SlideShare uma empresa Scribd logo
1 de 6
Baixar para ler offline
Cabling, maintenance and planning processes for offshore
wind farms


By Al Tuttle



Despite the battles that were fought about the safety and viability of deep sea wind
farms, builders are getting international permits for more turbines. They are being
built or are approved in some of the angriest waters north of the equator. Compared
to rather mild waters of New England, where the first wind farm on the east coast of
North America has been approved off Massachusetts, the North Sea and Baltic Sea
are more treacherous and unpredictable.



Europe has over 4,000 wind turbines and manufacturing companies of components,
turbines, seagoing vessels and cables are learning more each year about the
process of building a wind farm, according to experts in the undersea cable field.
Power transfer cables are very specialized and made only by a few companies
around the world. Every wind farm uses a complex combination of undersea, buried
cables, turbine connectors, splices and connections at an at-sea substation.



One challenge in the arena of wind technology at sea is developing and refining best
practices for installing arrays of cables in giant fields of wind turbines, said Joel
Whitman of Global Marine Systems. Global Marine is one of the world’s largest
marine cable layers and offshore service providers. (1) The company has worked on
some of the biggest wind farms in the world, particularly in European waters.




-------------------------------------------------------------------------------------------------------------------
                                                     ----------

                             IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany

              t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de

       Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
“There are significant problems when laying cable in the ocean that everyone is still
trying to solve,” Whitman said. Installing cable along the seabed means
encountering landscapes as varied as those on land. With miles and miles of seabed
to cross, and with cable to be buried two meters deep, the possibilities for
encountering obstacles that slow or stop progress are multiplied. Companies like
Global Marine use the most sophisticated electronic equipment available to map and
analyze the seabed. There are steep hills, rugged bottoms and material that ranges
from mud and silt to hard clay and rock.

                             There are always a great number of unknowns when a
                             project the size of a wind farm at sea is being
                             developed. While the water is generally 70 meters
                             deep or shallower, the cable is exposed to powerful
                             stress forces when installed and being buried, or while
                             connected to the Whitman said. Some of the
                             arguments used against giant wind farms are ironically
                             environmentally based. As a power source born and
                             developed in part because it uses no or very little
                             fossil-based fuels, the natural view of wind power is
                             that it is supremely clean and friendly to every
                             environment. Since each tower is the size of the
                             Statue of Liberty and a field can be 100 square miles,
                             some groups against seaborne wind power say that the
 Photo courtesy Siemens
                             energy needed to create all the parts, put them in the
ocean and connect them, is more than the energy the wind farm can create in
several years’ production. These groups decry the pollution supposedly created by
this manufacture and construction. They also claim that in spite of the 4,000 units
working in Europe, none of the electric rates paid in affected countries have gone
down. Some people also argue that fishing areas and shipping lanes are threatened
by giant wind farms.



Extensive right-of-way negotiations can solve many of these navigation problems.
Those negotiations must be part of a deeper research and development plan for

-------------------------------------------------------------------------------------------------------------------
                                                     ----------

                             IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany

              t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de

       Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
each project. Wind farms are still trying to reach a point of profitability, Whitman
said, because the companies and consortiums put together to build and operate
them have not planned every step completely enough. More companies working
together will benefit every wind project, he said. These larger groups of manpower
and machine power, combined with more experts researching every part of the
plan, will make every project more complete before any work is done in the water.
“When everything is running well, the whole system is profitable,” he said.
Seaborne wind farms have no construction impact on property (as do land-based
farms), no noise pollution problems and      are generally not a threat to visibility.



However, many of the projects Global Marine has been involved with run into
problems that take a lot of money to fix. The turbines are linked in a line, so that if
                                    one goes out of service due to a cable problem,
                                    the rest in front of the down turbine all stop
                                    working. “If the last turbine is out, it is the only
                                    one out and is not as much of an emergency as
                                    is a turbine that goes down and stops all the
                                    rest with it,” he said. The result is an
                                    emergency need for cable, crews and ships.



