop on the soil surface below the footing area. However the actual distribution of the soil is not uniform, but depends on may factors especially the composition of the soil and degree of flexibility of the footing.
  • 94. Distribution of Soil Pressure Soil pressure distribution in cohesionless soil. Soil pressure distribution in cohesive soil.
  • 95. Design Considerations Footings must be designed to carry the column loads and transmit them to the soil safely while satisfying code limitations. The area of the footing based on the allowable bearing soil capacity Two-way shear or punching shear. One-way bearing Bending moment and steel reinforcement required * * * *
  • 96. Design Considerations Footings must be designed to carry the column loads and transmit them to the soil safely while satisfying code limitations. Bearing capacity of columns at their base Dowel requirements Development length of bars Differential settlement * * * *
  • 97. Size of Footing The area of footing can be determined from the actual external loads such that the allowable soil pressure is not exceeded.   pressuresoilallowable weight-selfincludingloadTotal footingofArea  footingofarea u u P q  Strength design requirements
  • 98. Two-Way Shear (Punching Shear) For two-way shear in slabs (& footings) Vc is smallest of long side/short side of column concentrated load or reaction area<2 length of critical perimeter around the column where, bc = b0 = ACI 11-35 dbfV 0c c c 4 2          b When b >2 the allowable Vc is reduced.
  • 99. Design of two-way shear Assume d. Determine b0: b0 = 4(c+d) for square columns where one side = c b0 = 2(c1+d) +2(c2+d) for rectangular columns of sides c1 and c2. 1 2
  • 100. Design of two-way shear The shear force Vu acts at a section that has a length b0 = 4(c+d) or 2(c1+d) +2(c2+d) and a depth d; the section is subjected to a vertical downward load Pu and vertical upward pressure qu. 3      columnsrrectangulafor columnssquarefor 21uuu 2 uuu dcdcqPV dcqPV  
  • 101. Design of two-way shear Allowable Let Vu=fVc 4 dbfV 0cc 4ff  0c u 4 bf V d f  If d is not close to the assumed d, revise your assumptions
  • 102. Design of one-way shear For footings with bending action in one direction the critical section is located a distance d from face of column dbfV 0cc 2ff 
  • 103. Design of one-way shear The ultimate shearing force at section m-m can be calculated          d cL bqV 22 uu If no shear reinforcement is to be used, then d can be checked
  • 104. Design of one-way shear bf V d 2 c u f  If no shear reinforcement is to be used, then d can be checked, assuming Vu = fVc
  • 105. Flexural Strength and Footing reinforcement 2 y u s           a df M A f The bending moment in each direction of the footing must be checked and the appropriate reinforcement must be provided.
  • 106. Flexural Strength and Footing reinforcement bf Af a 85.0 c sy  Another approach is to calculated Ru = Mu / bd2 and determine the steel percentage required r . Determine As then check if assumed a is close to calculated a
  • 107. Flexural Strength and Footing reinforcement The minimum steel percentage required in flexural members is 200/fy with minimum area and maximum spacing of steel bars in the direction of bending shall be as required for shrinkage temperature reinforcement.
  • 108. Flexural Strength and Footing reinforcement The reinforcement in one-way footings and two-way footings must be distributed across the entire width of the footing. 1 2 directionshortinentreinforcemTotal widthbandinentReinforcem   b footingofsideshort footingofsidelong b where
  • 109. Bearing Capacity of Column at Base The loads from the column act on the footing at the base of the column, on an area equal to area of the column cross-section. Compressive forces are transferred to the footing directly by bearing on the concrete. Tensile forces must be resisted by reinforcement, neglecting any contribution by concrete.
  • 110. Bearing Capacity of Column at Base Force acting on the concrete at the base of the column must not exceed the bearing strength of the concrete  1c1 85.0 AfN f where f = 0.7 and A1 =bearing area of column
  • 111. Bearing Capacity of Column at Base The value of the bearing strength may be multiplied by a factor for bearing on footing when the supporting surface is wider on all sides than the loaded area. 0.2/ 12 AA The modified bearing strength    1c2 121c2 85.02 /85.0 AfN AAAfN f f  
  • 112. Dowels in Footings A minimum steel ratio r = 0.005 of the column section as compared to r = 0.01 as minimum reinforcement for the column itself. The number of dowel bars needed is four these may be placed at the four corners of the column. The dowel bars are usually extended into the footing, bent at the ends, and tied to the main footing reinforcement. The dowel diameter shall not =exceed the diameter of the longitudinal bars in the column by more than 0.15 in.
