Clean Water Facility
City Council Workshop – March 5, 2018
• Project Summary
• Clean Water Facility Update
• City Council Questions
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 2
• 2008 Sewer Comp Plan indicates
need for new wastewater treatment
plant by 2017
• 2010 NPDES permit included a
deadline for developing a facilities
plan
Project Summary
3/5/2018City Council Workshop 3
• 2013 Facilities Plan accepted by DOE
and adopted by City Council
• 2014 Former Whidbey Island Bank
building purchased to locate new
plant
• 2015 Construction begins
Project Summary
3/5/2018City Council Workshop 4
• Project Summary
• Clean Water Facility Update
• City Council Questions
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 5
1. What caused our last final cost estimate of $121.9
million to be underestimated?
2. Please reconcile and outline the budgets for GMPs
10 through 13.
3. What was the reference to the $2 million over
budget in the GMP#11 presentation?
City Council Questions
from 2/15 workshop
3/5/2018City Council Workshop 6
4. How are we going to pay for the increase in cost?
5. How will bonding affect our debt ratios and bond
ratings going forward?
6. How will taking more loans effect our debt ratios
and credit ratings? Will it take longer to repay the
loans?
City Council Questions
3/5/2018City Council Workshop 7
7. Going forward, please provide a chart showing:
• What we’ve contracted to spend
• What we have actually spent
• Same for soft costs
• Estimates for any [work] not yet contracted
• How has project contingency been used?
City Council Questions
3/5/2018City Council Workshop 8
8. What is the plan going forward to keep a tight rein
on costs?
9. When has information been presented about the
cost increases?
10.As often as we give a report, make sure all costs
are included and described.
City Council Questions
3/5/2018City Council Workshop 9
11.What will the monthly rate be, if known?
12.How will work in Windjammer Park affect events?
City Council Questions
3/5/2018City Council Workshop 10
• Project Summary
• Clean Water Facility Update
• City Council Questions
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 11
• What is GC/CM?
• Alternative to Design-bid-build
• The project must be approved by the state
• Introduces the contractor early in the project
• Majority of work competitively bid
• Guaranteed Maximum Price = GMP
• GMP components are not Change Orders
• GMP is a component of an overall scope of work
General Contractor /
Construction Manager
3/5/2018City Council Workshop 12
• Why did we choose GC/CM?
• Concerns about cultural resources in the area
• Early equipment procurement
• Complex site conditions
• Better value for the City
• Ability to manage project risk sooner
General Contractor /
Construction Manager
3/5/2018City Council Workshop 13
• Design-Bid-Build – Traditional Public Works Process
• General Contractor / Construction Manager (GC/CM)
– Alternative Public Works Process
General Contractor /
Construction Manager
Design Bid Build
Design
Bring on Contractor
Build
3/5/2018City Council Workshop 14
• Has it worked? YES!
• Allowed early site exploration
• Started deep excavation before design was complete
• Reserved the crane before Seattle construction boom
• Relocated odor control facilities to the north
• Early bidding to beat red hot construction market
• Allowed City to secure low interest funding in stages
over multiple years
General Contractor /
Construction Manager
3/5/2018City Council Workshop 15
• Has it worked? YES! (Cont.)
• Self performed work (Heavy Civil)
• Early site work to address cultural resource concerns
• Early equipment procurement
• MBR / UV / Dryer
• Allowed engineers to design around specific equipment
• Concrete work (no bids on GMP 8)
• Admin Building Framing (received zero bids – TWICE!)
General Contractor /
Construction Manager
3/5/2018City Council Workshop 16
• Project Summary
• Clean Water Facility Update
• City Council Questions
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 17
3/5/2018City Council Workshop 18
We are here
3/5/2018City Council Workshop 19
We are here
If this project was Design-
Bid-Build we wouldn’t
have bid the project until
here
3/5/2018City Council Workshop 20
March 2016
January 2017
January 2018
• City Beach Street will be closed for reconstruction
• Restrooms and kitchen will be closed
• Access to Windjammer Park will be limited
• Increased communications with City Council
• Community notifications and updates will continue
• Ribbon cutting celebration
What to Expect in 2018
3/5/2018City Council Workshop 21
• Project Summary
• Clean Water Facility Update
• City Council Questions
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 22
• When we started the project our finance software was not set up
for project cost tracking
• BARS ≠ Project Cost Tracking
• City’s process for project cost reporting was not set up for a multi-
year project of this complexity and magnitude
• Initial project cost tracking was performed by KBA
• Costs were reconciled with City’s financial system at the end 2016
• Initially, total project budgeted cost was difficult to track or predict
Project Cost Tracking
3/5/2018City Council Workshop 23
• Acquisitions (e.g., real property, property leases, etc.)
• Administration
• Finance
• Professional Services - Design
• Professional Services - Construction
• Construction
Cost Categories
3/5/2018City Council Workshop 24
• The following items are not included in the total project cost:
• Facilities Plan / Engineering Report
• Planning documents are not typically included in the total project cost
• Outfall Design and Construction
• The outfall had collapsed and would have been repaired regardless
• Windjammer Park Phase 1 elements funded by General Fund
• Elements of Phase 1 not required by permit
Not Included!
3/5/2018City Council Workshop 25
• Definitions for presentation
• Contracted/Estimated Budget= Contracted &
Estimated Costs
• Expenses thru 1/31/2018 = Invoices for work
performed through January 2018
• Balance = Remainder to be spent on project
Project Costs Glossary
3/5/2018City Council Workshop 26
Total Estimated Project Costs
3/5/2018City Council Workshop 27
ACQUISITIONS
$3,396,326
ADMINISTRATI
ON
$692,852
FINANCE
$258,638
PROFESSIONAL
SERVICES DESIGN
$9,446,427
PROFESSIONAL
SERVICES
CONSTRUCTION…
CONSTRUCTIO
N
$116,738,781
$140,725,906
Contracted/Estimated Budget
3/5/2018City Council Workshop 28
CONTRACTED/ESTIMATED
BUDGET
$49,947,187
35%
Thru 1/31/2018
$90,778,718
65%
$140,725,906
Estimated Project Budget vs. Actual
3/5/2018City Council Workshop 29
CATEGORY
CONTRACTED /
ESTIMATED
BUDGET
ACTUAL THRU
1/31/2018
REMAINING
BALANCE
BUDGE
T % of
CONST
ACQUISITIONS $3,396,326 3,349,689 $46,636 2.9%
ADMINISTRATION $692,852 $461,262 $231,590 0.6%
FINANCE $258,638 $216,173 $42,466 0.2%
PROFESSIONAL
SERVICES DESIGN $10,191,582 $6,521,947 $3,669,635 8.7%
PROFESSIONAL
SERVICES
CONSTRUCTION $9,447,727 $9,233,605 $214,122 8.1%
CONSTRUCTION $116,738,781 $70,996,042 $45,742,739
TOTAL $140,725,906 $90,778,718 $49,947,188
Total Estimated Project Costs
3/5/2018City Council Workshop 30
CATEGORY
Sept 2016
Estimate
Jan 2018
Estimate
ACQUISITIONS $3,496,000 $3,396,326
ADMINISTRATION $12,000 $692,852
FINANCE $879,000 $258,638
PROFESSIONAL SERVICES DESIGN $9,515,000 $9,446,427
PROFESSIONAL SERVICES
CONSTRUCTION $10,093,000 $10,191,582
CONSTRUCTION $97,997,000 $116,740,081
TOTAL $121,992,000 $140,725,906
Why have costs changed?
3/5/2018City Council Workshop 31
• Facilities Plan Adoption
• Included ±55 acres
• Freund property added
late in the process
• Did not account for
specific site conditions
Why have costs changed?
3/5/2018City Council Workshop 32
• 30% CWF Design – 4/7/15
• EI&C Increased to high end estimate
• Site size reduced
• Different solids handling
• City Beach Street
• Bayshore Drive included
• 200-seat training facility
• Park not included
• Whidbey Island Bank demo not included
4/7/2015
$135M Estimated Total Project Cost
Using Hoffman’s 30% Estimate
Why have costs changed?
3/5/2018City Council Workshop 33
• 60% CWF Design – 9/30/15
• Reduced deep-ex footprint
• Combined buildings
• Greater detail in drawings
• Better vendor quotes
• Completed Site Prep A
• Confirmed soils
• Mitigation not included
• Selected different dryer
9/30/2015$131M Estimated Total Project Cost
Using Hoffman’s 60% Estimate
Why have costs changed?
3/5/2018City Council Workshop 34
• 90% CWF Design – 9/27/16
• Reconfigured MBR sump
• Deleted 98 stone columns
by moving odor control
• Includes some work outside
CWF footprint
• Park mitigation not designed
• Odor control design not
complete 9/27/2016
$122M Estimated Total Project Cost
Using Hoffman’s June 2016 Estimate
Why have costs changed?
3/5/2018City Council Workshop 35
• March 5, 2018
• Historically, previous estimates had different assumptions
• May or may not have included type of solids handling,
Bayshore extension, removal of bank building, Windjammer
Phase 1, etc.
• GMPs 10, 11 & 12 were competitively bid in a hot market
• Dramatic cost increases in Seattle market, drew bidders
and workforce away from Oak Harbor
• Unanticipated cost increase in materials
Why have costs changed?
3/5/2018City Council Workshop 36
• Estimated direct cost vs. bid results
Sept 16 Est. Award Difference
GMP 10 – Concrete #3 $ 3,047,680 $4,809,815 $ 1,762,135
GMP 11 -
Superstructure
$ 11,492,566 $ 17,934,490 $ 6,442,049
