SlideShare uma empresa Scribd logo
1 de 16
Baixar para ler offline
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
John Grover
BJ Process & Pipeline Services
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Introduction
The increasing number of subsea and deepwater developments brings new
challenges where there are no surface connections to the pipeline available
for pipeline testing and pre-commissioning.
Once constructed / installed such subsea and deepwater systems still have
to undergo certain pre-commissioning and commissioning operations, from
initial flooding, gauging & testing up to final start up.
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Global Market Overview
Offshore pipeline installation forecasts show significant growth in both water
depth and length, however shallow water lines still dominant
• Significant growth in WD of 100m+
• Growth in NPS 16 to 24 range reflects subsea developments
• Regional growth in Australia, Indonesia, Malaysia and India
• Growing trend of smaller finds in deeper waters
• Develop several smaller discoveries together
Source – Infield Systems Ltd
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Objective
• Flooding and pigging subsea pipelines using a
Remote Flooding Module
• Pressurisation using subsea hydrotest oump
• Use of smart gauge tools (SGT) to gauge
pipelines – allows the gauging of lines with
reduced bore & testing without pig recovery.
• Use of subsea data loggers to record
pressures and temperatures
• Use of systems to transmit this data to surface
real-time during the test period
• A look at the next generation of technologies
for deepwater pipeline pre-commissioning
Whilst the provision of such services in shallow water and topside-to-topside
developments is routinely achieved, providing the same services at water depths in
excess of 1,000m poses many challenges. In this paper we shall review the unique
challenges in providing such services deepwater, and then review current / planned
technologies including:
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Oil Pipeline Pre-commissioning
Fill line with
treated &
filtered water
Run sufficient
cleaning pigs to meet
agreed cleanliness
Prove internal bore
by running a gauge
pig of caliper tool
Perform
hydrostatic
strength test
Optional
caliper survey
/ OOS survey
Line ready for
commissioning
/ lay up
1 2 3
4 5 6
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Gas Pipeline Pre-commissioning
Steps 1 to 4 as
for oil pipelines
– line tested
Dewater & swab line
to remove bulk water
– run desal slug
Dry line to an
agreed “dewpoint”
using dry air or
vacuum
Optional
caliper survey
/ OOS survey
Line ready for
commissioning
/ lay up
1 2 3
4 5 6Purge & pack
the line with
nitrogen gas
April 4th, 2003 BP Equipment Presentation Andy Barden
April 4th, 2003 BP Equipment Presentation Andy Barden
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Challenges in Deepwater Environment
Hydrotesting is a common requirement for all deepwater pipelines &
flexibles – here we review the unique challenge this brings subsea:
1. Large diameter line from surface vessel to deepwater PLET
needed to flood the line with filtered, treated water
2. Long duration for water temperature to stabilise if surface water
(say 25degC) used to flood line at 1000m WD (say 4degC)
3. Recovery of gauging tool to surface to verify mechanical
condition prior to pressure testing
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Challenges in Deepwater Environment
Hydrotesting is a common requirement for all deepwater pipelines &
flexibles – here we review the unique challenge this brings subsea:
1. Large diameter line from surface vessel to deepwater PLET
needed to flood the line with filtered, treated water – use of RFM
eliminates the need for large diameter subsea downlines. Also
SHP allows line to go straight in to hydrotest again saving time
and reducing risk
2. Long duration for water temperature to stabilise if surface water
(say 25degC) used to flood line at 1000m WD (say 4degC) – the
RFM floods the line using ambient temperature water meaning
no stabilisation time
3. Recovery of gauging tool to surface to verify mechanical
condition prior to pressure testing – the SGT (Smart Gauge Tool)
