SlideShare uma empresa Scribd logo
1 de 13
LINE SIZING
Liquid Phase Case
Chemical Engineer
Juan Pablo Hernández Castillo
PROCESS ENGINEERS TASKS
 Process engineers play an important role in the design of plants.
Some of the most common activities process engineers do are relating to:
1. Design of pipelines
2. Design of equipments
3. Design of instruments, such as control and safety relieve valves.
4. P&ID’s construction
5. Design of control strategy of differents parts of the plant.
6. Checking As Built’s
7. Design of the philosophy of operation of a particular section of the plant.
Among others…
Today, i would like to share with all of you, the steps taken into account when
designing pipelines.
Currently, one the most known international standard to design pipelines is
provided by the American Petroleum Institute.
API 14E. Recommended Practice for Design and Installation of Offshore
Production Platform Piping Systems.
API 14E design for the following states:
1. Liquid phase
2. Single Phase Gas
3. Gas-Liquid Phase lines.
DESIGN OF PIPELINES
Considerations
 API 14E stablish that in order to have a accurate pipe design, two main
conditions must be met: Velocity and Pressure Drop
 Velocity: In order to avoid
Sedimentation of particles 𝟑
𝐟𝐭
𝐬
Erosion (due to high velocity) 15
𝐟𝐭
𝐬
 Pressure Drop: In order to meet pressure drop conditions.
API stablish 1
𝒑𝒔𝒊
𝟏𝟎𝟎 𝒇𝒕
<
Flow Diagram
Example
 A process engineer is asked to design a pump
which can transport water from one deposit to
another.
PARAMETER SYMBOL VALUE UNIT
TEMPERATURE T 77 °F
VISCOSITY µ 1,85E-05 lb/(ft.s)
DENSITY ρ 1,92 slugs/ft3
SPECIFIC GRAVITY s 1
VOLUMETRIC FLOW RATE 2 ft3/s
30776,9031 barrels/day
PIPE LENGHT L 60 ft
PIPE ROUGHNESS ε 1,50E-04 ft
PUMP EFICCIENCY %
POTENTIAL HEAD ∆z 50 ft
SPECIFIC WEIGHT γ 62,2 lb/ft3
Q
INITIAL DATA
Assumptions
 The area in which the system is located : Industry sector
 1 Month= 30 days
 The system works 24h/30 days/1 year
 Average kWh (according to CREG) =$599,722 COP
 Suction and discharge same pipe size
 Comercial Steel Schedule 40 and Schedule 80 design try
 Pipeline lenght of 60 ft
Results
For Schedule 40 Comercial Steel:
For Schedule 80 Comercial Steel:
V(ft/s) Elbows Valves Line
1 231,41 1154,72 6543,42 10836,53 18534,6789 18584,6789 19417 3134,56224 $ 4.901.665 $ 18.136.160.855
2 59,60 63,28 358,57 312,51 734,354596 784,354596 560 132,292212 $ 200.029 $ 740.108.907
3 27,05 12,35 69,99 40,35 122,686563 172,686563 72,29 29,1259687 $ 42.695 $ 157.971.260
4 15,71 3,93 22,29 9,97 36,1998787 86,1998787 17,87 14,5387975 $ 20.832 $ 77.077.751
5 10,00 1,50 8,50 3,15 13,1419988 63,1419988 5,64 10,6497683 $ 15.063 $ 55.733.044
6 6,92 0,67 3,82 1,24 5,7340002 55,7340002 2,22 9,40030725 $ 13.223 $ 48.925.559