GMP 12 – Odor Control $ 1,728,659 $ 3,957,515 $ 2,228,856
Total $ 16,268,905 $ 26,701,820 $ 10,433,040*Reflects comparison of bids received and their respective estimates.
Estimate prepared in June 2016 and awarded Dec 2016 to Feb 2016
Why have costs changed?
3/5/2018City Council Workshop 37
• Estimated direct cost vs. bid results
Sept 16 Est. Estimated Difference
GMP 10, 11, 12 $ 16,268,905 $ 26,701,820 $ 10,433,040
Windjammer Park Ph 1 $ 3,000,000 $ 5,300,000 $ 2,300,000
Subtotal $ 12,733,040
Risk Contingency 3.5% $ 445,656
Owner Contingency 2.5% $ 318,326
Tax 8.7% $ 1,174,241
Total $ 14,671,263
• Cost increases have been reflected in every GMP
contract component and consultant amendment
presented at various workshops and council meetings
• Total Project Cost could have been communicated
better, but every amendment included a summary for
that contract (Hoffman, Carollo, ERCI, KBA, etc.)
• Staff intends to improve how we communicate the
Total Project Cost
When has information been
presented about cost increases?
3/5/2018City Council Workshop 38
• All GMPs were competitively bid or negotiated with third
party validation
• The following items were negotiated with Hoffman:
• Negotiated Support Services (Crane rental, survey, etc.)
• Early equipment procurement (MBR, UV, Dryer)
• Based on competitive cost proposals
• Transferred risk to Hoffman
• Concrete work
• Some site work related to Archaeology
• Bid packages where no bids were received
How are project costs managed?
3/5/2018City Council Workshop 39
• All invoices are checked by:
• KBA
• Project Manager
• City Engineer
• Finance
• Dept of Ecology (if submitted for reimbursement)
• RCW requires an audit of the project at end of project
• Dept of Ecology loans require single audit yearly (fed and state)
• 2 years of clean audits
How are project costs managed?
3/5/2018City Council Workshop 40
• Two types of contingencies in Hoffman contract
• Risk Contingency – for scope gap between GMPs and subcontracts
• Owner Contingency – for owner responsible changes
• Contingencies are tracked with Construction Change
Memorandums
• Cost savings transferred to Contingency
• Unused Risk and Owner Contingencies returned to City
• Unused Negotiated Support Services will be returned to City
How have contingencies been used?
3/5/2018City Council Workshop 41
• A contingency can be added to or deducted
• For example…
• CCM73 – Reduced underdrain for deep foundation.
Lower $175,379
• CCM77 - Modified micro-piles for soil conditions.
Increased cost by $75,000, but saved $650,000 if we
had continued down that path.
How have contingencies been used?
3/5/2018City Council Workshop 42
• A contingency can be added to or deducted from
• For example…
• Reduced underdrain for deep foundation. Lower
$175,379
• Modified micro-piles for soil conditions (reduced
micro-pile depth). Lowered cost by $650,000
How have contingencies been used?
3/5/2018City Council Workshop 43
• What is the balance of the contingencies as of
January 15, 2018?
How have contingencies been used?
3/5/2018City Council Workshop 44
Contracted Available
Risk Contingency $ 3,087,525 $ 2,308,350
Owner
Contingency
$ 1,587,993 $ 92,620
Total $ 4,675,518 $ 2,400,970
Working on credits of ±$550,000
to the Owners Contingency
• City Council Workshop Questions
• Clean Water Facility Update
• Project Summary
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 45
• The effective interest rate has decreased
• City initially considered 20 year bonds at 6%
• As the project progressed we considered 30 year bonds
• Completion of the Facilities Plan allowed the City to apply for
State Revolving Fund loans through DOE
• Through a series of competitive applications, the City was
able to obtain low interest loans, forgivable principal on loans
and grants that have reduced the lifetime cost of the project
Project Funding
3/5/2018City Council Workshop 46
Funding Source Amount Term (yrs) Rate
2015 SRF $8,260,000 20 2.70%
Revenue Bonds $25,720,000 30 3.43%
2016 SRF - Loan $15,631,331 20 1.90%
2016 SRF - Forgivable $463,154
2016 SRF – Centennial Grant $4,586,846
2016 DOC – Grant $2,450,000
.09 Funds - Grant $1,000,000
2017 SRF $44,766,854 20 1.60%
2018 SRF $29,124,301 20 1.20%
Sewer / SDF Cash $8,673,420
Total $140,725,906
Project Funding
3/5/2018City Council Workshop 47
• Obtaining State Revolving Fund (SRF) loans has reduced
the need to obtain additional revenue bonds
• Low interest SRF loans @ 20 years will result in a lower
lifetime cost than if we issued bonds
• Grant Funding of $8,500,000 ~ requires no repayment
• Revenue bonds will not impact our ability to obtain
general obligation bonds in the future
How will the proposed funding
impact the City?
3/5/2018City Council Workshop 48
• City Council Workshop Questions
• Clean Water Facility Update
• Project Summary
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 49
• Rates are determined for the entire sewer fund
• Clean Water Facility
• RBC Plant (going away)
• Lagoons (turning over to Navy)
• Citywide Collections
• Capital Projects
• Citywide Operations & Maintenance
Rates
3/5/2018City Council Workshop 50
Rate
O&M
Funding
Capital
Projects
Rates – 2010 Estimated
3/5/2018City Council Workshop 51
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
$40.00 $42.00
$47.00
$52.00
$57.50
$64.75
$72.85
$81.95
$92.20
$-
$10
$20
$30
$40
$50
$60
$70
$80
$90
$100
ResidentialUtilityRate
Rate estimate based on $70M
treatment plant at Lagoon site
with less capacity.
Bonds 20 yrs @ 6%
Rates – 2010 Adopted
3/5/2018City Council Workshop 52
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75
$40.00 $42.00
$47.00
$52.00
$57.50
$64.75
$-
$10
$20
$30
$40
$50
$60
$70
$80
$90
$100
ResidentialUtilityRate
Ordinance 1587
adopted first 6 years
Rates – March 2016 Estimated
3/5/2018City Council Workshop 53
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75
March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90
$77.70
$89.36
$102.76
$118.17
$135.90
$-
$20
$40
$60
$80
$100
$120
$140
$160
ResidentialUtilityRate
Rates were evaluated in March 2016
in preparation for acquiring bonds
based on an MBR facility and a
$120M Estimated Total Project Cost
Rates – March 2016 Adopted
3/5/2018City Council Workshop 54
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75
March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90
2016 Ord 1760 $77.70 $89.36 $102.76
$77.70
$89.36
$102.76
$-
$20
$40
$60
$80
$100
$120
$140
$160
ResidentialUtilityRate
Ordinance 1760
Adopted 3 years of the March
2016 estimate
Rates – Sept 2016 Estimated
3/5/2018City Council Workshop 55
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75
March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90
2016 Ord 1760 $77.70 $89.36 $102.76
Sept '16 Estimate $77.70 $89.36 $102.76 $110.98 $119.86
$77.70
$89.36
$102.76
$110.98
$119.86
$-
$20
$40
$60
$80
$100
$120
$140
$160
ResidentialUtilityRate
In Sept 2016, rates were checked
with new funding and an Estimated
Total Project Cost of $121.9M
Rates – January 2018 Estimated
3/5/2018City Council Workshop 56
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20
2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75
March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90
2016 Ord 1760 $77.70 $89.36 $102.76
Sept '16 Estimate $77.70 $89.36 $102.76 $110.98 $119.86
Jan '18 Estimate $77.70 $89.36 $102.76 $106.36 $110.08
$77.70
$89.36
$102.76 $106.36 $110.08
$-
$20
$40
$60
$80
$100
$120
$140
$160
ResidentialUtilityRate
In January 2018, rates were checked
with current funding and an
Estimated Total Project Cost of
$140M
• After construction is complete
• Will be adopted before Ordinance 1760 expires
• Will likely be for an additional 3-year period
• May be impacted by Navy participation
Next Rate Adjustment
3/5/2018City Council Workshop 57
• Even though the project cost has increased, active
pursuit of additional low cost funding has maintained a
rate consistent with past projections and allowed the
City to construct a project that will serve the city for the
next 40-50 years.
Rate Summary
3/5/2018City Council Workshop 58Rate
O&M
Fundin
g
Capital
Project
s
• City Council Workshop Questions
• Clean Water Facility Update
• Project Summary
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 59
• Agenda
• Windjammer Park Integration Plan
• What is included?
• Schedule
• Current design/construction status
• Anticipated cost
• Funding
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 60
3/5/2018 61
Windjammer Park Integration Plan
• Public feedback
• Community Advisory Group
• 17 members representing diverse
community interests
• 5 meetings
• Endorsed final plan
• 2 in-person and online public
meetings
City Council Workshop
62
Decembe
r 2015
Januar
y 2016
February
2016
March
2016
April
2016
May/
June
2016
Council and CAG Process
• Provide
feedback on 3
concept
alternatives
• Present WPIP
concept to
community
• Gather community
feedback (Public
Open House and
Online Open
House)
• Review preferred
plan to be
presented to City
Council
• Provide final
feedback
• CAG forms
• CAG provides
feedback on
design
guidelines
• Introduce CAG
and WPIP to
community
• Gather
community
feedback (Public
Open House)
COUNCIL
• Programming
priorities
• Approves CAG
COUNCIL
Report:
Alternatives and
Public feedback
COUNCIL
Approves plan
COUNCIL
CAG formation update
and initial priorities list/
design guidelines
3/5/2018