allows results of gauging survey to be annunciated via a pinger
and can then be left in for the test saving 1 recovery run
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
RFM Overview
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
RFM Overview
• Small, compact, light 4.2m x 3.2m x 2.5 / 6,000kg
• Fully meets specifications
• Chemicals on board, introduced by venturi
• Filtration on board
• Instrumentation onboard
• Range of pipeline sizes, set to desired
flowrate/pig speed
• Additional hydro-test capability if desired
• Particularly beneficial in deepwater
• ROV friendly - ROV Engineers Involved in Design
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
SHP Overview
• BJ designed hydraulically driven test pump
operated by ROV
• Various flows and pressures available,
determined by available ROV power but
circa 35 litres/minute to 600 Barg
• Eliminates the need for and downline
• Can be fitted to RFM Boost Pump skid or
stand alone skid
• Saves time vs. down-line deployment
Pipeline
Nomial
bore
(inches)
Length
(metres)
Vol/bar
(litres)
Bar/min ex SHP
Test Pressure
(bar)
Vol to test
pressure
(litres)
Time to test
pressure
(hours)
TS-WI-FL-01 12 9553 31.83 0.94 431 114523 7.62
TS-P-FL-01 10 9577 21.71 1.38 431 9921 5.20
TS-P-FL-02 10 9248 20.96 1.43 431 9580 5.02
TS-T-FL-01 8 9553 13.57 2.21 431 6210 3.25
TS-GL-FL-01 8 9479 13.47 2.23 431 6162 3.23
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
SGT Overview
Developed using patented sensor / pressure vessel unit. Uses a
segmented urethane disc to supplement the existing aluminium
gauge plate. by recording the number of deformations beyond the
given tolerance. For deepwater pipelines this means the following:
• Smart gauge is run at flooding stage
prior to hydrotest and is received in
laydown head
• ROV / surface hydrophone picks up the
signal and immediately confirms the
success of the gauging run
• Hydrotest can then proceed without
removal of the laydown head to
inspect the gauge plate
• Fixed gauge plate is then rechecked
upon final removal of the laydown head
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Subsea Data-logger Overview
• Can be connected to 4 lines
at once saving time
• Monitors pipelines during
hydrostatic test
• Records pressure and
temperature
• Allows vessels to carry out
other work
• Recovered and downloaded
when convenient
• Deployed and recovered by
ROV
• Can be linked to surface via
BJ Update™ system
Video
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Subsea Operation
V
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Future Developments
DEVELOPMENT
• Remote closing of valves at
discharge end of pipeline under
test
• Improved pig detection for both
launch and receive
• Real time transmission of test
data to surface using acoustic
telemetry
BENEFIT
Saves 1 vessel move and 1 ROV
deployment = $ and time saving
Removes need to “over-pump”
during any subsea pigging
operation = $ saving &
environmental benefit
Already under field trials (BJ
Update™) and soon operational –
means vessel can work elsewhere
during test = $ saving & improved
vessel utilisation
DEEP OFFSHORE TECHNOLOGY INTERNATIONAL
Advances in Subsea and Deepwater Pipeline Pre-commissioning
Summary & Conclusions
1. System design has a major impact on how a line can be tested and
commissioned – in the Asia Pacific Region we are seeing many using
complete subsea architecture with few permanent surface connections
2. The biggest risk in deepwater pipeline operations is making and maintaining
the connection between the vessel and subsea connection
3. The cost of any support vessel required to support subsea pre-commissioning
far outweighs the cost of the subsea pre-commissioning spread
4. Today it is possible to flood, gauge and hydrotest a deepwater pipeline
without the use of any down-line – at BJ Services alone this technique has
been successful employed on over 100 pipelines
5. As ROV size and hydraulic power increases it will be possible to run larger
pumps improving flooding and testing time
6. Combining remote valve closing, remote data transmission and guaranteed
pig location we can further reduce the risk whilst improving the efficiency of
deepwater pipeline pre-commissioning