  • 113. Development length of the Reinforcing Bars The development length for compression bars was given but not less than Dowel bars must be checked for proper development length. cbyd /02.0 fdfl  in.8003.0 by df
  • 114. Differential Settlement Footing usually support the following loads Dead loads from the substructure and superstructure Live load resulting from material or occupancy Weight of material used in backfilling Wind loads
  • 115. General Requirements for Footing Design A site investigation is required to determine the chemical and physical properties of the soil. Determine the magnitude and distribution of loads form the superstructure. Establish the criteria and the tolerance for the total and differential settlements of the structure. 1 2 3
  • 116. General Requirements for Footing Design Determine the most suitable and economic type of foundation. Determine the depth of the footings below the ground level and the method of excavation. Establish the allowable bearing pressure to be used in design. 4 5 6
  • 117. General Requirements for Footing Design Determine the pressure distribution beneath the footing based on its width Perform a settlement analysis. 7 8
  • 118. EFFECT OF DISCONTINUTY STRIKE & DIP ORIENTATION IN EXPLORATION/TUNNELING STRIKE PERPENDICULAR TO TUNNEL AXIS STRIKE PARALLEL TO TUNNEL AXIS Drive with dip: Dip 45- 90° Drive with dip: Dip 20-45° Dip 45-90° Dip 20-45° Very favorable Favorable Very favorable Fair Drive against dip: Dip 45-90° Drive against dip: Dip 20- 45° Dip 0-20° , Irrespective of strike angle Fair Unfavorable Fair
  • 119. TOWER OF PISA, ITALY
  • 120. MAIN FACTORS AFFECTING THE ROCK QUALITY  Topography of area  Types Soil/rock on Surface as well as Subsurface.  Degree of weathering  Number of Joint sets  Spacing between joints  Cavity  Filling material  Dewatering/ ground water inflow  Direction and amount of Dip and strike
  • 121.
  • 122.
  • 123.
  • 124. METHODS OF STUDY THE ROCK QUALITY • A number of Geotechnical parameters govern condition of Rock mass and the nature of its discontinuities. Main two are:- • (1) RMR (2) Q SYSTEM • (1) RMR (Rock Mass rating): • Bieniawski (1973), proposed RMR system, also know as ‘Geomechanics Classification” for jointed rock masses. Many modifications has undergone time to time. • Five basic parameters considered for RMR: STRENGTH OF ROCK, RQD (Rock Quality Designation), SPACING OF JOINTS, CONDITION OF JOINTS & GROUND WATER CONDITION. • Final RMR value related to five classes of rock mass i.e. ‘very good’, ‘good’’, ‘fair’, ‘poor’, ‘very poor’ rock.
  • 125. METHODS OF STUDY THE ROCK QUALITY  Q- SYSTEM (ROCK MASS QUALITY)  Proposed by Basedon in 1974, based on the study of 200 tunnel case histories.  The rock quality Q is determined by estimating six parameters. These are RQD, JOINT SET NUMBER (Jn), JOINT ROUGHNESS NUMBER (Jr), JOINT ALTERATION NUMBER (Ja) AND STRESS REDUCTION FACTOR (SRF).  Q= (RQD/Jn) x (Jr/Ja) X (Jw/SRF) (Barton et. al. 1974)  The numerical value Q ranges from 0.001 (for exceptionally poor quality squeezing ground) to 1000 (for exceptionally good quality rock which is practically unjointed).  Q-value is divided into 9 categories of rock quality which are related to support requirement depending upon excavation span and intended use of excavation.
  • 126. SURFACE/SUBSURFACE INVESTIGATION INVESTIGATIONS FIELD INVESTIGATIONS LABOURATURY INVESTIGATIONS (A) Geotechnical (a) Physical properties of Soil & Rock (B) Hydrological (b) Geomechanical Properties (C) Geophysical (c ) Petrological studies of rock & soil (D) Construction material Main Field tests are Drilling, Pit excavation, Deformability test (Goodman Jack Test & Hydro Fracture test), Load bearing capacity test (Plate Load Test), Water Percolation test (permeability test), Earth resistivity test, Seismic reflection test (know the subsurface fault/ shear zone), aggregate test , topographical studies etc. Studies of Satellite imageries is very useful to understand the topography, geomorphology of area.
