BP Don ‘Live Well Abandonment’ - Application Of Post Project Actions For 2nd Phase Success
1. BP Don ‘Live Well Abandonment’
Application Of Post Project Actions For 2nd Phase Success
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
2. Project Overview
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
3. Choice of Vessel
• Vessel Specific Safety Case (Hydrocarbon handling capabilities)
• Light Well Intervention Package: Wireline
Pumping / Cementing
Coiled Tubing
• Integral Saturation Diving Spread
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
4. Project Detail
5” Vertical Tree
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
5. Project Detail
Diver Work Platform
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
6. Project Detail
Diver Work Platform
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
7. Project Detail
Hydraulic Prong Removal Tool
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
8. Project Detail
10 Core / 8 Core Hook Up
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
9. Project Detail
Mechanical Tree Cap
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
10. Project Detail
Tree ROV Hot Stab Panel (Divers Required)
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
11. Project Detail
Diver Cold Cutting Equipment (Basic)
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
12. ‘Lessons Learned’ Summary
• Acknowledge and address all debrief actions
• Redesign HPRT with annulus circulation capabilities
• Design more diver work platforms for concurrent operations
• Reduce connect / disconnect operations to reduce timely testing
• Consider heave state for E-fire tool sensitivity
• Reduce number of 3rd party operators / equipment where practicable
• Redesign procedure pack (make user friendly)
• Increase PRV release pressures for increased pumping rates
• Review MOC documentation and implement changes in revised procedures
• Incorporate all additional small changes / typos
• Incorporate larger procedures (site instructions) written up in the field
• Risk assess previous site instructions / MOC’s at phase 2 level 1
• Incorporate SJA’s into live project risk assessment
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
13. Phase 1 Indicators & Actions
Safe Job Analysis 3
Management of Change 15
Level 1 Risk Assessments 1
Level 2 Risk Assessments 1
Time Out For Safety 68
TRAC Cards 1063
Area Inspections 9
ER Drills 186
Safety Observations 344
(17% - Improvement Suggestions)
(30% - Positive Observations)
(53% - At Risk Observations)
Other Indicators
Debrief Actions Addressed and Closed 31
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”
14. Lessons Learned
Operation Specific Time Comparison Table (Hrs)
“All information contained in this document is confidential and proprietary to Helix Well Ops UK Ltd. No information may be divulged in whole or in part to any company
or person without written permission of Helix Well Ops UK Ltd.”