Scaffolding & Underpinning
Scaffolding
ïŹ Definitions
– It’s a temporary structure to provide a platform at
different levels of a building for workers and
Materials.
– It is used when height of wall or column or other
structural member of a building exceeds about
1.5m.
Component Parts
ïŹ Standards:- These are vertical members of
the frame work, supporting on the ground or
embedded into the ground.
ïŹ Ledgers:- these are the horizontal members,
running parallel to the wall.
ïŹ Braces:- These are diagonal members fixed
on standards.
Component Parts
ïŹ Putlogs:- These are the transverse
members, placed at right angles to the wall
with one end supported on ledgers and other
end on the wall.
ïŹ Boarding:- These are horizontal platform to
support workmen & material; these are
supported on putlogs.
ïŹ Guard Rail:- This is a rail, provided like a
ledger, at the working level.
Components Parts
Scaffolding
Definition
ïŹ Scaffold
– It is the temporary support system provided for
the construction & maintenance purposes.
– It consists of supports and a working plate form
for workers and Materials.
ïŹ Scaffolding
– Method of construction of scaffolds is called
scaffolding.
Types of Scaffolding
ïŹ Following are the types of scaffolds
1. Single Scaffolds
2. Double Scaffolds
3. Ladder Scaffolds
4. Cantilever Scaffolds
5. Suspended Scaffolds
6. Steel or Tubular Scaffolds
Single Scaffolds
ïŹ It consists of Standards, Putlogs, Ledgers,
Wooden boards, Braces.
ïŹ Used for Ordinary Buildings.
ïŹ It is also known as Brick-layers Scaffolding.
ïŹ It is commonly used for brick-laying and also
called putlog scaffolding.
Single Scaffolding
1.2 m
Single Scaffolding
Double Scaffolding
ïŹ It consists of two rows of standards.
ïŹ The first row is placed at 20 to 30 cm away
from the wall, while the other frame work is
placed at 1 m distance from first one.
ïŹ Raking shores are provided.
ïŹ Used for superior works.
ïŹ It is also called as Independent Scaffolding.
Double Scaffolding
Cantilever Scaffolding
ïŹ It consists of cantilever, standards, putlogs.
ïŹ It is used under following circumstances:
 Ground is weak to support.
 Construction of upper part of the wall is to
be carried out.
 It is required to keep the ground, near wall,
free for traffic.
Cantilever Scaffolding
Cantilever Scaffolding
Suspended Scaffolding
ïŹ It consists of
– Ropes
– Working platforms
Ropes can be raised
Manually or
mechanically
Used for light construction
and finishing works of
multistory buildings.
Suspended Scaffolding
Steel or Tubular Scaffolds
ïŹ It consists of
– Steel tubes (1-1/2” – 2-1/2” diameter)
– Coupler or Clamps (to hold pipes in different
positions)
– Prop nuts (to hold single pipes)
– Bolts, Nuts & washers
– Wedge & Clip
Scaffold pipes
Coupler or Clamps
Scaffold
fittings
Scaffold fittings
Prop nuts, clamp and fasteners
Wedge & Clip
Under-Pinning
ïŹ Definition:-
The process of placing a new
foundation under an existing one or
strengthening an existing foundation is called
as Underpinning of foundations.
Purposes
ïŹ To strengthen the shallow foundation of existing
building when a building with deep foundation is
to be constructed adjoining it.
ïŹ To strengthen the existing foundation which has
settled and caused cracks in the wall.
ïŹ To deepen the existing foundation (resting on
poor strata so as to rest it on deeper soil strata
of higher bearing power.
ïŹ To construct a basement in the existing building.
Methods
ïŹ Pit Method
ïŹ Pile Method
Pit method
ïŹ Old wall is supported by a
bearing plate, steel beam
and jacks.
ïŹ Excavation up to new
depth is carried out.
ïŹ Foundation is provided.
ïŹ P.C.C (1:2:4) is provided
for new foundation.
ïŹ For proper joint b/w old
and new work,
strengthening and to avoid
settlement vertical steel
bars may be added.
Steel Bars
Pile method
ïŹ Piles are driven at
regular interval.
ïŹ Piles are connected by
concrete or steel
needles, penetrating
through wall.
ïŹ These beam incidentally
act as pile cap.
ïŹ Used in clayey soil &
water logged areas.
P
I
L
E
P
I
L
E
P
I
L
E
Pile Cap
P.C.C
Hard Strata
P.C.C (1:2:4)

Mais conteĂșdo relacionado

Mais procurados

Mais procurados (20)