Mais conteúdo relacionado

Mais procurados

Surface casing vent testing nov 13-2013
Surface casing vent testing nov 13-2013Surface casing vent testing nov 13-2013
Surface casing vent testing nov 13-2013
Mike Beck
 
Does Heavy Oil Recovery Need Steam?
Does Heavy Oil Recovery Need Steam?Does Heavy Oil Recovery Need Steam?
Does Heavy Oil Recovery Need Steam?
Society of Petroleum Engineers
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Society of Petroleum Engineers
 
Illuminating Insights Into Well and Reservoir Optimisation Using Fibre-optic...
Illuminating Insights Into Well and Reservoir Optimisation Using  Fibre-optic...Illuminating Insights Into Well and Reservoir Optimisation Using  Fibre-optic...
Illuminating Insights Into Well and Reservoir Optimisation Using Fibre-optic...
Society of Petroleum Engineers
 
Westbay Nova Product Brochure 2015
Westbay Nova Product Brochure 2015Westbay Nova Product Brochure 2015
Westbay Nova Product Brochure 2015
Nathan Lopez
 
Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15
John Grover
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Society of Petroleum Engineers
 
Integrated Historical Data Workflow: Maximizing the Value of a Mature Asset
Integrated Historical Data Workflow: Maximizing the Value of a Mature AssetIntegrated Historical Data Workflow: Maximizing the Value of a Mature Asset
Integrated Historical Data Workflow: Maximizing the Value of a Mature Asset
Society of Petroleum Engineers
 
Elgin Water Solutions Presentation
Elgin Water Solutions PresentationElgin Water Solutions Presentation
Elgin Water Solutions Presentation
John McNeill
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Society of Petroleum Engineers
 

Mais procurados (20)

Surface Casing Vent Testing - Surface Solutions Inc.
Surface Casing Vent Testing - Surface Solutions Inc.Surface Casing Vent Testing - Surface Solutions Inc.
Surface Casing Vent Testing - Surface Solutions Inc.
 
Surface casing vent testing nov 13-2013
Surface casing vent testing nov 13-2013Surface casing vent testing nov 13-2013
Surface casing vent testing nov 13-2013
 
Icrc 002-4033
Icrc 002-4033Icrc 002-4033
Icrc 002-4033
 
Thriving in a Lower for Longer Environment - Mary Van Domelen
Thriving in a Lower for Longer Environment - Mary Van DomelenThriving in a Lower for Longer Environment - Mary Van Domelen
Thriving in a Lower for Longer Environment - Mary Van Domelen
 
Charles Hinrichsen
Charles HinrichsenCharles Hinrichsen
Charles Hinrichsen
 
Does Heavy Oil Recovery Need Steam?
Does Heavy Oil Recovery Need Steam?Does Heavy Oil Recovery Need Steam?
Does Heavy Oil Recovery Need Steam?
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
 
WP Offshore Coating Techniques Aug 2015
WP Offshore Coating Techniques Aug 2015WP Offshore Coating Techniques Aug 2015
WP Offshore Coating Techniques Aug 2015
 
PetroSync - HPHT Drilling Operation
PetroSync - HPHT Drilling OperationPetroSync - HPHT Drilling Operation
PetroSync - HPHT Drilling Operation
 
Illuminating Insights Into Well and Reservoir Optimisation Using Fibre-optic...
Illuminating Insights Into Well and Reservoir Optimisation Using  Fibre-optic...Illuminating Insights Into Well and Reservoir Optimisation Using  Fibre-optic...
Illuminating Insights Into Well and Reservoir Optimisation Using Fibre-optic...
 
CO2 in the Subsurface - From EOR to Storage
CO2 in the Subsurface - From EOR to StorageCO2 in the Subsurface - From EOR to Storage
CO2 in the Subsurface - From EOR to Storage
 
Westbay Nova Product Brochure 2015
Westbay Nova Product Brochure 2015Westbay Nova Product Brochure 2015
Westbay Nova Product Brochure 2015
 
Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
 
SCC WITH KIM.PPTX
SCC WITH KIM.PPTXSCC WITH KIM.PPTX
SCC WITH KIM.PPTX
 
SPE Well Prep Paper
SPE Well Prep PaperSPE Well Prep Paper
SPE Well Prep Paper
 
Integrated Historical Data Workflow: Maximizing the Value of a Mature Asset
Integrated Historical Data Workflow: Maximizing the Value of a Mature AssetIntegrated Historical Data Workflow: Maximizing the Value of a Mature Asset
Integrated Historical Data Workflow: Maximizing the Value of a Mature Asset
 
Elgin Water Solutions Presentation
Elgin Water Solutions PresentationElgin Water Solutions Presentation
Elgin Water Solutions Presentation
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
 

Destaque

20130411110129735 (2)
20130411110129735 (2)20130411110129735 (2)
20130411110129735 (2)
John Grover
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
John Grover
 
Evidence of style guide
Evidence of style guideEvidence of style guide
Evidence of style guide
JakeMason94
 
Specfic research and analysis
Specfic research and analysisSpecfic research and analysis
Specfic research and analysis
JakeMason94
 
