IOSR Journal of Business and Management (IOSR-JBM)
e-ISSN: 2278-487X, p-ISSN: 2319-7668. Volume 11, Issue 4 (Jul. - Aug. 2013), PP 10-17
www.iosrjournals.org
www.iosrjournals.org 10 | Page
Complex Project Crashing Algorithm
Nafish Sarwar Islam
(Department of Business Administration, East West University, Bangladesh)
Abstract: Crashing is the procedure by which project duration can be shorten up by expediting selective
activities with in the project. But it requires allocating more resources than usual to compress an activity’s
duration, which in turns increases the budget of that activity. So, crashing is basically a time-cost trade-off by
which specific deadline can be achieved. The traditional method of crashing only considers average activity
times for the calculation of the critical path, ignoring the stochastic nature of activity time. This report is written
to develop an algorithm for optimum crashing method to minimize the required cost while attaining a specified
completion time.
Keywords – Critical Path, Project Crashing Algorithm, Time-Cost Trade-Off
I. INTRODUCTION
Two of the most popular approaches to project management are the Critical Path Method (CPM) and
the Project Evaluation and Review Technique (PERT), which were developed short after the World War II. The
Critical Path Method (CPM) and the Project Evaluation and Review Technique (PERT) methods have been used
since the 1950s to estimate the completion time of a project. CPM is a deterministic approach to calculate the
duration of a project, and PERT is a probabilistic approach that enhances CPM by considering uncertainty in
activity durations by calculating the probability to complete the project by a given time [1]. J.E. Kelly of
Remington-Rand and M.B. Walker of DuPont developed CPM in the 1957 to assist in scheduling maintenance
shutdowns of chemical processing plants. While PERT was developed shortly after by the U.S. Navy to manage
the development of the Polaris missile. The original PERT Navy report (1958) does not identify the names of
developers [2]. Both CPM and PERT are network based techniques, where PERT can be considered as an
extension of CPM. After constructing the network diagram from precedence relationships and duration times
PERT planning involves the following steps:
(i) Estimating the time required for each activity
(ii) Calculating slack time of each activity
(iii) Determining the critical path(s)
(iv) Project crashing
(i) Estimating the Time Required for Each Activity
A distinguishing feature of PERT is to deal with the uncertainty in activity completion times. The
model includes three time estimates which are considered to follow the generalized beta distribution:
Optimistic time (a): the shortest time in which the activity can be completed.
Most likely time (m): the completion time having the highest probability.
Pessimistic time (b): the longest time that an activity might require.
The expected time for each activity can be estimated using the following weighted average:
Expected time = [(a + 4m + b) / 6]; and the variance is: Variance = [(b - a) / 6]2
(ii) Calculating Slack time of Each Activity
The amount of time that a non-critical path activity can be delayed without delaying the project is
referred to as slack time. As a matter of fact activities within the critical path(s) have a zero slack value. So if
activities outside the critical path speed up or slow down up to their available slack time, the total project time
does not change. To calculate slack time it is required to find out the following four values of each activity:
ES – Earliest Start time, EF - Earliest Finish time, LS - Latest Start time, LF - Latest Finish time.
These times are calculated using the expected time for the relevant activities. The earliest start and
finish times of each activity are determined by working forward through the network and determining the
earliest time at which an activity can start and finish considering its predecessor activities. The latest start and
finish times are found by working backward through the network and determining the latest time that an activity
Submitted date 12 June 2013 Accepted Date: 17 June 2013
Complex Project Crashing Algorithm
www.iosrjournals.org 11 | Page
can start and finish without delaying the project considering the particular activity is predecessor of how many
activities. The difference in the latest and earliest finish of each activity is that activity's slack;
Slack Time = (Ls – Es).
(iii) Determining the Critical Path(s)
The critical path is determined by adding the times for the activities in each sequence and determining
the longest path in the project. That is why critical path determines the total completion time required for the
project. For instance, if a project network diagram has 14 available paths, and by adding the times for the
activities in path number 1, 4 and 7 gives the highest value compared to others, then that value would be the
project completion time, while path number 1, 4 and 7 will be the critical paths. Now say “C” is an activity
which is not available in critical paths, but available in path number 3, 6, 8 and 11 and among these four paths
path number 11 gives maximum value if we add the times for the activities in path number 3, 6, 8 and 11. So,
slack time of activity “C” can be calculated by subtracting the total duration of path number 11 from the total
duration of any critical path 1, 4 or, 7; which is the project duration. Thus project’s critical path(s) can be
identified by considering the path(s) through the network in which none of the activities have slack.
(iv) Project Crashing
The variance in the project completion time can be calculated by summing the variances in the
completion times of the activities in the critical path. Given this variance, one can calculate the probability that
the project will be completed by a certain date assuming a normal probability distribution for the critical path.
The normal distribution assumption holds if the number of activities in the path is large enough for the central
limit theorem to be applied. So, there would be 50% probability of completing a project if desired time and
expected completion times are equal to each other. Since the critical path determines the completion date of the
project, the project can be accelerated by adding the resources required to decrease the time for the activities in
the critical path. Such a shortening of the project is referred as project crashing. Therefore, crashing is spending
more money on the project in order to speed up accomplishment of scheduled activities [3]. Since crashing a
project requires additional costs, crashing decisions need to be made in a cost-effective way [4]. Several
simulation based crashing methods are developed in past two decades. These methods are heuristics that are
developed to return satisfactory solutions but not necessarily an optimal solution. This research endeavored to
generate an algorithm for optimum crashing method to minimize the required cost while meeting a specified
completion time.
II. LITERATURE REVIEW
Van Slyke (1963) was the first of many researchers to apply Monte Carlo simulations to study PERT
[5]. Pritsker and Happ (1966) developed a modification of PERT called the Graphical Evaluation and Review
Technique (GERT) [6]. Kennedy and Thrall (1976) developed a modification of GERT called Project Length
Analysis and Evaluation Technique (PLANET) [7]. Ameen (1987) developed Computer Assisted PERT
Simulation (CAPERTSIM) [8]. Badiru (1991) reported development of another simulation program for project
management, called STARC [9]. Bissiri and Dunbar (1999) suggested the use of simulation to obtain the
average time of each activity, the critical path, and the near critical paths to crash a project network. A near
critical path in their model is a path which length is smaller than the original completion date but it is larger than
the target completion date after crashing. After the path information is collected a linear program is applied to
