BLESSINGS BUILDERS (Pvt.) LIMITED
PROJECT REPORT ON THR CONSTRUCTION OF THREE HOSTEL BLOCKS
AT UET PESHAWAR JALOZAI CAMPUS
SUBMITTED TO SUBMITTED BY
Dr. Ali Ahsan Ahmed ALI Malik
B08-001
Date: 23rd
December, 2010
ACKNOWLEDGEMENT
• We are thankful to Allah Almighty who is the creator of this universe.
• Special thanks to Dr. Ali Ahsan for providing us the knowledge about
Project Management and for nourishing our mind.
• We are thankful to UET Peshawar for awarding us with this project.
• We are thankful to Abid Brothers (Pvt.) Limited who gave us all the
necessary information to perform this project.
• We are thankful to all those people involve, who worked hard to complete
this project.
EXECUTIVE SUMMARY
NATURE OF THE COMPANY Construction Company
CORPORATE STATUS Private Limited
Company
LOCATION OF THE PROJECT UET Peshawar Jalozai
I am a graduate of BBA and I have graduated from Case Business School
Islamabad. I have recently started my construction company named as Blessings
Builders (Pvt.) Limited. I have selected this field because there is a lot of potential
for this business to grow in a continuously changing world like today.
Blessings Builders (Pvt.) Limited will start the construction of three hostel blocks
at UET Peshawar Jalozai Campus. Our company has done a number of
government construction projects. Our recent project was a school building in
Muzafarabad in the earthquake affected area.
TABLE OF CONTENTS
 PROJECT CHARTER
 PROJECT PLAN
 REQUIREMNTS COLLECTION
 SCOPE DEFINITION
 PAYMENT SCHEDULE
 BILL OF QUANTITIES
 QUALITY MANAGEMENT PLAN
 STAKEHOLDER REGISTER
 COMMUNICATION MANAGEMENT PLAN
 HUMAN RESOURCE PLAN
 RISK MANAGEMENT PLAN
 PROCUREMENT PLAN
PROJECT CHARTER
Project: Construction of hostel blocks of UET Peshawar
Project manager: Ahmed Ali Malik
Contractor: Blessings Builders (Pvt.) Limited
Tender Issuer: UET Peshawar
Date: 23rd
Dec, 2010
IDENTIFICATION
UET Peshawar Issued a tender for the construction of three hostel blocks. As the number of students
are increasing each year so is the demand of the hostel blocks because most of the students are from
different areas of Pakistan.
Blessing Builders (Pvt.) Limited Bid on the above mentioned tender which was issued by UET Peshawar
and submitted proposal for the project. Blessing Builders (Pvt.) Limited has a well organized project
team as well as necessary equipment for the construction of the hostel blocks.
Based on the proposal submitted by the contractor, UET Peshawar selected Blessings Builders (Pvt.)
Limited for the construction of the hostel blocks.
PROJECT SCOPE
Blessings Builders Pvt. Limited selected a consulting company (Hasmat Consulting Pvt. Limited) to
design the architectural and structural drawings and designs for the construction of the three hostel
blocks at UET Peshawar. The consulting company will therefore design the drawings and make all the
technical specifications in the process of the complete delivery of the hostel blocks. As well as
consulting company will appoint an engineer to approve and check the status of the project at each
point of completion. The total covered area of the project should be 35,000 Sq. ft. Therefore Blessings
Builders (Pvt.) Limited will complete the construction of the hostel blocks as per the requirements and
specifications.
PROJECT OBJECTIVES
To provide flawless, safe, rigid and tolerant construction so that the end product is as per the
requirements of the client. Blessing Builders (Pvt.) desires to complete the project within the approved
budget and time and with the involvement of all the project teams and also to provide the final product
as per the expectations of the client.
PROJECT SCHEDULE
Project to be completed within two years from the date of signing of contract.
MILESTONES
Sr. no Task month year
1 Design of structural & architectural Drawings December 2010
2 Mobilization December 2010
3 Survey of the site December 2010
4 Excavation January 2011
5 Construction of foundations February 2011
6 construction of ground floors & ground floor roofs April 2011
7 construction of first level floors December 2011
8 completion of wood work May 2011
9 completion of electrical and plumbing work January 2012
10 completion of paint work and external work December 2012
11 finishing and fixtures April 2013
12 handing and taking over December 2013
PROJECT BUDGET & SPONSORSHIP
UET Peshawar will be sponsoring the whole project from starting date to the end of the project. UET
Peshawar has approved a budget of thirty million rupees i.e. Rs. 30,000,000/-.
ORGANIZATION & RESPONSIBILTIES
Blessing Builders (Pvt.) Limited has well organized project team and their roles and responsibilities will
be mentioned in the Human Resource plan.
RISK ASSESMENT
Some of the risks that Blessings Builders (Pvt.) Limited face:
• Political Envoirment of Pakistan
• Unstable market conditions
• Laws and regulations of the Pakistan concerning construction
• Shortage of materials
• Over costing of the project
• Project not to be completed within the time frame
SUBCONTRACTORS
Presently we are planning to execute all of the work on our own so we are not hiring any sub
contractors.
STAKE HOLDERS
The following parties have their stakes involved in the project:
• Blessings Builders (Pvt.) Limited (Contractor)
• Project Team Including Labor
• UET Peshawar (Client)
• Hashmat Consulting Pvt. Limited (Consultants)
• Tenet (People who would be using the final product)
• Suppliers
DELIEVERABLES
Blessings Builders (Pvt.) Limited will be constructing three hostel blocks at the Jalozai campus of UET
Peshawar. Each hostel has different phases of construction which are in detail mentioned in project
plan.
ACHIEVEMENTS
Blessings builders (Pvt.) limited has a good reputation of the previously done projects. Our previous
projects are a good example to show that we do not compromise on quantity or quality and deliver the
product as per the expectations of the client.
PROJECT PLAN
• Scope
To identify the requirements of the construction of the hostel blocks, the building works and
the external works.
• Hours of working
The core working hours will be from 8.00 am to 5.00 pm (Mondays to Sundays). Some
employees will be working outside the core working hours which are necessary for strategic
construction operations and in case of emergencies. The strategic operations may require work
to be carried out through night time period.
• Total project time
The project shall be completed within seven hundred and eighty eight calendar days from the
date receiving the “letter of acceptance”.
• Critical Path Method
Once the letter of acceptance is received we will submit CPM for the entire project indicating
various activities of work to be performed.
• Soil test
Once the agreement is signed the first job to be undertaken would be to conduct a soil test.
This will be done by the experienced surveyors and professionals. This will provide a complete
description of the natural ground.
• Clearing and grubbing
One of the first steps in construction is clearing and grubbing. Clearing of trash is important to
the stability of the foundation. For this purpose we will use tractors having a front blade. Trees
and other large vegetation within the boundaries will be removed from the construction site.
• Excavation
The area where excavation is to be done will be surveyed by the surveyor and the surveyor will
mark according to the approved layout and drawings. Our surveyor will verify the marked area
with the drawings approved by the consultant. Once satisfied, the consultant will be called for
inspection. The marked area will be excavated using excavator/ shovel. All excavated material
will be moved away to another area.
• Leveling of ground
The excavated area will be leveled and compacted to (as per specifications) with suitable
machinery like compactors. The excavated, leveled and compacted area will be at all times kept
free from water or other contamination sources.
• Structure works
The layout of the building foundation will be carried out according to the drawings. Anti termite
solution will be then sprayed over it.
After 24 hours of spraying anti termite the PCC lean concrete will be laid down by using
concrete mixtures and laborers.
The foundations will be marked on the lean concrete and the cutting and bending of steel
reinforcement will be started.
The steel will be laid down and will be bind together to form a structure as per the drawings
then concrete will be poured on it.
• PCC lean is plain cement concrete. It is laid on the foundation as a base without any
steel reinforcements. The nominal mix ratio for the PCC laid in the foundations would
be (1:4:8).In this mix the portion of cement will be 1, the portion of sand will be 4 and
the portion of stone ballast will 8.
• RCC is reinforced cement concrete. It will be laid in foundation, column stems and
plinth beams with a nominal mix ratio of (1:1.5:3). It also consists of steel
reinforcements which will add in compliance with the approved drawings.
• Super Structure works
In super structure work reinforced cement concrete will be laid in the columns, beams, slabs,
stairs and over head water tank with a nominal mix ratio of (1:1.5:3).
• Architectural Works
After the completion of the structural work we will start architectural work. Architectural work
will consist of brick work in foundation, ground level and first floor. After the completion of
brick work plaster will start on the brick work. After that installation of wooden door frames,
aluminum windows and wooden doors will start. Accordingly the flooring will also start.
• Finishing work
We will start the brick work as soon the base and concrete work gets finished. The brick work
will give a shape to the structure. The bricks will be procured from an approved source. The
brick work will be done by the skilled labor. The fixing of door frames will also start.
The plaster work will start after the brick work gets completed. The plaster work will be done
by mixture machine and skilled labor.
All the activities will be done as per schedule submitted by the contractor. All the structural
work will be done with technical specifications and by the direction of the engineer in charge.
Face work will be started after when building structure is completed. This work will be done by
special laborers of face work. All the materials will be procured from the approved source.
• Electrical and Plumbing work
Electrical and plumbing work inside the structure will start when the structure gets complete.
Electrical wiring and its necessary accessories will be fitted before the plaster. Plumbing pipes
will be laid down on the floor before the ceramic tiles and marble is installed. After the
electrical and plumbing work gets complete paint work and lightening will start. All electrical
and plumbing work will be done according to the approved diagrams. At each completion stage
each work will be inspected by the site engineer and quality control officer.
• External work
o Water & gas supply works
• The area will be marked as per the approved drawings where water and gas supply
pipes have to be laid down.
• Trenches will be excavated with excavator for lying of pipes.