Stairs
StairsStairs
Stairs
 
Types of pitched roofs
Types of pitched roofsTypes of pitched roofs
Types of pitched roofs
 
Steel grillage fondation
Steel grillage fondation Steel grillage fondation
Steel grillage fondation
 
Stairs
StairsStairs
Stairs
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Foundations
FoundationsFoundations
Foundations
 
Report on stairs
Report on stairsReport on stairs
Report on stairs
 
Chapter 7 stairs & staircases
Chapter 7 stairs & staircasesChapter 7 stairs & staircases
Chapter 7 stairs & staircases
 
Flooring
FlooringFlooring
Flooring
 
Basic component of buildings
Basic component of buildingsBasic component of buildings
Basic component of buildings
 
Arches
ArchesArches
Arches
 
7. building components
7. building components7. building components
7. building components
 
Shoring
ShoringShoring
Shoring
 
DPC, Back Filling and Plinth Protection.pptx
DPC, Back Filling and Plinth Protection.pptxDPC, Back Filling and Plinth Protection.pptx
DPC, Back Filling and Plinth Protection.pptx
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Timber staircase
Timber staircaseTimber staircase
Timber staircase
 
Stairs Ppt
Stairs PptStairs Ppt
Stairs Ppt
 
Stone masonry
Stone masonry Stone masonry
Stone masonry
 
PRECAST CONCRETE STAIRS
  PRECAST CONCRETE STAIRS  PRECAST CONCRETE STAIRS
PRECAST CONCRETE STAIRS
 

Semelhante a Scaffolding & underpinning

SCAFFOLDING.pptx
SCAFFOLDING.pptxSCAFFOLDING.pptx
SCAFFOLDING.pptxHiteshAshani1
 
Temporary structures
Temporary structuresTemporary structures
Temporary structuresDivya Vishnoi
 
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdfNotes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdfVICTOR A. KIPLAGAT
 
formwork.pdf
formwork.pdfformwork.pdf
formwork.pdfhassanakhar
 
Temporary works
Temporary worksTemporary works
Temporary worksAditya Mistry
 
Lecture 8 a.pptx
Lecture 8 a.pptxLecture 8 a.pptx
Lecture 8 a.pptxBurkaDinka
 
Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary worksKHUSHBU SHAH
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdfFaizanSolanki
 
Retaining wall
Retaining wallRetaining wall
Retaining wallkajal018
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
Temporary works
Temporary worksTemporary works
Temporary worksBhavik Patel
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldingsHamdija Velagic
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 

Semelhante a Scaffolding & underpinning (20)

Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Group no 9
Group no 9Group no 9
Group no 9
 
SCAFFOLDING.pptx
SCAFFOLDING.pptxSCAFFOLDING.pptx
SCAFFOLDING.pptx
 
Temporary structures
Temporary structuresTemporary structures
Temporary structures
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdfNotes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
 
formwork.pdf
formwork.pdfformwork.pdf
formwork.pdf
 
Temporary works
Temporary worksTemporary works
Temporary works
 
Lecture 8 a.pptx
Lecture 8 a.pptxLecture 8 a.pptx
Lecture 8 a.pptx
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary works
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Wall construction
Wall construction Wall construction
Wall construction
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Temporary works
Temporary worksTemporary works
Temporary works
 
Module 3
Module 3Module 3
Module 3
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldings
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 

Mais de Jitesh Dhule

Stone masonry
Stone masonryStone masonry
Stone masonryJitesh Dhule
 
Safety in construction
Safety in constructionSafety in construction
Safety in constructionJitesh Dhule
 
Masonry special features
Masonry special featuresMasonry special features
Masonry special featuresJitesh Dhule
 
Doors and windows
Doors and windowsDoors and windows
Doors and windowsJitesh Dhule
 

Mais de Jitesh Dhule (9)

Stone masonry
Stone masonryStone masonry
Stone masonry
 
Safety in construction
Safety in constructionSafety in construction
Safety in construction
 
Foundation
FoundationFoundation
Foundation
 
Roofs
RoofsRoofs
Roofs
 
Masonry special features
Masonry special featuresMasonry special features
Masonry special features
 
Formwork
FormworkFormwork
Formwork
 
Doors and windows
Doors and windowsDoors and windows
Doors and windows
 
Bricks
BricksBricks
Bricks
 
Arches
ArchesArches
Arches
 

Último

Top Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoordharasingh5698
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Call Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night StandCall Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night Standamitlee9823
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar â‰ŒđŸ” Delhi door step de...
Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar  â‰ŒđŸ” Delhi door step de...Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar  â‰ŒđŸ” Delhi door step de...
Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar â‰ŒđŸ” Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsArindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 