8 4,00 0,21 1,19 0,31 1,7113024 51,7113024 0,56 8,72182383 $ 12.229 $ 45.247.677
10 2,54 0,08 0,48 0,10 0,6638566 50,6638566 0,18 8,54515766 $ 11.972 $ 44.295.237
Nominal Diameter(in)
hL(ft)
∑hL(ft) ha(ft) $COP$(USD)PA(kW)∆P(psi)
∆P(psi) PA(kW) $(USD) $COP
Elbows Valves Line
1 278,05 1666,98 9446,25 17548,38 28661,6114 28711,6114 31443,67 4842,60896 $ 7.610.740 $ 28.159.736.856
2 67,73 81,71 463,04 435,91 980,66872 1030,66872 781,08 173,836484 $ 264.039 $ 976.943.993
3 30,28 15,47 87,67 53,97 157,10938 207,10938 96,70 34,9318513 $ 51.469 $ 190.435.597
4 17,40 4,82 27,33 12,95 45,1058345 95,1058345 23,21 16,0409097 $ 23.076 $ 85.381.495
5 10,99 1,81 10,27 4,01 16,0918776 66,0918776 7,18 11,147306 $ 15.800 $ 58.461.385
6 7,67 0,83 4,69 1,61 7,12831215 57,1283121 2,88 9,63547718 $ 13.570 $ 50.208.479
8 4,38 0,25 1,43 0,39 2,07145528 52,0714553 0,70 8,78256857 $ 12.318 $ 45.576.435
10 2,78 0,10 0,58 0,13 0,8053278 50,8053278 0,23 8,56901872 $ 12.006 $ 44.423.454
ha(ft)V(ft/s)Nominal Diameter
hL(ft)
∑hL(ft)
Analysis
 From the previous results, it must be highlighted that the only schedule pipe which met the
velocity-pressure drop requierements was the Schedule 40.
Schedule 40
 Despite the velocity was aceptable from 5 to 8 in nominal diameter. It was noted that the only
diameter which met the requierement of pressure drop(∆P= below 0,6 psi) was the 8 in pipe.
 In the other hand, it was seen that the proper selection of the pipe size does affects the cost of
operation.
 If for example: A process engineer had chosen a 6 inch pipe without taking into account the
requirements, then the cost of operation would have exceed 994 USD per year of operation.
Schedule 40
 Although 5, 6 and 8 inch diameter did meet the velocity requirements, the pressure drop conditions
were not reached.
Bad decisions during the piping design and pump selection can lead to years of unnecessarily high
cost of operation.
Schedule 40- Conditions analysis
Schedule 40- Cost analysis
REFERENCES
[1] R. Mott, Mecánica de fluidos, Dayton: Pearson, 2006.
[2] A. 14E, Recommended Practice for Design and Installation of Offshore Production Platform
Piping Systems., Washington: American Pretroleum Institute, 1991.
[3] C. d. R. d. E. y. G. (CREG), «TARIFAS DE ENERGÍA ELÉCTRICA ($/kWh) REGULADAS POR LA
COMISIÓN DE REGULACIÓN DE ENERGÍAY GAS (CREG) JUNIO DE 2020,» ENEL CODENSA, 2020.
[4] B. d. l. R. d. Colombia, «Tasa Representativa de Mercado (TRM-Peso por dolar),» Banco de la
Republica de Colombia, Colombia, 2020.
¡THANKS FOR
WATCHING!
 Juan Pablo Hernández Castillo
Contact:
Email: juanpaheca@outlook.es
Cel: +57 304 395 5569
LinkedIn:
www.linkedin.com/in/juanhdezcastillo

