Roads and Bridges

Construction Methods & resources




       by:
                               1
  Jihad Daniel
Types of Roads
• Various types of roads are in use
  around the world. Roads range in
  size from private driveways, to
  the stereotypical two-lane
  highways, to high capacity dual
  carriageway routes, such as
  freeways and motorways.

                             • In addition, depending
                               on their types, roads may
                               have different types of
                               junction.                2
Types of Junctions
                  Bridge
               interchange




                             Intersection
 Flyover and
 underpasses   Junctions          at
                                grade




               Interchange
                    at
                  grade

                                            3
Types of Junctions
• Interchange at grade



                         • Intersection at grade




                                                   4
Types of Junctions
• Flyovers



                 • Bridge interchange




                                    5
Road Structure
• Cross section of a road: main
  road situated outside towns and
  cities.
• Platform: horizontal surface raised
  above the surrounding ground.
• Shoulder: space between the
  roadway and the ditch.
• Median strip: separation between
  two carriageway.
• Wearing course: surface layer of
  the road (asphalt).
• Carriageway: central part reserved
  for vehicle traffic.
• Ditch: channel that carries away
  water.                                6
Road Structure
• Subgrade: upper surface of
  platform.
  (this is valid in a cut section)
• In a Fill Section, the
  embankment constitute the
  platform and the subgrade.
• Subbase: lower surface of a road
  structure.
• Base course: main foundation
  element (bituminous / granular).
• Wearing Course (Bituminous in
  general)


                                     7
Road Profile
• The right of way ground formation maybe, as the road profile requires,
  natural ground, cut or fill. In case of fill, ground formation is filled in layers
  to comply with the profile. The work is called embankment.
• Embankment is made in layers with thickness varying from 20 to 40 cm
  depending on the material used.
• In case of cut this could be open cut or tunnel.




                                                                                       8
Materials




Selected    Crushed    Asphaltic
                                   Roads
   fill    aggregate   concrete




                                           9
Road Furniture and
     Incidental Works
Road furniture refers to
all fixtures in the road
reserve. The term
includes fixtures on the
road surface such as:

-   Signs,
-   Markings,
-   Safety barriers,
-   Road studs, etc.
                           10
Method of Construction
The system is based on a monthly output of
major work items using the minimum
equipment considered necessary to carry out the
work during a month of 25 working days, each
day being 8 working hours.




                                              11
Road works planning
        criteria
• Planning road works, as a first step, depends on the
  extent of earthmoving quantities.

• Generally, the most driving is the fill making the
  embankment, especially for the case of high
  embankments.

• The basic equipment is as follows:
                                                       12
Fill
From Common Excavation of Borrow Excavation:
     Basic Equipment for One Work Team
No. of Items                             Item
     6                Dump Trucks (8 m3), 12 to 15 Tons
     1                Front-end Loader (2m3 bucket)
     1                Motor Grader (150 hp)
     2                Water Trucks (12 m3)
     1                Vibratory Roller (40 kw)
     1                Farm Tractor (if roller is not self-
                      propelled)




                                                             13
Cut & Fill
From Common Excavation or Borrow Excavation:
      Basic Equipment for Two Work Teams
No. of Items                          Item
    12                   Dump Trucks (8 m3)
    2                    Front-end Loader (2 m3)
    2                    Bulldozers (200-300 hp)
    3                    Motor Grader (150 hp)
    2                    Vibratory Rollers (40 kw)
    6                    Water Tanker Trucks (12,000 liters)
    2                    Farm Tractors (if roller is not self-
                         propelled)
    1                    Pneumatic Roller (25 mg)


                                                                 14
Production rates
Assuming:

Number of dump trucks =12
Truck capacity = 8 m3 per truck
Average haul distance=1 km (from borrow pit/stockpile to job site)
Number of cycles : (Cycle time 8 minutes)
Efficiency on truck capacity: 70%
Therefore, rate (2 teams) of 100,000 m3/month based on the following use a basic
   production:
           Production Rate = 12 x 8 x 60/8 x 0.7 x 25 x 8 = 100,800 m3/month
     • For quantities up to 1,500,000 m3 use the basic production rate of
        100,000 m3/month (2 work teams)
     • For quantities between 1,500,000 m3 and 2,500,000 m3 adjust the equipment
        to provide a production rate of 150,000 m3/month (3 work teams)
                                                                            15
Production rates (cont’d)
 • For quantities greater than 2,500,000 m3 adjust the equipment
   to provide a minimum production rate of 200,000 m3/month
   (4 work teams).
 • The overall monthly production rate shall be adjusted to
   allow 2 months buildup prior to peak production and 1
   month slow down prior to completion of the work.