 





City Council Workshop
Proposed
Phase 1
3/5/2018 63
Original Phase
1
To include
part of
Phase 2 & 3
City Council Workshop
Windjammer Park Phase 1
3/5/2018 64
• Includes Clean Water
Facility mitigation and
restoration
• November 15, 2016 –
City Council amended
Carollo’s contract to
include design
City Council Workshop
Windjammer Park Phase 1
Open House
3/5/2018 65
• 167 community members attended
in-person and online open houses in
January 2017
• 97 community members provided
input on park character and theme
City Council Workshop
• What does this include?
• Everything outside the Clean Water Facility within Phase 1!
• Demolition of the former Whidbey Island Bank building
• Improvements to City Beach Street
• New kitchens and restrooms
• Pathways and landscaping
• Splash park!
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 66
3/5/2018City Council Workshop 67
Sport
Courts
Maintenanc
e Building
Increased Interior
Space
Removed
Fireplace
Removed Path
Increased Number
of Garry Oak
TreesWhat has
changed
since
60%
design?
• Current design/construction status
• Design complete
• Design split into 7 bid packages
• Bid opening on 5 packages March 1, 2018
• Water play area and feature bid opening March 15, 2018
• Vehicle and pedestrian gates bid opening on March 22, 2018
• Construction through Spring 2019
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 68
• Anticipated cost
• 60% Design Cost Estimate ~ $10M to $15M
• Design broken into 7 bid packages to maximize
competition and local participation
• Packages further broken into schedules to allow City
flexibility in choosing which ones to construct at this
time
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 69
70 3/5/2018City Council Workshop
71 3/5/2018City Council Workshop
72 3/5/2018City Council Workshop
• Available Sewer Funds = $5.3M
• For work around Clean Water Facility
• Restoration of disturbed areas
• Mitigation of impacts on the park
• Permit requirements
• East side kitchen and restrooms
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 73
• Available General Funds = ?
• Splash park
• Plaza / Pavilion
• West Kitchen
• Additional Paths
• Landscaping
• Maintenance Facility
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 74
Will likely need
to pick and
choose which
elective items
are constructed
• Potential funding gap
• Bids will likely exceed secured funding to complete non-
CWF improvements
• What can we do?
• Design has been split into multiple bid packages
• Release more general fund dollars to complete project
• Postpone some improvement and seek additional outside
funding
Windjammer Park
Phase 1 Update
3/5/2018City Council Workshop 75
• 2018 events may need to be held elsewhere
• Planning to move RV Dump Station to a new location
• Planning for Windmill relocation and future phases
• Waterfront trail will remain open
• Conversations about construction sequencing
• Community notifications and updates
What to Expect in 2018
3/5/2018City Council Workshop 76
What to Expect in 2018
3/5/2018City Council Workshop 77
• City Council Workshop Questions
• Clean Water Facility Update
• Project Summary
• GC/CM Delivery Method Review
• Schedule
• Current Project Cost Estimate
• Funding
• Rates
• Windjammer Park Phase 1
• Next Steps and Questions
Agenda
3/5/2018City Council Workshop 78
• Improve communications with City Council
• Monthly update – second council meeting
• Total Project Cost summary every council meeting
• Continue to seek ways to keep project cost and rates
down
• Continue communicating with community
• Workshop in March to discuss park improvements
Next Steps
3/5/2018City Council Workshop 79
Questions?
3/5/2018City Council Workshop 80
3/5/2018City Council Workshop 81