Golf slide show
Golf slide showGolf slide show
Golf slide show
Bretski5
 
Mat persamaan kuadrat
Mat   persamaan kuadratMat   persamaan kuadrat
Mat persamaan kuadrat
Juse Oktabri
 

Destaque (18)

Appendix h economics final dec2010
Appendix h economics final dec2010Appendix h economics final dec2010
Appendix h economics final dec2010
 
JustinONeillresume1
JustinONeillresume1JustinONeillresume1
JustinONeillresume1
 
20130411110129735 (2)
20130411110129735 (2)20130411110129735 (2)
20130411110129735 (2)
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
 
Premioinnovas@lute percorso chirurgico intelligente oi v1
Premioinnovas@lute percorso chirurgico intelligente oi v1Premioinnovas@lute percorso chirurgico intelligente oi v1
Premioinnovas@lute percorso chirurgico intelligente oi v1
 
Оконная пленка Korqu 2 (выбор пленки)
Оконная пленка Korqu 2 (выбор пленки)Оконная пленка Korqu 2 (выбор пленки)
Оконная пленка Korqu 2 (выбор пленки)
 
Distribution the particular Wings- The software Safety measures Concurrence r...
Distribution the particular Wings- The software Safety measures Concurrence r...Distribution the particular Wings- The software Safety measures Concurrence r...
Distribution the particular Wings- The software Safety measures Concurrence r...
 
Evidence of style guide
Evidence of style guideEvidence of style guide
Evidence of style guide
 
Specfic research and analysis
Specfic research and analysisSpecfic research and analysis
Specfic research and analysis
 
Research & analysis
Research & analysisResearch & analysis
Research & analysis
 
Evaluation
EvaluationEvaluation
Evaluation
 
Golf slide show
Golf slide showGolf slide show
Golf slide show
 
Mat persamaan kuadrat
Mat   persamaan kuadratMat   persamaan kuadrat
Mat persamaan kuadrat
 
20160917街を使い倒して街を再生する
20160917街を使い倒して街を再生する20160917街を使い倒して街を再生する
20160917街を使い倒して街を再生する
 
символьный тип данных
символьный  тип  данныхсимвольный  тип  данных
символьный тип данных
 
Vista chamber chairmans circle
Vista chamber chairmans circleVista chamber chairmans circle
Vista chamber chairmans circle
 
エコイノベーションで実現する サステナブルなライフスタイル 絵巻用語解説集(Ver1)
エコイノベーションで実現する サステナブルなライフスタイル 絵巻用語解説集(Ver1) エコイノベーションで実現する サステナブルなライフスタイル 絵巻用語解説集(Ver1)
エコイノベーションで実現する サステナブルなライフスタイル 絵巻用語解説集(Ver1)
 
Projek Agropreneur
Projek AgropreneurProjek Agropreneur
Projek Agropreneur
 

Semelhante a 26-grover-john-draft

26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
John Grover
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
John Grover
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
John Grover
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Abhinav Bisht
 
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Charlie Reith
 
perris dam_Godwin et al AEG conf fnl(3)
perris dam_Godwin et al AEG conf fnl(3)perris dam_Godwin et al AEG conf fnl(3)
perris dam_Godwin et al AEG conf fnl(3)
William Godwin
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
daniel cobar
 
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme [IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
IJET - International Journal of Engineering and Techniques
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the future
Statoil
 
"Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr...
"Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr..."Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr...
"Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr...
Society of Petroleum Engineers
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
Egyptian Engineers Association
 

Semelhante a 26-grover-john-draft (20)

26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
 
Shell Subsea Control.pdf
Shell Subsea Control.pdfShell Subsea Control.pdf
Shell Subsea Control.pdf
 
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
 
Technical Prospects of Floating LNG
Technical Prospects of Floating LNGTechnical Prospects of Floating LNG
Technical Prospects of Floating LNG
 
Agr Field Operations Pipeline Inspection
Agr Field Operations Pipeline InspectionAgr Field Operations Pipeline Inspection
Agr Field Operations Pipeline Inspection
 
Subsea Separation presentation
Subsea Separation presentationSubsea Separation presentation
Subsea Separation presentation
 