determine the crashing strategy [10]. Haga (1998) [11] along with Haga and O’keffe (2001) [2], also Haga and
Marold (2004) [12], and Haga and Marold (2005) [13] worked with heuristic crashing methods for project
management utilizing simulation. Haga and Marold (2004), propose a simulation-based method that deals with
the time-cost trade-off involved with crashing a project. The method that they proposed is a two steps approach.
The first step is to apply the traditional PERT method to crash the project, and the second step consists in testing
each activity that had not been crashed to the upper crashing limit to determine if crashing that activity further
reduces the average total cost of the project. Haga and Marold (2005) developed a method to monitor and
control a project. The output of this method is a list of crashing points at which the project should be reviewed
to decide if activities need to be crashed. Crashing points are determined by a backward run through the project
network. The crashing points are established at the beginning of the project and they remain fixed during the
entire project life.
III. PROJECT CRASHING ALGORITHM
The project crashing algorithm described in this section is designed to give the mathematically correct
time-cost trade-off curve for small project networks which are to be solved by hand. The algorithm proceeds
from a network description of the project and the normal and crash times and durations for the project activities
to a set of tables which enable the time-cost trade-off graph to be plotted. The three tables are the project activity
marginal cost list with available compression, a path list for the project network, and a breakpoint table for the
Complex Project Crashing Algorithm
www.iosrjournals.org 12 | Page
steps in the project crashing process. These will be developed for an illustrative numerical example after a
general statement of the algorithm is given.
GENERAL ALGORITHM SPECIFICATION
Step1. Each activity is assumed to have a known Normal cost if completed in a Normal time, and a (larger)
Crash Cost if completed in a (shorter) Crash time. Compute the marginal crashing costs (i.e. cost per unit time)
for each activity according to the following formula:
Marginal Cost = (change in cost)/(change in time) = (Crash cost - Normal cost)/(Normal time - Crash time)
Place these marginal costs in the first column of the project activity list. Place the number of time periods of
crashing availability in the second column of the table.
Step2. Enumerate all the paths through the project network, and list them with their normal time durations in the
path list. Identify the critical path(s) as those with longest duration, and mark the critical activities as such in the
third column of the project activity list started in Step1.
Step3. Identify the normal project duration, the normal project cost and the normal critical path in the first row
of the breakpoint table, labeled as iteration 0.
Step4. Select that subset of critical activities which, when compressed in parallel, enable all current critical
paths to become shorter, and do so at the least group marginal cost, where the group marginal cost for a subset
of critical activities is the sum of the marginal costs for activities in the group.
Step5. Compress the selected critical activities until one or both of the following two conditions occur: (i) one
(or more) of the compressed activities becomes fully crashed (i.e. is reduced to crash time); or (ii) a new path
becomes critical.
Step6. Record the selected activities, number of time periods compressed, the new project duration, the group
marginal cost for the selected activities, the added cost resulting from the compression, the new total direct cost,
and the new critical path (if any) as items in the breakpoint table for this iteration. Update the compression
availabilities and the path list to reflect the reduction in path lengths resulting from the selected compression.
Step7. Repeat steps 4 through 6 until all activities on some (any) critical path become fully crashed. At this
point the breakpoint table is complete, as no further time reduction is possible. Plot the time-cost trade-off graph
by linear interpolation between the time/cost pairs which occur in each row of the breakpoint table.
Algorithm Summery
I. Calculate cost slope of each activity of the project
II. Identify critical path and find the expected duration of the project
III. Select among the activities on critical path an activity which has least cost slope. For more than one
critical path, select one activity on each critical path such that total cost of crashing all these activities is
minimum among all such combinations of activities
IV. Reduce the activity time of the selected activity progressively until either crashed time is reached or the
previous non-critical parallel path becomes critical
V. Proceed above steps until there is at least one critical path on which none of the activities can be further
crashed
NUMERICAL EXAMPLE
The activities involved in the project, the precedence relations between them, and the activity durations
in weeks are shown in the following table:
TABLE 1: Activities and Immediate Predecessors
Activity Description Predecessor
Duration
(weeks)
A
Build internal
components None 2
B Modify roof and floor None 3
C
Construct collection
stack A 2
D
Pour concrete and
install frame B 4
E
Build high-
temperature burner C 4
F Install control system C 3
G
Install air pollution
device D,E 5
H Inspection and testing F,G 2
Complex Project Crashing Algorithm
www.iosrjournals.org 13 | Page
The network representation of the project is given in the following figure:
FIGURE 1: Project’s Network Diagram
An analysis of early times shows that the duration of the project given the normal activity times is 15
weeks, which is 3 weeks longer than has been allotted for the project. Hence, the project time must be reduced,
but the time reduction must be accomplished at least cost. Therefore, a tabulation of the normal and crash times
and costs for each activity is compiled from time and cost estimates, with the following result:
TABLE 2: Normal and Crash Data
Times (weeks) Cost ($)
Activity Normal Crash Normal Crash
A 2 1 22,000 22,900
B 3 1 30,000 34,000
C 2 1 26,000 26,800
D 4 3 48,000 49,000
E 4 2 56,000 57,400
F 3 2 30,000 30,500
G 5 2 80,000 86,000
H 2 1 16,000 19,000
The first step in the procedure is to compute the marginal crash costs and the available compression for
each project activity in the project activity table, as shown below.
ACTIVITY CRASH COST
PER WEEK
AVAILABLE
COMPRESSION
CRITICAL
OR, NOT
A $900 1 Y
B 2000 2 N
C 800 1 Y
D 1000 1 N
E 700 2 Y
F 500 1 N
G 2000 3 Y
H 3000 1 Y
The second step is to enumerate all the possible paths through the project network and list them in the
path list for the project. (Recall that a path must respect the direction indicated on each directed arc, so that B-D-
E-F-H, for example, would not be an admissible path). The path lengths using normal times are listed in the first
column.
Complex Project Crashing Algorithm
www.iosrjournals.org 14 | Page
A-C-F-H 9
A-C-E-G-H 15
B-D-G-H 14
Examination of the marginal costs for the activities on the critical path A-C-E-G-H reveals that the
minimum marginal cost occurs for activity E at $700 per week. We see that there are two weeks of compression
available for activity E. However, we must also check the path list to see if any new paths become critical as we
compress activity E. Since activity E only occurs on the second path, the first and third path stay at constant
duration as E is compressed. This means that the third path, B-D-G-H, becomes critical after E is crashed only
one week. Thus the first breakpoint recorded in the breakpoint table occurs after activity E is compressed just
one week.
Iter. Activities
Crashed
Crashed
by
Project
Duration
Group
M/C
Added
Cost
Total
Costs
New Critical
Path
0 - - 15 - - 308,000 A-C-E-G-H
1 E 1 14 700 700 308,700 B-D-G-H
Update the compression available for E to 1. Updating the path list accordingly yields:
A-C-F-H 9 9
A-C-E-G-H 15 14
