SlideShare uma empresa Scribd logo
1 de 35
Baixar para ler offline
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Reliability Assessment
Slide 2© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Power System Reliability
Analysis
• Reliability
– The probability of a system performing its
function adequately for the period of time and
operation conditions intended
• Adequacy
– Sufficient facilities within the system to satisfy
customer demand
• Security
– Ability of the system to respond favorably to
disturbances arising within that system
Slide 3© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Power System Reliability
Analysis
– Used in system planning and operation
– Reliability Assessment for:
• Generation station and generation capacity
• Composite generation and transmission system
• Distribution system
• Substation and switching stations
• Protection system
Slide 4© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Power System Reliability
Analysis
• Various Indices to Measure Reliability
– Customer Interruption Frequency
– Customer Interruption Duration
– Customer Curtailment – Power/Energy Not
Served
– Reliability Worth Study
– Minimize Total Cost: Reliability Cost and
Consumer Interruption Cost
Slide 5© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Analysis
• Concerned with availability and quality of power
supply at each customer’s service entrance –
Adequacy Analysis
• Statistics show that failures in distribution systems
contribute as much as 90% towards the
unavailability of supply to a load as compared with
other parts of electric power systems
Slide 6© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Reliability Analysis Using ETAP
• Assesses distribution system reliability level for
radial and looped systems with a very efficient
algorithm
• Considers single and double contingencies
• Assesses reliability level for system and each load
point based on component failure model and
system configuration
• Performs sensitivity analysis to identify the optimal
location to make greatest improvement on system
reliability at minimum cost
Slide 7© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Single & Double Contingencies
• Consider a system with two or more parallel
branches.
• In case of Single Contingency Analysis failure of
only one branch at a time is considered.
• In case of Double Contingency Analysis
simultaneous failure of two branches at a time is
also considered in addition to failure of one branch
at a time.
Slide 8© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Single & Double Contingency
Example
Single Contingency:
• Failure of T5 or T6 at
a time is considered.
Double Contingency
• Simultaneous failure
of T5 & T6 and failure
of T5 or T6 at a time is
considered.
Slide 9© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Component Model
A - Active Failure Rate (No of Failures/Year)
• Causes the operation of the protection devices around
the failed component, i.e. a short-circuit fault
• Failed component itself (and those components that are
directly connected to this failed component) restores to
service after repair or replacement
P- Passive Failure Rate (No of Failures/Year)
• Does not cause the operation of protection around the
failed component, i.e. an open circuit fault
• Failed component itself restores to service after repair
or replacement
Slide 10© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Component Model
• Mean Time To Repair in hours (MTTR)
Time required to repair a component outage
and/or restore the system to its normal operating
state
• Mean Repair Rate (No of repairs per year) ( )
= 8760/MTTR
• Mean Time To Failure (years) (MTTF):
MTTF = 1.0/( A+ P)
Slide 11© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Component Model
• Mean Time Between Failure (Year) (MTBF)
MTBF = MTTF + MTTR/8760
• Forced Outage Rate (Unavailability) (FOR)
FOR = MTTR/(MTBF*8760)
• Switching Time
– Time in hours for isolating a fault occurred at the
component
– Assume that CB/Fuse trip a fault instantaneously
• Time for replacing a failed element by a spare one,
in hours rP
Slide 12© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Single-Component Concepts
• Two-State Model
– A two-state up/down representation is used for
the operation/repair cycle of a component (such
as lines, cables, transformers, breakers, fuses,
switches, loads and busbars)
DOWN
= ( A+ P) Up
Down
MTTF
……..
……..
MTTF
MTTR MTTR
UP
Slide 13© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Model for Components in
Series/Parallel
Two Components in Series
sys
rr
sys
rrrr
sysr 2211
)
22
)(
11
(
2211
1, r1
Component 1 Component 2
21sys
2, r2
Slide 14© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Model for Components in
Series/Parallel
Two Components in Parallel
1, r1
Component 1
Component 2
2, r2
)
21
(
21
2211
1
)
21
(
21 rr
rr
rr
sys
21
21
rr
rr
sysr
Slide 15© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
System Modeling
• Fault Current Interruption
– Only overcurrent protection devices (CB and
fuse) can interrupt fault current
– Fault current interruption is assumed to be
instantaneous
– Assumed to have no effect on components with
multiple source connection and isolated from
fault by CB/fuses
Slide 16© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
System Modeling
• Fault Isolation
– All switching devices can isolate faults. CBs and
fuses isolate fault instantaneously
– Switches isolate fault at switching time of the
faulted component
– Switching time for a load is equal to that of the
closest component
Slide 17© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
System Modeling
Normally Open Tie: Open tie PD can be closed
(switching time) to provide back up power
– Two terminal buses should be energized
– Can have several PDs connected in series and
with one or more open
