Chargebacks: Reconciling Primavera Enterprise
Actuals to the General Ledger
Presenters:
Matthew Friedman, Director of Integration Services - EcoSys
Management
Jeffrey Finkiel, Senior Financial Analyst - Guardian Life Insurance
 Primavera Service Provider and Technology
Partner
 Have supported over 130 enterprise project
management Implementations
 EcoSys Financial Manager software: bridges
project management with financial management
 Headquarters in New York; Branch offices in
London, Atlanta, San Francisco
EcoSys Management
 Headquarters in New York City
 $41 Billion including subsidiaries
 5000 employees, 700 in IT, incl. Consultants
 Provider of life, health, disability to individuals
and businesses
 Has rigorously reduced IT spending through
strong financial control
 Fifth largest mutual life insurance company in
US
 85 agencies around the country
Guardian Life Insurance
Agenda - M
Providing Project Accountability via Chargebacks
Primavera Timesheets
& Expenses
• Justification of Costs: Charging back to Department Profit Centers
• How to determine in your GL how to calculate the actual cost of
doing business for a given month, by project
• Reconciliation: From Primavera Timesheets & Expenses to
PeopleSoft General Ledger
PeopleSoft
General Ledger
RECONCILIATION
Guardian Chargeback Rates & Costs
Rates are area specific. E.g. separate rates for Group, Life, Equity, etc.
Outside Svcs. - Emp, Expenses
Based upon the direct expense that needs to be recovered through project work
Method
Matt: See Excel SS (Sheet 2)
Current Guardian Financial Processes
Chargeback costs segregated
Business units split project funding by percentage
Results fed monthly through general ledger
Consolidated bill provided to business units by each IT division
Budgeting process incorporates commitments and targets on spending types (i.e. New
development vs. Production support)
Tying Project Mgt to Financial Results - Overview - M
3. Resources Enter/Submit Timesheets
> Log Tiemsheet Hours to Projects
> Submit Timesheets or
> Revise and Resubmit Timesheets
4. Timesheet Approval by COB Mondays
> RMs Review Timesheet
> RMs Reject/Approve Timesheets or
> RMs Approve Resubmitted Timesheets
$$
4a. Actuals Applied to Projects
by COB Tuesdays
> PMs Apply Timesheet Actuals
> PMs Update Project Plans, if needed
$
$
$
3a. PMs Log Expense Actuals
> Start Activities
> Log Actual Costs
6. Project Plan Updates
> PMs Update/Clarify TeamPlay
Information per Jeff Fikiel's
Email Requests
$
8. General Ledger
> CB App. Dev. Prog. Chargebacks Processed to ABC MainFrame Database
> Reconciled Consultant Invoiced Costs Processed to CDS (Cash Disbursement System)
Pay to
$
4b. VIC Feed
> Consultant Timesheets Fed to Vendor
Invoice Control Interface
> Consultant Timesheets Reconciled to
Received Invoices
8a. CB Reports
> Monthly CB Project Actuals
> Consolidate CB Report
> YTD CB Aanalysis Report
> Spend Type Analysis
7. Financial Manager – Final Run
> Jeff Finkiel Generates Final FM
GL Feed File for FM&C
(PeopleSoft) 5. Financial Manager – Test Run
> Jeff Finkiel Begins 2 Iterations of
FM GL Feed File Test Runs.
> Jeff Finkiel contacts PMs
Required to Resolve Questionable
Entries.
Evolution of a process - M
Better Detail – Can catch many smaller issues.
Police the Projects – beyond the scope of what the CPMO does.
Ease of use for Non-PMs i.e. Finance People
Reports are scalable and easier to manipulate.