B-D-G-H 14 14
Returning now to step 4, we seek the least cost combination of activities which, when compressed in
parallel, will enable both critical paths to become shorter. Now we have a choice, since the two critical paths
overlap on the G-H part of the paths. We can either crash one activity, G or H, which is common to both CP-s,
or we can crash two activities in parallel, one from the A-C-E branch and one from the B-D branch. Comparing
the marginal costs for G and H, we find that of these two, G would have the lesser marginal cost at $2,000 per
week. Along the A-C-E branch, E has the least marginal cost at $700 per week. Along the B-D branch, D has
the least marginal cost at $1,000 per week. Thus the D&E combination has a group marginal cost of only $1,700
in comparison with $2,000 per week for G. Thus our next step is to compress D&E together. Since there is only
one week of compression available on D and on E, the next step is to crash D&E together by one week.
Iter. Activities
Crashed
Crashed
by
Project
Duration
Group
M/C
Added
Cost
Total
Costs
New Critical
Path
0 - - 15 - - 308,000 A-C-E-G-H
1 E 1 14 700 700 308,700 B-D-G-H
2 D&E 1 13 1700 1700 310,400
Reduce the availability of D and E to zero. Updating the path list accordingly results in:
A-C-F-H 9 9 9
A-C-E-G-H 15 14 13
B-D-G-H 14 14 13
Complex Project Crashing Algorithm
www.iosrjournals.org 15 | Page
Since both D and E are fully crashed, the least cost activity from the A-C-E branch is C at $800 per
week, and the least cost activity from the B-D branch is B at $2,000, so the C&B combination at $2,800 is the
best that can be done using two activities in parallel. Since this is more than the $2,000 per week cost of activity
G, our next step is to crash G. And since G is on both critical paths, we can crash it the full three weeks that are
available for this activity. The breakpoint table then becomes as follows.
Iter. Activities
Crashed
Crashed
by
Project
Duration
Group
M/C
Added
Cost
Total
Costs
New Critical
Path
0 - - 15 - - 308,000 A-C-E-G-H
1 E 1 14 700 700 308,700 B-D-G-H
2 D&E 1 13 1700 1700 310,400
3 G 3 10 2000 6000 316,400
Reduce the availability of G to zero. Updating the path list yields:
A-C-F-H 9 9 9 9
A-C-E-G-H 15 14 13 10
B-D-G-H 14 14 13 10
Since G is now fully crashed, activity H is the only one activity which will cause both critical paths to
become shorter, and it costs $3,000 per week. Thus the C&B combination is the least cost available at this point,
so the next step is to crash B and C in parallel. In this case all three paths get shorter together, so no new critical
paths occur. However, C has only one week of compression available, so the C&B combination can be
compressed only one week. Thus the next breakpoint table is as follows.
Iter. Activities
Crashed
Crashed
by
Project
Duration
Group
M/C
Added
Cost
Total
Costs
New Critical Path
0 - - 15 - - 308,000 A-C-E-G-H
1 E 1 14 700 700 308,700 B-D-G-H
2 D&E 1 13 1700 1700 310,400
3 G 3 10 2000 6000 316,400
4 B&C 1 9 2800 2800 319,200
Reduce the availability of B to 1 and C to zero. The updated path list becomes:
A-C-F-H 9 9 9 9 8
A-C-E-G-H 15 14 13 10 9
B-D-G-H 14 14 13 10 9
At this point A and B are the only two activities on the upper and lower branches with remaining
compression availability, and their combined cost is $2,900 which is still less than the $3,000 for activity H and
since they each have only 1 week of compression remaining, the next step is to crash A&B together by a week.
Complex Project Crashing Algorithm
www.iosrjournals.org 16 | Page
Iter. Activities
Crashed
Crashed
By
Project
Duration
Group
M/C
Added
Cost
Total
Cost
New Critical
Path
0 - - 15 - - 308,000 A-C-E-G-H
1 E 1 14 700 700 308,700 B-D-G-H
2 D&E 1 13 1700 1700 310,400
3 G 3 10 2000 6000 316,400
4 B&C 1 9 2800 2800 319,200
5 A&B 1 8 2900 2900 322,100
The availability of A and B are reduced to zero. The updated path list becomes:
A-C-F-H 9 9 9 9 8 7
A-C-E-G-H 15 14 13 10 9 8
B-D-G-H 14 14 13 10 9 8
At this point H is the only activity left to shorten the last two paths, and only one week of compression
is available, so the final step in the breakpoint table is to compress H by one week.
Iter. Activities
Crashed
Crashed
by
Project
Duration
Group
M/C
Added
Cost
Total
Costs
New Critical
Path
0 - - 15 - - 308,000 A-C-E-G-H
1 E 1 14 700 700 308,700 B-D-G-H
2 D&E 1 13 1700 1700 310,400
3 G 3 10 2000 6000 316,400
4 B&C 1 9 2800 2800 319,200
5 A&B 1 8 2900 2900 322,100
6 H 1 7 3000 3000 325,100
The final path list is therefore:
A-C-F-H 9 9 9 9 8 7 6
A-C-E-G-H 15 14 13 10 9 8 7
B-D-G-H 14 14 13 10 9 8 7
Since both critical paths are now fully crashed, the project crashing process is complete. The optimal
time-cost trade-off values are contained in the project duration and project cost columns of the final breakpoint
table. The final step of the process is to graph these points and connect them with straight line segments, as
shown on Figure 2 [given on next page].
The only remaining task is to interpolate for the project cost corresponding to the 12 week project
duration. Since this is just one week less than the 13 week solution in the breakpoint table, activity G will be
crashed only one week rather than three, so the project cost for the 12 week schedule will be $310,400 plus
Complex Project Crashing Algorithm
www.iosrjournals.org 17 | Page
$2,000 or $312,400. This result can be computed directly from the final breakpoint table, but the shape of the
complete trade-off curve is of interest as well, and is more easily seen from the chart.
IV. CONCLUSION
In this paper the algorithm proposed for unit crashing reduces the cost of project. When activities are
crashed by one day then only the crashing cost corresponding to one day is increased thereby reducing the
project duration as well as cost. The purpose of this study was to explore the suitability of a new method to
crash PERT networks. This approach is well suitable for places where cost is of major consideration. Plans for
future research include running the simulation on additional networks, preferably real-world projects.
FIGURE 2: Time-Cost Trade-Off Diagram
REFERENCES
[1] Lee, D., and Arditi, D. (2006) Automated statistical analysis in stochastic project scheduling simulation. Journal of Construction
Engineering and Management, 132(3): 268-277.
[2] Haga, W. A. & Tim O’keefe. (July 14, 2001) Crashing Pert Networks: A Simulation Approach. 4th International conference of
the Academy of Business and Administrative Sciences Conference Quebec City, Canada.
[3] Rosenau, M. D. and G. D. Githens. (2005) Successful Project Management: a Step-by-step Approach with Practical Examples.
4th Ed., Wiley, Hoboken, N.J.
[4] Michael E. Kuhl and Radhamés A. Tolentino-Peña. (2008) A Dynamic Crashing Method For Project Management Using
Simulation-Based Optimization. Winter Simulation Conference, S. J. Mason, R. R. Hill, L. Mönch, O. Rose, T. Jefferson, J. W.
Fowler eds.
[5] Van Slyke, R. M. (1963). Monte Carlo methods and the PERT problem; Operations Research, 13, 141-143.
[6] Pritsker, A. B. & Happ, W. W. (1966). GERT: Graphical evaluation and review technique, Part-I, Fundamental Journal of
Industrial Engineering, 17(5), 267-274.
[7] Kennedy, K. W. & Thrall, R. M. (1976). PLANET: A Simulation approach to PERT; Computers and Operations Research, 3,
313-325.
[8] Ameen, D. A. (April 1987). A computer assisted PERT simulation. Journal of Systems Management, 6-9.
[9] Badiru, A. B. (1991). A simulation approach to network analysis. Simulation, 57, (4), 245-255.
[10] Bissiri, Y., and S. Dunbar. (1999). Resource allocation model for a fast-tracked project. International Conference on Intelligent
Processing and Manufacturing of Materials, 635-640.
[11] Haga, W. A. (1998). Crashing PERT networks; Ph.D. Dissertation, University of Northern Colorado, Colorado.
[12] Haga, W. A., and K. A. Marold. (2004). A simulation approach to the PERT-CPM time-cost trade-off problem. Project
Management Journal, 35(2): 31-37.
[13] Haga, W. A., and K. A. Marold. (2005). Monitoring and control of PERT networks. The Business Review, 3(2): 240-245.