  • 127. • On the basis of RMR and Q Value, geologist suggest supporting system in excavated rock/soil. • On the basis of geotechnical & geologist report project designer has fixed the structure design and remedies measures. RESULTS
  • 128. CAREER IN ENGINEERING GEOLOGY • Infrastructure Projects as Hydro Power Plant, Tunnels for railway/transport, Canal, Dam, reservoir, highways, bridges, buildings, water treatment plant, land use, environmental studies etc. • For Mine and Quarry excavations, mine reclamation. • For coastal engineering, sand replenishment, sea cliff stability, water front development. • For offshore drilling platform, sub sea pipeline and cables etc.
  • 130. INTRODUCTION A tunnel is an underground passageway, completely enclosed except for openings for egress, commonly at each end. A tunnel may be for road traffic,road traffic,canal,hydroelectric station,sewer etc. The Delaware Aqueduct in New York USA is the longest tunnel, of any type, in the world at 137 km (85 mi)
  • 131. REQUIRMENTS OF TUNNEL  IT IS VERY USEFUL WHERE BRIDGE FAIL TO FULFILL REQUIRMENTS LIKE IN SEA ,IN URBAN AREA ,AND IN MOUNTAINS.  EFFICIENT COPARED TO BRIDGES.   IN WAR TIME IT IS MUCH DIFFICULT TO DESTROY A TUNNEL BUT DESTRUCTION OF BRIDGE IS TOO EASY.  LOTS OF LAND AND TIME IS SAVED.
  • 132. MAIN PURPOSES 1.IN ROAD TRAFFICS 2.IN SEWERS 3.IN MININGS 4.IN RAIL TRAFFICS 5.IN HYDROELECTRIC STATIONS etc.
  • 133. The process for bored tunnelling involves all or some of the following operations: • Probe drilling (when needed) • Grouting (when needed) • Excavation (or blasting) • Supporting • Transportation of muck • Lining or coating/sealing • Draining • Ventilation
  • 134. PROBE DRILLING • This type of drilling is done in order to find out suitable method for drilling . • It consist of drilling in sample, by various method to find most suitable . • It is necessary part of all drilling operation .
  • 135. GROUTING • It is the process of providing additional support to drilled mine. • It is done by a liquid called grout ,consist of water ,cement ,color tint and sometime fine gravel . • Good surface is achieved .
  • 136. EXCAVATION • Excavation is the digging and recording of artifacts at an archaeological site. • It is necessary to know the archaeological importance of a site before digging . • This is performed by experts in a scientific way. • Many governments grants permission for tunneling after finding a go certificate in excavation.
  • 137. SUPPORTING • After initial mining , tunnel need supports for further processing . • For the sake of life a perfect planning is needed for support. • In ancient time timber and masonry were the main methods. • Today support is provided by injecting final pipe or building it completely before further tunneling
  • 138. Transportation of muck • In ancient time transportation was done by steam engine and by Manual transport. • Today it is done by modern methods and process is automatic . • TBMs are also come with proper arrangment for the transport of muck.
  • 139. LINING OR COATING • Lining of proper material is done by modern methods like polishing ,painting to prevent wear and tear and corrosion. • Very necessary part where corrosive metals are being used.
  • 140. DRAINING • Draining is the process to remove the water or other liquid from working site . • Very important where water level is very high. • Pumps and pipes are used for this purpose.
  • 141. VENTILATION • Proper ventilation is required for safety of workers. • This is done by proper checking of oxygen and other parameters . • Proper installations for exit of hazardous gasses coming out from tunneling .
  • 142. tunnel construction methods: • Classical methods • Cut-and-cover • Drill and blast • Tunnel boring machines (TBMs) • Immersed tunnels • Tunnel jacking • Other methods .