• After that excavation pipes and fittings will be procured on site.
• Pressure pipes will be installed on a good compacted surface.
• For jointing of pipes we will use manufacture’s recommended heater welding machines
and fittings.
• Valves and other kind of fittings will be installed before the construction of chambers.
• The valve chamber will be constructed as mentioned in the approved drawings and in
compliance with the specifications.
• The necessary inspection will be done by the quality control engineer.
o Ground water tanks (GWT)
• Layout of GWT will be established as per the drawings.
• Excavation will be done for lying of reinforced cement concrete (RCC).
• Cutting, bending and fixing of steel reinforcement will be made as per the approved
drawings
• The cutting of steel reinforcements will be done by electric cutter and fixing will be
done by skilled labor.
• After fixing of steel reinforcements, structure of the steel will be laid down
according to the GWT drawings for pouring the concrete.
• A final inspection of the structured steel reinforcements will be done and the
concrete will be poured.
• After completing concrete works the pipes and other accessories will be installed as
per approval of the engineer.
o Sewerage works
• Trenches will be excavated for laying of pipes and manholes up to the required
level
• The manholes will be constructed of bricks as mentioned in the approved drawings
and according to the specifications.
• Pipes will be installed on a good compacted surface.
• Trenches and man holes will be filled back once the testing of pipes is completed.
• The testing will be done by the quality control engineer.
• Walls of the manholes will be plastered and painted.
• All materials for the above activities will be procured from an approved source.
After the completion of all the above mentioned work, site clearance will start which will consist of
moving of machinery, disposal of hazardous material etc. After the site clearance the product or the
constructed buildings will be handed over to UET Peshawar.
REQUIREMENTS COLLECTION & DEFINING SCOPE
PROJECT REQUIREMENTS
UET Peshawar issued an invitation to tender for the complete delivery of the final product of the
construction of three hostel blocks at UET Peshawar Jalozai campus inclusive of designing and design
approval, manufacturing, transportation and full installation of equipment and services within the time
frame and cost as specified below. The total covered area of the project should be 35,000 Sq. ft. The
hostels should have a capacity to entertain 200 hostilities.
PROJECT COST
Total project cost for three hostel blocks is Rs. 30,000,000/- or rupees thirty million. All the three hostel
blocks should be completed within the above mentioned budget.
PROJECT TIME FRAME
Total project time is seven hundred and eighty eight or 788 calendar days. All the three hostel blocks
should be completed within the above mentioned time.
PROJECT SCOPE
The contractor (Blessings Builders Pvt. Limited) responded to the previously mentioned invitation to
tender and has been selected by UET Peshawar to provide the above mentioned complete delivery of
the three hostel blocks within the time frame and project cost that is mentioned by UET Peshawar.
Blessings Builders Pvt. Limited selected a consulting company to design the architectural and structural
drawings and designs for the construction of the three hostel blocks at UET Peshawar. The consulting
company will therefore design the drawings and make all the technical specifications in the process of
the complete delivery of the hostel blocks. As well as consulting company will appoint an engineer to
approve and check the status of the project at each point of completion.
Blessings Builders Pvt. Limited shall be entirely responsible for the transportation and handling of the
equipment and materials for each structure to the site.
Payment schedule
1st
payment
• Advance Payment
• Construction of Reinforced cement concrete (RCC) foundations up to the plinth level beam
2nd
payment
• Construction of RCC frame structure up to roof beam level
• Construction of ground floor RCC roof.
3rd
payment
• Completion of brick work and plastering in ground and first floors
• Construction of floors and wall finishes
• Completion of wood work
4th
payment
• Completion of electrical works
• Completion of plumbing works
• Completion of paint works
5th
payment
• Completion of all electric, plumbing and external works
• Final acceptance and handing over
CONSTRUCTION OF 3 HOSTEL BLOCKS
AT JALOZAI CAMPUS OF UET PESHAWAR
BILL OF QUATITIES
Sr. NO DESCRIPTION UNIT QUANTITY
UNIT
RATE (Rs)
TOTAL
AMOUNT
(Rs)
STRUCTURE WORK
1 Excavation of all kinds of materials
including rocks and disposal of all kinds
Sft 35000 15 525000
of materials outside the project limits
2
Fill and back fill of the area that was
Excavated with suitable material and
soil. Sft 15400 10 154000
3
Termite control treatment as approved
by The engineer. Sft 9500 15 142500
4 Steel reinforcement round bars. M.ton 60 105000 6300000
5
Providing and laying plain cement
concrete (PCC) in foundation. Sft 2600 200 520000
6
Providing and laying Reinforced cement
Concrete (RCC) in foundations Sft 12000 325 3900000
7
Providing and laying reinforced cement
Concrete in column and column stems Sft 2250 350 787500
8 Bricks Pieces 42000 3.5 147000
9 Sand Dumpers 20 3000 60000
10 Stone Ballast Dumpers 10 3600 3600
11 Aluminum Windows Sft 240 1000 240000
12 Wood Sft 1000 1200 120000
13
Providing and laying of RCC in column
and column stems in foundations and
ground floor. Sft 1225 350 428750
14
Providing and laying RCC in column and
Column stems in first floor. Sft 1000 350 350000
15
Providing and laying RCC in plinth
beams. Sft 120 350 42000
16
Providing and laying RCC in slabs and
stairs. Sft 75 350 26250
17
Providing and laying RCC in over head
water tanks Sft 460 350 161000
ARCHITECTURAL WORK
18
Brick work of foundation, complete in all
respects Sft 3575 275 983125
19
Brick work of ground floor, complete in
all respects Sft 6300 275 1732500
20
Brick work of first floor, complete in all
respects Sft 5125 275 1409375
21
Cement sand plaster on interior walls,
columns and beams Sft 375 300 112500
22
Cement sand plaster on exterior walls,
columns, beams at ground floor Sft 6850 350 239750
23
Cement sand plaster on exterior walls,
columns, beams and over head water
tanks at first floor Sft 4620 35 161700
24 Cement sand plaster on stairs. Sft 360 35 12600
25 Providing and fixing wooden frames. Sft 21 3600 75600
26 Providing and fixing aluminum windows. Sft 61 4000 244000
27
Three coats of plastic emulsion on
external as well as internal walls Sft 12400 25 310000
28
Three coats of synthetic enamel paint of
approved quality and color as per
instructions Sft 1640 20 32800
29 Three coats of weather shield paint. Sft 3850 25 96250
30
Providing and fixing stair railing on all
steps of stairs Sft 510 200 102000
31
Providing and fixing wooden doors and
wooden wardrobes Sft 205 2500 512500
32
Providing and laying of crushed stone,
sand and cement for concreting of floor. Sft 1090 65 70850
33
Providing and laying of marble and
ceramic tiles for flooring Sft 4680 150 702000
34
Providing and fixing of borders and
skirting with ceramic tiles and marbles. Sft 780 60 46800
35
External finishes including face work as
per the requirements mentioned. Sft 12400 35 434000
36 Providing and fixing of false ceiling Sft 1525 100 152500
PLUMBING WORK
37
Providing and fixing of water supply
pipes and fittings of all types. Meters 280 845 236600
38
Providing and fixing of waste pipes, vent
pipes and their fittings of all types. Meters 155 1650 255750
ELECTRICAL WORK
39
Providing and fixing of for electric wires
of all types Underground and inside the
walls. Rft 400 220 88000
40 Providing and fixing of light fixtures. Pieces 44 6500 286000
41 Providing and fixing of LT cables and Rft 300 70 21000
42 Distribution boards. Pieces 3 45000 135000
43
Providing and fixing of Transformer and
earthing cables Rft 160 30 4800
TOTAL COST Rs. 22,365,600/-
Quality Management Plan
To achieve the desired quality of the end product and to work according to the set standard of the
previously done projects by Blessings Builders (Pvt.) Limited, following quality management plan has
been developed in accordance to the previously mentioned project plan.
• Fixed working hours and schedule has been set in order to complete the project in time and
to perform flawless work.
• Blessings Builders (Pvt.) Limited will hire professionals to conduct soil test in order to get a full
description of the natural ground. This will help the project team to prepare for all the
necessary actions to be performed while excavating.
• Once the soil test report is received excavation will be performed by skilled labor and
machinery. When the excavation is complete site officer and site engineer will survey the site
and no further work will be performed unless we get an approval.
• Quality control officer and site engineer will regularly monitor the structure work at each
phase of completion. They will also monitor type and quality of cement, sand, steel
reinforcements, brick on each or prior purchase. Only that material would be used which
would be mentioned before the work is performed.
• The nominal mix or ratio of cement, sand, stone ballast and steel reinforcements shall be
observed and followed while laying of Plain Cement Concrete (PCC) and Reinforced Cement
Concrete (RCC) in foundations, columns, beams, slabs etc.
• Pre concrete inspection
The site engineer will check and confirm that the latest issue of drawings have been
stamped and approved by the consultants before the pouring of concrete.
• Checking of line and level
Checks will be made by the site engineer to confirm that the steel reinforcements are in
line and at correct location.
• Form work
The site engineer and site officer will jointly check the form work to ensure that all the
requirements have been satisfied. The checks will include the inspection of joints,
tolerance, position of the laid materials etc.
• Reinforcing steel
Reinforcing steel will be fixed in accordance with the stamped and approved drawings.
Regular checks will be made by the site engineer to ensure that the work is being done
in compliance with the approved drawings.
• Cleanliness
The site engineer and site officer will check that the entire area where concrete is to be
poured is clean and free from dust and construction related debris.
• Vibrator and tools
The site engineer will check that the number and type of vibrators are available for the
pouring of concrete and will also ensure that the vibrators and other tools are in good
working order.
• Other checks
The site engineer and site officer will check that the materials required for the
construction are readily available at all times and the materials are acquired as per the
schedule.
• Safety inspection
The site officer will inspect the pour area including the access of roads for concrete
delivery, temporary electric works and other materials necessary required for the