TECHNIQUES OF UNDERWATER STRUCTURE INSPECTION AND WHO TO CONTACT FOR THE JOB
TECHNIQUES OF UNDERWATER STRUCTURE INSPECTION AND WHO TO CONTACT FOR THE JOBTECHNIQUES OF UNDERWATER STRUCTURE INSPECTION AND WHO TO CONTACT FOR THE JOB
TECHNIQUES OF UNDERWATER STRUCTURE INSPECTION AND WHO TO CONTACT FOR THE JOB
 
perris dam_Godwin et al AEG conf fnl(3)
perris dam_Godwin et al AEG conf fnl(3)perris dam_Godwin et al AEG conf fnl(3)
perris dam_Godwin et al AEG conf fnl(3)
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
 
AUV-based Cathodic Protection (CP) Automatic Inspection Technology for offsho...
AUV-based Cathodic Protection (CP) Automatic Inspection Technology for offsho...AUV-based Cathodic Protection (CP) Automatic Inspection Technology for offsho...
AUV-based Cathodic Protection (CP) Automatic Inspection Technology for offsho...
 
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme [IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
[IJET-V1I2P10] Authors :L. O. Osuman, A. Dosunmu , B .S. Odagme
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field development
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
 
Short Resume
Short Resume Short Resume
Short Resume
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the future
 
"Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr...
"Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr..."Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr...
"Deepwater Managed Pressure Drilling and Well Drillability, Efficiency and Pr...
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 