Mais conteúdo relacionado

Mais procurados

Mais procurados (14)

Cpmpert
CpmpertCpmpert
Cpmpert
 
Roles of project managers in oe
Roles of project managers in oeRoles of project managers in oe
Roles of project managers in oe
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean Construction
 
The Process of Project Selection
The Process of Project SelectionThe Process of Project Selection
The Process of Project Selection
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project Organization and Structure
Project Organization and StructureProject Organization and Structure
Project Organization and Structure
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Senior executive performance appraisal
Senior executive performance appraisalSenior executive performance appraisal
Senior executive performance appraisal
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
Project management
Project managementProject management
Project management
 
Lean Construction Management
Lean Construction Management Lean Construction Management
Lean Construction Management
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 

Destaque

Design and Analysis of Triple-Band Multi Slotted Microstrip Patch Antenna
Design and Analysis of Triple-Band Multi Slotted Microstrip Patch AntennaDesign and Analysis of Triple-Band Multi Slotted Microstrip Patch Antenna
Design and Analysis of Triple-Band Multi Slotted Microstrip Patch AntennaIOSR Journals
 
Evaluation of Wash and Light Fastness of Some Selected Printed Fabrics
Evaluation of Wash and Light Fastness of Some Selected Printed FabricsEvaluation of Wash and Light Fastness of Some Selected Printed Fabrics
Evaluation of Wash and Light Fastness of Some Selected Printed FabricsIOSR Journals
 
Sustaining Value Creation through Knowledge of Customer Expectations
Sustaining Value Creation through Knowledge of Customer ExpectationsSustaining Value Creation through Knowledge of Customer Expectations
Sustaining Value Creation through Knowledge of Customer ExpectationsIOSR Journals
 
Project Managers Vs Operations Managers: A comparison based on the style of l...
Project Managers Vs Operations Managers: A comparison based on the style of l...Project Managers Vs Operations Managers: A comparison based on the style of l...
Project Managers Vs Operations Managers: A comparison based on the style of l...IOSR Journals
 
Automatic DNA Sequence Generation for Secured Effective Multi -Cloud Storage
Automatic DNA Sequence Generation for Secured Effective Multi -Cloud StorageAutomatic DNA Sequence Generation for Secured Effective Multi -Cloud Storage
Automatic DNA Sequence Generation for Secured Effective Multi -Cloud StorageIOSR Journals
 
Performance Evaluation of Basic Segmented Algorithms for Brain Tumor Detection
Performance Evaluation of Basic Segmented Algorithms for Brain Tumor DetectionPerformance Evaluation of Basic Segmented Algorithms for Brain Tumor Detection
Performance Evaluation of Basic Segmented Algorithms for Brain Tumor DetectionIOSR Journals
 
Computer aided environment for drawing (to set) fill in the blank from given ...
Computer aided environment for drawing (to set) fill in the blank from given ...Computer aided environment for drawing (to set) fill in the blank from given ...
Computer aided environment for drawing (to set) fill in the blank from given ...IOSR Journals
 
Effect of glycine as an impurity on the properties of Epsomite single crystals
Effect of glycine as an impurity on the properties of Epsomite single crystalsEffect of glycine as an impurity on the properties of Epsomite single crystals
Effect of glycine as an impurity on the properties of Epsomite single crystalsIOSR Journals
 
Exploring the Effect of Web Based Communications on Organizations Service Qua...
Exploring the Effect of Web Based Communications on Organizations Service Qua...Exploring the Effect of Web Based Communications on Organizations Service Qua...
Exploring the Effect of Web Based Communications on Organizations Service Qua...IOSR Journals
 
Factors Influencing the Choice of Promotional Practices of Agricultural Equip...
Factors Influencing the Choice of Promotional Practices of Agricultural Equip...Factors Influencing the Choice of Promotional Practices of Agricultural Equip...
Factors Influencing the Choice of Promotional Practices of Agricultural Equip...IOSR Journals
 
Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...
Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...
Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...IOSR Journals
 
Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...
Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...
Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...IOSR Journals
 
Influence of the speed in advance and the laser’s power on the zone affected ...
Influence of the speed in advance and the laser’s power on the zone affected ...Influence of the speed in advance and the laser’s power on the zone affected ...
Influence of the speed in advance and the laser’s power on the zone affected ...IOSR Journals
 
Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...
Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...
Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...IOSR Journals
 
Fluidization Characteristics of Nano Particles with the Assist of Stirrer
Fluidization Characteristics of Nano Particles with the Assist of StirrerFluidization Characteristics of Nano Particles with the Assist of Stirrer
Fluidization Characteristics of Nano Particles with the Assist of StirrerIOSR Journals
 
Automatic Controlling Of Train Using Wireless Protocol Zigbee
Automatic Controlling Of Train Using Wireless Protocol Zigbee Automatic Controlling Of Train Using Wireless Protocol Zigbee
Automatic Controlling Of Train Using Wireless Protocol Zigbee IOSR Journals
 
Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...
Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...
Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...IOSR Journals
 

Destaque (20)

Design and Analysis of Triple-Band Multi Slotted Microstrip Patch Antenna
Design and Analysis of Triple-Band Multi Slotted Microstrip Patch AntennaDesign and Analysis of Triple-Band Multi Slotted Microstrip Patch Antenna
Design and Analysis of Triple-Band Multi Slotted Microstrip Patch Antenna
 
Evaluation of Wash and Light Fastness of Some Selected Printed Fabrics
Evaluation of Wash and Light Fastness of Some Selected Printed FabricsEvaluation of Wash and Light Fastness of Some Selected Printed Fabrics
Evaluation of Wash and Light Fastness of Some Selected Printed Fabrics
 
J010515361
J010515361J010515361
J010515361
 
Sustaining Value Creation through Knowledge of Customer Expectations
Sustaining Value Creation through Knowledge of Customer ExpectationsSustaining Value Creation through Knowledge of Customer Expectations
Sustaining Value Creation through Knowledge of Customer Expectations
 
M017127578
M017127578M017127578
M017127578
 
Project Managers Vs Operations Managers: A comparison based on the style of l...
Project Managers Vs Operations Managers: A comparison based on the style of l...Project Managers Vs Operations Managers: A comparison based on the style of l...
Project Managers Vs Operations Managers: A comparison based on the style of l...
 
Automatic DNA Sequence Generation for Secured Effective Multi -Cloud Storage
Automatic DNA Sequence Generation for Secured Effective Multi -Cloud StorageAutomatic DNA Sequence Generation for Secured Effective Multi -Cloud Storage
Automatic DNA Sequence Generation for Secured Effective Multi -Cloud Storage
 
Performance Evaluation of Basic Segmented Algorithms for Brain Tumor Detection
Performance Evaluation of Basic Segmented Algorithms for Brain Tumor DetectionPerformance Evaluation of Basic Segmented Algorithms for Brain Tumor Detection
Performance Evaluation of Basic Segmented Algorithms for Brain Tumor Detection
 
Computer aided environment for drawing (to set) fill in the blank from given ...
Computer aided environment for drawing (to set) fill in the blank from given ...Computer aided environment for drawing (to set) fill in the blank from given ...
Computer aided environment for drawing (to set) fill in the blank from given ...
 
A012610106
A012610106A012610106
A012610106
 
Effect of glycine as an impurity on the properties of Epsomite single crystals
Effect of glycine as an impurity on the properties of Epsomite single crystalsEffect of glycine as an impurity on the properties of Epsomite single crystals
Effect of glycine as an impurity on the properties of Epsomite single crystals
 
Exploring the Effect of Web Based Communications on Organizations Service Qua...
Exploring the Effect of Web Based Communications on Organizations Service Qua...Exploring the Effect of Web Based Communications on Organizations Service Qua...
Exploring the Effect of Web Based Communications on Organizations Service Qua...
 
Factors Influencing the Choice of Promotional Practices of Agricultural Equip...
Factors Influencing the Choice of Promotional Practices of Agricultural Equip...Factors Influencing the Choice of Promotional Practices of Agricultural Equip...
Factors Influencing the Choice of Promotional Practices of Agricultural Equip...
 
Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...
Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...
Restoration of Images Corrupted by High Density Salt & Pepper Noise through A...
 
Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...
Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...
Shear Stress Prediction Using FEA-ANN Hybrid Modeling Of Eicher 11.10 Chassis...
 
Influence of the speed in advance and the laser’s power on the zone affected ...
Influence of the speed in advance and the laser’s power on the zone affected ...Influence of the speed in advance and the laser’s power on the zone affected ...
Influence of the speed in advance and the laser’s power on the zone affected ...
 
Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...
Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...
Leisure Patterns Among Nigerian University Lecturers: the Potential for Leisu...
 
Fluidization Characteristics of Nano Particles with the Assist of Stirrer
Fluidization Characteristics of Nano Particles with the Assist of StirrerFluidization Characteristics of Nano Particles with the Assist of Stirrer
Fluidization Characteristics of Nano Particles with the Assist of Stirrer
 
Automatic Controlling Of Train Using Wireless Protocol Zigbee
Automatic Controlling Of Train Using Wireless Protocol Zigbee Automatic Controlling Of Train Using Wireless Protocol Zigbee
Automatic Controlling Of Train Using Wireless Protocol Zigbee
 
Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...
Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...
Efficient Sub Area Tree Routing Protocol (Estr) For Collision Avoidance in Mo...
 

Semelhante a Complex Project Crashing Algorithm Optimization

12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET Journal
 
Overview1) Overview – The continued discussion of .docx
Overview1)             Overview – The continued discussion of .docxOverview1)             Overview – The continued discussion of .docx
Overview1) Overview – The continued discussion of .docxalfred4lewis58146
 
Overview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxOverview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxalfred4lewis58146
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxjeffevans62972
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPMPadamNepal1
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 

Semelhante a Complex Project Crashing Algorithm Optimization (20)

12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Overview1) Overview – The continued discussion of .docx
Overview1)             Overview – The continued discussion of .docxOverview1)             Overview – The continued discussion of .docx
Overview1) Overview – The continued discussion of .docx
 
Overview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxOverview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docx
 
Project management
Project managementProject management
Project management
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
 
Project management
Project managementProject management
Project management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 

Mais de IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Último

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 

Último (20)