Mais conteúdo relacionado

Mais procurados

Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
Crosstown TO
 
Final Design Presentation
Final Design PresentationFinal Design Presentation
Final Design Presentation
Brian Weaver
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 

Mais procurados (20)

DURBAN PORT COMMITTEE - 20 April
 DURBAN PORT COMMITTEE - 20 April DURBAN PORT COMMITTEE - 20 April
DURBAN PORT COMMITTEE - 20 April
 
Lick Creek Trail Restoration
Lick Creek Trail RestorationLick Creek Trail Restoration
Lick Creek Trail Restoration
 
State of the City of Norman
State of the City of NormanState of the City of Norman
State of the City of Norman
 
Greenway to Park Conversion
Greenway to Park ConversionGreenway to Park Conversion
Greenway to Park Conversion
 
City Council November 20, 2012 Finance
City Council November 20, 2012 FinanceCity Council November 20, 2012 Finance
City Council November 20, 2012 Finance
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Northgate Surface Parking Lot Special Events
Northgate Surface Parking Lot Special EventsNorthgate Surface Parking Lot Special Events
Northgate Surface Parking Lot Special Events
 
2019 MATC Intern Program - Jacob Hudgens
2019 MATC Intern Program - Jacob Hudgens2019 MATC Intern Program - Jacob Hudgens
2019 MATC Intern Program - Jacob Hudgens
 
Final Design Presentation
Final Design PresentationFinal Design Presentation
Final Design Presentation
 
Wastewater Master Plan Update
Wastewater Master Plan UpdateWastewater Master Plan Update
Wastewater Master Plan Update
 
Item #14 ppt ah pool
Item #14  ppt ah poolItem #14  ppt ah pool
Item #14 ppt ah pool
 
Athens sinking fund 2016 boe update 03 21 2016
Athens sinking fund 2016 boe update 03 21 2016Athens sinking fund 2016 boe update 03 21 2016
Athens sinking fund 2016 boe update 03 21 2016
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
 
DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)
 
Annual Review of Comprehensive Plan and UDO
Annual Review of Comprehensive Plan and UDOAnnual Review of Comprehensive Plan and UDO
Annual Review of Comprehensive Plan and UDO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 

Semelhante a Clean Water Facility Update

Planning Performance Agreements use in Islington Council
Planning Performance Agreements use in Islington CouncilPlanning Performance Agreements use in Islington Council
Planning Performance Agreements use in Islington Council
PAS_Team
 
Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016
Anil Kumar Gupta
 

Semelhante a Clean Water Facility Update (20)

Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13
 
Bemidji Guaranteed Energy Savings Program
Bemidji Guaranteed Energy Savings ProgramBemidji Guaranteed Energy Savings Program
Bemidji Guaranteed Energy Savings Program
 
A5 Form Based Codes
A5 Form Based CodesA5 Form Based Codes
A5 Form Based Codes
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Recent Projects/Portfolio
Recent Projects/PortfolioRecent Projects/Portfolio
Recent Projects/Portfolio
 