 The quantity of embankment placed should be converted in road
 length terms to enable the planner to define the interface
 between subsequent activities. (e.g. when to start sub-base
 activities after embankment)

                                                              16
Production rates (cont’d)
  Planning the amount of earthworks and defining the time
  required to place the whole quantity would be as follows:
               1st month                50,000 m3
               2nd month               100,000 m3
            3rd (last month)            50,000 m3

• Duration = 1500,000 – (50,000 + 100,000 + 50,000)
                                  100,000
            = 13 months
  Using higher capacity trucks and improving efficiency would
  reduce this duration.

                                                                17
Bulldozer




            18
grader




         19
ASPHALT PAVEMENT
       Basic Equipment for Two Work Teams
 No. of Items                          Item
     2                    Paver
    6-12                  Dump Truck (35 tons) (number
                          depends on hauled distance)
     2                    Bulldozers (200-300 hp)
     1                    Steel Roller
     2                    Rubber Rollers
     1                    Water Tanker Truck
     1                    Prime/Tack Coat Spreader
     6-8                  Laborers



                                                         20
ASPHALT PAVEMENT
                       Production Rates
    Equipment                       Production Rate
Prime Coat Spreader    2 km of road, full width
Tack Coat Spreader     3 km of road, full width


Asphalt Placing Crew   2,500 tons (1,000 m3) per day – 6 no. 35 tons
                       trucks with hauling distance up to 10 km

 Dump Truck Cycle      Depends on number of trucks, truck capacity,
                       efficiency factor, cycle time

  Production Rate      Usually report on daily or weekly basis



                                                                       21
ASPHLAT TRUCK
 FILLING PAVER




                 22
STEEL ROLLER
FOLLOWING PAVER




                  23
Finished Road




                24
Finished Road




                25
Railways
• There are many similarities
  between railways and
  roads, in the way of
  construction and material
  used, till top of
  embankment level (sub-
  grade for roads and sub-
  ballast for railways)
• Above this level, the
  activities are completely
  different starting with
  ballast and sleepers laying.   26
Bridges
• Bridges can be of different nature and types. They can
  be made of steel, concrete and other materials such as
  stones, timber, etc.
• They can be skew, straight, curved, flat or arched. The
  presentation will be limited to straight concrete
  structured bridges.
• The spans vary between long, medium and short spans.
               Long           50- 350 or more meters
              Medium              30-45 meters
               Short              12-25 meters

                                                        27
Bridges
The deck structure and
method of construction
are dependent on the
span length, pier height
and accessibility.
 • Long span bridges are
   cable stayed.
 • Medium span bridges
   are box girder type.

                           28
Bridge deck types
                               • Example of box girder

• Example of girder and slab




                                                         29
Method of Construction
The substructure:
 • Footings on solid ground or piles
 • Piers with or without a cross head
The superstructure of deck:
 • Girder and slab
 • Box girder
Deck and piers are often in contact via elastomeric
bearings.
Parapets are complementary to the deck. They are
installed/cast subsequent to deck casting             30
Cast-in-situ
box girder deck




                  31
Fragnet for typical
bridge construction




                      32
Fragnet for typical
bridge construction




                      33

Mais conteúdo relacionado

Mais procurados

Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil EngineeringKailash Chander
 
Bituminous mix design.pptx
Bituminous mix design.pptxBituminous mix design.pptx
Bituminous mix design.pptxASHIKBELLARY
 
Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37 Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37 SupriyaPal10
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...Malyar Talash
 
Transportation and highway engineering part 1
Transportation and highway engineering part 1 Transportation and highway engineering part 1
Transportation and highway engineering part 1 GEOMIND
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume studyZawad khalil
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Waste material concrete ppt
Waste material  concrete pptWaste material  concrete ppt
Waste material concrete pptUday Kakde
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
 
Conen 442 module1c: Capacity analysis and Level of Service
Conen  442 module1c: Capacity analysis and Level of ServiceConen  442 module1c: Capacity analysis and Level of Service
Conen 442 module1c: Capacity analysis and Level of ServiceWael ElDessouki
 
Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway RAMPRASAD KUMAWAT
 

Mais procurados (20)

114 site layout
114 site layout114 site layout
114 site layout
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
Unit 3
Unit 3Unit 3
Unit 3
 
Burmister 2 layer
Burmister 2 layerBurmister 2 layer
Burmister 2 layer
 
Bituminous mix design.pptx
Bituminous mix design.pptxBituminous mix design.pptx
Bituminous mix design.pptx
 
Sight distance
Sight distanceSight distance
Sight distance
 
Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37 Design of flexible pavements as per IRC37
Design of flexible pavements as per IRC37
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
 
Transportation and highway engineering part 1
Transportation and highway engineering part 1 Transportation and highway engineering part 1
Transportation and highway engineering part 1
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Waste material concrete ppt
Waste material  concrete pptWaste material  concrete ppt
Waste material concrete ppt
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
Conen 442 module1c: Capacity analysis and Level of Service
Conen  442 module1c: Capacity analysis and Level of ServiceConen  442 module1c: Capacity analysis and Level of Service
Conen 442 module1c: Capacity analysis and Level of Service
 
Soil Compaction
Soil CompactionSoil Compaction
Soil Compaction
 
Canal lining
Canal liningCanal lining
Canal lining
 
Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway
 
Green concrete
Green concreteGreen concrete
Green concrete
 
Valuation
ValuationValuation
Valuation
 

Destaque

1. classification of urban roads 28 jun
1. classification of urban roads 28 jun1. classification of urban roads 28 jun
1. classification of urban roads 28 junPrathamesh Kulkarni
 
The road to breaking bridges and stereotypes
The road to breaking bridges and stereotypesThe road to breaking bridges and stereotypes
The road to breaking bridges and stereotypesEva Lantsoght
 
Resume of Ashwani Tyagi
Resume of Ashwani TyagiResume of Ashwani Tyagi
Resume of Ashwani TyagiAshwani Tyagi
 
TLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 MayTLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 MayRiverFirst Initiative
 
RIMS Update - Bridge Data Guidelines for Asset Management of Road Bridges
RIMS Update - Bridge Data Guidelines for Asset Management of Road BridgesRIMS Update - Bridge Data Guidelines for Asset Management of Road Bridges
RIMS Update - Bridge Data Guidelines for Asset Management of Road BridgesSimon Gough
 
How To Use A Clinometer
How To Use A ClinometerHow To Use A Clinometer
How To Use A Clinometeraltairlahad
 
clinometer
clinometerclinometer
clinometerpatolia
 
Roadway condition presentation grp 04
Roadway condition presentation grp 04Roadway condition presentation grp 04
Roadway condition presentation grp 04Stone Rayhan
 
150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_JavadJavad Akhtar
 
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges Hyeok Jin Choi
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
Bridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics StaticsBridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics StaticsAdibah Hanusi
 
CONSTRUCTION; A406 FLYOVER
CONSTRUCTION; A406 FLYOVERCONSTRUCTION; A406 FLYOVER
CONSTRUCTION; A406 FLYOVERSyed Rizvi
 
Non destructive testing of railway bridges
Non destructive testing of railway bridgesNon destructive testing of railway bridges
Non destructive testing of railway bridgesHarsh Singh
 
Roller compaction machines
Roller compaction machinesRoller compaction machines
Roller compaction machinespradip dangar
 

Destaque (20)

1. classification of urban roads 28 jun
1. classification of urban roads 28 jun1. classification of urban roads 28 jun
1. classification of urban roads 28 jun
 
The road to breaking bridges and stereotypes
The road to breaking bridges and stereotypesThe road to breaking bridges and stereotypes
The road to breaking bridges and stereotypes
 
Resume of Ashwani Tyagi
Resume of Ashwani TyagiResume of Ashwani Tyagi
Resume of Ashwani Tyagi
 
Kamal static road roller
Kamal static road rollerKamal static road roller
Kamal static road roller
 
TLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 MayTLS/KVA RiverFIRST Project Criteria, 24-25 May
TLS/KVA RiverFIRST Project Criteria, 24-25 May
 
Unit 3 integrated hse
Unit 3 integrated hseUnit 3 integrated hse
Unit 3 integrated hse
 
