P I P E L I N E S & F L O W L I N E S
Coiled tubing offers pre-commissioning
tool for deepwater pipelines
System can be applied for contingency dewatering
A
s submarine gas pipelines are installed in ever-deeper waters,
the challenge of pre-commissioning becomes more complex.
For all deepwater pipelines, technology exists today to per-
form parts of the pre-commissioning entirely subsea using
autonomous or remotely operated vehicle (ROV) powered
equipment to flood, gauge, and test the pipeline.
However, there remain many situations where it is necessary to
connect from the surface to the deepwater pipeline, thus forming a
reliable conduit to the pipeline that facilitates the injection of water,
air, nitrogen, and mono-ethylene glycol (MEG); or even to be used
for subsea depressurization.
The goal here is to demonstrate what can be achieved on major
subsea pipeline pre-commissioning projects through the selection of
the best equipment and techniques.
Employing a “down-line”
A down-line is best described as a conduit between a marine ves-
sel at the surface and a subsea pipeline connection. For our pur-
poses here, we will consider only the use of down-lines for pipeline
pre-commissioning.
The pre-commissioning process flow chart illustrates the pre-
commissioning process as typically applied to oil pipelines. The
process for gas lines is similar, but involves additional steps prior to
handover such as removal of hydrotest water (dewatering), drying,
MEG swabbing, and nitrogen packing.
Where the pipeline has one or both terminations subsea, then a
down-line may be required to perform the pre-commissioning service.
The following key attributes are desired from a down-line system:
• Be able to convey the pre-commissioning fluids (water, air,
glycol, nitrogen) from the surface to the subsea injection point
at the highest possible rate to achieve the pigging parameters
agreed for the project
• Be space efficient both for transporting to/from the mobilization
point and for installation on the pre-commissioning support vessel
• Be cost effective
• Be robust and reliable
• Include contingency for critical items
• Be self-supporting during deployment and recovery
• Have fast deployment and recovery rates
• In many applications, be able to withstand the external hydro-
static pressure at the deepest point.
Deepwater deployment
Traditional oilfield coiled tubing units have been used to make a
connection between the surface spreads and subsea pipelines for
many years. Typically, such units used coiled tubing of 2-in. outer
diameter (OD) and below, with the oilfield design generally neces-
sitating deployment via a moonpool equipped marine vessel.
In 2012, Baker Hughes designed and built coiled tubing systems
specifically designed for deepwater down-line applications.
The design brief for the customized system was as follows:
• Capable of operating in water depths up to 3,000 m (9,842 ft)
• Designed for large diameter pipe of 27
⁄8 in. or 3½ in.
• DNV-certified to allow offshore lifting
• Road transportable in two loads
• Standard basic components giving easy access to spare parts
and trained mechanics/operators
• Flexible frame to allow use on a wide variety of vessels, either
through a moonpool or over the side.
Historically, the main use of the coiled tubing down-line has been
as a conduit for supplying air or nitrogen to dewater the subsea pipe-
lines. This also typically requires that MEG or another pipeline hy-
drate-inhibiting fluid be pumped as part of a conditioning pig train.
To date, coiled tubing has been used in water depths of around 2,200
m (7,217 ft), but with exploration already taking place in water depths
down to 3,000 m (9,842 ft), this was selected as the target water depth.
John Grover • Andy Barden
Baker Hughes
Pre-commissioning flow chart for typical oil pipelines.
(All images courtesy Baker Hughes.)
P I P E L I N E S  F L O W L I N E S
Coiled tubing system design
Initial evaluation of a number of deepwater pipeline projects in-
dicated that compressed air injection rates in excess of 10,000 cf/
min (283 cm/day) would be required, injected on to a down-line up
to 3,000 m long.
Engineering for such scenarios showed that the 2-in. coiled tub-
ing used to date is not large enough for these flow rates, with the
high-pressure drop equating to surface pressures greater than
could be achieved. Thus engineering focused on the two largest pipe
sizes available:
•  27
⁄8-in. pipe is readily available and there is considerable experi-
ence with this pipe in downhole applications.
• 3½-in. pipe is not widely used in downhole applications, as high
flow rates are not typically required, but it is manufactured, and
readily available. These larger pipe sizes have much lower pres-
sure drop, and are better suited for these applications.
In looking at reel dimensions, it was decided to opt for a reel that