Cookham Wood Lean & Mean Jane Foulkes
Cookham Wood  Lean & Mean Jane FoulkesCookham Wood  Lean & Mean Jane Foulkes
Cookham Wood Lean & Mean Jane Foulkes
 
The Commercial Energy Codes Support Program
The Commercial Energy Codes Support ProgramThe Commercial Energy Codes Support Program
The Commercial Energy Codes Support Program
 
Corporate member event September 2015, BIM and Soft Landings
Corporate member event September 2015, BIM and Soft LandingsCorporate member event September 2015, BIM and Soft Landings
Corporate member event September 2015, BIM and Soft Landings
 
Fy 19 PPT Administration and Finance
Fy 19 PPT Administration and FinanceFy 19 PPT Administration and Finance
Fy 19 PPT Administration and Finance
 
Chicago main tif presentation - city council august 13, 2012
Chicago main tif presentation - city council august 13, 2012Chicago main tif presentation - city council august 13, 2012
Chicago main tif presentation - city council august 13, 2012
 
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
Using BIM in Small Architectural Practices: Barriers and Benefits for Retrofi...
 
Northgate District Study & Plan
Northgate District Study & PlanNorthgate District Study & Plan
Northgate District Study & Plan
 
Developer's Forum - RSTF Update Final Report
Developer's Forum - RSTF Update Final ReportDeveloper's Forum - RSTF Update Final Report
Developer's Forum - RSTF Update Final Report
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
 
Planning Performance Agreements use in Islington Council
Planning Performance Agreements use in Islington CouncilPlanning Performance Agreements use in Islington Council
Planning Performance Agreements use in Islington Council
 
Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016
 
Cost effective construction and green building
Cost effective construction and green buildingCost effective construction and green building
Cost effective construction and green building
 
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
 
NVBIA NAIOP Update July 14, 2016
NVBIA NAIOP Update July 14, 2016NVBIA NAIOP Update July 14, 2016
NVBIA NAIOP Update July 14, 2016
 

Último

Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 

Último (20)