      Photo courtesy Siemens           The supply of cable on hand is critical for
                                       repairs. Whitman’s company has been involved
in projects that did not have enough backup cable on hand. In one instance,
Whitman said that the wind farm operators had asked for only one mile of cable be
stored as inventory for an emergency. That is less than one length of connection
cable between two turbines. When a turbine cable far up the line failed, the
company waited weeks for more repair cable to be made, Whitman said. So an
extremely expensive supply chain problem occurs in the repair and maintenance
area when not enough cable (and other contingent supplies) are not kept on hand.
Regular maintenance has not been addressed in depth either, according to
Whitman. Checking connections and cable is not a perfect art, but is necessary and
is an area that needs more specialized equipment. Every tower is made in four
parts: the original electrical connection is made before the turbine is placed on the

-------------------------------------------------------------------------------------------------------------------
                                                     ----------

                             IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany

              t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de

       Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
transition piece. After the turbine is put onto the assembly, that connection
becomes more difficult to inspect and replace or repair. The same is true for cable
running between turbines, connecting them in a line, and for cable running to and
away from the substation. When cable is inspected and tested at the factory, it is
easier to detect defects visually. After cable is buried and tests are completed for
every section, the cable becomes exposed to the underwater environment on a
permanent basis. This is a challenge to the rugged reliability of the cable,
connections and turbine construction.



There are only a handful of companies supplying undersea power cable. The
seagoing environment is far different from land-based wind farm tracts. There are
pluses and minuses for either environment: the sea has no surface terrain but the
seabed has a variety of landscapes. The cables are made under strict quality and
environmental rules by companies like nkt cables of Denmark (2), which is a world
leader not only in cable manufacturing but in research, safety and technology. The
company is researching more durable materials for use in cabling. They are also
very concerned about using as environmentally friendly materials as possible. nkt
cable replaced dangerous materials like lead and PVC in its cable products.



It is becoming more obvious that not only are wind farms here to stay, but more,
bigger projects are on the way. In Denmark, Germany and England, projects are
planned using even bigger wind fields and bigger turbines. In the case of farms
planned for the Baltic and North Seas, extremely complex connections and farm
hubs are planned, with power going to several countries. (3) These projects add
layers of complexity to the entire construction process: supply and security, land
and water lease, manufacturing prediction, quality support and more. According to
experts like Joel Whitman, this complexity demands that the partners in the project
broaden the scope of planning and consider more redundancies than have been
included thus far. One of the critical areas that needs a longer look is maintenance.



Now, many years after the building of the first offshore wind farms, evidence is
building about the need for more comprehensive maintenance programs and backup

-------------------------------------------------------------------------------------------------------------------
                                                     ----------

                             IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany

              t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de

       Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
equipment. According to one report (4), these huge yet extremely precise machines
are beginning to need repair or replacement. The report notes that turbines in the
North Sea are expected to last 20 years but some are failing at age eight. It could
simply be the very difficult North Sea conditions, but those conditions are prevalent
in other European waters. Finally, the report notes that the expenses of building
each completed turbine has exceeded estimates while output has been less than
expected, in megawatts/unit.



As the size of farms increases and more farms are planned, the final maintenance
and contingency inventory and funding must be increased. That comes from better
overall long range planning. The more experience operating consortiums have at
maintaining an average wind farm, the better they will be able to anticipate
maintenance problems.



Al Tuttle

Freelance Editor



Al Tuttle is news and features editor whose experience includes Media News
Group, Reed Elsevier and New York Times New England. He specializes in industrial
and commercial writing. He was in sales for industrial distribution companies and
manufacturers for 15 years.




    1. http://www.globalmarinesystems.com/Capabilities/subsea_cable_maintenanc
       e
    2. http://nktcables.com/Products/Offshore


-------------------------------------------------------------------------------------------------------------------
                                                     ----------

                             IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany

              t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de

       Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
3. http://www.ewea.org/fileadmin/ewea_documents/documents/publications/re
       ports/OffshoreGrid__report.pdf
    4. http://www.forbes.com/sites/energysource/2012/01/11/shaky-foundations-
       for-offshore-wind-farms/




              Want to know more about offshore cabeling?
    Check out our Download Centre, where you will find more articles,
            white papers and interviews regarding this topic:

                               http://bit.ly/offshore-cabeling




-------------------------------------------------------------------------------------------------------------------
                                                     ----------

                             IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany

              t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de

       Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de

Mais conteúdo relacionado

Destaque

Off-Highway Engines - Selective Catalytic Reduction
Off-Highway Engines - Selective Catalytic ReductionOff-Highway Engines - Selective Catalytic Reduction
Off-Highway Engines - Selective Catalytic ReductionTorben Haagh
 
Grid Integration: Requirements for Wind Turbines
Grid Integration: Requirements for Wind TurbinesGrid Integration: Requirements for Wind Turbines
Grid Integration: Requirements for Wind TurbinesTorben Haagh
 