pouring and preparation for the pour is safe and does not endanger the health and
safety of the personnel involved.
• Works inspection
Our civil, mechanical, electrical and plumbing engineer will carry out their own
inspection to ensure that the work has been done properly as per the requirements of
the approved drawings.
• Consultants inspection
When the above inspections have been carried out by our staff, the concrete work is
then ready for inspection by the consultants.
After the approval of the consultant only the structural work will be started.
• All the material weather it will be used in the structural, architectural, electrical, plumbing and
for floor work will be procured from approved source and will be inspected and then passed
by the Quality Control Lab so that the agreed and expected quality can be achieved.
• Before handing over a final check will be made by the quality control officer and site engineer
to check for flaws or damage so that the terms and conditions of the agreement may not get
violated
STAKEHOLDER REGISTER
Company
Name:
Blessings Builders (Pvt.) Limited
Project Name Construction Of Three Hostel Blocks at Jalozai Campus UET Peshawar
Prepared By: Ahmed Ali Malik (Project Manager)
Date: 23rd
Dec, 2010
Project
Stakeholder
Role in Project
Type of
Stakeholder
Type of
Communication
Project
Interests
Impact on Project
Outcome
Blessings
Builders (Pvt.)
Limited
Contractor Internal
Official
Meeting, Project
Documentation,
RFQ, Payment
Schedule,
e mails.
To deliver
the project in
time and
within the
approved
budget.
Influencer
Project Team
Including Labor
Engineers,
builders and
skilled labor
Internal
Project
performance
feedback, face
to face
communication
To perform
work as per
the
requirements
and collect
wages.
Supporter
UET Peshawar Client External
Project
Performance
Documentation
To receive
the final
product as
per their
requirements.
Influencer
Hashmat
Consulting Pvt.
Limited
Consultant ,
Quality Control
Inspector,
Architect
Internal
Project
Performance
Documentation
To check
weather the
work is being
performed as
per the
requirements
mentioned in
the drawings
Influencer
Tenet
Students or
Hostilities at
UET Peshawar
External Nil
To live in a
comfortable
building
Influencer
Supplier Building
material,
electrical,
plumbing
material
External RFQ, Invoices,
Payment
Schedule
To deliever
good material
of approved
quality on
time and
Supporter
supplier
collect
payments on
invoices.
COMMUNICATON OBJECTIVES
1. Communication with the client (UET Peshawar)
a. To keep the client informed of the project progress
b. To see if the client needs any change or modification in the project plan
c. To update/inform the client regarding accomplishments of the project milestone(s) so
as to disperse timely payments.
2. Communication with the consultant
a. To keep the consultant informed of the client needs.
b. To keep the consultant informed of any change or modification in the architectural
plans as per the need of the client.
c. To keep the consultant informed of the project progress so that the consultant can
make his inspection plan accordingly.
3. Communication with the project team
a. To provide daily tasks to the project team.
b. To keep a record of the accomplished and unaccomplished tasks.
c. To check whether the work done is right or wrong.
d. To provide performance feedback to the project team.
4. Communication with the supplier
a. To provide Request for Quotation (RFQ) to the supplier of material.
b. To keep a record of the purchased items or materials from the supplier.
c. To keep check whether the materials are being delivered as per schedule.
COMMUNICATION PLAN
• Communication with the client will be through monthly meetings and all the project
performance will be delivered through documentation. Meetings will be scheduled before the
start of construction.
• Communication with the consultant will be done via e mails. In return the consultant will
provide a schedule for onsite inspection.
• Communication with the project team will be done on daily basis with a face to face
interaction.
• Communication with the supplier will be done through documentation on every purchase, RFQ
will be submitted to the supplier in return the supplier will give quotations and best suitable
supplier will be chosen. The supplier will submit invoices of the delivered materials on each
purchase.
HUMAN RESOURCE PLAN
This Human Resource Plan describes our staff requirements over the next two years. The areas of
responsibilities and experience requirements for each staff position, organization chart as well as salary
and remunerations should be provided.
ORGANIZATION CHART
EMPLOYEE PLAN
(YEAR 1-2)
Sr.
No. Job Title Job description
1 Managing Director Decision maker of the entire project, running the organization.
2 Project Manager Managing the project and the project
3 Security Incharge
Responsible of the security of the project site and managing the
security guards.
4 Store Keeper Incharge of the store and all the necessary materials and equipment
5 Purchase Incharge
Incharge of all the purchases made for the construction of the
project through suppliers.
6
Workshop Equipment
Incharge Responsible for running the workshop and the equipment.
7
Senior Quantity
Surveyor
Responsible for keeping the record of quantity of material
purchases or to be acquired.
8 Computer Engineer Responsible for making computerized form of the entire project.
9 Planning Engineer responsible for planning all the engineering work
10 Safety Engineer responsible for monitoring and planning all the structural work
11
Quality Control
manager managing and controlling the quality
12 Construction Manager managing the construction work
13 Security Guard responsible for the security of the project site
14
Building Material
Officer responsible for the ordering and monitoring the building material
15
Electrical/Mechanic
Goods Officer
responsible for ordering and monitoring the electrical and
mechanical goods
16 General Goods Officer responsible for providing day to day goods
17
Assistant Quality
Control assisting the senior quantity surveyor
18
Quality Control
Inspector inspecting and monitoring the quality standard
19 Surveyor surveyor of the whole project
20 Site Engineer Civil responsible for the structural, architectural and plumbing work
21 Site Engineer Electrical responsible for the electrical work
22 Assistant Surveyor assisting the surveyor
23 Foreman Civil managing the civil labor
24 Foreman Electric managing the electricians
25 Consultant
making and designing the architectural and structural designs and
drawings
26 Finance Manager Managing all the finances associated with the project
27
Human Resource
Manager Managing all the employees associated with the project
COMPENSATION AND BENEFITS
(Year 1-2)
Name of Position Nature of position No. of Position(s) Salary/ Remuneration (Rs)
Managing Director Salary (Per Month) 1 35,000
Project Manager Salary (Per Month) 1 30,000
Security Incharge Salary (Per Month) 1 18,000
Store Keeper Salary (Per Month) 1 19,000
Purchase Incharge
Remuneration
(Contract) 1 22,000
Workshop
Equipment
Incharge
Remuneration
(Contract) 1 19,000
Senior Quantity
Surveyor
Remuneration
(Contract) 1 21,000
Computer Engineer
Remuneration
(Contract) 1 12,000
Planning Engineer
Remuneration
(Contract) 1 21,000
Safety Engineer
Remuneration
(Contract) 1 18,000
Quality Control
manager Salary (Per Month) 1 20,000
Construction
Manager Salary (Per Month) 1 26,000
Security Guard Salary (Per Month) 1 8,000
Building Material
Officer
Remuneration
(Contract) 1 12,000
Electrical/Mechani
c Goods Officer
Remuneration
(Contract) 1 12,000
General Goods
Officer
Remuneration
(Contract) 1 12,000
Assistant Quantity
Control
Remuneration
(Contract) 1 12,000
Quality Control
Inspector
Remuneration
(Contract) 1 14,000
Surveyor
Remuneration
(Contract) 1 12,000
Site Engineer Civil
Remuneration
(Contract) 3 16,000
Site Engineer
Electrical
Remuneration
(Contract) 1 16,000
Assistant Surveyor
Remuneration
(Contract) 1 9,000
Foreman Civil
Remuneration
(Contract) 3 11,000
Foreman Electric
Remuneration
(Contract) 1 11,000
Consultant
Remuneration
(Contract) 1 35,000
Totals: 441,000
RISK MANAGEMENT PLAN
RISK REGISTER
Sr.
No RISK RISK MANAGEMENT IMPACT
1
Over costing more
than the budget
allocated
Blessings Builders (Pvt.) Limited (Contractor) will take a bank loan
for the completion of the project High
2
In case the project
does not completes
in time
The contractor will appoint more labor for the completion of the
project High
3
Machinery Break
Down
We have on site workshop for equipment and machinery
maintenance Low
4 Theft
Store Keeper & Security Guard would be investigated and
necessary action would be taken against them Medium
5 Employee Attrition
Immediately new experienced employee will be hired for that
position Medium
6 Material Shortage Forecasting would be done and materials would be procured Low
7
Political Envoirment
Of Pakistan
Measures will be taken to avoid such situation which will affect
the project Medium
8 Competition
Our company strategy distinguishes us from our competitors is to
provide the best quality in the lowest cost and time possible Low
9
Changing Market
conditions
As the inflation rate of Pakistan is quite high so we will make an
agreement with our suppliers for the purchase of materials Medium
10 Load shedding
We will provide standby generators on the site to encounter load
shedding High
11 Natural Disaster
We will make the structure of the buildings strong enough to bear
8 rector scale of earthquake and build the boundary walls high
enough to block flood Low
12 Material Damage Material will be replaced Low
PROJECT PROCUREMENT PLAN
Project Name: Construction Of Three Hostel Blocks At UET Peshawar
Prepared by: Ahmed Ali Malik (Project Manager)
Procurement Statement
Blessings Builders (Pvt.) Limited will procure all the necessary materials required for the construction of
the hostel blocks from approved sources which include the following:
• Cement
• Steel reinforcements
• Sand
• Bricks
• Stone Ballast
• Wood
• Glass Windows
• Electrical equipment
• Plumbing equipment
• Paint
• PVC piping
Estimated Cost
Total estimated cost for all the procurements is twenty million rupees. i.e Rs. 20,000,000/- and keeping
in reserve +/- 20% of the estimated cost.
Vendor Selection
Blessings Builder (Pvt.) limited will issue a tender through news papers regarding Request For
Quotations (RFQ). The suppliers or vendors will submit their quotations through mails.
Selection Process & Criteria
The suppliers will be selected on the following criteria:
• Low cost
• Quality of the materials
• Timely delivery
• Reputation in the market
Project Procurement team
Sr. No JOB TITLE PROCUREMENT ROLE
1 Project Manager Overlooks the whole procurement team
2 Purchase Section Incharge
Manages the procurement team and all the purchases made for the
project
3 Building Material Incharge
Responsible for procuring building material like cement, sand,
wood etc.
4 Electrical Goods Incharge Responsible for procuring Electrical equipment and accessories
5 General Goods Incharge
Responsible for procuring General Goods required for running day
to day operations