The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 

Clean Water Facility Update

  • 1. Clean Water Facility City Council Workshop – March 5, 2018
  • 2. • Project Summary • Clean Water Facility Update • City Council Questions • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 2
  • 3. • 2008 Sewer Comp Plan indicates need for new wastewater treatment plant by 2017 • 2010 NPDES permit included a deadline for developing a facilities plan Project Summary 3/5/2018City Council Workshop 3
  • 4. • 2013 Facilities Plan accepted by DOE and adopted by City Council • 2014 Former Whidbey Island Bank building purchased to locate new plant • 2015 Construction begins Project Summary 3/5/2018City Council Workshop 4
  • 5. • Project Summary • Clean Water Facility Update • City Council Questions • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 5
  • 6. 1. What caused our last final cost estimate of $121.9 million to be underestimated? 2. Please reconcile and outline the budgets for GMPs 10 through 13. 3. What was the reference to the $2 million over budget in the GMP#11 presentation? City Council Questions from 2/15 workshop 3/5/2018City Council Workshop 6
  • 7. 4. How are we going to pay for the increase in cost? 5. How will bonding affect our debt ratios and bond ratings going forward? 6. How will taking more loans effect our debt ratios and credit ratings? Will it take longer to repay the loans? City Council Questions 3/5/2018City Council Workshop 7
  • 8. 7. Going forward, please provide a chart showing: • What we’ve contracted to spend • What we have actually spent • Same for soft costs • Estimates for any [work] not yet contracted • How has project contingency been used? City Council Questions 3/5/2018City Council Workshop 8
  • 9. 8. What is the plan going forward to keep a tight rein on costs? 9. When has information been presented about the cost increases? 10.As often as we give a report, make sure all costs are included and described. City Council Questions 3/5/2018City Council Workshop 9
  • 10. 11.What will the monthly rate be, if known? 12.How will work in Windjammer Park affect events? City Council Questions 3/5/2018City Council Workshop 10
  • 11. • Project Summary • Clean Water Facility Update • City Council Questions • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 11
  • 12. • What is GC/CM? • Alternative to Design-bid-build • The project must be approved by the state • Introduces the contractor early in the project • Majority of work competitively bid • Guaranteed Maximum Price = GMP • GMP components are not Change Orders • GMP is a component of an overall scope of work General Contractor / Construction Manager 3/5/2018City Council Workshop 12
  • 13. • Why did we choose GC/CM? • Concerns about cultural resources in the area • Early equipment procurement • Complex site conditions • Better value for the City • Ability to manage project risk sooner General Contractor / Construction Manager 3/5/2018City Council Workshop 13
  • 14. • Design-Bid-Build – Traditional Public Works Process • General Contractor / Construction Manager (GC/CM) – Alternative Public Works Process General Contractor / Construction Manager Design Bid Build Design Bring on Contractor Build 3/5/2018City Council Workshop 14
  • 15. • Has it worked? YES! • Allowed early site exploration • Started deep excavation before design was complete • Reserved the crane before Seattle construction boom • Relocated odor control facilities to the north • Early bidding to beat red hot construction market • Allowed City to secure low interest funding in stages over multiple years General Contractor / Construction Manager 3/5/2018City Council Workshop 15
  • 16. • Has it worked? YES! (Cont.) • Self performed work (Heavy Civil) • Early site work to address cultural resource concerns • Early equipment procurement • MBR / UV / Dryer • Allowed engineers to design around specific equipment • Concrete work (no bids on GMP 8) • Admin Building Framing (received zero bids – TWICE!) General Contractor / Construction Manager 3/5/2018City Council Workshop 16
  • 17. • Project Summary • Clean Water Facility Update • City Council Questions • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 17
  • 19. 3/5/2018City Council Workshop 19 We are here If this project was Design- Bid-Build we wouldn’t have bid the project until here
  • 20. 3/5/2018City Council Workshop 20 March 2016 January 2017 January 2018
  • 21. • City Beach Street will be closed for reconstruction • Restrooms and kitchen will be closed • Access to Windjammer Park will be limited • Increased communications with City Council • Community notifications and updates will continue • Ribbon cutting celebration What to Expect in 2018 3/5/2018City Council Workshop 21
  • 22. • Project Summary • Clean Water Facility Update • City Council Questions • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 22
  • 23. • When we started the project our finance software was not set up for project cost tracking • BARS ≠ Project Cost Tracking • City’s process for project cost reporting was not set up for a multi- year project of this complexity and magnitude • Initial project cost tracking was performed by KBA • Costs were reconciled with City’s financial system at the end 2016 • Initially, total project budgeted cost was difficult to track or predict Project Cost Tracking 3/5/2018City Council Workshop 23
  • 24. • Acquisitions (e.g., real property, property leases, etc.) • Administration • Finance • Professional Services - Design • Professional Services - Construction • Construction Cost Categories 3/5/2018City Council Workshop 24
  • 25. • The following items are not included in the total project cost: • Facilities Plan / Engineering Report • Planning documents are not typically included in the total project cost • Outfall Design and Construction • The outfall had collapsed and would have been repaired regardless • Windjammer Park Phase 1 elements funded by General Fund • Elements of Phase 1 not required by permit Not Included! 3/5/2018City Council Workshop 25
  • 26. • Definitions for presentation • Contracted/Estimated Budget= Contracted & Estimated Costs • Expenses thru 1/31/2018 = Invoices for work performed through January 2018 • Balance = Remainder to be spent on project Project Costs Glossary 3/5/2018City Council Workshop 26
  • 27. Total Estimated Project Costs 3/5/2018City Council Workshop 27 ACQUISITIONS $3,396,326 ADMINISTRATI ON $692,852 FINANCE $258,638 PROFESSIONAL SERVICES DESIGN $9,446,427 PROFESSIONAL SERVICES CONSTRUCTION… CONSTRUCTIO N $116,738,781 $140,725,906
  • 28. Contracted/Estimated Budget 3/5/2018City Council Workshop 28 CONTRACTED/ESTIMATED BUDGET $49,947,187 35% Thru 1/31/2018 $90,778,718 65% $140,725,906
  • 29. Estimated Project Budget vs. Actual 3/5/2018City Council Workshop 29 CATEGORY CONTRACTED / ESTIMATED BUDGET ACTUAL THRU 1/31/2018 REMAINING BALANCE BUDGE T % of CONST ACQUISITIONS $3,396,326 3,349,689 $46,636 2.9% ADMINISTRATION $692,852 $461,262 $231,590 0.6% FINANCE $258,638 $216,173 $42,466 0.2% PROFESSIONAL SERVICES DESIGN $10,191,582 $6,521,947 $3,669,635 8.7% PROFESSIONAL SERVICES CONSTRUCTION $9,447,727 $9,233,605 $214,122 8.1% CONSTRUCTION $116,738,781 $70,996,042 $45,742,739 TOTAL $140,725,906 $90,778,718 $49,947,188
  • 30. Total Estimated Project Costs 3/5/2018City Council Workshop 30 CATEGORY Sept 2016 Estimate Jan 2018 Estimate ACQUISITIONS $3,496,000 $3,396,326 ADMINISTRATION $12,000 $692,852 FINANCE $879,000 $258,638 PROFESSIONAL SERVICES DESIGN $9,515,000 $9,446,427 PROFESSIONAL SERVICES CONSTRUCTION $10,093,000 $10,191,582 CONSTRUCTION $97,997,000 $116,740,081 TOTAL $121,992,000 $140,725,906
  • 31. Why have costs changed? 3/5/2018City Council Workshop 31 • Facilities Plan Adoption • Included ±55 acres • Freund property added late in the process • Did not account for specific site conditions
  • 32. Why have costs changed? 3/5/2018City Council Workshop 32 • 30% CWF Design – 4/7/15 • EI&C Increased to high end estimate • Site size reduced • Different solids handling • City Beach Street • Bayshore Drive included • 200-seat training facility • Park not included • Whidbey Island Bank demo not included 4/7/2015 $135M Estimated Total Project Cost Using Hoffman’s 30% Estimate
  • 33. Why have costs changed? 3/5/2018City Council Workshop 33 • 60% CWF Design – 9/30/15 • Reduced deep-ex footprint • Combined buildings • Greater detail in drawings • Better vendor quotes • Completed Site Prep A • Confirmed soils • Mitigation not included • Selected different dryer 9/30/2015$131M Estimated Total Project Cost Using Hoffman’s 60% Estimate
  • 34. Why have costs changed? 3/5/2018City Council Workshop 34 • 90% CWF Design – 9/27/16 • Reconfigured MBR sump • Deleted 98 stone columns by moving odor control • Includes some work outside CWF footprint • Park mitigation not designed • Odor control design not complete 9/27/2016 $122M Estimated Total Project Cost Using Hoffman’s June 2016 Estimate
  • 35. Why have costs changed? 3/5/2018City Council Workshop 35 • March 5, 2018 • Historically, previous estimates had different assumptions • May or may not have included type of solids handling, Bayshore extension, removal of bank building, Windjammer Phase 1, etc. • GMPs 10, 11 & 12 were competitively bid in a hot market • Dramatic cost increases in Seattle market, drew bidders and workforce away from Oak Harbor • Unanticipated cost increase in materials
  • 36. Why have costs changed? 3/5/2018City Council Workshop 36 • Estimated direct cost vs. bid results Sept 16 Est. Award Difference GMP 10 – Concrete #3 $ 3,047,680 $4,809,815 $ 1,762,135 GMP 11 - Superstructure $ 11,492,566 $ 17,934,490 $ 6,442,049 GMP 12 – Odor Control $ 1,728,659 $ 3,957,515 $ 2,228,856 Total $ 16,268,905 $ 26,701,820 $ 10,433,040*Reflects comparison of bids received and their respective estimates. Estimate prepared in June 2016 and awarded Dec 2016 to Feb 2016
  • 37. Why have costs changed? 3/5/2018City Council Workshop 37 • Estimated direct cost vs. bid results Sept 16 Est. Estimated Difference GMP 10, 11, 12 $ 16,268,905 $ 26,701,820 $ 10,433,040 Windjammer Park Ph 1 $ 3,000,000 $ 5,300,000 $ 2,300,000 Subtotal $ 12,733,040 Risk Contingency 3.5% $ 445,656 Owner Contingency 2.5% $ 318,326 Tax 8.7% $ 1,174,241 Total $ 14,671,263
  • 38. • Cost increases have been reflected in every GMP contract component and consultant amendment presented at various workshops and council meetings • Total Project Cost could have been communicated better, but every amendment included a summary for that contract (Hoffman, Carollo, ERCI, KBA, etc.) • Staff intends to improve how we communicate the Total Project Cost When has information been presented about cost increases? 3/5/2018City Council Workshop 38
  • 39. • All GMPs were competitively bid or negotiated with third party validation • The following items were negotiated with Hoffman: • Negotiated Support Services (Crane rental, survey, etc.) • Early equipment procurement (MBR, UV, Dryer) • Based on competitive cost proposals • Transferred risk to Hoffman • Concrete work • Some site work related to Archaeology • Bid packages where no bids were received How are project costs managed? 3/5/2018City Council Workshop 39