Performance of contracts ppt @ bec doms
Performance of contracts ppt @ bec doms Performance of contracts ppt @ bec doms
Performance of contracts ppt @ bec doms Babasab Patil
 
Что такое Kpi и как с этим бороться?
Что такое Kpi и как с этим бороться?Что такое Kpi и как с этим бороться?
Что такое Kpi и как с этим бороться?Lazat Takyrbashova
 
Aktiviti kelaskan makanan
Aktiviti kelaskan makananAktiviti kelaskan makanan
Aktiviti kelaskan makananone piece
 
Maria, mare de jesús
Maria, mare de jesúsMaria, mare de jesús
Maria, mare de jesúscintacugat
 
Comunicato stampa is c io j - 21.02.12
Comunicato stampa is c io j - 21.02.12Comunicato stampa is c io j - 21.02.12
Comunicato stampa is c io j - 21.02.12antodiga
 
Geografía Séptimo D
Geografía Séptimo DGeografía Séptimo D
Geografía Séptimo Dmpcpolania3
 
ARTEMIS Magazine 06 March 2010
ARTEMIS Magazine 06 March 2010ARTEMIS Magazine 06 March 2010
ARTEMIS Magazine 06 March 2010Else Embregts
 

Destaque (13)

Off-Highway Engines - Selective Catalytic Reduction
Off-Highway Engines - Selective Catalytic ReductionOff-Highway Engines - Selective Catalytic Reduction
Off-Highway Engines - Selective Catalytic Reduction
 
Grid Integration: Requirements for Wind Turbines
Grid Integration: Requirements for Wind TurbinesGrid Integration: Requirements for Wind Turbines
Grid Integration: Requirements for Wind Turbines
 
Performance of contracts ppt @ bec doms
Performance of contracts ppt @ bec doms Performance of contracts ppt @ bec doms
Performance of contracts ppt @ bec doms
 
Что такое Kpi и как с этим бороться?
Что такое Kpi и как с этим бороться?Что такое Kpi и как с этим бороться?
Что такое Kpi и как с этим бороться?
 
страх
страхстрах
страх
 
Aktiviti kelaskan makanan
Aktiviti kelaskan makananAktiviti kelaskan makanan
Aktiviti kelaskan makanan
 
Liga
LigaLiga
Liga
 
Why to have a baby
Why to have a babyWhy to have a baby
Why to have a baby
 
Maria, mare de jesús
Maria, mare de jesúsMaria, mare de jesús
Maria, mare de jesús
 
Comunicato stampa is c io j - 21.02.12
Comunicato stampa is c io j - 21.02.12Comunicato stampa is c io j - 21.02.12
Comunicato stampa is c io j - 21.02.12
 
Geografía Séptimo D
Geografía Séptimo DGeografía Séptimo D
Geografía Séptimo D
 
Breadfruit lit rev
Breadfruit lit revBreadfruit lit rev
Breadfruit lit rev
 
ARTEMIS Magazine 06 March 2010
ARTEMIS Magazine 06 March 2010ARTEMIS Magazine 06 March 2010
ARTEMIS Magazine 06 March 2010
 

Semelhante a Offshore cabeling: Cabling maintenance planning processes

Visite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore windVisite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore windCCILVN
 
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...Cathie Associates
 
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Roxtec UK & Ireland
 
Technology Conference_Final_PVC Covered Jumper
Technology Conference_Final_PVC Covered JumperTechnology Conference_Final_PVC Covered Jumper
Technology Conference_Final_PVC Covered JumperSeeralin Nayager (Pr Eng)
 
E&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebE&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebAmber Thomas
 
World Offshore Wind Market Forecast 2015-2024
World Offshore Wind Market Forecast 2015-2024World Offshore Wind Market Forecast 2015-2024
World Offshore Wind Market Forecast 2015-2024Douglas-Westwood
 
The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9
The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9
The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9Joël Devautour
 
Wind Generators: the advantages and disadvantages
Wind Generators: the advantages and disadvantagesWind Generators: the advantages and disadvantages
Wind Generators: the advantages and disadvantagesTorben Haagh
 
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...Dennis Keen
 
Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice ReportPaul Soko
 
Siting and Planning Design of Wind Turbines
Siting and Planning Design of Wind TurbinesSiting and Planning Design of Wind Turbines
Siting and Planning Design of Wind TurbinesHimanshu Paghdal
 