Improved Efficiencies from start to finish.
-No need to create individual SQL queries and export to Excel. Than combine
these spreadsheets to come up with the required data that needs to be
validated.
Past Method - MainFrame
Past Method - Remind
Past Method – 1st EcoSys Method - M
Resources enter
timesheets
Project Managers
enter expenses
Resource
timesheets
approv ed
Timesheets applied
to project plan by
project manager
First Business Day of Month: Financial Reporting runs
1) Script to Check Data
2) Run script to execute stored procedure that generates G/L
Feed Records and creates G/L f eed f ile
G/L Feed f ile imported into ABC G/L sy stem by FM&C
which contains chargeouts and chargebacks
Current EcoSys FM Method
Financial Manager (FM) is the financial repository for
Primavera Data
Import Labor Costs and Expenses from Primavera into FM
Costs are Summarized by Budget Category in FM
A Debits/Credits Report Is Generated from FM in a format
ready for Input to PeopleSoft
Graph of 4 Systems – Accuracy & Labor Estimates
Business Days to Complete
14 days
5 days
10 days
2 days
0 2 4 6 8 10 12 14 16
Mainframe System
Remind by Changepoint
EcoSys PM
EcoSys FM
65% Accuracy
85% Accuracy
95% Accuracy
97-99% Accuracy
Questions?
Timesheet to General Ledger - Overview
Resources Records Project Work by COB Fridays
> Log Tiemsheet Hours to Projects
> Submit Timesheets or
> Revise and Resubmit Timesheets
Timesheet Approval by COB Mondays
> RMs Review Timesheet
> RMs Reject/Approve Timesheets or
> RMs Approve Resubmitted Timesheets
$$
Actuals Applied to Projects
by COB Tuesdays
> PMs Apply Timesheet Actuals
> PMs Update Project Plans, if needed
$
$
$
PMs Log Expense Actuals
> Start Activities
> Log Actual Costs
IT Finance Administrator Processes a Test GL Feed
> GL Feed Test Runs.
> Contact PMs Required
to Resolve Questionable Entries.
Project Plan Updates
> PMs Update/Clarify Primavera
Information as per administrators Requests
IT Finance Admintrator Process GL Feed
> Administrator Processes GL Feed File
from EcoSys FM
$
General Ledger
> EcoSys FM generated file is entered into PeoplSoft GL
CB Reports from FM
> Monthly CB Project Actuals
> CB and Non CB Project Costs
> YTD CB Aanalysis Report
> Spend Type Analysis
> Reconciled Consultant Invoiced Costs
7. Financial Manager – Final Run
> Jeff Finkiel Generates Final FM
GL Feed File for FM&C
(PeopleSoft)
5. Financial Manager – Test Run
> Jeff Finkiel Begins 2 Iterations of
FM GL Feed File Test Runs.
> Jeff Finkiel contacts PMs
Required to Resolve Questionable
Entries.
Profit Center Budget Allocations to IT Projects
CB System Timeline – Evolution Slide – SS – SS #1
Mainframe - ~1960’s – Dec. 1999
Changepoint Remind – Jan. 2000 – Dec. 2001
Guardian Purchases Primavera TeamPlay
EcoSys PM (SQL based process) - Jan. 2001 – Dec. 2006
EcoSys Financial Manager – Jan 2007 - Future
Remind System
Here's a screen shot of what the charges were for a project from Remind.
Remind System
Mainframe Method
People entered timesheets into a crude spreadsheet on the MF.
All calculations done through the MF
MF sent file directly to ABC financial system (ABC was the insurance industry standard ledger system)
You were able to enter time to any project in your area.
Only check was a once daily generated report
Adjustments were completely manual
Needed to rely on the MF programmer to make adjustments
Standard reports
Chargebacks - Reconciling Actuals to the General Ledger