Slide 18© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Library for Reliability Analysis
• Component Reliability
– Data for each type of component - transformer,
bus, line, etc.
• Active Failure Rate
• Passive Failure Rate
• Repair Time
• Switching Time
• Replacement Time
• …
– Typical data from IEEE Standard
Slide 19© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Library for Reliability Analysis
• Sector Customer Interruption Cost
– Standard Industrial Classification (SIC) is used
to divide customers into seven categories of
large user, industrial, commercial, agriculture,
residential, government & institutions and office
& buildings.
– Sector Customer Damage Functions (SCDF) are
interruption costs for several discrete outage
durations.
Slide 20© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Library for Reliability Analysis
– A log-log interpolation of the cost data is used
where the interruption duration lies between two
separate times.
– If fault duration is outside the range, a linear
extrapolation with the same slope as that
between the two largest durations are used to
calculate the interruption cost.
Slide 21© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Indices
Nej jei ,
Average Failure Rate at Load Point i, i(f/yr)
• e,j - The average failure rate of element j (or element
combination j, such as double contingency).
• Ne - The total number of the elements whose faults will
interrupt load point i.
Annual Outage Duration at Load Point i, Ui(hr/yr)
Nej ij
r
jei
U
,
• rij --Failure duration at load point i due to a failed element j.
Slide 22© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Indices
Average Outage Duration at Load Point, ri(hr)
ii
U
i
r /
Expected Energy Not Supplied Index at Load Point, EENSi
(MWhr/yr)
iU
i
PiEENS Pi - the average load of load point i.
Expected Interruption Cost Index at Load Point, ECOSTi
(k$/yr)
Nej jeij
rf
i
P
i
ECOST
,
)(
The EENS and ECOST for a bus are calculated based on loads that
are directly connected to that bus due to the outage of that bus.
Where f(rij) is the SCDF.
Slide 23© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Indices
Interrupted Energy Assessment Rate Index at Load Point,
IEARi ($/kWhr)
System Average Interruption Frequency Index, SAIFI
(f/customer.yr)
System Average Interruption Duration Index, SAIDI
(hr/customer.yr)
iEENS
iECOST
iIEAR
i
N
i
N
iSAIFI
servedcustomerofnumberTotal
onsinterrupticustomerofnumberTotal
Where N is the number of customers at load point i
i
N
i
N
i
U
SAIDI
servedcustomerofnumberTotal
durationsoninterrupticustomerofSum
Slide 24© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Indices
Customer Average Interruption Duration Index,
CAIDI(hr/customer interruption)
Average Service Availability Index, ASAI(pu)
ii
N
i
N
i
U
CAIDI
onsinterrupticustomerofnumberTotal
sdurationoninterrupticustomerofSum
8760
8760
demandedhoursCustomer
serviceavailableofhoursCustomer
i
N
i
U
i
N
i
N
ASAI
Where 8760 is the number of hours in a calendar year
Slide 25© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Indices
Average Service Unavailability Index, ASUI(pu)
System Expected Energy Not Supplied Index, EENS (MWhr/yr)
ASAIASUI 1
EENS = Total energy not supplied by the system = EENSi
System Expected Interruption Cost Index, ECOST(k$/yr)
ECOST = ECOSTi
Slide 26© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment
Distribution System Reliability
Indices
Average Energy Not Supplied Index, AENS
(MWhr/customer.yr)
System Interrupted Energy Assessment Rate Index,
IEAR($/kWhr)
i
N
i
EENS
AENS
servedcustomerofnumberTotal
systemby thesuppliednotenergyTotal
EENS
ECOSTIEAR
RA Example 1 Using ETAP
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 27
RA Example 1 Using ETAP
Data:
Active failure rate for breakers: a = 0.003 failure/year
Passive failure rate for breakers: p = 0.002
failure/year
Failure rate for Bus, Utility: = 0.001 failure/year
MTTR for breakers: 30 hours
MTTR for buses, utility: 2 hours
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 28
RA Example 1 Using ETAP
Reliability Indices at LP1:
Failure rate for the main bus:
• CB1 fails actively OR passively
• CB2 and CB3 fail actively
• Utility fails
• Main bus itself fails
yearfailure
BusMainUtilityCBaCBaCBpaLP
/013.0
001.0001.0003.0003.0005.0
3211
The main bus would be de-energized if:
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 29
RA Example 1 Using ETAP
Annual unavailability for the main bus:
yearhour
MTTR
MTTRMTTR
MTTRMTTRU
BusMainBusMain
UtilityUtilityCBaCB
CBaCBCBpaCBLP
/334.0
001.02001.02003.030003.030005.030
33
22111
Time to replace the main bus:
hours
U
rLP 692.25
013.0
334.0
1
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 30
RA Example 2 Using ETAP
Results for the Single Contingency case
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 31
RA Example 2 Using ETAP
Results for the Double Contingency case
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 32
RA Example 2 Using ETAP
Calculations for the Double Contingency case:
For simplicity for hand calculations:
• Failure rates for the breakers connecting the transformers to the buses are
taken to be zero
• Failure rates of the two transformers are taken to be 1; MTTR = 200 hr.
Therefore the failure rate at Bus 2 due to double contingency:
yearfailures
rr
rr
double /0436681.0
8760
20012001
1
8760
)200200(11
8760
1
8760
)(
2211
2121
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 33
RA Example 2 Using ETAP
Calculations for the Double Contingency case:
Failure rate for the single contingency case:
Therefore total failure rate at Bus 2 :
yearfailures
gledoubleBus
/0546681.0011.00436681.0
sin2
yearfailures
A
CBBusMainBus
P
CB
A
CBUgle
/011.0
62111sin
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 34
RA Example 3 Using ETAP
© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 35