  • 143. Classical Methods  Among the classical methods are the Belgian, English, German, Austrian, Italian and American systems. These methods had much in common with early mining methods and were used until last half of the 19th century.  Excavation was done by hand or simple drilling equipment.  Supports were predominantly timber, and transportation of muck was done on cars on narrow gauge tracks and powered by steam.  Progress was typically in multiple stages i.e. progress in one drift, then support, then drift in another drift, and so on.  The lining would be of brickwork. These craft-based methods are no longer applicable, although some of their principles have been used in combination up to present day. Nevertheless some of the world’s great tunnels were built with these methods.
  • 144. The English method (crown-bar method, figure left) started from a central top heading which allowed two timber crown bars to be hoisted into place, the rear ends supported on a completed length of lining, the forward ends propped within the central heading. Development of the heading then allowed additional bars to be erected around the perimeter of the face with boards between each pair to exclude the ground. The system is economical in timber, permits construction of the arch of the tunnel in full-face excavation, and is tolerant of a wide variety of ground conditions, but depends on relatively low ground pressures.
  • 145.  The Austrian (cross-bar) method required a strongly constructed central bottom heading upon which a crown heading was constructed. The timbering for full-face excavation was then heavily braced against the central headings, with longitudinal poling boards built on timber bars carried on each frame of timbering. As the lining advanced, so was the timbering propped against each length to maintain stability. The method was capable of withstanding high ground pressures but had high demand for timber.
  • 146. • The German method (core-leaving method) provided a series of box headings within which the successive sections of the side walls of the tunnel were built from the footing upwards, thus a forerunner of the system of multiple drifts. The method depends on the central dumpling being able to resists without excessive movement pressure transmitted from the side walls, in providing support to the top 'key' heading prior to completion of the arch and to ensuring stability while the invert arch is extended in sections. • The Belgian system (underpinning or flying arch method) started from the construction of a top heading, propped approximately to the level of the springing of the arch for a horseshoe tunnel. This heading was then extended to each side to permit construction of the upper part of the arch, which was extended by under- pinning, working from side headings. The system was only practicable where rock loads were not heavy. • The first sizeable tunnel in soft ground was the Tronquoy tunnel on the St Quentin canal in France in 1803, where the method of construction, based on the use of successive headings to construct sections of the arch starting from the footing, was a forerunner to the German system described above.
  • 148. Cut and Cover Method
  • 149. CUT & COVER METHOD The principal problem to be solved in connection with this construction method is to how to maintain surface traffic, with the least disturbance during the construction period. One method is to restrict traffic to a reduced street width, another to direct traffic to a bypassing street.  Another way of supporting the sidewalls of open trenches is to substitute sheet-pile walls by concrete curtain walls cast under bentonite slurry (ICOS method), and using steel struts. This is especially a requisite in narrower streets trimmed with old sensitive buildings with their foundation plane well above the bottom level of the pit. This type of trench wall becomes a requirement for maintenance of surface traffic due to the anticipation of vibration effects potentially harmful to the stability of buildings with foundations lying on cohesionless soils.
  • 150. DRILL AND BLAST 1.Before the advent of tunnel boring machines, drilling and blasting was the only economical way of excavating long tunnels through hard rock, where digging is not possible. 2.Even today, the method is still used in the construction of tunnels.
  • 151. HOW DRILL AND BLAST IS BEING DONE.
  • 152. Mechanical Drilling and Cutting-Crushing Strength of rock
  • 153. TBM • In various size Tunnel Boring Machines(TBM) are used for drilling a vast type of tunnels . • Transportation of muck , supporting and all other actions are done automatically. • Very useful in boring tunnel where all other methods fail. • A main method in use in now a days.
  • 154.
  • 155. IMMERSED TUNNELS 1.THIS TYPE OF TUNNELS ARE PARTLY OR WHOLLY ARE UNDERWATWER. 2.THEY DO NOT BLOCK THE ROOT FOR SHIPS SO THERE IS NO PROBLEM OF CONGESSION OF TRAFFIC AS IN CASE OF BRIDGES OVER RIVERS OR SEAS.
  • 156. TUNNEL JACKING 1.IT IS A PROCESS TO MAKE TUNNELS IN ALREADY EXISTING BOADIES SUCH AS ROADS ,RAILWAYS. 2.IN THIS METHOD ESPECIALLY MADE PIPES ARE PUSHED BY A HYDRAULIC RAM IN GROUND . 3.MAXIMUM DIAMETER OF TUNNEL BY THIS METHOD IS AROUND 2.4 METER.