Mais conteúdo relacionado

Mais procurados

Quoted Works and Contracts Co-Ordinator - Info
Quoted Works and Contracts Co-Ordinator - InfoQuoted Works and Contracts Co-Ordinator - Info
Quoted Works and Contracts Co-Ordinator - Info
Mabel Reyneke-Fourie
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
TRIslides
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status report
Tom Evans
 

Mais procurados (19)

Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
 
Quoted Works and Contracts Co-Ordinator - Info
Quoted Works and Contracts Co-Ordinator - InfoQuoted Works and Contracts Co-Ordinator - Info
Quoted Works and Contracts Co-Ordinator - Info
 
Completing the Incurred Cost Proposal
Completing the Incurred Cost ProposalCompleting the Incurred Cost Proposal
Completing the Incurred Cost Proposal
 
Europeana Cloud - Progress and Financial Reporting
Europeana Cloud - Progress and Financial ReportingEuropeana Cloud - Progress and Financial Reporting
Europeana Cloud - Progress and Financial Reporting
 
Project cost management a simplified approach white paper - Oracle Primaver...
Project cost management   a simplified approach white paper - Oracle Primaver...Project cost management   a simplified approach white paper - Oracle Primaver...
Project cost management a simplified approach white paper - Oracle Primaver...
 
Accounting System Compliance for Non-Accountants
Accounting System Compliance for Non-AccountantsAccounting System Compliance for Non-Accountants
Accounting System Compliance for Non-Accountants
 
Sage 100Cloud Year-end Processing and Payroll Webinar 2019
Sage 100Cloud Year-end Processing and Payroll Webinar 2019Sage 100Cloud Year-end Processing and Payroll Webinar 2019
Sage 100Cloud Year-end Processing and Payroll Webinar 2019
 
Accounting Systems for Government Contractors
Accounting Systems for Government ContractorsAccounting Systems for Government Contractors
Accounting Systems for Government Contractors
 
2012 Microsoft Dynamics GP Year End Closing
2012 Microsoft Dynamics GP Year End Closing2012 Microsoft Dynamics GP Year End Closing
2012 Microsoft Dynamics GP Year End Closing
 
Maximo Planning & Scheduling - BPD Zenith Presentation
Maximo Planning & Scheduling - BPD Zenith PresentationMaximo Planning & Scheduling - BPD Zenith Presentation
Maximo Planning & Scheduling - BPD Zenith Presentation
 
Generic rlresume
Generic rlresumeGeneric rlresume
Generic rlresume
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Pdg cipmo
Pdg   cipmoPdg   cipmo
Pdg cipmo
 
Dynamics GP Year end close 2015
Dynamics GP Year end close 2015Dynamics GP Year end close 2015
Dynamics GP Year end close 2015
 
Sage 100 year-end Processing Webinar 2020
Sage 100 year-end Processing Webinar 2020Sage 100 year-end Processing Webinar 2020
Sage 100 year-end Processing Webinar 2020
 
Instructions of fill in cash
Instructions of fill in cashInstructions of fill in cash
Instructions of fill in cash
 
Sage Enterprise Management year-end Processing Webinar 2018
Sage Enterprise Management year-end Processing Webinar 2018Sage Enterprise Management year-end Processing Webinar 2018
Sage Enterprise Management year-end Processing Webinar 2018
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status report
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 

Semelhante a Chargebacks - Reconciling Actuals to the General Ledger

Improving the Bottom Line - IT Financial Management Best Practices
Improving the Bottom Line - IT Financial Management Best PracticesImproving the Bottom Line - IT Financial Management Best Practices
Improving the Bottom Line - IT Financial Management Best Practices
Jeffrey Finkiel
 
Leveraging Primavera to Fulfill Financial Management Strategies
Leveraging Primavera to Fulfill Financial Management StrategiesLeveraging Primavera to Fulfill Financial Management Strategies
Leveraging Primavera to Fulfill Financial Management Strategies
Jeffrey Finkiel
 
Vimal Resume v1
Vimal Resume v1Vimal Resume v1
Vimal Resume v1
Vimal Shah
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
RSARAVANAN_Resume
RSARAVANAN_ResumeRSARAVANAN_Resume
RSARAVANAN_Resume
R Saravanan
 

Semelhante a Chargebacks - Reconciling Actuals to the General Ledger (20)

Improving the Bottom Line - IT Financial Management Best Practices
Improving the Bottom Line - IT Financial Management Best PracticesImproving the Bottom Line - IT Financial Management Best Practices
Improving the Bottom Line - IT Financial Management Best Practices
 
Leveraging Primavera to Fulfill Financial Management Strategies
Leveraging Primavera to Fulfill Financial Management StrategiesLeveraging Primavera to Fulfill Financial Management Strategies
Leveraging Primavera to Fulfill Financial Management Strategies
 
Tim Howard
Tim HowardTim Howard
Tim Howard
 
Erp.ppt
Erp.pptErp.ppt
Erp.ppt
 
Capital budgeting techniques in project management
Capital budgeting techniques in project management Capital budgeting techniques in project management
Capital budgeting techniques in project management
 
Intacct Project Accounting and Financials for your Services Business
Intacct Project Accounting and Financials for your Services BusinessIntacct Project Accounting and Financials for your Services Business
Intacct Project Accounting and Financials for your Services Business
 