Mais conteúdo relacionado

Mais procurados

ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2Himmelstern
 
ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)Himmelstern
 
ETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationHimmelstern
 
Fault Calculations
Fault CalculationsFault Calculations
Fault Calculationsmichaeljmack
 
Inter Connected Power System(Turbine Speed Governing Mechanism )
Inter Connected Power System(Turbine Speed Governing Mechanism)Inter Connected Power System(Turbine Speed Governing Mechanism)
Inter Connected Power System(Turbine Speed Governing Mechanism )Raviraj solanki
 
ETAP - pde gis - Data Exchange
ETAP -   pde gis - Data ExchangeETAP -   pde gis - Data Exchange
ETAP - pde gis - Data ExchangeHimmelstern
 
Buck boost converter
Buck boost converterBuck boost converter
Buck boost converterSathiya kumar
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordinationHimmelstern
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardHimmelstern
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdfAjay Bhatnagar
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIAArun Muraleedharan
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordinationmichaeljmack
 
Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability IssuesChandan Kumar
 
[Webinar Slides] Advanced distribution management system integration of renew...
[Webinar Slides] Advanced distribution management system integration of renew...[Webinar Slides] Advanced distribution management system integration of renew...
[Webinar Slides] Advanced distribution management system integration of renew...Schneider Electric
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNINGNishaDangi99
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detailSlides Hub
 