would handle 3,000 m of 27
⁄8-in. and around 2,300 m (7,545 ft) of
3½-in. pipe. This gives reel dimensions of 96 in. (2.43 m) between
flanges, with a core diameter of 120 in. (3.05 m) and flange diameter
of 180 in. (4.57 m), and reel skid dimensions of 223 in. (5.66 m) long,
144 in. (3.65 m) wide and 182 in. (4.66 m) high. The weight of the
skid with pipe is 90,000 lb (41,000 kg).
The rest of the equipment was mounted on a single skid for ease
of transportation and lifting. This skid also provides the basis of the
overboard deployment system. A trolley system was used, which al-
lowed the pipe and ancillary equipment to be rigged up in-board of
the vessel and then jacked out over the side of the vessel.
The primary driver for this was an “over-the-side” deployment
scenario, but this would work just as well for a moonpool deploy-
ment. The skid accommodates the control cabin, the power pack,
the gooseneck and all ancillary equipment in its transport mode.
Prior to use, the control cabin was lifted off the skid and replaced
by the tubing reel, which partially balanced the weight of the tubing
when deployed over the side. The cabin can be located in a number
of places around the skid within a 30-ft (9-m) radius of the power
pack, giving flexibility depending on vessel layout. The main trans-
port skid was 40-ft (12.2-m) long by 12-ft (3.65-m) wide, weighing ap-
proximately 80,000 lb; so although it is a permit load, it can be trans-
ported by conventional truck. The use of a spreader beam gives a
single point DNV-certified lift for offshore lifting.
The power pack, injector, gooseneck, and control cabin were all
effectively standard components. The reel was also standard in the
way it functions, but the dimensions are unique to meet the criteria
outlined above.
Deployment challenges
The main issue associated with deploying the coiled
tubing as a down-line in deepwater environment is the
impact of current on the coiled tubing string and the
vessel movement. This impact results from wave ac-
tion, which can cause fatigue in the pipe string. In
downhole applications, high-cycle fatigue is not an is-
sue, since the tubing is constrained by the well, but in
open water this is not the case.
Historically, several projects have been carried out in
the relatively benign environment of the Gulf of Mex-
ico. The calm sea state and relatively weak currents
have not caused any major issues with the coiled tub-
ing, even in deployments lasting several weeks. Howev-
er, in more aggressive sea states, this has the potential
to impact the coiled tubing and limit its working life.
The first project in which these more extreme con-
ditions were encountered required the project team
to look at this in more detail. In order to assess this
potential impact, extensive modeling was carried out to determine
the effect of different conditions on the coiled tubing string and the
entire jumper system across to the pipeline end termination.
Modeling was undertaken using OrcaFlex to look at deployment
analysis, in-place analysis, and high-cycle fatigue. This software re-
quires the following inputs in order to model the behavior of the
coiled tubing:
• Detailed physical parameters of the coiled tubing and all the
equipment attached to the end of the string in the various de-
ployed conditions
• Metocean data
• Vessel data and details of the hang-off point for the coiled tubing
• Response amplitude operator data for the vessel.
Specific issues to be addressed as part of the analysis:
• Assess the allowable yield stress utilization in the coil tubing
across the range of conditions that could be encountered dur-
ing operations
• Assess the need for a bend stiffener for the coiled tubing based
on the above
• Examine vortex-induced vibration and whether lock-in would
occur
• Evaluate the movement of the hose bundle during the operation
and assess the need for buoyancy and a bend restrictor to pre-
vent the minimum bending radius from being exceeded
• Evaluate potential clashing of the coiled tubing and/or hose
bundle with the vessel’s hull during deployment
• Look at the likely tension and bending moments in the hose
bundle and the breakaway coupling during the operation.
The initial static analysis of the system revealed that a bend stiff-
ener was required. Without one, the current acting on the coiled
tubing would cause an overbend in the string at the vessel interface.
Various types of bend stiffeners were evaluated, and a steel tube
of reducing wall thickness was agreed upon, which would limit the
radius of curvature of the coil and allow progressively more bending
of the coil over its length. With this in place, the bend of the coiled
tubing is limited to a level below the allowable limits of stress utiliza-
tion based on curvature and tension.
In many instances with the vessel in a fixed position, it is possible
for the hose and bottom hole assembly (BHA) to be tensioned beyond