FM presentation
FM  presentationFM  presentation
FM presentation
 
Resume puja bajaj
Resume puja bajajResume puja bajaj
Resume puja bajaj
 
Resume puja bajaj
Resume puja bajajResume puja bajaj
Resume puja bajaj
 
JDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work OrdersJDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work Orders
 
Resume_Sandeep
Resume_SandeepResume_Sandeep
Resume_Sandeep
 
Vimal Resume v1
Vimal Resume v1Vimal Resume v1
Vimal Resume v1
 
Pallavi Shrivastava- Finance
Pallavi Shrivastava- FinancePallavi Shrivastava- Finance
Pallavi Shrivastava- Finance
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Resume
ResumeResume
Resume
 
British American Tobacco GP Upgrade
British American Tobacco GP UpgradeBritish American Tobacco GP Upgrade
British American Tobacco GP Upgrade
 
Chapter 5: Completing the Account Cycle
Chapter 5: Completing the Account Cycle Chapter 5: Completing the Account Cycle
Chapter 5: Completing the Account Cycle
 
duncan-collins-DC
duncan-collins-DCduncan-collins-DC
duncan-collins-DC
 
RSARAVANAN_Resume
RSARAVANAN_ResumeRSARAVANAN_Resume
RSARAVANAN_Resume
 
My Huffman Design
My Huffman DesignMy Huffman Design
My Huffman Design
 

Chargebacks - Reconciling Actuals to the General Ledger

  • 1. Chargebacks: Reconciling Primavera Enterprise Actuals to the General Ledger Presenters: Matthew Friedman, Director of Integration Services - EcoSys Management Jeffrey Finkiel, Senior Financial Analyst - Guardian Life Insurance
  • 2.  Primavera Service Provider and Technology Partner  Have supported over 130 enterprise project management Implementations  EcoSys Financial Manager software: bridges project management with financial management  Headquarters in New York; Branch offices in London, Atlanta, San Francisco EcoSys Management
  • 3.  Headquarters in New York City  $41 Billion including subsidiaries  5000 employees, 700 in IT, incl. Consultants  Provider of life, health, disability to individuals and businesses  Has rigorously reduced IT spending through strong financial control  Fifth largest mutual life insurance company in US  85 agencies around the country Guardian Life Insurance
  • 5. Providing Project Accountability via Chargebacks Primavera Timesheets & Expenses • Justification of Costs: Charging back to Department Profit Centers • How to determine in your GL how to calculate the actual cost of doing business for a given month, by project • Reconciliation: From Primavera Timesheets & Expenses to PeopleSoft General Ledger PeopleSoft General Ledger RECONCILIATION
  • 6. Guardian Chargeback Rates & Costs Rates are area specific. E.g. separate rates for Group, Life, Equity, etc. Outside Svcs. - Emp, Expenses Based upon the direct expense that needs to be recovered through project work Method Matt: See Excel SS (Sheet 2)
  • 7. Current Guardian Financial Processes Chargeback costs segregated Business units split project funding by percentage Results fed monthly through general ledger Consolidated bill provided to business units by each IT division Budgeting process incorporates commitments and targets on spending types (i.e. New development vs. Production support)
  • 8. Tying Project Mgt to Financial Results - Overview - M 3. Resources Enter/Submit Timesheets > Log Tiemsheet Hours to Projects > Submit Timesheets or > Revise and Resubmit Timesheets 4. Timesheet Approval by COB Mondays > RMs Review Timesheet > RMs Reject/Approve Timesheets or > RMs Approve Resubmitted Timesheets $$ 4a. Actuals Applied to Projects by COB Tuesdays > PMs Apply Timesheet Actuals > PMs Update Project Plans, if needed $ $ $ 3a. PMs Log Expense Actuals > Start Activities > Log Actual Costs 6. Project Plan Updates > PMs Update/Clarify TeamPlay Information per Jeff Fikiel's Email Requests $ 8. General Ledger > CB App. Dev. Prog. Chargebacks Processed to ABC MainFrame Database > Reconciled Consultant Invoiced Costs Processed to CDS (Cash Disbursement System) Pay to $ 4b. VIC Feed > Consultant Timesheets Fed to Vendor Invoice Control Interface > Consultant Timesheets Reconciled to Received Invoices 8a. CB Reports > Monthly CB Project Actuals > Consolidate CB Report > YTD CB Aanalysis Report > Spend Type Analysis 7. Financial Manager – Final Run > Jeff Finkiel Generates Final FM GL Feed File for FM&C (PeopleSoft) 5. Financial Manager – Test Run > Jeff Finkiel Begins 2 Iterations of FM GL Feed File Test Runs. > Jeff Finkiel contacts PMs Required to Resolve Questionable Entries.