RIMS Update - Bridge Data Guidelines for Asset Management of Road Bridges
RIMS Update - Bridge Data Guidelines for Asset Management of Road BridgesRIMS Update - Bridge Data Guidelines for Asset Management of Road Bridges
RIMS Update - Bridge Data Guidelines for Asset Management of Road Bridges
 
How To Use A Clinometer
How To Use A ClinometerHow To Use A Clinometer
How To Use A Clinometer
 
clinometer
clinometerclinometer
clinometer
 
Roadway condition presentation grp 04
Roadway condition presentation grp 04Roadway condition presentation grp 04
Roadway condition presentation grp 04
 
150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad
 
Road and flyover planning v2.0
Road and flyover planning v2.0Road and flyover planning v2.0
Road and flyover planning v2.0
 
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
Bridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics StaticsBridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics Statics
 
RiverFirst Vision (Final 2012)
RiverFirst Vision (Final 2012)RiverFirst Vision (Final 2012)
RiverFirst Vision (Final 2012)
 
CONSTRUCTION; A406 FLYOVER
CONSTRUCTION; A406 FLYOVERCONSTRUCTION; A406 FLYOVER
CONSTRUCTION; A406 FLYOVER
 
Non destructive testing of railway bridges
Non destructive testing of railway bridgesNon destructive testing of railway bridges
Non destructive testing of railway bridges
 
Roller compaction machines
Roller compaction machinesRoller compaction machines
Roller compaction machines
 
HIGHWAY ppt BY SHASHI SHEKHAR DBGI
HIGHWAY  ppt BY SHASHI SHEKHAR DBGIHIGHWAY  ppt BY SHASHI SHEKHAR DBGI
HIGHWAY ppt BY SHASHI SHEKHAR DBGI
 

Semelhante a J.S. Daniel paper for roads and bridges construction methods & resources

MODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptxMODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptxsurekha1287
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliTauhid Mohammad
 
Presentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptxPresentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptxAyushsharma131736
 
powerpoint nittin bhagat.pptx
powerpoint nittin bhagat.pptxpowerpoint nittin bhagat.pptx
powerpoint nittin bhagat.pptxaps ratnuchak
 
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptxvikrantsingh170151
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipmentTareq Shreehah
 
Drag line excavator
Drag line excavatorDrag line excavator
Drag line excavatorParth Desani
 
labour vs machionary (cep lecture)
labour vs machionary (cep lecture)labour vs machionary (cep lecture)
labour vs machionary (cep lecture)Safiullah Khan
 
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTUVATSAL PATEL
 
EQUIPMENTS USED IN CONCRETE WORKS
EQUIPMENTS USED IN CONCRETE WORKSEQUIPMENTS USED IN CONCRETE WORKS
EQUIPMENTS USED IN CONCRETE WORKSKAPADIARAJ
 
Construction equipment ppt
Construction equipment pptConstruction equipment ppt
Construction equipment pptDINESH TAMBE
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segmentsAxay Sharma
 
construction equipment.pptx
construction equipment.pptxconstruction equipment.pptx
construction equipment.pptxkingbutu
 
chapter 4 construction equipments.pptx
chapter 4  construction equipments.pptxchapter 4  construction equipments.pptx
chapter 4 construction equipments.pptxDine38
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentationATUL SHUKLA
 
Mine 417 Research-WPS Office.pptx
Mine 417 Research-WPS Office.pptxMine 417 Research-WPS Office.pptx
Mine 417 Research-WPS Office.pptxEmmanuelTokpahII
 
CH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].pptCH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].pptRamchandraYadav20
 
Batching plant ppt
Batching plant pptBatching plant ppt
Batching plant pptdip17
 

Semelhante a J.S. Daniel paper for roads and bridges construction methods & resources (20)

MODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptxMODULE 2 Construction Equipment.pptx
MODULE 2 Construction Equipment.pptx
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauli
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Presentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptxPresentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptx
 
powerpoint nittin bhagat.pptx
powerpoint nittin bhagat.pptxpowerpoint nittin bhagat.pptx
powerpoint nittin bhagat.pptx
 
Auxiliary equipment
Auxiliary equipmentAuxiliary equipment
Auxiliary equipment
 
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
1522901342777_constructionequipment-130411074220-phpapp01-1.pptx
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Drag line excavator
Drag line excavatorDrag line excavator
Drag line excavator
 
labour vs machionary (cep lecture)
labour vs machionary (cep lecture)labour vs machionary (cep lecture)
labour vs machionary (cep lecture)
 