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 

Complex Project Crashing Algorithm Optimization

  • 1. IOSR Journal of Business and Management (IOSR-JBM) e-ISSN: 2278-487X, p-ISSN: 2319-7668. Volume 11, Issue 4 (Jul. - Aug. 2013), PP 10-17 www.iosrjournals.org www.iosrjournals.org 10 | Page Complex Project Crashing Algorithm Nafish Sarwar Islam (Department of Business Administration, East West University, Bangladesh) Abstract: Crashing is the procedure by which project duration can be shorten up by expediting selective activities with in the project. But it requires allocating more resources than usual to compress an activity’s duration, which in turns increases the budget of that activity. So, crashing is basically a time-cost trade-off by which specific deadline can be achieved. The traditional method of crashing only considers average activity times for the calculation of the critical path, ignoring the stochastic nature of activity time. This report is written to develop an algorithm for optimum crashing method to minimize the required cost while attaining a specified completion time. Keywords – Critical Path, Project Crashing Algorithm, Time-Cost Trade-Off I. INTRODUCTION Two of the most popular approaches to project management are the Critical Path Method (CPM) and the Project Evaluation and Review Technique (PERT), which were developed short after the World War II. The Critical Path Method (CPM) and the Project Evaluation and Review Technique (PERT) methods have been used since the 1950s to estimate the completion time of a project. CPM is a deterministic approach to calculate the duration of a project, and PERT is a probabilistic approach that enhances CPM by considering uncertainty in activity durations by calculating the probability to complete the project by a given time [1]. J.E. Kelly of Remington-Rand and M.B. Walker of DuPont developed CPM in the 1957 to assist in scheduling maintenance shutdowns of chemical processing plants. While PERT was developed shortly after by the U.S. Navy to manage the development of the Polaris missile. The original PERT Navy report (1958) does not identify the names of developers [2]. Both CPM and PERT are network based techniques, where PERT can be considered as an extension of CPM. After constructing the network diagram from precedence relationships and duration times PERT planning involves the following steps: (i) Estimating the time required for each activity (ii) Calculating slack time of each activity (iii) Determining the critical path(s) (iv) Project crashing (i) Estimating the Time Required for Each Activity A distinguishing feature of PERT is to deal with the uncertainty in activity completion times. The model includes three time estimates which are considered to follow the generalized beta distribution: Optimistic time (a): the shortest time in which the activity can be completed. Most likely time (m): the completion time having the highest probability. Pessimistic time (b): the longest time that an activity might require. The expected time for each activity can be estimated using the following weighted average: Expected time = [(a + 4m + b) / 6]; and the variance is: Variance = [(b - a) / 6]2 (ii) Calculating Slack time of Each Activity The amount of time that a non-critical path activity can be delayed without delaying the project is referred to as slack time. As a matter of fact activities within the critical path(s) have a zero slack value. So if activities outside the critical path speed up or slow down up to their available slack time, the total project time does not change. To calculate slack time it is required to find out the following four values of each activity: ES – Earliest Start time, EF - Earliest Finish time, LS - Latest Start time, LF - Latest Finish time. These times are calculated using the expected time for the relevant activities. The earliest start and finish times of each activity are determined by working forward through the network and determining the earliest time at which an activity can start and finish considering its predecessor activities. The latest start and finish times are found by working backward through the network and determining the latest time that an activity Submitted date 12 June 2013 Accepted Date: 17 June 2013
  • 2. Complex Project Crashing Algorithm www.iosrjournals.org 11 | Page can start and finish without delaying the project considering the particular activity is predecessor of how many activities. The difference in the latest and earliest finish of each activity is that activity's slack; Slack Time = (Ls – Es). (iii) Determining the Critical Path(s) The critical path is determined by adding the times for the activities in each sequence and determining the longest path in the project. That is why critical path determines the total completion time required for the project. For instance, if a project network diagram has 14 available paths, and by adding the times for the activities in path number 1, 4 and 7 gives the highest value compared to others, then that value would be the project completion time, while path number 1, 4 and 7 will be the critical paths. Now say “C” is an activity which is not available in critical paths, but available in path number 3, 6, 8 and 11 and among these four paths path number 11 gives maximum value if we add the times for the activities in path number 3, 6, 8 and 11. So, slack time of activity “C” can be calculated by subtracting the total duration of path number 11 from the total duration of any critical path 1, 4 or, 7; which is the project duration. Thus project’s critical path(s) can be identified by considering the path(s) through the network in which none of the activities have slack. (iv) Project Crashing The variance in the project completion time can be calculated by summing the variances in the completion times of the activities in the critical path. Given this variance, one can calculate the probability that the project will be completed by a certain date assuming a normal probability distribution for the critical path. The normal distribution assumption holds if the number of activities in the path is large enough for the central limit theorem to be applied. So, there would be 50% probability of completing a project if desired time and expected completion times are equal to each other. Since the critical path determines the completion date of the project, the project can be accelerated by adding the resources required to decrease the time for the activities in the critical path. Such a shortening of the project is referred as project crashing. Therefore, crashing is spending more money on the project in order to speed up accomplishment of scheduled activities [3]. Since crashing a project requires additional costs, crashing decisions need to be made in a cost-effective way [4]. Several simulation based crashing methods are developed in past two decades. These methods are heuristics that are developed to return satisfactory solutions but not necessarily an optimal solution. This research endeavored to generate an algorithm for optimum crashing method to minimize the required cost while meeting a specified completion time. II. LITERATURE REVIEW Van Slyke (1963) was the first of many researchers to apply Monte Carlo simulations to study PERT [5]. Pritsker and Happ (1966) developed a modification of PERT called the Graphical Evaluation and Review Technique (GERT) [6]. Kennedy and Thrall (1976) developed a modification of GERT called Project Length Analysis and Evaluation Technique (PLANET) [7]. Ameen (1987) developed Computer Assisted PERT Simulation (CAPERTSIM) [8]. Badiru (1991) reported development of another simulation program for project management, called STARC [9]. Bissiri and Dunbar (1999) suggested the use of simulation to obtain the average time of each activity, the critical path, and the near critical paths to crash a project network. A near critical path in their model is a path which length is smaller than the original completion date but it is larger than the target completion date after crashing. After the path information is collected