  • 40. • All invoices are checked by: • KBA • Project Manager • City Engineer • Finance • Dept of Ecology (if submitted for reimbursement) • RCW requires an audit of the project at end of project • Dept of Ecology loans require single audit yearly (fed and state) • 2 years of clean audits How are project costs managed? 3/5/2018City Council Workshop 40
  • 41. • Two types of contingencies in Hoffman contract • Risk Contingency – for scope gap between GMPs and subcontracts • Owner Contingency – for owner responsible changes • Contingencies are tracked with Construction Change Memorandums • Cost savings transferred to Contingency • Unused Risk and Owner Contingencies returned to City • Unused Negotiated Support Services will be returned to City How have contingencies been used? 3/5/2018City Council Workshop 41
  • 42. • A contingency can be added to or deducted • For example… • CCM73 – Reduced underdrain for deep foundation. Lower $175,379 • CCM77 - Modified micro-piles for soil conditions. Increased cost by $75,000, but saved $650,000 if we had continued down that path. How have contingencies been used? 3/5/2018City Council Workshop 42
  • 43. • A contingency can be added to or deducted from • For example… • Reduced underdrain for deep foundation. Lower $175,379 • Modified micro-piles for soil conditions (reduced micro-pile depth). Lowered cost by $650,000 How have contingencies been used? 3/5/2018City Council Workshop 43
  • 44. • What is the balance of the contingencies as of January 15, 2018? How have contingencies been used? 3/5/2018City Council Workshop 44 Contracted Available Risk Contingency $ 3,087,525 $ 2,308,350 Owner Contingency $ 1,587,993 $ 92,620 Total $ 4,675,518 $ 2,400,970 Working on credits of ±$550,000 to the Owners Contingency
  • 45. • City Council Workshop Questions • Clean Water Facility Update • Project Summary • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 45
  • 46. • The effective interest rate has decreased • City initially considered 20 year bonds at 6% • As the project progressed we considered 30 year bonds • Completion of the Facilities Plan allowed the City to apply for State Revolving Fund loans through DOE • Through a series of competitive applications, the City was able to obtain low interest loans, forgivable principal on loans and grants that have reduced the lifetime cost of the project Project Funding 3/5/2018City Council Workshop 46
  • 47. Funding Source Amount Term (yrs) Rate 2015 SRF $8,260,000 20 2.70% Revenue Bonds $25,720,000 30 3.43% 2016 SRF - Loan $15,631,331 20 1.90% 2016 SRF - Forgivable $463,154 2016 SRF – Centennial Grant $4,586,846 2016 DOC – Grant $2,450,000 .09 Funds - Grant $1,000,000 2017 SRF $44,766,854 20 1.60% 2018 SRF $29,124,301 20 1.20% Sewer / SDF Cash $8,673,420 Total $140,725,906 Project Funding 3/5/2018City Council Workshop 47
  • 48. • Obtaining State Revolving Fund (SRF) loans has reduced the need to obtain additional revenue bonds • Low interest SRF loans @ 20 years will result in a lower lifetime cost than if we issued bonds • Grant Funding of $8,500,000 ~ requires no repayment • Revenue bonds will not impact our ability to obtain general obligation bonds in the future How will the proposed funding impact the City? 3/5/2018City Council Workshop 48
  • 49. • City Council Workshop Questions • Clean Water Facility Update • Project Summary • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 49
  • 50. • Rates are determined for the entire sewer fund • Clean Water Facility • RBC Plant (going away) • Lagoons (turning over to Navy) • Citywide Collections • Capital Projects • Citywide Operations & Maintenance Rates 3/5/2018City Council Workshop 50 Rate O&M Funding Capital Projects
  • 51. Rates – 2010 Estimated 3/5/2018City Council Workshop 51 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 $- $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 ResidentialUtilityRate Rate estimate based on $70M treatment plant at Lagoon site with less capacity. Bonds 20 yrs @ 6%
  • 52. Rates – 2010 Adopted 3/5/2018City Council Workshop 52 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $- $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 ResidentialUtilityRate Ordinance 1587 adopted first 6 years
  • 53. Rates – March 2016 Estimated 3/5/2018City Council Workshop 53 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90 $77.70 $89.36 $102.76 $118.17 $135.90 $- $20 $40 $60 $80 $100 $120 $140 $160 ResidentialUtilityRate Rates were evaluated in March 2016 in preparation for acquiring bonds based on an MBR facility and a $120M Estimated Total Project Cost
  • 54. Rates – March 2016 Adopted 3/5/2018City Council Workshop 54 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90 2016 Ord 1760 $77.70 $89.36 $102.76 $77.70 $89.36 $102.76 $- $20 $40 $60 $80 $100 $120 $140 $160 ResidentialUtilityRate Ordinance 1760 Adopted 3 years of the March 2016 estimate
  • 55. Rates – Sept 2016 Estimated 3/5/2018City Council Workshop 55 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90 2016 Ord 1760 $77.70 $89.36 $102.76 Sept '16 Estimate $77.70 $89.36 $102.76 $110.98 $119.86 $77.70 $89.36 $102.76 $110.98 $119.86 $- $20 $40 $60 $80 $100 $120 $140 $160 ResidentialUtilityRate In Sept 2016, rates were checked with new funding and an Estimated Total Project Cost of $121.9M
  • 56. Rates – January 2018 Estimated 3/5/2018City Council Workshop 56 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2010 Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 2010 Ord 1587 $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 March '16 Estimate $77.70 $89.36 $102.76 $118.17 $135.90 2016 Ord 1760 $77.70 $89.36 $102.76 Sept '16 Estimate $77.70 $89.36 $102.76 $110.98 $119.86 Jan '18 Estimate $77.70 $89.36 $102.76 $106.36 $110.08 $77.70 $89.36 $102.76 $106.36 $110.08 $- $20 $40 $60 $80 $100 $120 $140 $160 ResidentialUtilityRate In January 2018, rates were checked with current funding and an Estimated Total Project Cost of $140M
  • 57. • After construction is complete • Will be adopted before Ordinance 1760 expires • Will likely be for an additional 3-year period • May be impacted by Navy participation Next Rate Adjustment 3/5/2018City Council Workshop 57
  • 58. • Even though the project cost has increased, active pursuit of additional low cost funding has maintained a rate consistent with past projections and allowed the City to construct a project that will serve the city for the next 40-50 years. Rate Summary 3/5/2018City Council Workshop 58Rate O&M Fundin g Capital Project s
  • 59. • City Council Workshop Questions • Clean Water Facility Update • Project Summary • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 59
  • 60. • Agenda • Windjammer Park Integration Plan • What is included? • Schedule • Current design/construction status • Anticipated cost • Funding Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 60
  • 61. 3/5/2018 61 Windjammer Park Integration Plan • Public feedback • Community Advisory Group • 17 members representing diverse community interests • 5 meetings • Endorsed final plan • 2 in-person and online public meetings City Council Workshop
  • 62. 62 Decembe r 2015 Januar y 2016 February 2016 March 2016 April 2016 May/ June 2016 Council and CAG Process • Provide feedback on 3 concept alternatives • Present WPIP concept to community • Gather community feedback (Public Open House and Online Open House) • Review preferred plan to be presented to City Council • Provide final feedback • CAG forms • CAG provides feedback on design guidelines • Introduce CAG and WPIP to community • Gather community feedback (Public Open House) COUNCIL • Programming priorities • Approves CAG COUNCIL Report: Alternatives and Public feedback COUNCIL Approves plan COUNCIL CAG formation update and initial priorities list/ design guidelines 3/5/2018              City Council Workshop
  • 63. Proposed Phase 1 3/5/2018 63 Original Phase 1 To include part of Phase 2 & 3 City Council Workshop
  • 64. Windjammer Park Phase 1 3/5/2018 64 • Includes Clean Water Facility mitigation and restoration • November 15, 2016 – City Council amended Carollo’s contract to include design City Council Workshop
  • 65. Windjammer Park Phase 1 Open House 3/5/2018 65 • 167 community members attended in-person and online open houses in January 2017 • 97 community members provided input on park character and theme City Council Workshop
  • 66. • What does this include? • Everything outside the Clean Water Facility within Phase 1! • Demolition of the former Whidbey Island Bank building • Improvements to City Beach Street • New kitchens and restrooms • Pathways and landscaping • Splash park! Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 66
  • 67. 3/5/2018City Council Workshop 67 Sport Courts Maintenanc e Building Increased Interior Space Removed Fireplace Removed Path Increased Number of Garry Oak TreesWhat has changed since 60% design?
  • 68. • Current design/construction status • Design complete • Design split into 7 bid packages • Bid opening on 5 packages March 1, 2018 • Water play area and feature bid opening March 15, 2018 • Vehicle and pedestrian gates bid opening on March 22, 2018 • Construction through Spring 2019 Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 68
  • 69. • Anticipated cost • 60% Design Cost Estimate ~ $10M to $15M • Design broken into 7 bid packages to maximize competition and local participation • Packages further broken into schedules to allow City flexibility in choosing which ones to construct at this time Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 69
  • 73. • Available Sewer Funds = $5.3M • For work around Clean Water Facility • Restoration of disturbed areas • Mitigation of impacts on the park • Permit requirements • East side kitchen and restrooms Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 73
  • 74. • Available General Funds = ? • Splash park • Plaza / Pavilion • West Kitchen • Additional Paths • Landscaping • Maintenance Facility Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 74 Will likely need to pick and choose which elective items are constructed
  • 75. • Potential funding gap • Bids will likely exceed secured funding to complete non- CWF improvements • What can we do? • Design has been split into multiple bid packages • Release more general fund dollars to complete project • Postpone some improvement and seek additional outside funding Windjammer Park Phase 1 Update 3/5/2018City Council Workshop 75
  • 76. • 2018 events may need to be held elsewhere • Planning to move RV Dump Station to a new location • Planning for Windmill relocation and future phases • Waterfront trail will remain open • Conversations about construction sequencing • Community notifications and updates What to Expect in 2018 3/5/2018City Council Workshop 76
  • 77. What to Expect in 2018 3/5/2018City Council Workshop 77
  • 78. • City Council Workshop Questions • Clean Water Facility Update • Project Summary • GC/CM Delivery Method Review • Schedule • Current Project Cost Estimate • Funding • Rates • Windjammer Park Phase 1 • Next Steps and Questions Agenda 3/5/2018City Council Workshop 78
  • 79. • Improve communications with City Council • Monthly update – second council meeting • Total Project Cost summary every council meeting • Continue to seek ways to keep project cost and rates down • Continue communicating with community • Workshop in March to discuss park improvements Next Steps 3/5/2018City Council Workshop 79