Mais conteúdo relacionado

Mais procurados

Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentationemdad bhuiyan
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONDAVIDSON ECHIDIKE
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Project report on construction of hotel/hostel
Project report on construction of hotel/hostelProject report on construction of hotel/hostel
Project report on construction of hotel/hostelmuhammed iqbal
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development PhaseKhyati Tewari
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTIONMd Shadab
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotelMuhammad Farhan Javed
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)rahul jangid
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 

Mais procurados (20)

Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project report on construction of hotel/hostel
Project report on construction of hotel/hostelProject report on construction of hotel/hostel
Project report on construction of hotel/hostel
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Construction process
Construction processConstruction process
Construction process
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotel
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 

Destaque

Interview with an Entrepreneur. His background and company profile.
Interview with an Entrepreneur. His background and company profile.Interview with an Entrepreneur. His background and company profile.
Interview with an Entrepreneur. His background and company profile.Marika Torcitto
 
Example of Company Performance Analysis
Example of Company Performance AnalysisExample of Company Performance Analysis
Example of Company Performance AnalysisSeredup Maya
 
Business Plan Sample - Edit for reddit
Business Plan Sample - Edit for redditBusiness Plan Sample - Edit for reddit
Business Plan Sample - Edit for redditMarcus Aurelius
 
Apple background of company
Apple background of companyApple background of company
Apple background of companyaroneb
 
Example of Company background
Example of Company backgroundExample of Company background
Example of Company backgroundfazzuan
 
Business Plan Sample - Great Example For Anyone Writing a Business Plan
Business Plan Sample - Great Example For Anyone Writing a Business PlanBusiness Plan Sample - Great Example For Anyone Writing a Business Plan
Business Plan Sample - Great Example For Anyone Writing a Business PlanThe Business Plan Team
 

Destaque (7)

Interview with an Entrepreneur. His background and company profile.
Interview with an Entrepreneur. His background and company profile.Interview with an Entrepreneur. His background and company profile.
Interview with an Entrepreneur. His background and company profile.
 