a linear program is applied to determine the crashing strategy [10]. Haga (1998) [11] along with Haga and O’keffe (2001) [2], also Haga and Marold (2004) [12], and Haga and Marold (2005) [13] worked with heuristic crashing methods for project management utilizing simulation. Haga and Marold (2004), propose a simulation-based method that deals with the time-cost trade-off involved with crashing a project. The method that they proposed is a two steps approach. The first step is to apply the traditional PERT method to crash the project, and the second step consists in testing each activity that had not been crashed to the upper crashing limit to determine if crashing that activity further reduces the average total cost of the project. Haga and Marold (2005) developed a method to monitor and control a project. The output of this method is a list of crashing points at which the project should be reviewed to decide if activities need to be crashed. Crashing points are determined by a backward run through the project network. The crashing points are established at the beginning of the project and they remain fixed during the entire project life. III. PROJECT CRASHING ALGORITHM The project crashing algorithm described in this section is designed to give the mathematically correct time-cost trade-off curve for small project networks which are to be solved by hand. The algorithm proceeds from a network description of the project and the normal and crash times and durations for the project activities to a set of tables which enable the time-cost trade-off graph to be plotted. The three tables are the project activity marginal cost list with available compression, a path list for the project network, and a breakpoint table for the
  • 3. Complex Project Crashing Algorithm www.iosrjournals.org 12 | Page steps in the project crashing process. These will be developed for an illustrative numerical example after a general statement of the algorithm is given. GENERAL ALGORITHM SPECIFICATION Step1. Each activity is assumed to have a known Normal cost if completed in a Normal time, and a (larger) Crash Cost if completed in a (shorter) Crash time. Compute the marginal crashing costs (i.e. cost per unit time) for each activity according to the following formula: Marginal Cost = (change in cost)/(change in time) = (Crash cost - Normal cost)/(Normal time - Crash time) Place these marginal costs in the first column of the project activity list. Place the number of time periods of crashing availability in the second column of the table. Step2. Enumerate all the paths through the project network, and list them with their normal time durations in the path list. Identify the critical path(s) as those with longest duration, and mark the critical activities as such in the third column of the project activity list started in Step1. Step3. Identify the normal project duration, the normal project cost and the normal critical path in the first row of the breakpoint table, labeled as iteration 0. Step4. Select that subset of critical activities which, when compressed in parallel, enable all current critical paths to become shorter, and do so at the least group marginal cost, where the group marginal cost for a subset of critical activities is the sum of the marginal costs for activities in the group. Step5. Compress the selected critical activities until one or both of the following two conditions occur: (i) one (or more) of the compressed activities becomes fully crashed (i.e. is reduced to crash time); or (ii) a new path becomes critical. Step6. Record the selected activities, number of time periods compressed, the new project duration, the group marginal cost for the selected activities, the added cost resulting from the compression, the new total direct cost, and the new critical path (if any) as items in the breakpoint table for this iteration. Update the compression availabilities and the path list to reflect the reduction in path lengths resulting from the selected compression. Step7. Repeat steps 4 through 6 until all activities on some (any) critical path become fully crashed. At this point the breakpoint table is complete, as no further time reduction is possible. Plot the time-cost trade-off graph by linear interpolation between the time/cost pairs which occur in each row of the breakpoint table. Algorithm Summery I. Calculate cost slope of each activity of the project II. Identify critical path and find the expected duration of the project III. Select among the activities on critical path an activity which has least cost slope. For more than one critical path, select one activity on each critical path such that total cost of crashing all these activities is minimum among all such combinations of activities IV. Reduce the activity time of the selected activity progressively until either crashed time is reached or the previous non-critical parallel path becomes critical V. Proceed above steps until there is at least one critical path on which none of the activities can be further crashed NUMERICAL EXAMPLE The activities involved in the project, the precedence relations between them, and the activity durations in weeks are shown in the following table: TABLE 1: Activities and Immediate Predecessors Activity Description Predecessor Duration (weeks) A Build internal components None 2 B Modify roof and floor None 3 C Construct collection stack A 2 D Pour concrete and install frame B 4 E Build high- temperature burner C 4 F Install control system C 3 G Install air pollution device D,E 5 H Inspection and testing F,G 2
  • 4. Complex Project Crashing Algorithm www.iosrjournals.org 13 | Page The network representation of the project is given in the following figure: FIGURE 1: Project’s Network Diagram An analysis of early times shows that the duration of the project given the normal activity times is 15 weeks, which is 3 weeks longer than has been allotted for the project. Hence, the project time must be reduced, but the time reduction must be accomplished at least cost. Therefore, a tabulation of the normal and crash times and costs for each activity is compiled from time and cost estimates, with the following result: TABLE 2: Normal and Crash Data Times (weeks) Cost ($) Activity Normal Crash Normal Crash A 2 1 22,000 22,900 B 3 1 30,000 34,000 C 2 1 26,000 26,800 D 4 3 48,000 49,000 E 4 2 56,000 57,400 F 3 2 30,000 30,500 G 5 2 80,000 86,000 H 2 1 16,000 19,000 The first step in the procedure is to compute the marginal crash costs and the available compression for each project activity in the project activity table, as shown below. ACTIVITY CRASH COST PER WEEK AVAILABLE COMPRESSION CRITICAL OR, NOT A $900 1 Y B 2000 2 N C 800 1 Y D 1000 1 N E 700 2 Y F 500 1 N G 2000 3 Y H 3000 1 Y The second step is to enumerate all the possible paths through the project network and list them in the path list for the project. (Recall that a path must respect the direction indicated on each directed arc, so that B-D- E-F-H, for example, would not be an admissible path). The path lengths using normal times are listed in the first column.