their design limit. In order to prevent this, it is necessary to move the
vessel such that the BHA remains within a given target area, so that
the hose and breakaway connector are not overly stressed. Buoyancy
and weights are attached to the hose bundle so that it remains in a
lazy S shape during the operation, without undue tension or bending
moments being applied to any of the components.
Schematic of dewatering
using coiled tubing system.
P I P E L I N E S  F L O W L I N E S
Eprinted and posted with permission to Baker Hughes Inc. from Offshore
June © 2015 PennWell Corporation
Vortex-induced vibration was found to be present in the initial analy-
sis without the bend stiffener, but the use of the bend stiffener reduced
this to the point where it was no longer an issue. Contact between the
tubing and the side of the vessel is possible in high current scenarios;
therefore, the vessel may have to be oriented accordingly to avoid this.
With the bend stiffener designed as described, the coil was ana-
lyzed for fatigue. As indicated earlier, high-cycle fatigue is a major con-
cern in this application, given the constant movement of the vessel.
In this particular instance, the coil was anticipated to be deployed for
about 32 days continuously. For a single deployment, fatigue was not
determined to be an issue in this case. However, it should be noted
that in the case of multiple deployments, the coil is also subjected to
low cycle fatigue each time it goes over the gooseneck. The combi-
nation of these two fatigue regimes requires further investigation to
determine a probable ultimate fatigue life of the coil.
Wet buckle contingency
Many subsea pipelines employ some type of wet buckle contin-
gency (WBC) dewatering system, however for large-bore, deep-
water pipelines, the compressed air spread required to dewater
the line is huge and the dewatering time very slow. For example,
a major Black Sea pipeline project would have required a standby
dewatering spread to be located in the vicinity of the subsea initia-
tion head. To mitigate this contingency requirement, Baker Hughes
developed a solution to partially dewater, isolate, and depressurize a
short deepwater section using a large-bore coiled tubing down-line.
This technique is summarized as follows:
1. An unplanned flooding event occurs. WBC flooding spread is
commissioned.
2. A wet buckle contingency flooding pig receiver/catching head
is installed. The head is fitted with a large bore discharge port
for air/water outlet during the WBC flooding operation.
3. The line is then flooded with filtered, treated seawater from the
WBC flooding spread and the free-flood, untreated seawater is
displaced with treated seawater within 20 days. Water treated
for a pre-agreed wet park period.
4. The WBC flooding pig receiver is then recovered to the sur-
face and a pipeline recovery tool is installed with a pre-loaded
smart plug
5. Concurrently, a coiled tubing (CT) dewatering system is in-
stalled on a dynamically positioned vessel
6. Once function tested, the CT dewatering system is deployed to
the recovery head
7. The smart plug is propelled about 3 km to 5 km (1.86 mi to 3.10
mi) into the line and treated water is discharged at the WBC
pumping location. This can be conducted at a lower velocity
than conventional dewatering.
8. The smart plug is set and the air pressure is bled down at the
surface.
9. Lay barge recovers line to surface and pipelay can recommence.
10. The smart plug is left in place until dewatering operations
commence after completion of pipelay.
With this technique, a project crew can then use the dewatering
air pressure to equalize across the smart plug and then push it to the
receiver as part of the dewatering train.
Conclusions
With this article, the authors have endeavored to demonstrate the
following:
1. Down-lines play an important role in the pre-commissioning of
deepwater pipelines
2. Coiled tubing should be considered as the preferred down-line
system except where very large bore down-lines are required.
Even then, multiple coiled tubing down-lines can be considered
as an alternative.
3. Custom marine coiled tubing systems provide the flexibility
for moonpool or over-the-side deployment and are largely self-
supporting once installed.
4. Engineering and modeling is required prior to deploying coiled
tubing in a blue-water environment.
5. A partial dewatering system offers a faster, lower cost alternative
to a full wet buckle contingency dewatering system, especially
for pipelines not intended for hydrostatic pressure testing. •
Acknowledgment 		
Based on a paper presented at the OPT conference in Amsterdam, The Netherlands,
Feb. 25-26, 2015.
Left:Two-inch coiled tubing being deployed via moonpool. Right: Coiled tubing unit in transit mode, showing main deployment skid and reel.
Complete spread in deployed configuration.