Example of Company Performance Analysis
Example of Company Performance AnalysisExample of Company Performance Analysis
Example of Company Performance Analysis
 
Business Plan Sample - Edit for reddit
Business Plan Sample - Edit for redditBusiness Plan Sample - Edit for reddit
Business Plan Sample - Edit for reddit
 
Apple background of company
Apple background of companyApple background of company
Apple background of company
 
SAMPLE BUSINESS PLAN
SAMPLE BUSINESS PLANSAMPLE BUSINESS PLAN
SAMPLE BUSINESS PLAN
 
Example of Company background
Example of Company backgroundExample of Company background
Example of Company background
 
Business Plan Sample - Great Example For Anyone Writing a Business Plan
Business Plan Sample - Great Example For Anyone Writing a Business PlanBusiness Plan Sample - Great Example For Anyone Writing a Business Plan
Business Plan Sample - Great Example For Anyone Writing a Business Plan
 

Semelhante a Construction of Three Hostel Blocks

Summer training at CPWD by Aaditi Dhyani
Summer training at CPWD by Aaditi DhyaniSummer training at CPWD by Aaditi Dhyani
Summer training at CPWD by Aaditi DhyaniAaditi Dhyani
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...DougDos
 
List of various Projects PPT . To know about the company
List of various Projects PPT . To know about the companyList of various Projects PPT . To know about the company
List of various Projects PPT . To know about the companyrebekahsantineer1
 
Construction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxConstruction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxSardarMuhammadHashir
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxSudas Duddey
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)TeohPeiNi
 
Structural engeeniring
Structural engeeniring Structural engeeniring
Structural engeeniring czlun
 
deepakppt-170326hfyfyuftuffyyf210140.pptx
deepakppt-170326hfyfyuftuffyyf210140.pptxdeepakppt-170326hfyfyuftuffyyf210140.pptx
deepakppt-170326hfyfyuftuffyyf210140.pptxSagarSb9
 
Resume of Ghulam Muhammad
Resume of Ghulam MuhammadResume of Ghulam Muhammad
Resume of Ghulam MuhammadGhulam Muhammad
 
Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)
Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)
Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)YONG WEN TING
 

Semelhante a Construction of Three Hostel Blocks (20)

Summer training at CPWD by Aaditi Dhyani
Summer training at CPWD by Aaditi DhyaniSummer training at CPWD by Aaditi Dhyani
Summer training at CPWD by Aaditi Dhyani
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
01ADNAN Mtech
01ADNAN Mtech01ADNAN Mtech
01ADNAN Mtech
 
List of various Projects PPT . To know about the company
List of various Projects PPT . To know about the companyList of various Projects PPT . To know about the company
List of various Projects PPT . To know about the company
 
Construction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxConstruction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptx
 
Dds profile
Dds profileDds profile
Dds profile
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Ravi Resume
Ravi ResumeRavi Resume
Ravi Resume
 
Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)
 
Ct3 presentation slides
Ct3 presentation slidesCt3 presentation slides
Ct3 presentation slides
 
final ppt.pptx
final ppt.pptxfinal ppt.pptx
final ppt.pptx
 
IPT Training
IPT TrainingIPT Training
IPT Training
 
Structural engeeniring
Structural engeeniring Structural engeeniring
Structural engeeniring
 
MazherCVUpdated (291116)
MazherCVUpdated (291116)MazherCVUpdated (291116)
MazherCVUpdated (291116)
 
deepakppt-170326hfyfyuftuffyyf210140.pptx
deepakppt-170326hfyfyuftuffyyf210140.pptxdeepakppt-170326hfyfyuftuffyyf210140.pptx
deepakppt-170326hfyfyuftuffyyf210140.pptx
 
Resume of Ghulam Muhammad
Resume of Ghulam MuhammadResume of Ghulam Muhammad
Resume of Ghulam Muhammad
 
Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)
Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)
Yong Wen Ting Sharon Gun Shim Wei (SITE VISIT REPORT)
 

Mais de Hagi Sahib

48 power rules book report
48 power rules book report48 power rules book report
48 power rules book reportHagi Sahib
 
Mp3 Player complete marketing plan
Mp3 Player complete marketing planMp3 Player complete marketing plan
Mp3 Player complete marketing planHagi Sahib
 
Tobacco market research paper Questionnaire
Tobacco market research paper Questionnaire Tobacco market research paper Questionnaire
Tobacco market research paper Questionnaire Hagi Sahib
 
Obstacles in way of development of Pakistan economy
Obstacles in way of development of Pakistan economy Obstacles in way of development of Pakistan economy
Obstacles in way of development of Pakistan economy Hagi Sahib
 
Trade secrets and conflicts of interest
Trade secrets and conflicts of interestTrade secrets and conflicts of interest
Trade secrets and conflicts of interestHagi Sahib
 
Planning tool for presentation
Planning tool for presentationPlanning tool for presentation
Planning tool for presentationHagi Sahib
 
Is google is taking over the world
Is google is taking over the worldIs google is taking over the world
Is google is taking over the worldHagi Sahib
 
Assignment on leadership qualities of zulfikar Ali bhutto
Assignment on leadership qualities of zulfikar Ali bhuttoAssignment on leadership qualities of zulfikar Ali bhutto
Assignment on leadership qualities of zulfikar Ali bhuttoHagi Sahib
 
Online shoe Business idea
Online shoe Business ideaOnline shoe Business idea
Online shoe Business ideaHagi Sahib
 
Online shoes business idea report docs
Online shoes business idea report docsOnline shoes business idea report docs
Online shoes business idea report docsHagi Sahib
 
Panteene pro v project plan
Panteene pro v project planPanteene pro v project plan
Panteene pro v project planHagi Sahib
 
Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project reportHagi Sahib
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectHagi Sahib
 
Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.Hagi Sahib
 
toy manufacturers project report.
toy manufacturers project report.toy manufacturers project report.
toy manufacturers project report.Hagi Sahib
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.Hagi Sahib
 
Barber shop tiny clippers for kids project.
Barber shop tiny clippers for kids project.Barber shop tiny clippers for kids project.
Barber shop tiny clippers for kids project.Hagi Sahib
 
CNG station construction project report.
CNG station construction project report.CNG station construction project report.
CNG station construction project report.Hagi Sahib
 
construction of Reservation software solution for Airline Companies project ...
construction of  Reservation software solution for Airline Companies project ...construction of  Reservation software solution for Airline Companies project ...
construction of Reservation software solution for Airline Companies project ...Hagi Sahib
 

Mais de Hagi Sahib (20)

48 power rules book report
48 power rules book report48 power rules book report
48 power rules book report
 
Mp3 Player complete marketing plan
Mp3 Player complete marketing planMp3 Player complete marketing plan
Mp3 Player complete marketing plan
 
Tobacco market research paper Questionnaire
Tobacco market research paper Questionnaire Tobacco market research paper Questionnaire
Tobacco market research paper Questionnaire
 
Obstacles in way of development of Pakistan economy
Obstacles in way of development of Pakistan economy Obstacles in way of development of Pakistan economy
Obstacles in way of development of Pakistan economy
 
PepsiCo
PepsiCoPepsiCo
PepsiCo
 
Trade secrets and conflicts of interest
Trade secrets and conflicts of interestTrade secrets and conflicts of interest
Trade secrets and conflicts of interest
 
Planning tool for presentation
Planning tool for presentationPlanning tool for presentation
Planning tool for presentation
 
Is google is taking over the world
Is google is taking over the worldIs google is taking over the world
Is google is taking over the world
 
Assignment on leadership qualities of zulfikar Ali bhutto
Assignment on leadership qualities of zulfikar Ali bhuttoAssignment on leadership qualities of zulfikar Ali bhutto
Assignment on leadership qualities of zulfikar Ali bhutto
 
Online shoe Business idea
Online shoe Business ideaOnline shoe Business idea
Online shoe Business idea
 
Online shoes business idea report docs
Online shoes business idea report docsOnline shoes business idea report docs
Online shoes business idea report docs
 
Panteene pro v project plan
Panteene pro v project planPanteene pro v project plan
Panteene pro v project plan
 
Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project report
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles project
 
Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.
 
toy manufacturers project report.
toy manufacturers project report.toy manufacturers project report.
toy manufacturers project report.
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.
 