ETAP - Cable pulling
ETAP - Cable pullingETAP - Cable pulling
ETAP - Cable pullingHimmelstern
 

Mais procurados (20)

ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
 
ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)
 
ETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationETAP - 09 motor-acceleration
ETAP - 09 motor-acceleration
 
Fault Calculations
Fault CalculationsFault Calculations
Fault Calculations
 
Protection and Switchgear
Protection and SwitchgearProtection and Switchgear
Protection and Switchgear
 
Inter Connected Power System(Turbine Speed Governing Mechanism )
Inter Connected Power System(Turbine Speed Governing Mechanism)Inter Connected Power System(Turbine Speed Governing Mechanism)
Inter Connected Power System(Turbine Speed Governing Mechanism )
 
ETAP - pde gis - Data Exchange
ETAP -   pde gis - Data ExchangeETAP -   pde gis - Data Exchange
ETAP - pde gis - Data Exchange
 
Buck boost converter
Buck boost converterBuck boost converter
Buck boost converter
 
NFPA 110 Overview
NFPA 110 OverviewNFPA 110 Overview
NFPA 110 Overview
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordination
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIA
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
 
Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability Issues
 
[Webinar Slides] Advanced distribution management system integration of renew...
[Webinar Slides] Advanced distribution management system integration of renew...[Webinar Slides] Advanced distribution management system integration of renew...
[Webinar Slides] Advanced distribution management system integration of renew...
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNING
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
 
ETAP - Cable pulling
ETAP - Cable pullingETAP - Cable pulling
ETAP - Cable pulling
 

Semelhante a ETAP - reliability assesment

ETAP - ocp - Optimal Capacitor Placement
ETAP -  ocp - Optimal Capacitor PlacementETAP -  ocp - Optimal Capacitor Placement
ETAP - ocp - Optimal Capacitor PlacementHimmelstern
 
IRJET- Improvement of Availability and Maintainability through Actions based ...
IRJET- Improvement of Availability and Maintainability through Actions based ...IRJET- Improvement of Availability and Maintainability through Actions based ...
IRJET- Improvement of Availability and Maintainability through Actions based ...IRJET Journal
 
ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stabilityHimmelstern
 
IRJET- Design Development and Analysis of Low Pressure Bladeless Turbine
IRJET- Design Development and Analysis of Low Pressure Bladeless TurbineIRJET- Design Development and Analysis of Low Pressure Bladeless Turbine
IRJET- Design Development and Analysis of Low Pressure Bladeless TurbineIRJET Journal
 
Wind turbine reliability
Wind turbine reliabilityWind turbine reliability
Wind turbine reliabilitykarthik451
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentationAfzal Tiwari
 
KBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC (A Yokogawa Company)
 
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...IRJET Journal
 
Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Dhanesh S
 
Optimising equipment Safety, Operations and Cost performance
Optimising equipment Safety, Operations and Cost performanceOptimising equipment Safety, Operations and Cost performance
Optimising equipment Safety, Operations and Cost performanceLloyd's Register Energy
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET Journal
 
IRJET- Design & Development of Hydraulically Dowel Pin Pressing Machine
IRJET- Design & Development of Hydraulically Dowel Pin Pressing MachineIRJET- Design & Development of Hydraulically Dowel Pin Pressing Machine
IRJET- Design & Development of Hydraulically Dowel Pin Pressing MachineIRJET Journal
 
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET- Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET Journal
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramHimmelstern
 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfssusera5c9a31
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapHimmelstern
 

Semelhante a ETAP - reliability assesment (20)

ETAP - ocp - Optimal Capacitor Placement
ETAP -  ocp - Optimal Capacitor PlacementETAP -  ocp - Optimal Capacitor Placement
ETAP - ocp - Optimal Capacitor Placement
 
IRJET- Improvement of Availability and Maintainability through Actions based ...
IRJET- Improvement of Availability and Maintainability through Actions based ...IRJET- Improvement of Availability and Maintainability through Actions based ...
IRJET- Improvement of Availability and Maintainability through Actions based ...
 
ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stability
 
IRJET- Design Development and Analysis of Low Pressure Bladeless Turbine
IRJET- Design Development and Analysis of Low Pressure Bladeless TurbineIRJET- Design Development and Analysis of Low Pressure Bladeless Turbine
IRJET- Design Development and Analysis of Low Pressure Bladeless Turbine
 
Wind turbine reliability
Wind turbine reliabilityWind turbine reliability
Wind turbine reliability
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentation
 
Unit 5 or
Unit 5 orUnit 5 or
Unit 5 or
 
KBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utility
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
 
Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Maintenance module1 ppt number 3
Maintenance module1 ppt number 3
 
Optimising equipment Safety, Operations and Cost performance
Optimising equipment Safety, Operations and Cost performanceOptimising equipment Safety, Operations and Cost performance
Optimising equipment Safety, Operations and Cost performance
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
 
IRJET- Design & Development of Hydraulically Dowel Pin Pressing Machine
IRJET- Design & Development of Hydraulically Dowel Pin Pressing MachineIRJET- Design & Development of Hydraulically Dowel Pin Pressing Machine
IRJET- Design & Development of Hydraulically Dowel Pin Pressing Machine
 
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material LiftingIRJET-  	  Design and Manufacturing of Ladder Roof Lift for Material Lifting
IRJET- Design and Manufacturing of Ladder Roof Lift for Material Lifting
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System Diagram
 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdf
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
 