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET Journal
 
Yin Sun Shell - Shell (Projects & Technology)
Yin Sun Shell - Shell (Projects & Technology)Yin Sun Shell - Shell (Projects & Technology)
Yin Sun Shell - Shell (Projects & Technology)GuidoBacker1
 
Cal Marine Power & Water "straw" scam presentation
Cal Marine Power & Water "straw" scam presentationCal Marine Power & Water "straw" scam presentation
Cal Marine Power & Water "straw" scam presentationFingerPointer
 
Impact of economical cable conductor sizing
Impact of economical cable conductor sizingImpact of economical cable conductor sizing
Impact of economical cable conductor sizingLeonardo ENERGY
 
Rotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade designRotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade designTorben Haagh
 

Semelhante a Offshore cabeling: Cabling maintenance planning processes (20)

Visite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore windVisite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore wind
 
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
 
Lightening Story
Lightening StoryLightening Story
Lightening Story
 
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
Sealing cables over land and sea - Panel Building & Systems Integration Magaz...
 
Technology Conference_Final_PVC Covered Jumper
Technology Conference_Final_PVC Covered JumperTechnology Conference_Final_PVC Covered Jumper
Technology Conference_Final_PVC Covered Jumper
 
E&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - WebE&TR A5 4pp Get Involved - Web
E&TR A5 4pp Get Involved - Web
 
World Offshore Wind Market Forecast 2015-2024
World Offshore Wind Market Forecast 2015-2024World Offshore Wind Market Forecast 2015-2024
World Offshore Wind Market Forecast 2015-2024
 
The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9
The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9
The flexibility of Alstom Grid’s high voltage solution - Think Grid n°9
 
Wind Generators: the advantages and disadvantages
Wind Generators: the advantages and disadvantagesWind Generators: the advantages and disadvantages
Wind Generators: the advantages and disadvantages
 
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
 
Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice Report
 
Siting and Planning Design of Wind Turbines
Siting and Planning Design of Wind TurbinesSiting and Planning Design of Wind Turbines
Siting and Planning Design of Wind Turbines
 
MARED116009EN_Digital
MARED116009EN_DigitalMARED116009EN_Digital
MARED116009EN_Digital
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
NZC - Innis
NZC - InnisNZC - Innis
NZC - Innis
 
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
 
Yin Sun Shell - Shell (Projects & Technology)
Yin Sun Shell - Shell (Projects & Technology)Yin Sun Shell - Shell (Projects & Technology)
Yin Sun Shell - Shell (Projects & Technology)
 
Cal Marine Power & Water "straw" scam presentation
Cal Marine Power & Water "straw" scam presentationCal Marine Power & Water "straw" scam presentation
Cal Marine Power & Water "straw" scam presentation
 
Impact of economical cable conductor sizing
Impact of economical cable conductor sizingImpact of economical cable conductor sizing
Impact of economical cable conductor sizing
 
Rotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade designRotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade design
 

Mais de Torben Haagh

Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...
Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...
Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...Torben Haagh
 
ISO26262 Conference 2019
ISO26262 Conference 2019ISO26262 Conference 2019
ISO26262 Conference 2019Torben Haagh
 
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas InstrumentsSOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas InstrumentsTorben Haagh
 
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...Torben Haagh
 
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019Torben Haagh
 
14th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 201914th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 2019Torben Haagh
 
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...Torben Haagh
 
Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019Torben Haagh
 
Cognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, GermanyCognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, GermanyTorben Haagh
 
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBWPräsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBWTorben Haagh
 
Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?Torben Haagh
 
Mythos und Realität des ERF
Mythos und Realität des ERFMythos und Realität des ERF
Mythos und Realität des ERFTorben Haagh
 
Expert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technologyExpert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technologyTorben Haagh
 
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an endENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an endTorben Haagh
 
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...Torben Haagh
 
Letzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr KonferenzticketLetzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr KonferenzticketTorben Haagh
 
Effizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-PartnernEffizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-PartnernTorben Haagh
 
Digitalisierte bAV
Digitalisierte bAV Digitalisierte bAV
Digitalisierte bAV Torben Haagh
 
Die Bank von morgen
Die Bank von morgenDie Bank von morgen
Die Bank von morgenTorben Haagh
 
"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach Davis"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach DavisTorben Haagh
 

Mais de Torben Haagh (20)

Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...
Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...
Siemens Gamesaa, RCAM Tecnologies, Goldwind, Nabrawind, ESTEYO confirmed spea...
 