Barber shop tiny clippers for kids project.
Barber shop tiny clippers for kids project.Barber shop tiny clippers for kids project.
Barber shop tiny clippers for kids project.
 
CNG station construction project report.
CNG station construction project report.CNG station construction project report.
CNG station construction project report.
 
construction of Reservation software solution for Airline Companies project ...
construction of  Reservation software solution for Airline Companies project ...construction of  Reservation software solution for Airline Companies project ...
construction of Reservation software solution for Airline Companies project ...
 

Último

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 

Último (20)

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 

Construction of Three Hostel Blocks

  • 1. BLESSINGS BUILDERS (Pvt.) LIMITED PROJECT REPORT ON THR CONSTRUCTION OF THREE HOSTEL BLOCKS AT UET PESHAWAR JALOZAI CAMPUS SUBMITTED TO SUBMITTED BY Dr. Ali Ahsan Ahmed ALI Malik B08-001 Date: 23rd December, 2010
  • 2. ACKNOWLEDGEMENT • We are thankful to Allah Almighty who is the creator of this universe. • Special thanks to Dr. Ali Ahsan for providing us the knowledge about Project Management and for nourishing our mind. • We are thankful to UET Peshawar for awarding us with this project. • We are thankful to Abid Brothers (Pvt.) Limited who gave us all the necessary information to perform this project. • We are thankful to all those people involve, who worked hard to complete this project. EXECUTIVE SUMMARY
  • 3. NATURE OF THE COMPANY Construction Company CORPORATE STATUS Private Limited Company LOCATION OF THE PROJECT UET Peshawar Jalozai I am a graduate of BBA and I have graduated from Case Business School Islamabad. I have recently started my construction company named as Blessings Builders (Pvt.) Limited. I have selected this field because there is a lot of potential for this business to grow in a continuously changing world like today. Blessings Builders (Pvt.) Limited will start the construction of three hostel blocks at UET Peshawar Jalozai Campus. Our company has done a number of government construction projects. Our recent project was a school building in Muzafarabad in the earthquake affected area. TABLE OF CONTENTS
  • 4.  PROJECT CHARTER  PROJECT PLAN  REQUIREMNTS COLLECTION  SCOPE DEFINITION  PAYMENT SCHEDULE  BILL OF QUANTITIES  QUALITY MANAGEMENT PLAN  STAKEHOLDER REGISTER  COMMUNICATION MANAGEMENT PLAN  HUMAN RESOURCE PLAN  RISK MANAGEMENT PLAN  PROCUREMENT PLAN PROJECT CHARTER Project: Construction of hostel blocks of UET Peshawar Project manager: Ahmed Ali Malik Contractor: Blessings Builders (Pvt.) Limited Tender Issuer: UET Peshawar
  • 5. Date: 23rd Dec, 2010 IDENTIFICATION UET Peshawar Issued a tender for the construction of three hostel blocks. As the number of students are increasing each year so is the demand of the hostel blocks because most of the students are from different areas of Pakistan. Blessing Builders (Pvt.) Limited Bid on the above mentioned tender which was issued by UET Peshawar and submitted proposal for the project. Blessing Builders (Pvt.) Limited has a well organized project team as well as necessary equipment for the construction of the hostel blocks. Based on the proposal submitted by the contractor, UET Peshawar selected Blessings Builders (Pvt.) Limited for the construction of the hostel blocks. PROJECT SCOPE Blessings Builders Pvt. Limited selected a consulting company (Hasmat Consulting Pvt. Limited) to design the architectural and structural drawings and designs for the construction of the three hostel blocks at UET Peshawar. The consulting company will therefore design the drawings and make all the technical specifications in the process of the complete delivery of the hostel blocks. As well as consulting company will appoint an engineer to approve and check the status of the project at each point of completion. The total covered area of the project should be 35,000 Sq. ft. Therefore Blessings Builders (Pvt.) Limited will complete the construction of the hostel blocks as per the requirements and specifications. PROJECT OBJECTIVES To provide flawless, safe, rigid and tolerant construction so that the end product is as per the requirements of the client. Blessing Builders (Pvt.) desires to complete the project within the approved budget and time and with the involvement of all the project teams and also to provide the final product as per the expectations of the client. PROJECT SCHEDULE Project to be completed within two years from the date of signing of contract. MILESTONES
  • 6. Sr. no Task month year 1 Design of structural & architectural Drawings December 2010 2 Mobilization December 2010 3 Survey of the site December 2010 4 Excavation January 2011 5 Construction of foundations February 2011 6 construction of ground floors & ground floor roofs April 2011 7 construction of first level floors December 2011 8 completion of wood work May 2011 9 completion of electrical and plumbing work January 2012 10 completion of paint work and external work December 2012 11 finishing and fixtures April 2013 12 handing and taking over December 2013 PROJECT BUDGET & SPONSORSHIP UET Peshawar will be sponsoring the whole project from starting date to the end of the project. UET Peshawar has approved a budget of thirty million rupees i.e. Rs. 30,000,000/-. ORGANIZATION & RESPONSIBILTIES Blessing Builders (Pvt.) Limited has well organized project team and their roles and responsibilities will be mentioned in the Human Resource plan. RISK ASSESMENT Some of the risks that Blessings Builders (Pvt.) Limited face: • Political Envoirment of Pakistan • Unstable market conditions • Laws and regulations of the Pakistan concerning construction • Shortage of materials • Over costing of the project • Project not to be completed within the time frame SUBCONTRACTORS
  • 7. Presently we are planning to execute all of the work on our own so we are not hiring any sub contractors. STAKE HOLDERS The following parties have their stakes involved in the project: • Blessings Builders (Pvt.) Limited (Contractor) • Project Team Including Labor • UET Peshawar (Client) • Hashmat Consulting Pvt. Limited (Consultants) • Tenet (People who would be using the final product) • Suppliers DELIEVERABLES Blessings Builders (Pvt.) Limited will be constructing three hostel blocks at the Jalozai campus of UET Peshawar. Each hostel has different phases of construction which are in detail mentioned in project plan. ACHIEVEMENTS Blessings builders (Pvt.) limited has a good reputation of the previously done projects. Our previous projects are a good example to show that we do not compromise on quantity or quality and deliver the product as per the expectations of the client. PROJECT PLAN
  • 8. • Scope To identify the requirements of the construction of the hostel blocks, the building works and the external works. • Hours of working The core working hours will be from 8.00 am to 5.00 pm (Mondays to Sundays). Some employees will be working outside the core working hours which are necessary for strategic construction operations and in case of emergencies. The strategic operations may require work to be carried out through night time period. • Total project time The project shall be completed within seven hundred and eighty eight calendar days from the date receiving the “letter of acceptance”. • Critical Path Method Once the letter of acceptance is received we will submit CPM for the entire project indicating various activities of work to be performed. • Soil test Once the agreement is signed the first job to be undertaken would be to conduct a soil test. This will be done by the experienced surveyors and professionals. This will provide a complete description of the natural ground.
  • 9. • Clearing and grubbing One of the first steps in construction is clearing and grubbing. Clearing of trash is important to the stability of the foundation. For this purpose we will use tractors having a front blade. Trees and other large vegetation within the boundaries will be removed from the construction site. • Excavation The area where excavation is to be done will be surveyed by the surveyor and the surveyor will mark according to the approved layout and drawings. Our surveyor will verify the marked area with the drawings approved by the consultant. Once satisfied, the consultant will be called for inspection. The marked area will be excavated using excavator/ shovel. All excavated material will be moved away to another area. • Leveling of ground The excavated area will be leveled and compacted to (as per specifications) with suitable machinery like compactors. The excavated, leveled and compacted area will be at all times kept free from water or other contamination sources. • Structure works The layout of the building foundation will be carried out according to the drawings. Anti termite solution will be then sprayed over it. After 24 hours of spraying anti termite the PCC lean concrete will be laid down by using concrete mixtures and laborers.