Mais conteúdo relacionado

Mais procurados

Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas Fields
Neil Barnard
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devices
Gurdeep singh Johar
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Ashwin Gadgil
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project
Saddam Mussie
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
John Grover
 

Mais procurados (19)

Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem
 
Offshore Riser Design
Offshore Riser DesignOffshore Riser Design
Offshore Riser Design
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas Fields
 
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
Design and Evaluation of Submersible 11/0.415kV Distribution Substation for F...
 
Culvertdesign
CulvertdesignCulvertdesign
Culvertdesign
 
Shale gas presentation
Shale gas presentationShale gas presentation
Shale gas presentation
 
Ch 27 culverts
Ch 27   culvertsCh 27   culverts
Ch 27 culverts
 
Mining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering ProcessesMining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering Processes
 
OGJ Nordstream
OGJ NordstreamOGJ Nordstream
OGJ Nordstream
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devices
 
Schmidt
SchmidtSchmidt
Schmidt
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
 
2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project2.2 gl for-hydaulic_design_of_shp_project
2.2 gl for-hydaulic_design_of_shp_project
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
 
over veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesover veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelines
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 
Application of intelligent well completion in optimizing production
Application of intelligent well completion in optimizing productionApplication of intelligent well completion in optimizing production
Application of intelligent well completion in optimizing production
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 

Destaque

OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact final
John Grover
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline Conference
John Grover
 
Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07
John Grover
 

Destaque (20)

PII_IQPC_May_04
PII_IQPC_May_04PII_IQPC_May_04
PII_IQPC_May_04
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan final
 
Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010
 
Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact final
 
Smp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_finalSmp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_final
 
Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010
 
Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010
 
Tasnia
TasniaTasnia
Tasnia
 
Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010
 
Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010
 
Smp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_finalSmp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_final
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline Conference
 
Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010
 
Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07
 
Smp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_finalSmp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_final
 
Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010
 
Appendix d theme review final_dec2010a
Appendix d theme review final_dec2010aAppendix d theme review final_dec2010a
Appendix d theme review final_dec2010a
 
Smp2 part a main report final
Smp2 part a main report finalSmp2 part a main report final
Smp2 part a main report final
 
Appendix j wfd assessment final_dec2010
Appendix j wfd assessment final_dec2010Appendix j wfd assessment final_dec2010
Appendix j wfd assessment final_dec2010
 

Semelhante a Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipelines - June 2015

26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
John Grover
 
SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)
Gregg Linville
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
Leo Youngman
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
Rakesh Sunari Magar
 
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
Emeka Ngwobia
 

Semelhante a Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipelines - June 2015 (20)

Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
 
CH6 Water Passages.pptx
CH6 Water Passages.pptxCH6 Water Passages.pptx
CH6 Water Passages.pptx
 
Mudline Suspension (MLS)
Mudline Suspension (MLS)Mudline Suspension (MLS)
Mudline Suspension (MLS)
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 
Curso_Hidro_1.pdf
Curso_Hidro_1.pdfCurso_Hidro_1.pdf
Curso_Hidro_1.pdf
 
Drilling imp
Drilling impDrilling imp
Drilling imp
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
Boat outfit
Boat outfitBoat outfit
Boat outfit
 
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
 
Breakwater construction
Breakwater constructionBreakwater construction
Breakwater construction
 
Piping layout/ Subsea
Piping layout/ SubseaPiping layout/ Subsea
Piping layout/ Subsea
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 
Alan sutton
Alan suttonAlan sutton
Alan sutton
 