  • 9. Evolution of a process - M Better Detail – Can catch many smaller issues. Police the Projects – beyond the scope of what the CPMO does. Ease of use for Non-PMs i.e. Finance People Reports are scalable and easier to manipulate. Improved Efficiencies from start to finish. -No need to create individual SQL queries and export to Excel. Than combine these spreadsheets to come up with the required data that needs to be validated.
  • 10. Past Method - MainFrame
  • 11. Past Method - Remind
  • 12. Past Method – 1st EcoSys Method - M Resources enter timesheets Project Managers enter expenses Resource timesheets approv ed Timesheets applied to project plan by project manager First Business Day of Month: Financial Reporting runs 1) Script to Check Data 2) Run script to execute stored procedure that generates G/L Feed Records and creates G/L f eed f ile G/L Feed f ile imported into ABC G/L sy stem by FM&C which contains chargeouts and chargebacks
  • 14. Financial Manager (FM) is the financial repository for Primavera Data
  • 15. Import Labor Costs and Expenses from Primavera into FM
  • 16. Costs are Summarized by Budget Category in FM
  • 17. A Debits/Credits Report Is Generated from FM in a format ready for Input to PeopleSoft
  • 18. Graph of 4 Systems – Accuracy & Labor Estimates Business Days to Complete 14 days 5 days 10 days 2 days 0 2 4 6 8 10 12 14 16 Mainframe System Remind by Changepoint EcoSys PM EcoSys FM 65% Accuracy 85% Accuracy 95% Accuracy 97-99% Accuracy
  • 20. Timesheet to General Ledger - Overview Resources Records Project Work by COB Fridays > Log Tiemsheet Hours to Projects > Submit Timesheets or > Revise and Resubmit Timesheets Timesheet Approval by COB Mondays > RMs Review Timesheet > RMs Reject/Approve Timesheets or > RMs Approve Resubmitted Timesheets $$ Actuals Applied to Projects by COB Tuesdays > PMs Apply Timesheet Actuals > PMs Update Project Plans, if needed $ $ $ PMs Log Expense Actuals > Start Activities > Log Actual Costs IT Finance Administrator Processes a Test GL Feed > GL Feed Test Runs. > Contact PMs Required to Resolve Questionable Entries. Project Plan Updates > PMs Update/Clarify Primavera Information as per administrators Requests IT Finance Admintrator Process GL Feed > Administrator Processes GL Feed File from EcoSys FM $ General Ledger > EcoSys FM generated file is entered into PeoplSoft GL CB Reports from FM > Monthly CB Project Actuals > CB and Non CB Project Costs > YTD CB Aanalysis Report > Spend Type Analysis > Reconciled Consultant Invoiced Costs 7. Financial Manager – Final Run > Jeff Finkiel Generates Final FM GL Feed File for FM&C (PeopleSoft) 5. Financial Manager – Test Run > Jeff Finkiel Begins 2 Iterations of FM GL Feed File Test Runs. > Jeff Finkiel contacts PMs Required to Resolve Questionable Entries.
  • 21. Profit Center Budget Allocations to IT Projects CB System Timeline – Evolution Slide – SS – SS #1 Mainframe - ~1960’s – Dec. 1999 Changepoint Remind – Jan. 2000 – Dec. 2001 Guardian Purchases Primavera TeamPlay EcoSys PM (SQL based process) - Jan. 2001 – Dec. 2006 EcoSys Financial Manager – Jan 2007 - Future
  • 23. Here's a screen shot of what the charges were for a project from Remind. Remind System
  • 24. Mainframe Method People entered timesheets into a crude spreadsheet on the MF. All calculations done through the MF MF sent file directly to ABC financial system (ABC was the insurance industry standard ledger system) You were able to enter time to any project in your area. Only check was a once daily generated report Adjustments were completely manual Needed to rely on the MF programmer to make adjustments Standard reports