26-grover-john-draft

  • 1. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning John Grover BJ Process & Pipeline Services
  • 2. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Introduction The increasing number of subsea and deepwater developments brings new challenges where there are no surface connections to the pipeline available for pipeline testing and pre-commissioning. Once constructed / installed such subsea and deepwater systems still have to undergo certain pre-commissioning and commissioning operations, from initial flooding, gauging & testing up to final start up.
  • 3. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Global Market Overview Offshore pipeline installation forecasts show significant growth in both water depth and length, however shallow water lines still dominant • Significant growth in WD of 100m+ • Growth in NPS 16 to 24 range reflects subsea developments • Regional growth in Australia, Indonesia, Malaysia and India • Growing trend of smaller finds in deeper waters • Develop several smaller discoveries together Source – Infield Systems Ltd
  • 4. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Objective • Flooding and pigging subsea pipelines using a Remote Flooding Module • Pressurisation using subsea hydrotest oump • Use of smart gauge tools (SGT) to gauge pipelines – allows the gauging of lines with reduced bore & testing without pig recovery. • Use of subsea data loggers to record pressures and temperatures • Use of systems to transmit this data to surface real-time during the test period • A look at the next generation of technologies for deepwater pipeline pre-commissioning Whilst the provision of such services in shallow water and topside-to-topside developments is routinely achieved, providing the same services at water depths in excess of 1,000m poses many challenges. In this paper we shall review the unique challenges in providing such services deepwater, and then review current / planned technologies including:
  • 5. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Oil Pipeline Pre-commissioning Fill line with treated & filtered water Run sufficient cleaning pigs to meet agreed cleanliness Prove internal bore by running a gauge pig of caliper tool Perform hydrostatic strength test Optional caliper survey / OOS survey Line ready for commissioning / lay up 1 2 3 4 5 6
  • 6. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Gas Pipeline Pre-commissioning Steps 1 to 4 as for oil pipelines – line tested Dewater & swab line to remove bulk water – run desal slug Dry line to an agreed “dewpoint” using dry air or vacuum Optional caliper survey / OOS survey Line ready for commissioning / lay up 1 2 3 4 5 6Purge & pack the line with nitrogen gas April 4th, 2003 BP Equipment Presentation Andy Barden April 4th, 2003 BP Equipment Presentation Andy Barden
  • 7. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Challenges in Deepwater Environment Hydrotesting is a common requirement for all deepwater pipelines & flexibles – here we review the unique challenge this brings subsea: 1. Large diameter line from surface vessel to deepwater PLET needed to flood the line with filtered, treated water 2. Long duration for water temperature to stabilise if surface water (say 25degC) used to flood line at 1000m WD (say 4degC) 3. Recovery of gauging tool to surface to verify mechanical condition prior to pressure testing
  • 8. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Challenges in Deepwater Environment Hydrotesting is a common requirement for all deepwater pipelines & flexibles – here we review the unique challenge this brings subsea: 1. Large diameter line from surface vessel to deepwater PLET needed to flood the line with filtered, treated water – use of RFM eliminates the need for large diameter subsea downlines. Also SHP allows line to go straight in to hydrotest again saving time and reducing risk 2. Long duration for water temperature to stabilise if surface water (say 25degC) used to flood line at 1000m WD (say 4degC) – the RFM floods the line using ambient temperature water meaning no stabilisation time 3. Recovery of gauging tool to surface to verify mechanical condition prior to pressure testing – the SGT (Smart Gauge Tool) allows results of gauging survey to be annunciated via a pinger and can then be left in for the test saving 1 recovery run
  • 9. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning RFM Overview
  • 10. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning RFM Overview • Small, compact, light 4.2m x 3.2m x 2.5 / 6,000kg • Fully meets specifications • Chemicals on board, introduced by venturi • Filtration on board • Instrumentation onboard • Range of pipeline sizes, set to desired flowrate/pig speed • Additional hydro-test capability if desired • Particularly beneficial in deepwater • ROV friendly - ROV Engineers Involved in Design
  • 11. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning SHP Overview • BJ designed hydraulically driven test pump operated by ROV • Various flows and pressures available, determined by available ROV power but circa 35 litres/minute to 600 Barg • Eliminates the need for and downline • Can be fitted to RFM Boost Pump skid or stand alone skid • Saves time vs. down-line deployment Pipeline Nomial bore (inches) Length (metres) Vol/bar (litres) Bar/min ex SHP Test Pressure (bar) Vol to test pressure (litres) Time to test pressure (hours) TS-WI-FL-01 12 9553 31.83 0.94 431 114523 7.62 TS-P-FL-01 10 9577 21.71 1.38 431 9921 5.20 TS-P-FL-02 10 9248 20.96 1.43 431 9580 5.02 TS-T-FL-01 8 9553 13.57 2.21 431 6210 3.25 TS-GL-FL-01 8 9479 13.47 2.23 431 6162 3.23
  • 12. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning SGT Overview Developed using patented sensor / pressure vessel unit. Uses a segmented urethane disc to supplement the existing aluminium gauge plate. by recording the number of deformations beyond the given tolerance. For deepwater pipelines this means the following: • Smart gauge is run at flooding stage prior to hydrotest and is received in laydown head • ROV / surface hydrophone picks up the signal and immediately confirms the success of the gauging run • Hydrotest can then proceed without removal of the laydown head to inspect the gauge plate • Fixed gauge plate is then rechecked upon final removal of the laydown head
  • 13. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Subsea Data-logger Overview • Can be connected to 4 lines at once saving time • Monitors pipelines during hydrostatic test • Records pressure and temperature • Allows vessels to carry out other work • Recovered and downloaded when convenient • Deployed and recovered by ROV • Can be linked to surface via BJ Update™ system Video
  • 14. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Subsea Operation V
  • 15. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Future Developments DEVELOPMENT • Remote closing of valves at discharge end of pipeline under test • Improved pig detection for both launch and receive • Real time transmission of test data to surface using acoustic telemetry BENEFIT Saves 1 vessel move and 1 ROV deployment = $ and time saving Removes need to “over-pump” during any subsea pigging operation = $ saving & environmental benefit Already under field trials (BJ Update™) and soon operational – means vessel can work elsewhere during test = $ saving & improved vessel utilisation
  • 16. DEEP OFFSHORE TECHNOLOGY INTERNATIONAL Advances in Subsea and Deepwater Pipeline Pre-commissioning Summary & Conclusions 1. System design has a major impact on how a line can be tested and commissioned – in the Asia Pacific Region we are seeing many using complete subsea architecture with few permanent surface connections 2. The biggest risk in deepwater pipeline operations is making and maintaining the connection between the vessel and subsea connection 3. The cost of any support vessel required to support subsea pre-commissioning far outweighs the cost of the subsea pre-commissioning spread 4. Today it is possible to flood, gauge and hydrotest a deepwater pipeline without the use of any down-line – at BJ Services alone this technique has been successful employed on over 100 pipelines 5. As ROV size and hydraulic power increases it will be possible to run larger pumps improving flooding and testing time 6. Combining remote valve closing, remote data transmission and guaranteed pig location we can further reduce the risk whilst improving the efficiency of deepwater pipeline pre-commissioning