  • 10. The foundations will be marked on the lean concrete and the cutting and bending of steel reinforcement will be started. The steel will be laid down and will be bind together to form a structure as per the drawings then concrete will be poured on it. • PCC lean is plain cement concrete. It is laid on the foundation as a base without any steel reinforcements. The nominal mix ratio for the PCC laid in the foundations would be (1:4:8).In this mix the portion of cement will be 1, the portion of sand will be 4 and the portion of stone ballast will 8. • RCC is reinforced cement concrete. It will be laid in foundation, column stems and plinth beams with a nominal mix ratio of (1:1.5:3). It also consists of steel reinforcements which will add in compliance with the approved drawings. • Super Structure works In super structure work reinforced cement concrete will be laid in the columns, beams, slabs, stairs and over head water tank with a nominal mix ratio of (1:1.5:3). • Architectural Works After the completion of the structural work we will start architectural work. Architectural work will consist of brick work in foundation, ground level and first floor. After the completion of brick work plaster will start on the brick work. After that installation of wooden door frames, aluminum windows and wooden doors will start. Accordingly the flooring will also start. • Finishing work
  • 11. We will start the brick work as soon the base and concrete work gets finished. The brick work will give a shape to the structure. The bricks will be procured from an approved source. The brick work will be done by the skilled labor. The fixing of door frames will also start. The plaster work will start after the brick work gets completed. The plaster work will be done by mixture machine and skilled labor. All the activities will be done as per schedule submitted by the contractor. All the structural work will be done with technical specifications and by the direction of the engineer in charge. Face work will be started after when building structure is completed. This work will be done by special laborers of face work. All the materials will be procured from the approved source. • Electrical and Plumbing work Electrical and plumbing work inside the structure will start when the structure gets complete. Electrical wiring and its necessary accessories will be fitted before the plaster. Plumbing pipes will be laid down on the floor before the ceramic tiles and marble is installed. After the electrical and plumbing work gets complete paint work and lightening will start. All electrical and plumbing work will be done according to the approved diagrams. At each completion stage each work will be inspected by the site engineer and quality control officer. • External work o Water & gas supply works • The area will be marked as per the approved drawings where water and gas supply pipes have to be laid down. • Trenches will be excavated with excavator for lying of pipes. • After that excavation pipes and fittings will be procured on site.
  • 12. • Pressure pipes will be installed on a good compacted surface. • For jointing of pipes we will use manufacture’s recommended heater welding machines and fittings. • Valves and other kind of fittings will be installed before the construction of chambers. • The valve chamber will be constructed as mentioned in the approved drawings and in compliance with the specifications. • The necessary inspection will be done by the quality control engineer. o Ground water tanks (GWT) • Layout of GWT will be established as per the drawings. • Excavation will be done for lying of reinforced cement concrete (RCC). • Cutting, bending and fixing of steel reinforcement will be made as per the approved drawings • The cutting of steel reinforcements will be done by electric cutter and fixing will be done by skilled labor. • After fixing of steel reinforcements, structure of the steel will be laid down according to the GWT drawings for pouring the concrete. • A final inspection of the structured steel reinforcements will be done and the concrete will be poured. • After completing concrete works the pipes and other accessories will be installed as per approval of the engineer. o Sewerage works
  • 13. • Trenches will be excavated for laying of pipes and manholes up to the required level • The manholes will be constructed of bricks as mentioned in the approved drawings and according to the specifications. • Pipes will be installed on a good compacted surface. • Trenches and man holes will be filled back once the testing of pipes is completed. • The testing will be done by the quality control engineer. • Walls of the manholes will be plastered and painted. • All materials for the above activities will be procured from an approved source. After the completion of all the above mentioned work, site clearance will start which will consist of moving of machinery, disposal of hazardous material etc. After the site clearance the product or the constructed buildings will be handed over to UET Peshawar. REQUIREMENTS COLLECTION & DEFINING SCOPE PROJECT REQUIREMENTS UET Peshawar issued an invitation to tender for the complete delivery of the final product of the construction of three hostel blocks at UET Peshawar Jalozai campus inclusive of designing and design approval, manufacturing, transportation and full installation of equipment and services within the time frame and cost as specified below. The total covered area of the project should be 35,000 Sq. ft. The hostels should have a capacity to entertain 200 hostilities. PROJECT COST Total project cost for three hostel blocks is Rs. 30,000,000/- or rupees thirty million. All the three hostel blocks should be completed within the above mentioned budget. PROJECT TIME FRAME Total project time is seven hundred and eighty eight or 788 calendar days. All the three hostel blocks should be completed within the above mentioned time.
  • 14. PROJECT SCOPE The contractor (Blessings Builders Pvt. Limited) responded to the previously mentioned invitation to tender and has been selected by UET Peshawar to provide the above mentioned complete delivery of the three hostel blocks within the time frame and project cost that is mentioned by UET Peshawar. Blessings Builders Pvt. Limited selected a consulting company to design the architectural and structural drawings and designs for the construction of the three hostel blocks at UET Peshawar. The consulting company will therefore design the drawings and make all the technical specifications in the process of the complete delivery of the hostel blocks. As well as consulting company will appoint an engineer to approve and check the status of the project at each point of completion. Blessings Builders Pvt. Limited shall be entirely responsible for the transportation and handling of the equipment and materials for each structure to the site. Payment schedule 1st payment • Advance Payment • Construction of Reinforced cement concrete (RCC) foundations up to the plinth level beam 2nd payment • Construction of RCC frame structure up to roof beam level • Construction of ground floor RCC roof. 3rd payment • Completion of brick work and plastering in ground and first floors • Construction of floors and wall finishes • Completion of wood work
  • 15. 4th payment • Completion of electrical works • Completion of plumbing works • Completion of paint works 5th payment • Completion of all electric, plumbing and external works • Final acceptance and handing over CONSTRUCTION OF 3 HOSTEL BLOCKS AT JALOZAI CAMPUS OF UET PESHAWAR BILL OF QUATITIES Sr. NO DESCRIPTION UNIT QUANTITY UNIT RATE (Rs) TOTAL AMOUNT (Rs) STRUCTURE WORK 1 Excavation of all kinds of materials including rocks and disposal of all kinds Sft 35000 15 525000
  • 16. of materials outside the project limits 2 Fill and back fill of the area that was Excavated with suitable material and soil. Sft 15400 10 154000 3 Termite control treatment as approved by The engineer. Sft 9500 15 142500 4 Steel reinforcement round bars. M.ton 60 105000 6300000 5 Providing and laying plain cement concrete (PCC) in foundation. Sft 2600 200 520000 6 Providing and laying Reinforced cement Concrete (RCC) in foundations Sft 12000 325 3900000 7 Providing and laying reinforced cement Concrete in column and column stems Sft 2250 350 787500 8 Bricks Pieces 42000 3.5 147000 9 Sand Dumpers 20 3000 60000 10 Stone Ballast Dumpers 10 3600 3600 11 Aluminum Windows Sft 240 1000 240000 12 Wood Sft 1000 1200 120000 13 Providing and laying of RCC in column and column stems in foundations and ground floor. Sft 1225 350 428750 14 Providing and laying RCC in column and Column stems in first floor. Sft 1000 350 350000 15 Providing and laying RCC in plinth beams. Sft 120 350 42000 16 Providing and laying RCC in slabs and stairs. Sft 75 350 26250 17 Providing and laying RCC in over head water tanks Sft 460 350 161000 ARCHITECTURAL WORK 18 Brick work of foundation, complete in all respects Sft 3575 275 983125 19 Brick work of ground floor, complete in all respects Sft 6300 275 1732500 20 Brick work of first floor, complete in all respects Sft 5125 275 1409375 21 Cement sand plaster on interior walls, columns and beams Sft 375 300 112500 22 Cement sand plaster on exterior walls, columns, beams at ground floor Sft 6850 350 239750 23 Cement sand plaster on exterior walls, columns, beams and over head water tanks at first floor Sft 4620 35 161700