Último

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 

Último (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

ETAP - reliability assesment

  • 1. © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Reliability Assessment
  • 2. Slide 2© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Power System Reliability Analysis • Reliability – The probability of a system performing its function adequately for the period of time and operation conditions intended • Adequacy – Sufficient facilities within the system to satisfy customer demand • Security – Ability of the system to respond favorably to disturbances arising within that system
  • 3. Slide 3© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Power System Reliability Analysis – Used in system planning and operation – Reliability Assessment for: • Generation station and generation capacity • Composite generation and transmission system • Distribution system • Substation and switching stations • Protection system
  • 4. Slide 4© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Power System Reliability Analysis • Various Indices to Measure Reliability – Customer Interruption Frequency – Customer Interruption Duration – Customer Curtailment – Power/Energy Not Served – Reliability Worth Study – Minimize Total Cost: Reliability Cost and Consumer Interruption Cost
  • 5. Slide 5© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Analysis • Concerned with availability and quality of power supply at each customer’s service entrance – Adequacy Analysis • Statistics show that failures in distribution systems contribute as much as 90% towards the unavailability of supply to a load as compared with other parts of electric power systems
  • 6. Slide 6© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Reliability Analysis Using ETAP • Assesses distribution system reliability level for radial and looped systems with a very efficient algorithm • Considers single and double contingencies • Assesses reliability level for system and each load point based on component failure model and system configuration • Performs sensitivity analysis to identify the optimal location to make greatest improvement on system reliability at minimum cost
  • 7. Slide 7© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Single & Double Contingencies • Consider a system with two or more parallel branches. • In case of Single Contingency Analysis failure of only one branch at a time is considered. • In case of Double Contingency Analysis simultaneous failure of two branches at a time is also considered in addition to failure of one branch at a time.
  • 8. Slide 8© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Single & Double Contingency Example Single Contingency: • Failure of T5 or T6 at a time is considered. Double Contingency • Simultaneous failure of T5 & T6 and failure of T5 or T6 at a time is considered.
  • 9. Slide 9© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Component Model A - Active Failure Rate (No of Failures/Year) • Causes the operation of the protection devices around the failed component, i.e. a short-circuit fault • Failed component itself (and those components that are directly connected to this failed component) restores to service after repair or replacement P- Passive Failure Rate (No of Failures/Year) • Does not cause the operation of protection around the failed component, i.e. an open circuit fault • Failed component itself restores to service after repair or replacement
  • 10. Slide 10© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Component Model • Mean Time To Repair in hours (MTTR) Time required to repair a component outage and/or restore the system to its normal operating state • Mean Repair Rate (No of repairs per year) ( ) = 8760/MTTR • Mean Time To Failure (years) (MTTF): MTTF = 1.0/( A+ P)
  • 11. Slide 11© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Component Model • Mean Time Between Failure (Year) (MTBF) MTBF = MTTF + MTTR/8760 • Forced Outage Rate (Unavailability) (FOR) FOR = MTTR/(MTBF*8760) • Switching Time – Time in hours for isolating a fault occurred at the component – Assume that CB/Fuse trip a fault instantaneously • Time for replacing a failed element by a spare one, in hours rP
  • 12. Slide 12© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Single-Component Concepts • Two-State Model – A two-state up/down representation is used for the operation/repair cycle of a component (such as lines, cables, transformers, breakers, fuses, switches, loads and busbars) DOWN = ( A+ P) Up Down MTTF …….. …….. MTTF MTTR MTTR UP
  • 13. Slide 13© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Model for Components in Series/Parallel Two Components in Series sys rr sys rrrr sysr 2211 ) 22 )( 11 ( 2211 1, r1 Component 1 Component 2 21sys 2, r2
  • 14. Slide 14© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Model for Components in Series/Parallel Two Components in Parallel 1, r1 Component 1 Component 2 2, r2 ) 21 ( 21 2211 1 ) 21 ( 21 rr rr rr sys 21 21 rr rr sysr
  • 15. Slide 15© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment System Modeling • Fault Current Interruption – Only overcurrent protection devices (CB and fuse) can interrupt fault current – Fault current interruption is assumed to be instantaneous – Assumed to have no effect on components with multiple source connection and isolated from fault by CB/fuses
  • 16. Slide 16© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment System Modeling • Fault Isolation – All switching devices can isolate faults. CBs and fuses isolate fault instantaneously – Switches isolate fault at switching time of the faulted component – Switching time for a load is equal to that of the closest component
  • 17. Slide 17© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment System Modeling Normally Open Tie: Open tie PD can be closed (switching time) to provide back up power – Two terminal buses should be energized – Can have several PDs connected in series and with one or more open