  • 5. Complex Project Crashing Algorithm www.iosrjournals.org 14 | Page A-C-F-H 9 A-C-E-G-H 15 B-D-G-H 14 Examination of the marginal costs for the activities on the critical path A-C-E-G-H reveals that the minimum marginal cost occurs for activity E at $700 per week. We see that there are two weeks of compression available for activity E. However, we must also check the path list to see if any new paths become critical as we compress activity E. Since activity E only occurs on the second path, the first and third path stay at constant duration as E is compressed. This means that the third path, B-D-G-H, becomes critical after E is crashed only one week. Thus the first breakpoint recorded in the breakpoint table occurs after activity E is compressed just one week. Iter. Activities Crashed Crashed by Project Duration Group M/C Added Cost Total Costs New Critical Path 0 - - 15 - - 308,000 A-C-E-G-H 1 E 1 14 700 700 308,700 B-D-G-H Update the compression available for E to 1. Updating the path list accordingly yields: A-C-F-H 9 9 A-C-E-G-H 15 14 B-D-G-H 14 14 Returning now to step 4, we seek the least cost combination of activities which, when compressed in parallel, will enable both critical paths to become shorter. Now we have a choice, since the two critical paths overlap on the G-H part of the paths. We can either crash one activity, G or H, which is common to both CP-s, or we can crash two activities in parallel, one from the A-C-E branch and one from the B-D branch. Comparing the marginal costs for G and H, we find that of these two, G would have the lesser marginal cost at $2,000 per week. Along the A-C-E branch, E has the least marginal cost at $700 per week. Along the B-D branch, D has the least marginal cost at $1,000 per week. Thus the D&E combination has a group marginal cost of only $1,700 in comparison with $2,000 per week for G. Thus our next step is to compress D&E together. Since there is only one week of compression available on D and on E, the next step is to crash D&E together by one week. Iter. Activities Crashed Crashed by Project Duration Group M/C Added Cost Total Costs New Critical Path 0 - - 15 - - 308,000 A-C-E-G-H 1 E 1 14 700 700 308,700 B-D-G-H 2 D&E 1 13 1700 1700 310,400 Reduce the availability of D and E to zero. Updating the path list accordingly results in: A-C-F-H 9 9 9 A-C-E-G-H 15 14 13 B-D-G-H 14 14 13
  • 6. Complex Project Crashing Algorithm www.iosrjournals.org 15 | Page Since both D and E are fully crashed, the least cost activity from the A-C-E branch is C at $800 per week, and the least cost activity from the B-D branch is B at $2,000, so the C&B combination at $2,800 is the best that can be done using two activities in parallel. Since this is more than the $2,000 per week cost of activity G, our next step is to crash G. And since G is on both critical paths, we can crash it the full three weeks that are available for this activity. The breakpoint table then becomes as follows. Iter. Activities Crashed Crashed by Project Duration Group M/C Added Cost Total Costs New Critical Path 0 - - 15 - - 308,000 A-C-E-G-H 1 E 1 14 700 700 308,700 B-D-G-H 2 D&E 1 13 1700 1700 310,400 3 G 3 10 2000 6000 316,400 Reduce the availability of G to zero. Updating the path list yields: A-C-F-H 9 9 9 9 A-C-E-G-H 15 14 13 10 B-D-G-H 14 14 13 10 Since G is now fully crashed, activity H is the only one activity which will cause both critical paths to become shorter, and it costs $3,000 per week. Thus the C&B combination is the least cost available at this point, so the next step is to crash B and C in parallel. In this case all three paths get shorter together, so no new critical paths occur. However, C has only one week of compression available, so the C&B combination can be compressed only one week. Thus the next breakpoint table is as follows. Iter. Activities Crashed Crashed by Project Duration Group M/C Added Cost Total Costs New Critical Path 0 - - 15 - - 308,000 A-C-E-G-H 1 E 1 14 700 700 308,700 B-D-G-H 2 D&E 1 13 1700 1700 310,400 3 G 3 10 2000 6000 316,400 4 B&C 1 9 2800 2800 319,200 Reduce the availability of B to 1 and C to zero. The updated path list becomes: A-C-F-H 9 9 9 9 8 A-C-E-G-H 15 14 13 10 9 B-D-G-H 14 14 13 10 9 At this point A and B are the only two activities on the upper and lower branches with remaining compression availability, and their combined cost is $2,900 which is still less than the $3,000 for activity H and since they each have only 1 week of compression remaining, the next step is to crash A&B together by a week.
  • 7. Complex Project Crashing Algorithm www.iosrjournals.org 16 | Page Iter. Activities Crashed Crashed By Project Duration Group M/C Added Cost Total Cost New Critical Path 0 - - 15 - - 308,000 A-C-E-G-H 1 E 1 14 700 700 308,700 B-D-G-H 2 D&E 1 13 1700 1700 310,400 3 G 3 10 2000 6000 316,400 4 B&C 1 9 2800 2800 319,200 5 A&B 1 8 2900 2900 322,100 The availability of A and B are reduced to zero. The updated path list becomes: A-C-F-H 9 9 9 9 8 7 A-C-E-G-H 15 14 13 10 9 8 B-D-G-H 14 14 13 10 9 8 At this point H is the only activity left to shorten the last two paths, and only one week of compression is available, so the final step in the breakpoint table is to compress H by one week. Iter. Activities Crashed Crashed by Project Duration Group M/C Added Cost Total Costs New Critical Path 0 - - 15 - - 308,000 A-C-E-G-H 1 E 1 14 700 700 308,700 B-D-G-H 2 D&E 1 13 1700 1700 310,400 3 G 3 10 2000 6000 316,400 4 B&C 1 9 2800 2800 319,200 5 A&B 1 8 2900 2900 322,100 6 H 1 7 3000 3000 325,100 The final path list is therefore: A-C-F-H 9 9 9 9 8 7 6 A-C-E-G-H 15 14 13 10 9 8 7 B-D-G-H 14 14 13 10 9 8 7 Since both critical paths are now fully crashed, the project crashing process is complete. The optimal time-cost trade-off values are contained in the project duration and project cost columns of the final breakpoint table. The final step of the process is to graph these points and connect them with straight line segments, as shown on Figure 2 [given on next page]. The only remaining task is to interpolate for the project cost corresponding to the 12 week project duration. Since this is just one week less than the 13 week solution in the breakpoint table, activity G will be crashed only one week rather than three, so the project cost for the 12 week schedule will be $310,400 plus
  • 8. Complex Project Crashing Algorithm www.iosrjournals.org 17 | Page $2,000 or $312,400. This result can be computed directly from the final breakpoint table, but the shape of the complete trade-off curve is of interest as well, and is more easily seen from the chart. IV. CONCLUSION In this paper the algorithm proposed for unit crashing reduces the cost of project. When activities are crashed by one day then only the crashing cost corresponding to one day is increased thereby reducing the project duration as well as cost. The purpose of this study was to explore the suitability of a new method to crash PERT networks. This approach is well suitable for places where cost is of major consideration. Plans for future research include running the simulation on additional networks, preferably real-world projects. FIGURE 2: Time-Cost Trade-Off Diagram REFERENCES [1] Lee, D., and Arditi, D. (2006) Automated statistical analysis in stochastic project scheduling simulation. Journal of Construction Engineering and Management, 132(3): 268-277. [2] Haga, W. A. & Tim O’keefe. (July 14, 2001) Crashing Pert Networks: A Simulation Approach. 4th International conference of the Academy of Business and Administrative Sciences Conference Quebec City, Canada. [3] Rosenau, M. D. and G. D. Githens. (2005) Successful Project Management: a Step-by-step Approach with Practical Examples. 4th Ed., Wiley, Hoboken, N.J. [4] Michael E. Kuhl and Radhamés A. Tolentino-Peña. (2008) A Dynamic Crashing Method For Project Management Using Simulation-Based Optimization. Winter Simulation Conference, S. J. Mason, R. R. Hill, L. Mönch, O. Rose, T. Jefferson, J. W. Fowler eds. [5] Van Slyke, R. M. (1963). Monte Carlo methods and the PERT problem; Operations Research, 13, 141-143. [6] Pritsker, A. B. & Happ, W. W. (1966). GERT: Graphical evaluation and review technique, Part-I, Fundamental Journal of Industrial Engineering, 17(5), 267-274. [7] Kennedy, K. W. & Thrall, R. M. (1976). PLANET: A Simulation approach to PERT; Computers and Operations Research, 3, 313-325. [8] Ameen, D. A. (April 1987). A computer assisted PERT simulation. Journal of Systems Management, 6-9. [9] Badiru, A. B. (1991). A simulation approach to network analysis. Simulation, 57, (4), 245-255. [10] Bissiri, Y., and S. Dunbar. (1999). Resource allocation model for a fast-tracked project. International Conference on Intelligent Processing and Manufacturing of Materials, 635-640. [11] Haga, W. A. (1998). Crashing PERT networks; Ph.D. Dissertation, University of Northern Colorado, Colorado. [12] Haga, W. A., and K. A. Marold. (2004). A simulation approach to the PERT-CPM time-cost trade-off problem. Project Management Journal, 35(2): 31-37. [13] Haga, W. A., and K. A. Marold. (2005). Monitoring and control of PERT networks. The Business Review, 3(2): 240-245.