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
 

Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipelines - June 2015

  • 1. P I P E L I N E S & F L O W L I N E S Coiled tubing offers pre-commissioning tool for deepwater pipelines System can be applied for contingency dewatering A s submarine gas pipelines are installed in ever-deeper waters, the challenge of pre-commissioning becomes more complex. For all deepwater pipelines, technology exists today to per- form parts of the pre-commissioning entirely subsea using autonomous or remotely operated vehicle (ROV) powered equipment to flood, gauge, and test the pipeline. However, there remain many situations where it is necessary to connect from the surface to the deepwater pipeline, thus forming a reliable conduit to the pipeline that facilitates the injection of water, air, nitrogen, and mono-ethylene glycol (MEG); or even to be used for subsea depressurization. The goal here is to demonstrate what can be achieved on major subsea pipeline pre-commissioning projects through the selection of the best equipment and techniques. Employing a “down-line” A down-line is best described as a conduit between a marine ves- sel at the surface and a subsea pipeline connection. For our pur- poses here, we will consider only the use of down-lines for pipeline pre-commissioning. The pre-commissioning process flow chart illustrates the pre- commissioning process as typically applied to oil pipelines. The process for gas lines is similar, but involves additional steps prior to handover such as removal of hydrotest water (dewatering), drying, MEG swabbing, and nitrogen packing. Where the pipeline has one or both terminations subsea, then a down-line may be required to perform the pre-commissioning service. The following key attributes are desired from a down-line system: • Be able to convey the pre-commissioning fluids (water, air, glycol, nitrogen) from the surface to the subsea injection point at the highest possible rate to achieve the pigging parameters agreed for the project • Be space efficient both for transporting to/from the mobilization point and for installation on the pre-commissioning support vessel • Be cost effective • Be robust and reliable • Include contingency for critical items • Be self-supporting during deployment and recovery • Have fast deployment and recovery rates • In many applications, be able to withstand the external hydro- static pressure at the deepest point. Deepwater deployment Traditional oilfield coiled tubing units have been used to make a connection between the surface spreads and subsea pipelines for many years. Typically, such units used coiled tubing of 2-in. outer diameter (OD) and below, with the oilfield design generally neces- sitating deployment via a moonpool equipped marine vessel. In 2012, Baker Hughes designed and built coiled tubing systems specifically designed for deepwater down-line applications. The design brief for the customized system was as follows: • Capable of operating in water depths up to 3,000 m (9,842 ft) • Designed for large diameter pipe of 27 ⁄8 in. or 3½ in. • DNV-certified to allow offshore lifting • Road transportable in two loads • Standard basic components giving easy access to spare parts and trained mechanics/operators • Flexible frame to allow use on a wide variety of vessels, either through a moonpool or over the side. Historically, the main use of the coiled tubing down-line has been as a conduit for supplying air or nitrogen to dewater the subsea pipe- lines. This also typically requires that MEG or another pipeline hy- drate-inhibiting fluid be pumped as part of a conditioning pig train. To date, coiled tubing has been used in water depths of around 2,200 m (7,217 ft), but with exploration already taking place in water depths down to 3,000 m (9,842 ft), this was selected as the target water depth. John Grover • Andy Barden Baker Hughes Pre-commissioning flow chart for typical oil pipelines. (All images courtesy Baker Hughes.)
  • 2. P I P E L I N E S F L O W L I N E S Coiled tubing system design Initial evaluation of a number of deepwater pipeline projects in- dicated that compressed air injection rates in excess of 10,000 cf/ min (283 cm/day) would be required, injected on to a down-line up to 3,000 m long. Engineering for such scenarios showed that the 2-in. coiled tub- ing used to date is not large enough for these flow rates, with the high-pressure drop equating to surface pressures greater than could be achieved. Thus engineering focused on the two largest pipe sizes available: • 27 ⁄8-in. pipe is readily available and there is considerable experi- ence with this pipe in downhole applications. • 3½-in. pipe is not widely used in downhole applications, as high flow rates are not typically required, but it is manufactured, and readily available. These larger pipe sizes have much lower pres- sure drop, and are better suited for these