Mais conteúdo relacionado

Mais procurados

Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureVarun Patel
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API BasedVijay Sarathy
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure Varun Patel
 
psv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptpsv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptssuser73bb74
 
Psv scenario-and-calculation
Psv scenario-and-calculationPsv scenario-and-calculation
Psv scenario-and-calculationChingLuh Nike
 
Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)
Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)
Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)Vikram Sharma
 
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsHeat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsProcess Ecology Inc
 
HTRI PRESENTATION.pdf
HTRI PRESENTATION.pdfHTRI PRESENTATION.pdf
HTRI PRESENTATION.pdfssuserbd5784
 
Design of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfDesign of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfAl AYAn University
 
ASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and SupportsASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and SupportsJim LeStage
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookAli Meshaikhis
 
Pressure relief system_design
Pressure relief system_designPressure relief system_design
Pressure relief system_designRahul Tewari
 
Steam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingSteam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingGerard B. Hawkins
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valvesAmol Dudhate
 
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)Chemical Engineering Guy
 
Shell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparisonShell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparisonJuan Pablo Hernandez
 
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1BHARAT BELLAD
 

Mais procurados (20)

Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API Based
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
Valve sizing
Valve sizingValve sizing
Valve sizing
 
psv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptpsv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.ppt
 
Psv scenario-and-calculation
Psv scenario-and-calculationPsv scenario-and-calculation
Psv scenario-and-calculation
 
Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)
Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)
Two-phase fluid flow: Guideline to Pipe Sizing for Two-Phase (Liquid-Gas)
 
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS DynamicsHeat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
Heat Exchanger Tube Rupture Scenario Evaluation using Aspen HYSYS Dynamics
 
HTRI PRESENTATION.pdf
HTRI PRESENTATION.pdfHTRI PRESENTATION.pdf
HTRI PRESENTATION.pdf
 
Design of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfDesign of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdf
 
ASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and SupportsASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and Supports
 
Flarenet
FlarenetFlarenet
Flarenet
 
Eng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbookEng handbook crosby pressure relief valve engineering handbook
Eng handbook crosby pressure relief valve engineering handbook
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
 
Pressure relief system_design
Pressure relief system_designPressure relief system_design
Pressure relief system_design
 
Steam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingSteam Reforming - Catalyst Loading
Steam Reforming - Catalyst Loading
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valves
 
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
 
Shell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparisonShell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparison
 
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1
 

Semelhante a Line sizing

Cge666 chapter 1-wk 1-2
Cge666 chapter 1-wk 1-2Cge666 chapter 1-wk 1-2
Cge666 chapter 1-wk 1-2Fiena Azmi
 
line sizing-mustang.pdf
line sizing-mustang.pdfline sizing-mustang.pdf
line sizing-mustang.pdfZeeshanAlam90
 
1st lect Fertilizers(1).pptx
1st lect Fertilizers(1).pptx1st lect Fertilizers(1).pptx
1st lect Fertilizers(1).pptxAbubakar171727
 
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting Karl Kolmetz
 
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...ahmedeng10
 
Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Nikhilesh Mane
 
Itt grinnell pipe hanger design & engineering 2008
Itt grinnell pipe hanger design & engineering 2008 Itt grinnell pipe hanger design & engineering 2008
Itt grinnell pipe hanger design & engineering 2008 ITTGRINNELL
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic processsimachem
 
Chemical_Process_Equipment_2.pptx
Chemical_Process_Equipment_2.pptxChemical_Process_Equipment_2.pptx
Chemical_Process_Equipment_2.pptxKaifyEngineer
 
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco FabASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco FabPiping Technology & Products, Inc.
 
Engineering design guideline hx rev 3
Engineering design guideline  hx rev 3Engineering design guideline  hx rev 3
Engineering design guideline hx rev 3huynhthanhtamga
 
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw PumpStudy of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw PumpIJMERJOURNAL
 
Refrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfRefrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfssuser642327
 
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersMechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersGerard B. Hawkins
 

Semelhante a Line sizing (20)

Cge666 chapter 1-wk 1-2
Cge666 chapter 1-wk 1-2Cge666 chapter 1-wk 1-2
Cge666 chapter 1-wk 1-2
 
Project Management
Project ManagementProject Management
Project Management
 
line sizing-mustang.pdf
line sizing-mustang.pdfline sizing-mustang.pdf
line sizing-mustang.pdf
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
1st lect Fertilizers(1).pptx
1st lect Fertilizers(1).pptx1st lect Fertilizers(1).pptx
1st lect Fertilizers(1).pptx
 
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
Piping Hydraulics Fluid Flow Selection, Sizing and Troubleshooting
 
Plumbing Design
Plumbing DesignPlumbing Design
Plumbing Design
 
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
07-ENGINEERING_DESIGN_GUIDELINES_instrumentation_sizing_and_selection_rev_web...
 
Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)
 
Itt grinnell pipe hanger design & engineering 2008
Itt grinnell pipe hanger design & engineering 2008 Itt grinnell pipe hanger design & engineering 2008
Itt grinnell pipe hanger design & engineering 2008
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
 
Chemical_Process_Equipment_2.pptx
Chemical_Process_Equipment_2.pptxChemical_Process_Equipment_2.pptx
Chemical_Process_Equipment_2.pptx
 
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco FabASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
 
Richard-Hock
Richard-HockRichard-Hock
Richard-Hock
 
Engineering design guideline hx rev 3
Engineering design guideline  hx rev 3Engineering design guideline  hx rev 3
Engineering design guideline hx rev 3
 
Pipe Support Engineering & Design - June
Pipe Support Engineering & Design - JunePipe Support Engineering & Design - June
Pipe Support Engineering & Design - June
 
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw PumpStudy of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
 
Refrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdfRefrigerant Piping Handbook.pdf
Refrigerant Piping Handbook.pdf
 
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersMechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
 
INTERNSHIP PPT
INTERNSHIP PPTINTERNSHIP PPT
INTERNSHIP PPT
 

Último

PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 

Último (20)

PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 

Line sizing

  • 1. LINE SIZING Liquid Phase Case Chemical Engineer Juan Pablo Hernández Castillo
  • 2. PROCESS ENGINEERS TASKS  Process engineers play an important role in the design of plants. Some of the most common activities process engineers do are relating to: 1. Design of pipelines 2. Design of equipments 3. Design of instruments, such as control and safety relieve valves. 4. P&ID’s construction 5. Design of control strategy of differents parts of the plant. 6. Checking As Built’s 7. Design of the philosophy of operation of a particular section of the plant. Among others…
  • 3. Today, i would like to share with all of you, the steps taken into account when designing pipelines. Currently, one the most known international standard to design pipelines is provided by the American Petroleum Institute. API 14E. Recommended Practice for Design and Installation of Offshore Production Platform Piping Systems. API 14E design for the following states: 1. Liquid phase 2. Single Phase Gas 3. Gas-Liquid Phase lines. DESIGN OF PIPELINES
  • 4. Considerations  API 14E stablish that in order to have a accurate pipe design, two main conditions must be met: Velocity and Pressure Drop  Velocity: In order to avoid Sedimentation of particles 𝟑 𝐟𝐭 𝐬 Erosion (due to high velocity) 15 𝐟𝐭 𝐬  Pressure Drop: In order to meet pressure drop conditions. API stablish 1 𝒑𝒔𝒊 𝟏𝟎𝟎 𝒇𝒕 <
  • 6. Example  A process engineer is asked to design a pump which can transport water from one deposit to another. PARAMETER SYMBOL VALUE UNIT TEMPERATURE T 77 °F VISCOSITY µ 1,85E-05 lb/(ft.s) DENSITY ρ 1,92 slugs/ft3 SPECIFIC GRAVITY s 1 VOLUMETRIC FLOW RATE 2 ft3/s 30776,9031 barrels/day PIPE LENGHT L 60 ft PIPE ROUGHNESS ε 1,50E-04 ft PUMP EFICCIENCY % POTENTIAL HEAD ∆z 50 ft SPECIFIC WEIGHT γ 62,2 lb/ft3 Q INITIAL DATA