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
11. to 14. CONSTRUCTION EQUIPMENTS (ACE) 2160601 GTU
 
EQUIPMENTS USED IN CONCRETE WORKS
EQUIPMENTS USED IN CONCRETE WORKSEQUIPMENTS USED IN CONCRETE WORKS
EQUIPMENTS USED IN CONCRETE WORKS
 
Construction equipment ppt
Construction equipment pptConstruction equipment ppt
Construction equipment ppt
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
construction equipment.pptx
construction equipment.pptxconstruction equipment.pptx
construction equipment.pptx
 
chapter 4 construction equipments.pptx
chapter 4  construction equipments.pptxchapter 4  construction equipments.pptx
chapter 4 construction equipments.pptx
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
 
Mine 417 Research-WPS Office.pptx
Mine 417 Research-WPS Office.pptxMine 417 Research-WPS Office.pptx
Mine 417 Research-WPS Office.pptx
 
CH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].pptCH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].ppt
 
Batching plant ppt
Batching plant pptBatching plant ppt
Batching plant ppt
 

Mais de J.S. Daniel

Planning in French Language
Planning in French LanguagePlanning in French Language
Planning in French LanguageJ.S. Daniel
 
J.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel
 
J.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost managementJ.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost managementJ.S. Daniel
 
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
 
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel
 

Mais de J.S. Daniel (7)

Planning in French Language
Planning in French LanguagePlanning in French Language
Planning in French Language
 
J.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel presentation on planning
J.S. Daniel presentation on planning
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
 
J.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost managementJ.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost management
 
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycle
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
 
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
 

Último

"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 

Último (20)