Notas do Editor

  1. This presentation will share updates since our last cost discussion in April.
  2. This presentation will share updates since our last cost discussion in April.
  3. Before we get into the details, we want to give you an overview of the current rate estimate We’ve taken multiple steps to manage and reduce project costs where possible and keep rates down. We’ll go over those throughout this presentation
  4. Before we get into the details, we want to give you an overview of the current rate estimate We’ve taken multiple steps to manage and reduce project costs where possible and keep rates down. We’ll go over those throughout this presentation
  5. Before we get into the details, we want to give you an overview of the current rate estimate We’ve taken multiple steps to manage and reduce project costs where possible and keep rates down. We’ll go over those throughout this presentation
  6. Before we get into the details, we want to give you an overview of the current rate estimate We’ve taken multiple steps to manage and reduce project costs where possible and keep rates down. We’ll go over those throughout this presentation
  7. Before we get into the details, we want to give you an overview of the current rate estimate We’ve taken multiple steps to manage and reduce project costs where possible and keep rates down. We’ll go over those throughout this presentation
  8. This presentation will share updates since our last cost discussion in April.
  9. This presentation will share updates since our last cost discussion in April.
  10. WHOA! Two years of construction?! So much has happened!
  11. WHOA! Two years of construction?! So much has happened!
  12. As you can see, there’s been a lot of progress! There is a lot to show for the time and effort since 2010.
  13. This presentation will share updates since our last cost discussion in April.
  14. This presentation will share updates since our last cost discussion in April.
  15. This presentation will share updates since our last cost discussion in April.
  16. This presentation will share updates since our last cost discussion in April.
  17. This presentation will share updates since our last cost discussion in April.