ISO26262 Conference 2019
ISO26262 Conference 2019ISO26262 Conference 2019
ISO26262 Conference 2019
 
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas InstrumentsSOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
 
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
 
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
 
14th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 201914th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 2019
 
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
 
Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019
 
Cognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, GermanyCognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, Germany
 
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBWPräsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
 
Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?
 
Mythos und Realität des ERF
Mythos und Realität des ERFMythos und Realität des ERF
Mythos und Realität des ERF
 
Expert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technologyExpert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technology
 
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an endENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
 
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
 
Letzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr KonferenzticketLetzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr Konferenzticket
 
Effizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-PartnernEffizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-Partnern
 
Digitalisierte bAV
Digitalisierte bAV Digitalisierte bAV
Digitalisierte bAV
 
Die Bank von morgen
Die Bank von morgenDie Bank von morgen
Die Bank von morgen
 
"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach Davis"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach Davis
 

Último

Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docxRodelinaLaud
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 

Último (20)

Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docx
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 

Offshore cabeling: Cabling maintenance planning processes

  • 1. Cabling, maintenance and planning processes for offshore wind farms By Al Tuttle Despite the battles that were fought about the safety and viability of deep sea wind farms, builders are getting international permits for more turbines. They are being built or are approved in some of the angriest waters north of the equator. Compared to rather mild waters of New England, where the first wind farm on the east coast of North America has been approved off Massachusetts, the North Sea and Baltic Sea are more treacherous and unpredictable. Europe has over 4,000 wind turbines and manufacturing companies of components, turbines, seagoing vessels and cables are learning more each year about the process of building a wind farm, according to experts in the undersea cable field. Power transfer cables are very specialized and made only by a few companies around the world. Every wind farm uses a complex combination of undersea, buried cables, turbine connectors, splices and connections at an at-sea substation. One challenge in the arena of wind technology at sea is developing and refining best practices for installing arrays of cables in giant fields of wind turbines, said Joel Whitman of Global Marine Systems. Global Marine is one of the world’s largest marine cable layers and offshore service providers. (1) The company has worked on some of the biggest wind farms in the world, particularly in European waters. ------------------------------------------------------------------------------------------------------------------- ---------- IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
  • 2. “There are significant problems when laying cable in the ocean that everyone is still trying to solve,” Whitman said. Installing cable along the seabed means encountering landscapes as varied as those on land. With miles and miles of seabed to cross, and with cable to be buried two meters deep, the possibilities for encountering obstacles that slow or stop progress are multiplied. Companies like Global Marine use the most sophisticated electronic equipment available to map and analyze the seabed. There are steep hills, rugged bottoms and material that ranges from mud and silt to hard clay and rock. There are always a great number of unknowns when a project the size of a wind farm at sea is being developed. While the water is generally 70 meters deep or shallower, the cable is exposed to powerful stress forces when installed and being buried, or while connected to the Whitman said. Some of the arguments used against giant wind farms are ironically environmentally based. As a power source born and developed in part because it uses no or very little fossil-based fuels, the natural view of wind power is that it is supremely clean and friendly to every environment. Since each tower is the size of the Statue of Liberty and a field can be 100 square miles, some groups against seaborne wind power say that the Photo courtesy Siemens energy needed to create all the parts, put them in the ocean and connect them, is more than the energy the wind farm can create in several years’ production. These groups decry the pollution supposedly created by this manufacture and construction. They also claim that in spite of the 4,000 units working in Europe, none of the electric rates paid in affected countries have gone down. Some people also argue that fishing areas and shipping lanes are threatened by giant wind farms. Extensive right-of-way negotiations can solve many of these navigation problems. Those negotiations must be part of a deeper research and development plan for ------------------------------------------------------------------------------------------------------------------- ---------- IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