  • 7. Assumptions  The area in which the system is located : Industry sector  1 Month= 30 days  The system works 24h/30 days/1 year  Average kWh (according to CREG) =$599,722 COP  Suction and discharge same pipe size  Comercial Steel Schedule 40 and Schedule 80 design try  Pipeline lenght of 60 ft
  • 8. Results For Schedule 40 Comercial Steel: For Schedule 80 Comercial Steel: V(ft/s) Elbows Valves Line 1 231,41 1154,72 6543,42 10836,53 18534,6789 18584,6789 19417 3134,56224 $ 4.901.665 $ 18.136.160.855 2 59,60 63,28 358,57 312,51 734,354596 784,354596 560 132,292212 $ 200.029 $ 740.108.907 3 27,05 12,35 69,99 40,35 122,686563 172,686563 72,29 29,1259687 $ 42.695 $ 157.971.260 4 15,71 3,93 22,29 9,97 36,1998787 86,1998787 17,87 14,5387975 $ 20.832 $ 77.077.751 5 10,00 1,50 8,50 3,15 13,1419988 63,1419988 5,64 10,6497683 $ 15.063 $ 55.733.044 6 6,92 0,67 3,82 1,24 5,7340002 55,7340002 2,22 9,40030725 $ 13.223 $ 48.925.559 8 4,00 0,21 1,19 0,31 1,7113024 51,7113024 0,56 8,72182383 $ 12.229 $ 45.247.677 10 2,54 0,08 0,48 0,10 0,6638566 50,6638566 0,18 8,54515766 $ 11.972 $ 44.295.237 Nominal Diameter(in) hL(ft) ∑hL(ft) ha(ft) $COP$(USD)PA(kW)∆P(psi) ∆P(psi) PA(kW) $(USD) $COP Elbows Valves Line 1 278,05 1666,98 9446,25 17548,38 28661,6114 28711,6114 31443,67 4842,60896 $ 7.610.740 $ 28.159.736.856 2 67,73 81,71 463,04 435,91 980,66872 1030,66872 781,08 173,836484 $ 264.039 $ 976.943.993 3 30,28 15,47 87,67 53,97 157,10938 207,10938 96,70 34,9318513 $ 51.469 $ 190.435.597 4 17,40 4,82 27,33 12,95 45,1058345 95,1058345 23,21 16,0409097 $ 23.076 $ 85.381.495 5 10,99 1,81 10,27 4,01 16,0918776 66,0918776 7,18 11,147306 $ 15.800 $ 58.461.385 6 7,67 0,83 4,69 1,61 7,12831215 57,1283121 2,88 9,63547718 $ 13.570 $ 50.208.479 8 4,38 0,25 1,43 0,39 2,07145528 52,0714553 0,70 8,78256857 $ 12.318 $ 45.576.435 10 2,78 0,10 0,58 0,13 0,8053278 50,8053278 0,23 8,56901872 $ 12.006 $ 44.423.454 ha(ft)V(ft/s)Nominal Diameter hL(ft) ∑hL(ft)
  • 9. Analysis  From the previous results, it must be highlighted that the only schedule pipe which met the velocity-pressure drop requierements was the Schedule 40. Schedule 40  Despite the velocity was aceptable from 5 to 8 in nominal diameter. It was noted that the only diameter which met the requierement of pressure drop(∆P= below 0,6 psi) was the 8 in pipe.  In the other hand, it was seen that the proper selection of the pipe size does affects the cost of operation.  If for example: A process engineer had chosen a 6 inch pipe without taking into account the requirements, then the cost of operation would have exceed 994 USD per year of operation. Schedule 40  Although 5, 6 and 8 inch diameter did meet the velocity requirements, the pressure drop conditions were not reached. Bad decisions during the piping design and pump selection can lead to years of unnecessarily high cost of operation.
  • 11. Schedule 40- Cost analysis
  • 12. REFERENCES [1] R. Mott, Mecánica de fluidos, Dayton: Pearson, 2006. [2] A. 14E, Recommended Practice for Design and Installation of Offshore Production Platform Piping Systems., Washington: American Pretroleum Institute, 1991. [3] C. d. R. d. E. y. G. (CREG), «TARIFAS DE ENERGÍA ELÉCTRICA ($/kWh) REGULADAS POR LA COMISIÓN DE REGULACIÓN DE ENERGÍAY GAS (CREG) JUNIO DE 2020,» ENEL CODENSA, 2020. [4] B. d. l. R. d. Colombia, «Tasa Representativa de Mercado (TRM-Peso por dolar),» Banco de la Republica de Colombia, Colombia, 2020.
  • 13. ¡THANKS FOR WATCHING!  Juan Pablo Hernández Castillo Contact: Email: juanpaheca@outlook.es Cel: +57 304 395 5569 LinkedIn: www.linkedin.com/in/juanhdezcastillo