  • 157.
  • 158. The choice of tunnelling method may be dictated by: • geological and hydrological conditions, • cross-section and length of continuous tunnel, • local experience and time/cost considerations (what is the value of time in the project), • limits of surface disturbance, and many others factors. • Tunnel methods . • Required speed of construction. • Shape of tunnel. • Managing the risk of variations in ground quality
  • 159. THE OTHER SIDE • Beside of many security measures , tunnelling is still not full proof. • Failure of automatic system will cause deadly results as depicted in Hollywood flick Die Hard 4.0. • High cost than bridges , but more fruitful from previous.
  • 160. NATM NATM NEW AUSTRIAN TUNNELING METHOD By ADIL BIN AYOUB 41-CE-13 B.Tech CIVIL ENGINEERING School of Engineering & Technology, BGSBU Rajouri J&K
  • 161. HISTORY OF NATM • The term New Austrian Tunneling Method Popularly Known as NATM got its name from Salzburg (Austria). • It was first used by Mr. Rabcewicz in 1962. It got world wise recognition in1964. • The first use of NATM in soft ground tunnel in Frankfurt (Europe) metro in 1969.
  • 162. DEFINITION OF NATM • The New Austrian Tunneling Method is a support method to stabilize the tunnel perimeter by means of sprayed concrete ,anchors and other support and uses monitoring too control stability. • Main idea is to use the geological stress of the surrounding rock mass to stabilize the tunnel itself
  • 163. BROAD PRINCIPLES OF NATM • Mobilization of the strength of rock mass • Shotcrete protection • Measurements and monitoring • Primary Lining • Closing of invert • Rock mass classification
  • 167. PRIMARY LINING Wire mesh and steel ribs
  • 170. WHY NATM • Flexibility to adopt different excavation geometries and very large cross sections. • Flexibility to install additional support measures, rock bolts, dowels, steel ribs if required. • Easy to install a waterproof membrane. • Easy to install primary support, i.e. shotcrete.
  • 171. SUMMARY OF THE PROCEDURE IN NATM • SHOTCRETING AT THE EXCAVATED AREA(PRIMARY LINING) • PLACING OF THE WIREMESH ALONG THE FACEOF THE TUNNEL • ERECTION OF THE LATTICE GIRDER ALONG THE FACE OF THE TUNNEL • PERTICULAR TYPE OF ROCKBOLTING • SHOTCRETING THE WHOLE ARRENGEMENT(SECONDARY LINING)
  • 172. CONCEPT OF 3D MONITORING • 3D MONITORING IS NEW TECHNIQUE USING FOR TAKING THE RIGHT ALIGNMENT OF THE TUNNEL • OPTICAL TARGETS ARE USED FOR DETRMINIG THE COORDINATES FOR MEASUREMENTS • THE COORDINATES SHOULD BE CHECKED DAILY • IT IS NECESSARY FOR THE TUNNEL AS BY IT WE KNOW ANY DISPLACEMENT AND WRONG ALIGNMENTS
  • 174.
  • 175. WHERE NATM IS USING IN INDIA • PRESENTLY IT IS USING WIDLELY IN KASHMIR RAILWAY PROJECT • THEY ARE USING IT IN THEIR TUNNELS LIKE IN PIR PANJAL TUNNEL , T-74R, T- 48 ETC
  • 176. NATM approach of design and execution of the tunneling in soft ground is advantageous and scientific way in comparision to the old way of tunneling. This system monitors rock mass deformation and design the support system with reference to the rock mass type . CONCLUSION
  • 177. Rock Slope Stability Analysis • A variety of engineering activities require excavation of rock cuts. • In civil engineering, projects include transportation systems such as highways and railways, dams for power production and water supply, and industrial and urban development.
  • 178. Fig 1: Rock slope in Hong Kong supported with tensioned rock anchors and reinforced concrete reaction blocks, and shotcrete.
  • 179. • Figure 1 is a rock cut, with a face angle of about 60◦, supported with tensioned anchors incorporating reinforced concrete bearing pads about 1m2 that distribute the anchor load on the face. • The face is also covered with shotcrete to prevent weathering and loosening between the bolts. • Water control measures include drain holes through the shotcrete and drainage channels on the benches and down the face to collect surface run-off. • The support is designed to both ensure long-term stability of the overall slope, and minimize rock falls that could be a hazard to traffic.