  • 3. each project. Wind farms are still trying to reach a point of profitability, Whitman said, because the companies and consortiums put together to build and operate them have not planned every step completely enough. More companies working together will benefit every wind project, he said. These larger groups of manpower and machine power, combined with more experts researching every part of the plan, will make every project more complete before any work is done in the water. “When everything is running well, the whole system is profitable,” he said. Seaborne wind farms have no construction impact on property (as do land-based farms), no noise pollution problems and are generally not a threat to visibility. However, many of the projects Global Marine has been involved with run into problems that take a lot of money to fix. The turbines are linked in a line, so that if one goes out of service due to a cable problem, the rest in front of the down turbine all stop working. “If the last turbine is out, it is the only one out and is not as much of an emergency as is a turbine that goes down and stops all the rest with it,” he said. The result is an emergency need for cable, crews and ships. Photo courtesy Siemens The supply of cable on hand is critical for repairs. Whitman’s company has been involved in projects that did not have enough backup cable on hand. In one instance, Whitman said that the wind farm operators had asked for only one mile of cable be stored as inventory for an emergency. That is less than one length of connection cable between two turbines. When a turbine cable far up the line failed, the company waited weeks for more repair cable to be made, Whitman said. So an extremely expensive supply chain problem occurs in the repair and maintenance area when not enough cable (and other contingent supplies) are not kept on hand. Regular maintenance has not been addressed in depth either, according to Whitman. Checking connections and cable is not a perfect art, but is necessary and is an area that needs more specialized equipment. Every tower is made in four parts: the original electrical connection is made before the turbine is placed on the ------------------------------------------------------------------------------------------------------------------- ---------- IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
  • 4. transition piece. After the turbine is put onto the assembly, that connection becomes more difficult to inspect and replace or repair. The same is true for cable running between turbines, connecting them in a line, and for cable running to and away from the substation. When cable is inspected and tested at the factory, it is easier to detect defects visually. After cable is buried and tests are completed for every section, the cable becomes exposed to the underwater environment on a permanent basis. This is a challenge to the rugged reliability of the cable, connections and turbine construction. There are only a handful of companies supplying undersea power cable. The seagoing environment is far different from land-based wind farm tracts. There are pluses and minuses for either environment: the sea has no surface terrain but the seabed has a variety of landscapes. The cables are made under strict quality and environmental rules by companies like nkt cables of Denmark (2), which is a world leader not only in cable manufacturing but in research, safety and technology. The company is researching more durable materials for use in cabling. They are also very concerned about using as environmentally friendly materials as possible. nkt cable replaced dangerous materials like lead and PVC in its cable products. It is becoming more obvious that not only are wind farms here to stay, but more, bigger projects are on the way. In Denmark, Germany and England, projects are planned using even bigger wind fields and bigger turbines. In the case of farms planned for the Baltic and North Seas, extremely complex connections and farm hubs are planned, with power going to several countries. (3) These projects add layers of complexity to the entire construction process: supply and security, land and water lease, manufacturing prediction, quality support and more. According to experts like Joel Whitman, this complexity demands that the partners in the project broaden the scope of planning and consider more redundancies than have been included thus far. One of the critical areas that needs a longer look is maintenance. Now, many years after the building of the first offshore wind farms, evidence is building about the need for more comprehensive maintenance programs and backup ------------------------------------------------------------------------------------------------------------------- ---------- IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
  • 5. equipment. According to one report (4), these huge yet extremely precise machines are beginning to need repair or replacement. The report notes that turbines in the North Sea are expected to last 20 years but some are failing at age eight. It could simply be the very difficult North Sea conditions, but those conditions are prevalent in other European waters. Finally, the report notes that the expenses of building each completed turbine has exceeded estimates while output has been less than expected, in megawatts/unit. As the size of farms increases and more farms are planned, the final maintenance and contingency inventory and funding must be increased. That comes from better overall long range planning. The more experience operating consortiums have at maintaining an average wind farm, the better they will be able to anticipate maintenance problems. Al Tuttle Freelance Editor Al Tuttle is news and features editor whose experience includes Media News Group, Reed Elsevier and New York Times New England. He specializes in industrial and commercial writing. He was in sales for industrial distribution companies and manufacturers for 15 years. 1. http://www.globalmarinesystems.com/Capabilities/subsea_cable_maintenanc e 2. http://nktcables.com/Products/Offshore ------------------------------------------------------------------------------------------------------------------- ---------- IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de
  • 6. 3. http://www.ewea.org/fileadmin/ewea_documents/documents/publications/re ports/OffshoreGrid__report.pdf 4. http://www.forbes.com/sites/energysource/2012/01/11/shaky-foundations- for-offshore-wind-farms/ Want to know more about offshore cabeling? Check out our Download Centre, where you will find more articles, white papers and interviews regarding this topic: http://bit.ly/offshore-cabeling ------------------------------------------------------------------------------------------------------------------- ---------- IQPC GmbH | Friedrichstr. 94 | D-10117 Berlin, Germany t: +49 (0) 30 2091 3330 | f: +49 (0) 30 2091 3263 | e: eq@iqpc.de | w: www.iqpc.de Visit IQPC for a portfolio of topic-related events, congresses, seminars and conferences: www.iqpc.de