applications. In looking at reel dimensions, it was decided to opt for a reel that would handle 3,000 m of 27 ⁄8-in. and around 2,300 m (7,545 ft) of 3½-in. pipe. This gives reel dimensions of 96 in. (2.43 m) between flanges, with a core diameter of 120 in. (3.05 m) and flange diameter of 180 in. (4.57 m), and reel skid dimensions of 223 in. (5.66 m) long, 144 in. (3.65 m) wide and 182 in. (4.66 m) high. The weight of the skid with pipe is 90,000 lb (41,000 kg). The rest of the equipment was mounted on a single skid for ease of transportation and lifting. This skid also provides the basis of the overboard deployment system. A trolley system was used, which al- lowed the pipe and ancillary equipment to be rigged up in-board of the vessel and then jacked out over the side of the vessel. The primary driver for this was an “over-the-side” deployment scenario, but this would work just as well for a moonpool deploy- ment. The skid accommodates the control cabin, the power pack, the gooseneck and all ancillary equipment in its transport mode. Prior to use, the control cabin was lifted off the skid and replaced by the tubing reel, which partially balanced the weight of the tubing when deployed over the side. The cabin can be located in a number of places around the skid within a 30-ft (9-m) radius of the power pack, giving flexibility depending on vessel layout. The main trans- port skid was 40-ft (12.2-m) long by 12-ft (3.65-m) wide, weighing ap- proximately 80,000 lb; so although it is a permit load, it can be trans- ported by conventional truck. The use of a spreader beam gives a single point DNV-certified lift for offshore lifting. The power pack, injector, gooseneck, and control cabin were all effectively standard components. The reel was also standard in the way it functions, but the dimensions are unique to meet the criteria outlined above. Deployment challenges The main issue associated with deploying the coiled tubing as a down-line in deepwater environment is the impact of current on the coiled tubing string and the vessel movement. This impact results from wave ac- tion, which can cause fatigue in the pipe string. In downhole applications, high-cycle fatigue is not an is- sue, since the tubing is constrained by the well, but in open water this is not the case. Historically, several projects have been carried out in the relatively benign environment of the Gulf of Mex- ico. The calm sea state and relatively weak currents have not caused any major issues with the coiled tub- ing, even in deployments lasting several weeks. Howev- er, in more aggressive sea states, this has the potential to impact the coiled tubing and limit its working life. The first project in which these more extreme con- ditions were encountered required the project team to look at this in more detail. In order to assess this potential impact, extensive modeling was carried out to determine the effect of different conditions on the coiled tubing string and the entire jumper system across to the pipeline end termination. Modeling was undertaken using OrcaFlex to look at deployment analysis, in-place analysis, and high-cycle fatigue. This software re- quires the following inputs in order to model the behavior of the coiled tubing: • Detailed physical parameters of the coiled tubing and all the equipment attached to the end of the string in the various de- ployed conditions • Metocean data • Vessel data and details of the hang-off point for the coiled tubing • Response amplitude operator data for the vessel. Specific issues to be addressed as part of the analysis: • Assess the allowable yield stress utilization in the coil tubing across the range of conditions that could be encountered dur- ing operations • Assess the need for a bend stiffener for the coiled tubing based on the above • Examine vortex-induced vibration and whether lock-in would occur • Evaluate the movement of the hose bundle during the operation and assess the need for buoyancy and a bend restrictor to pre- vent the minimum bending radius from being exceeded • Evaluate potential clashing of the coiled tubing and/or hose bundle with the vessel’s hull during deployment • Look at the likely tension and bending moments in the hose bundle and the breakaway coupling during the operation. The initial static analysis of the system revealed that a bend stiff- ener was required. Without one, the current acting on the coiled tubing would cause an overbend in the string at the vessel interface. Various types of bend stiffeners were evaluated, and a steel tube of reducing wall thickness was agreed upon, which would limit the radius of curvature of the coil and allow progressively more bending of the coil over its length. With this in place, the bend of the coiled tubing is limited to a level below the allowable limits of stress utiliza- tion based on curvature and tension. In many instances with the vessel in a fixed position, it is possible for the hose and bottom hole assembly (BHA) to be tensioned beyond their design limit. In order to prevent this, it is necessary to move the vessel such that the BHA remains within a given target area, so that the hose and breakaway connector are not overly stressed. Buoyancy and weights are attached to the hose bundle so that it remains in a lazy S shape during the operation, without undue tension or bending moments being applied to any of the components. Schematic of dewatering using coiled tubing system.