  • 180. Principles of Rock Slope Engineering • The design of rock cuts for civil projects such as highways and railways is usually concerned with details of the structural geology. • That is, the orientation and characteristics (such as length, roughness and infilling materials) of the joints, bedding and faults that occur behind the rock face. • For example, Figure 2 shows a cut slope in shale containing smooth bedding planes that are continuous over the full height of the cut and dip at an angle of about 50° towards the highway.
  • 181. Figure 2: Cut face coincident with continuous, low friction bedding planes in shale on Trans Canada Highway near Lake Louise, Alberta.
  • 182. • Since the friction angle of these discontinuities is about 20–25°, any attempt to excavate this cut at a steeper angle than the dip of the beds would result in blocks of rock sliding from the face on the beds; the steepest unsupported cut that can be made is equal to the dip of the beds. • However, as the alignment of the road changes so that the strike of the beds is at right angles to the cut face (right side of photograph), it is not possible for sliding to occur on the beds, and a steeper face can be excavated.
  • 183. • For many rock cuts on civil projects, the stresses in the rock are much less than the rock strength so there is little concern that fracturing of intact rock will occur. • Therefore, slope design is primarily concerned with the stability of blocks of rock formed by the discontinuities. • Intact rock strength, which is used indirectly in slope design, relates to the shear strength of discontinuities and rock masses, as well as excavation methods and costs.
  • 184. Shear Strength of Discontinuities • If geological mapping and/or diamond drilling identify discontinuities on which shear failure could take place, it will be necessary to determine the friction angle and cohesion of the sliding surface in order to carry out stability analyses. • The investigation program should also obtain information on characteristics of the sliding surface that may modify the shear strength parameters. • Important discontinuity characteristics include continuous length, surface roughness, and the thickness and characteristics of any infilling, as well as the effect of water on the properties of the infilling.
  • 185. Definition of Cohesion and Friction Angle • In rock slope design, rock is assumed to be a Coulomb material in which the shear strength of the sliding surface is expressed in terms of the cohesion (c) and the friction angle (φ) (Coulomb, 1773). • Assume a number of test samples were cut from a block of rock containing smooth, planar discontinuity. • Furthermore, the discontinuity contains a cemented infilling material such that a tensile force would have to be applied to the two halves of the sample in order to separate them.
  • 186. Fig 3 (a) Shear test of discontinuity
  • 187. • Each sample is subjected to a force at right angles to the discontinuity surface (normal stress, σ), and a force is applied in the direction parallel to the discontinuity (shear stress, τ) while the shear displacement (δs) is measured (Figure 3 (a)). • For a test carried out at a constant normal stress, a typical plot of the shear stress against the shear displacement is shown in Figure 3 (b).
  • 188. Fig 3 (b): plot of shear displacement vs shear stress
  • 189. • At small displacements, the specimen behaves elastically and the shear stress increases linearly with displacement. • As the force resisting movement is overcome, the curve become non-linear and then reaches a maximum that represents the peak shear strength of the discontinuity. • Thereafter, the stress required to cause displacement decreases and eventually reaches a constant value termed the residual shear strength. • If the peak shear strength values from tests carried out at different normal stress levels are plotted, a relationship shown in Figure 3 (c) is obtained; this is termed a Mohr diagram (Mohr, 1900).
  • 190. Fig 3(c): Mohr plot of peak strength
  • 191. • The features of this plot are; • first, it is approximately linear and the slope of the line is equal to the peak friction angle φp of the rock surface. • Second, the intercept of the line with the shear stress axis represents the cohesive strength c of the cementing material. • This cohesive component of the total shear strength is independent of the normal stress, but the frictional component increases with increasing normal stress. • Based on the relationship illustrated on Figure 3 (c), the peak shear strength is defined by the equation.
  • 192. • Friction Angle: The angle of internal friction is measure of the ability of a material (could be rock or soil or whatever) to withstand a shear stress. • Cohesion: The force of attraction that holds molecules of a given substance together. OR The sticking together of particles of the same substance. Mohr plot of peak and residual strength is shown in Fig 3 (d).
  • 193. Fig 3 (d): Mohr plot of peak and residual strength.
  • 194. . .