Último (20)

Top Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor đŸ“± {7001035870} VIP Escorts chittoor
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Call Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night StandCall Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 đŸ„” Book Your One night Stand
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar â‰ŒđŸ” Delhi door step de...
Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar  â‰ŒđŸ” Delhi door step de...Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar  â‰ŒđŸ” Delhi door step de...
Call Now ≜ 9953056974 â‰ŒđŸ” Call Girls In New Ashok Nagar â‰ŒđŸ” Delhi door step de...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

Scaffolding & underpinning

  • 2. Scaffolding ïŹ Definitions – It’s a temporary structure to provide a platform at different levels of a building for workers and Materials. – It is used when height of wall or column or other structural member of a building exceeds about 1.5m.
  • 3. Component Parts ïŹ Standards:- These are vertical members of the frame work, supporting on the ground or embedded into the ground. ïŹ Ledgers:- these are the horizontal members, running parallel to the wall. ïŹ Braces:- These are diagonal members fixed on standards.
  • 4. Component Parts ïŹ Putlogs:- These are the transverse members, placed at right angles to the wall with one end supported on ledgers and other end on the wall. ïŹ Boarding:- These are horizontal platform to support workmen & material; these are supported on putlogs. ïŹ Guard Rail:- This is a rail, provided like a ledger, at the working level.
  • 7. Definition ïŹ Scaffold – It is the temporary support system provided for the construction & maintenance purposes. – It consists of supports and a working plate form for workers and Materials. ïŹ Scaffolding – Method of construction of scaffolds is called scaffolding.
  • 8. Types of Scaffolding ïŹ Following are the types of scaffolds 1. Single Scaffolds 2. Double Scaffolds 3. Ladder Scaffolds 4. Cantilever Scaffolds 5. Suspended Scaffolds 6. Steel or Tubular Scaffolds
  • 9. Single Scaffolds ïŹ It consists of Standards, Putlogs, Ledgers, Wooden boards, Braces. ïŹ Used for Ordinary Buildings. ïŹ It is also known as Brick-layers Scaffolding. ïŹ It is commonly used for brick-laying and also called putlog scaffolding.
  • 12. Double Scaffolding ïŹ It consists of two rows of standards. ïŹ The first row is placed at 20 to 30 cm away from the wall, while the other frame work is placed at 1 m distance from first one. ïŹ Raking shores are provided. ïŹ Used for superior works. ïŹ It is also called as Independent Scaffolding.
  • 13.
  • 15. Cantilever Scaffolding ïŹ It consists of cantilever, standards, putlogs. ïŹ It is used under following circumstances:  Ground is weak to support.  Construction of upper part of the wall is to be carried out.  It is required to keep the ground, near wall, free for traffic.
  • 18. Suspended Scaffolding ïŹ It consists of – Ropes – Working platforms Ropes can be raised Manually or mechanically Used for light construction and finishing works of multistory buildings.
  • 20. Steel or Tubular Scaffolds ïŹ It consists of – Steel tubes (1-1/2” – 2-1/2” diameter) – Coupler or Clamps (to hold pipes in different positions) – Prop nuts (to hold single pipes) – Bolts, Nuts & washers – Wedge & Clip
  • 25. Prop nuts, clamp and fasteners
  • 27. Under-Pinning ïŹ Definition:- The process of placing a new foundation under an existing one or strengthening an existing foundation is called as Underpinning of foundations.
  • 28. Purposes ïŹ To strengthen the shallow foundation of existing building when a building with deep foundation is to be constructed adjoining it. ïŹ To strengthen the existing foundation which has settled and caused cracks in the wall. ïŹ To deepen the existing foundation (resting on poor strata so as to rest it on deeper soil strata of higher bearing power. ïŹ To construct a basement in the existing building.
  • 30. Pit method ïŹ Old wall is supported by a bearing plate, steel beam and jacks. ïŹ Excavation up to new depth is carried out. ïŹ Foundation is provided. ïŹ P.C.C (1:2:4) is provided for new foundation. ïŹ For proper joint b/w old and new work, strengthening and to avoid settlement vertical steel bars may be added. Steel Bars
  • 31. Pile method ïŹ Piles are driven at regular interval. ïŹ Piles are connected by concrete or steel needles, penetrating through wall. ïŹ These beam incidentally act as pile cap. ïŹ Used in clayey soil & water logged areas. P I L E P I L E P I L E Pile Cap P.C.C Hard Strata P.C.C (1:2:4)