  • 3. P I P E L I N E S F L O W L I N E S Eprinted and posted with permission to Baker Hughes Inc. from Offshore June © 2015 PennWell Corporation Vortex-induced vibration was found to be present in the initial analy- sis without the bend stiffener, but the use of the bend stiffener reduced this to the point where it was no longer an issue. Contact between the tubing and the side of the vessel is possible in high current scenarios; therefore, the vessel may have to be oriented accordingly to avoid this. With the bend stiffener designed as described, the coil was ana- lyzed for fatigue. As indicated earlier, high-cycle fatigue is a major con- cern in this application, given the constant movement of the vessel. In this particular instance, the coil was anticipated to be deployed for about 32 days continuously. For a single deployment, fatigue was not determined to be an issue in this case. However, it should be noted that in the case of multiple deployments, the coil is also subjected to low cycle fatigue each time it goes over the gooseneck. The combi- nation of these two fatigue regimes requires further investigation to determine a probable ultimate fatigue life of the coil. Wet buckle contingency Many subsea pipelines employ some type of wet buckle contin- gency (WBC) dewatering system, however for large-bore, deep- water pipelines, the compressed air spread required to dewater the line is huge and the dewatering time very slow. For example, a major Black Sea pipeline project would have required a standby dewatering spread to be located in the vicinity of the subsea initia- tion head. To mitigate this contingency requirement, Baker Hughes developed a solution to partially dewater, isolate, and depressurize a short deepwater section using a large-bore coiled tubing down-line. This technique is summarized as follows: 1. An unplanned flooding event occurs. WBC flooding spread is commissioned. 2. A wet buckle contingency flooding pig receiver/catching head is installed. The head is fitted with a large bore discharge port for air/water outlet during the WBC flooding operation. 3. The line is then flooded with filtered, treated seawater from the WBC flooding spread and the free-flood, untreated seawater is displaced with treated seawater within 20 days. Water treated for a pre-agreed wet park period. 4. The WBC flooding pig receiver is then recovered to the sur- face and a pipeline recovery tool is installed with a pre-loaded smart plug 5. Concurrently, a coiled tubing (CT) dewatering system is in- stalled on a dynamically positioned vessel 6. Once function tested, the CT dewatering system is deployed to the recovery head 7. The smart plug is propelled about 3 km to 5 km (1.86 mi to 3.10 mi) into the line and treated water is discharged at the WBC pumping location. This can be conducted at a lower velocity than conventional dewatering. 8. The smart plug is set and the air pressure is bled down at the surface. 9. Lay barge recovers line to surface and pipelay can recommence. 10. The smart plug is left in place until dewatering operations commence after completion of pipelay. With this technique, a project crew can then use the dewatering air pressure to equalize across the smart plug and then push it to the receiver as part of the dewatering train. Conclusions With this article, the authors have endeavored to demonstrate the following: 1. Down-lines play an important role in the pre-commissioning of deepwater pipelines 2. Coiled tubing should be considered as the preferred down-line system except where very large bore down-lines are required. Even then, multiple coiled tubing down-lines can be considered as an alternative. 3. Custom marine coiled tubing systems provide the flexibility for moonpool or over-the-side deployment and are largely self- supporting once installed. 4. Engineering and modeling is required prior to deploying coiled tubing in a blue-water environment. 5. A partial dewatering system offers a faster, lower cost alternative to a full wet buckle contingency dewatering system, especially for pipelines not intended for hydrostatic pressure testing. • Acknowledgment Based on a paper presented at the OPT conference in Amsterdam, The Netherlands, Feb. 25-26, 2015. Left:Two-inch coiled tubing being deployed via moonpool. Right: Coiled tubing unit in transit mode, showing main deployment skid and reel. Complete spread in deployed configuration.