  • 18. Slide 18© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Library for Reliability Analysis • Component Reliability – Data for each type of component - transformer, bus, line, etc. • Active Failure Rate • Passive Failure Rate • Repair Time • Switching Time • Replacement Time • … – Typical data from IEEE Standard
  • 19. Slide 19© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Library for Reliability Analysis • Sector Customer Interruption Cost – Standard Industrial Classification (SIC) is used to divide customers into seven categories of large user, industrial, commercial, agriculture, residential, government & institutions and office & buildings. – Sector Customer Damage Functions (SCDF) are interruption costs for several discrete outage durations.
  • 20. Slide 20© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Library for Reliability Analysis – A log-log interpolation of the cost data is used where the interruption duration lies between two separate times. – If fault duration is outside the range, a linear extrapolation with the same slope as that between the two largest durations are used to calculate the interruption cost.
  • 21. Slide 21© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Indices Nej jei , Average Failure Rate at Load Point i, i(f/yr) • e,j - The average failure rate of element j (or element combination j, such as double contingency). • Ne - The total number of the elements whose faults will interrupt load point i. Annual Outage Duration at Load Point i, Ui(hr/yr) Nej ij r jei U , • rij --Failure duration at load point i due to a failed element j.
  • 22. Slide 22© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Indices Average Outage Duration at Load Point, ri(hr) ii U i r / Expected Energy Not Supplied Index at Load Point, EENSi (MWhr/yr) iU i PiEENS Pi - the average load of load point i. Expected Interruption Cost Index at Load Point, ECOSTi (k$/yr) Nej jeij rf i P i ECOST , )( The EENS and ECOST for a bus are calculated based on loads that are directly connected to that bus due to the outage of that bus. Where f(rij) is the SCDF.
  • 23. Slide 23© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Indices Interrupted Energy Assessment Rate Index at Load Point, IEARi ($/kWhr) System Average Interruption Frequency Index, SAIFI (f/customer.yr) System Average Interruption Duration Index, SAIDI (hr/customer.yr) iEENS iECOST iIEAR i N i N iSAIFI servedcustomerofnumberTotal onsinterrupticustomerofnumberTotal Where N is the number of customers at load point i i N i N i U SAIDI servedcustomerofnumberTotal durationsoninterrupticustomerofSum
  • 24. Slide 24© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Indices Customer Average Interruption Duration Index, CAIDI(hr/customer interruption) Average Service Availability Index, ASAI(pu) ii N i N i U CAIDI onsinterrupticustomerofnumberTotal sdurationoninterrupticustomerofSum 8760 8760 demandedhoursCustomer serviceavailableofhoursCustomer i N i U i N i N ASAI Where 8760 is the number of hours in a calendar year
  • 25. Slide 25© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Indices Average Service Unavailability Index, ASUI(pu) System Expected Energy Not Supplied Index, EENS (MWhr/yr) ASAIASUI 1 EENS = Total energy not supplied by the system = EENSi System Expected Interruption Cost Index, ECOST(k$/yr) ECOST = ECOSTi
  • 26. Slide 26© 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Distribution System Reliability Indices Average Energy Not Supplied Index, AENS (MWhr/customer.yr) System Interrupted Energy Assessment Rate Index, IEAR($/kWhr) i N i EENS AENS servedcustomerofnumberTotal systemby thesuppliednotenergyTotal EENS ECOSTIEAR
  • 27. RA Example 1 Using ETAP © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 27
  • 28. RA Example 1 Using ETAP Data: Active failure rate for breakers: a = 0.003 failure/year Passive failure rate for breakers: p = 0.002 failure/year Failure rate for Bus, Utility: = 0.001 failure/year MTTR for breakers: 30 hours MTTR for buses, utility: 2 hours © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 28
  • 29. RA Example 1 Using ETAP Reliability Indices at LP1: Failure rate for the main bus: • CB1 fails actively OR passively • CB2 and CB3 fail actively • Utility fails • Main bus itself fails yearfailure BusMainUtilityCBaCBaCBpaLP /013.0 001.0001.0003.0003.0005.0 3211 The main bus would be de-energized if: © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 29
  • 30. RA Example 1 Using ETAP Annual unavailability for the main bus: yearhour MTTR MTTRMTTR MTTRMTTRU BusMainBusMain UtilityUtilityCBaCB CBaCBCBpaCBLP /334.0 001.02001.02003.030003.030005.030 33 22111 Time to replace the main bus: hours U rLP 692.25 013.0 334.0 1 © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 30
  • 31. RA Example 2 Using ETAP Results for the Single Contingency case © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 31
  • 32. RA Example 2 Using ETAP Results for the Double Contingency case © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 32
  • 33. RA Example 2 Using ETAP Calculations for the Double Contingency case: For simplicity for hand calculations: • Failure rates for the breakers connecting the transformers to the buses are taken to be zero • Failure rates of the two transformers are taken to be 1; MTTR = 200 hr. Therefore the failure rate at Bus 2 due to double contingency: yearfailures rr rr double /0436681.0 8760 20012001 1 8760 )200200(11 8760 1 8760 )( 2211 2121 © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 33
  • 34. RA Example 2 Using ETAP Calculations for the Double Contingency case: Failure rate for the single contingency case: Therefore total failure rate at Bus 2 : yearfailures gledoubleBus /0546681.0011.00436681.0 sin2 yearfailures A CBBusMainBus P CB A CBUgle /011.0 62111sin © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 34
  • 35. RA Example 3 Using ETAP © 1996-2009 Operation Technology, Inc. – Workshop Notes: Reliability Assessment Slide 35