"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 

J.S. Daniel paper for roads and bridges construction methods & resources

  • 1. Roads and Bridges Construction Methods & resources by: 1 Jihad Daniel
  • 2. Types of Roads • Various types of roads are in use around the world. Roads range in size from private driveways, to the stereotypical two-lane highways, to high capacity dual carriageway routes, such as freeways and motorways. • In addition, depending on their types, roads may have different types of junction. 2
  • 3. Types of Junctions Bridge interchange Intersection Flyover and underpasses Junctions at grade Interchange at grade 3
  • 4. Types of Junctions • Interchange at grade • Intersection at grade 4
  • 5. Types of Junctions • Flyovers • Bridge interchange 5
  • 6. Road Structure • Cross section of a road: main road situated outside towns and cities. • Platform: horizontal surface raised above the surrounding ground. • Shoulder: space between the roadway and the ditch. • Median strip: separation between two carriageway. • Wearing course: surface layer of the road (asphalt). • Carriageway: central part reserved for vehicle traffic. • Ditch: channel that carries away water. 6
  • 7. Road Structure • Subgrade: upper surface of platform. (this is valid in a cut section) • In a Fill Section, the embankment constitute the platform and the subgrade. • Subbase: lower surface of a road structure. • Base course: main foundation element (bituminous / granular). • Wearing Course (Bituminous in general) 7
  • 8. Road Profile • The right of way ground formation maybe, as the road profile requires, natural ground, cut or fill. In case of fill, ground formation is filled in layers to comply with the profile. The work is called embankment. • Embankment is made in layers with thickness varying from 20 to 40 cm depending on the material used. • In case of cut this could be open cut or tunnel. 8
  • 9. Materials Selected Crushed Asphaltic Roads fill aggregate concrete 9
  • 10. Road Furniture and Incidental Works Road furniture refers to all fixtures in the road reserve. The term includes fixtures on the road surface such as: - Signs, - Markings, - Safety barriers, - Road studs, etc. 10
  • 11. Method of Construction The system is based on a monthly output of major work items using the minimum equipment considered necessary to carry out the work during a month of 25 working days, each day being 8 working hours. 11
  • 12. Road works planning criteria • Planning road works, as a first step, depends on the extent of earthmoving quantities. • Generally, the most driving is the fill making the embankment, especially for the case of high embankments. • The basic equipment is as follows: 12
  • 13. Fill From Common Excavation of Borrow Excavation: Basic Equipment for One Work Team No. of Items Item 6 Dump Trucks (8 m3), 12 to 15 Tons 1 Front-end Loader (2m3 bucket) 1 Motor Grader (150 hp) 2 Water Trucks (12 m3) 1 Vibratory Roller (40 kw) 1 Farm Tractor (if roller is not self- propelled) 13
  • 14. Cut & Fill From Common Excavation or Borrow Excavation: Basic Equipment for Two Work Teams No. of Items Item 12 Dump Trucks (8 m3) 2 Front-end Loader (2 m3) 2 Bulldozers (200-300 hp) 3 Motor Grader (150 hp) 2 Vibratory Rollers (40 kw) 6 Water Tanker Trucks (12,000 liters) 2 Farm Tractors (if roller is not self- propelled) 1 Pneumatic Roller (25 mg) 14
  • 15. Production rates Assuming: Number of dump trucks =12 Truck capacity = 8 m3 per truck Average haul distance=1 km (from borrow pit/stockpile to job site) Number of cycles : (Cycle time 8 minutes) Efficiency on truck capacity: 70% Therefore, rate (2 teams) of 100,000 m3/month based on the following use a basic production: Production Rate = 12 x 8 x 60/8 x 0.7 x 25 x 8 = 100,800 m3/month • For quantities up to 1,500,000 m3 use the basic production rate of 100,000 m3/month (2 work teams) • For quantities between 1,500,000 m3 and 2,500,000 m3 adjust the equipment to provide a production rate of 150,000 m3/month (3 work teams) 15
  • 16. Production rates (cont’d) • For quantities greater than 2,500,000 m3 adjust the equipment to provide a minimum production rate of 200,000 m3/month (4 work teams). • The overall monthly production rate shall be adjusted to allow 2 months buildup prior to peak production and 1 month slow down prior to completion of the work. The quantity of embankment placed should be converted in road length terms to enable the planner to define the interface between subsequent activities. (e.g. when to start sub-base activities after embankment) 16
  • 17. Production rates (cont’d) Planning the amount of earthworks and defining the time required to place the whole quantity would be as follows: 1st month 50,000 m3 2nd month 100,000 m3 3rd (last month) 50,000 m3 • Duration = 1500,000 – (50,000 + 100,000 + 50,000) 100,000 = 13 months Using higher capacity trucks and improving efficiency would reduce this duration. 17
  • 18. Bulldozer 18
  • 19. grader 19
  • 20. ASPHALT PAVEMENT Basic Equipment for Two Work Teams No. of Items Item 2 Paver 6-12 Dump Truck (35 tons) (number depends on hauled distance) 2 Bulldozers (200-300 hp) 1 Steel Roller 2 Rubber Rollers 1 Water Tanker Truck 1 Prime/Tack Coat Spreader 6-8 Laborers 20
  • 21. ASPHALT PAVEMENT Production Rates Equipment Production Rate Prime Coat Spreader 2 km of road, full width Tack Coat Spreader 3 km of road, full width Asphalt Placing Crew 2,500 tons (1,000 m3) per day – 6 no. 35 tons trucks with hauling distance up to 10 km Dump Truck Cycle Depends on number of trucks, truck capacity, efficiency factor, cycle time Production Rate Usually report on daily or weekly basis 21
  • 26. Railways • There are many similarities between railways and roads, in the way of construction and material used, till top of embankment level (sub- grade for roads and sub- ballast for railways) • Above this level, the activities are completely different starting with ballast and sleepers laying. 26
  • 27. Bridges • Bridges can be of different nature and types. They can be made of steel, concrete and other materials such as stones, timber, etc. • They can be skew, straight, curved, flat or arched. The presentation will be limited to straight concrete structured bridges. • The spans vary between long, medium and short spans. Long 50- 350 or more meters Medium 30-45 meters Short 12-25 meters 27
  • 28. Bridges The deck structure and method of construction are dependent on the span length, pier height and accessibility. • Long span bridges are cable stayed. • Medium span bridges are box girder type. 28
  • 29. Bridge deck types • Example of box girder • Example of girder and slab 29
  • 30. Method of Construction The substructure: • Footings on solid ground or piles • Piers with or without a cross head The superstructure of deck: • Girder and slab • Box girder Deck and piers are often in contact via elastomeric bearings. Parapets are complementary to the deck. They are installed/cast subsequent to deck casting 30
  • 32. Fragnet for typical bridge construction 32
  • 33. Fragnet for typical bridge construction 33