  • 17. 24 Cement sand plaster on stairs. Sft 360 35 12600 25 Providing and fixing wooden frames. Sft 21 3600 75600 26 Providing and fixing aluminum windows. Sft 61 4000 244000 27 Three coats of plastic emulsion on external as well as internal walls Sft 12400 25 310000 28 Three coats of synthetic enamel paint of approved quality and color as per instructions Sft 1640 20 32800 29 Three coats of weather shield paint. Sft 3850 25 96250 30 Providing and fixing stair railing on all steps of stairs Sft 510 200 102000 31 Providing and fixing wooden doors and wooden wardrobes Sft 205 2500 512500 32 Providing and laying of crushed stone, sand and cement for concreting of floor. Sft 1090 65 70850 33 Providing and laying of marble and ceramic tiles for flooring Sft 4680 150 702000 34 Providing and fixing of borders and skirting with ceramic tiles and marbles. Sft 780 60 46800 35 External finishes including face work as per the requirements mentioned. Sft 12400 35 434000 36 Providing and fixing of false ceiling Sft 1525 100 152500 PLUMBING WORK 37 Providing and fixing of water supply pipes and fittings of all types. Meters 280 845 236600 38 Providing and fixing of waste pipes, vent pipes and their fittings of all types. Meters 155 1650 255750 ELECTRICAL WORK 39 Providing and fixing of for electric wires of all types Underground and inside the walls. Rft 400 220 88000 40 Providing and fixing of light fixtures. Pieces 44 6500 286000 41 Providing and fixing of LT cables and Rft 300 70 21000 42 Distribution boards. Pieces 3 45000 135000 43 Providing and fixing of Transformer and earthing cables Rft 160 30 4800 TOTAL COST Rs. 22,365,600/-
  • 18. Quality Management Plan To achieve the desired quality of the end product and to work according to the set standard of the previously done projects by Blessings Builders (Pvt.) Limited, following quality management plan has been developed in accordance to the previously mentioned project plan. • Fixed working hours and schedule has been set in order to complete the project in time and to perform flawless work. • Blessings Builders (Pvt.) Limited will hire professionals to conduct soil test in order to get a full description of the natural ground. This will help the project team to prepare for all the necessary actions to be performed while excavating.
  • 19. • Once the soil test report is received excavation will be performed by skilled labor and machinery. When the excavation is complete site officer and site engineer will survey the site and no further work will be performed unless we get an approval. • Quality control officer and site engineer will regularly monitor the structure work at each phase of completion. They will also monitor type and quality of cement, sand, steel reinforcements, brick on each or prior purchase. Only that material would be used which would be mentioned before the work is performed. • The nominal mix or ratio of cement, sand, stone ballast and steel reinforcements shall be observed and followed while laying of Plain Cement Concrete (PCC) and Reinforced Cement Concrete (RCC) in foundations, columns, beams, slabs etc. • Pre concrete inspection The site engineer will check and confirm that the latest issue of drawings have been stamped and approved by the consultants before the pouring of concrete. • Checking of line and level Checks will be made by the site engineer to confirm that the steel reinforcements are in line and at correct location. • Form work The site engineer and site officer will jointly check the form work to ensure that all the requirements have been satisfied. The checks will include the inspection of joints, tolerance, position of the laid materials etc. • Reinforcing steel
  • 20. Reinforcing steel will be fixed in accordance with the stamped and approved drawings. Regular checks will be made by the site engineer to ensure that the work is being done in compliance with the approved drawings. • Cleanliness The site engineer and site officer will check that the entire area where concrete is to be poured is clean and free from dust and construction related debris. • Vibrator and tools The site engineer will check that the number and type of vibrators are available for the pouring of concrete and will also ensure that the vibrators and other tools are in good working order. • Other checks The site engineer and site officer will check that the materials required for the construction are readily available at all times and the materials are acquired as per the schedule. • Safety inspection The site officer will inspect the pour area including the access of roads for concrete delivery, temporary electric works and other materials necessary required for the pouring and preparation for the pour is safe and does not endanger the health and safety of the personnel involved.
  • 21. • Works inspection Our civil, mechanical, electrical and plumbing engineer will carry out their own inspection to ensure that the work has been done properly as per the requirements of the approved drawings. • Consultants inspection When the above inspections have been carried out by our staff, the concrete work is then ready for inspection by the consultants. After the approval of the consultant only the structural work will be started. • All the material weather it will be used in the structural, architectural, electrical, plumbing and for floor work will be procured from approved source and will be inspected and then passed by the Quality Control Lab so that the agreed and expected quality can be achieved. • Before handing over a final check will be made by the quality control officer and site engineer to check for flaws or damage so that the terms and conditions of the agreement may not get violated
  • 23. Company Name: Blessings Builders (Pvt.) Limited Project Name Construction Of Three Hostel Blocks at Jalozai Campus UET Peshawar Prepared By: Ahmed Ali Malik (Project Manager) Date: 23rd Dec, 2010 Project Stakeholder Role in Project Type of Stakeholder Type of Communication Project Interests Impact on Project Outcome Blessings Builders (Pvt.) Limited Contractor Internal Official Meeting, Project Documentation, RFQ, Payment Schedule, e mails. To deliver the project in time and within the approved budget. Influencer Project Team Including Labor Engineers, builders and skilled labor Internal Project performance feedback, face to face communication To perform work as per the requirements and collect wages. Supporter UET Peshawar Client External Project Performance Documentation To receive the final product as per their requirements. Influencer Hashmat Consulting Pvt. Limited Consultant , Quality Control Inspector, Architect Internal Project Performance Documentation To check weather the work is being performed as per the requirements mentioned in the drawings Influencer Tenet Students or Hostilities at UET Peshawar External Nil To live in a comfortable building Influencer Supplier Building material, electrical, plumbing material External RFQ, Invoices, Payment Schedule To deliever good material of approved quality on time and Supporter
  • 24. supplier collect payments on invoices. COMMUNICATON OBJECTIVES 1. Communication with the client (UET Peshawar) a. To keep the client informed of the project progress b. To see if the client needs any change or modification in the project plan c. To update/inform the client regarding accomplishments of the project milestone(s) so as to disperse timely payments. 2. Communication with the consultant a. To keep the consultant informed of the client needs. b. To keep the consultant informed of any change or modification in the architectural plans as per the need of the client. c. To keep the consultant informed of the project progress so that the consultant can make his inspection plan accordingly. 3. Communication with the project team a. To provide daily tasks to the project team. b. To keep a record of the accomplished and unaccomplished tasks. c. To check whether the work done is right or wrong. d. To provide performance feedback to the project team. 4. Communication with the supplier a. To provide Request for Quotation (RFQ) to the supplier of material. b. To keep a record of the purchased items or materials from the supplier.
  • 25. c. To keep check whether the materials are being delivered as per schedule. COMMUNICATION PLAN • Communication with the client will be through monthly meetings and all the project performance will be delivered through documentation. Meetings will be scheduled before the start of construction. • Communication with the consultant will be done via e mails. In return the consultant will provide a schedule for onsite inspection. • Communication with the project team will be done on daily basis with a face to face interaction. • Communication with the supplier will be done through documentation on every purchase, RFQ will be submitted to the supplier in return the supplier will give quotations and best suitable supplier will be chosen. The supplier will submit invoices of the delivered materials on each purchase.
  • 26. HUMAN RESOURCE PLAN This Human Resource Plan describes our staff requirements over the next two years. The areas of responsibilities and experience requirements for each staff position, organization chart as well as salary and remunerations should be provided. ORGANIZATION CHART
  • 27. EMPLOYEE PLAN (YEAR 1-2) Sr. No. Job Title Job description 1 Managing Director Decision maker of the entire project, running the organization. 2 Project Manager Managing the project and the project 3 Security Incharge Responsible of the security of the project site and managing the security guards. 4 Store Keeper Incharge of the store and all the necessary materials and equipment 5 Purchase Incharge Incharge of all the purchases made for the construction of the project through suppliers. 6 Workshop Equipment Incharge Responsible for running the workshop and the equipment. 7 Senior Quantity Surveyor Responsible for keeping the record of quantity of material purchases or to be acquired. 8 Computer Engineer Responsible for making computerized form of the entire project. 9 Planning Engineer responsible for planning all the engineering work 10 Safety Engineer responsible for monitoring and planning all the structural work 11 Quality Control manager managing and controlling the quality 12 Construction Manager managing the construction work 13 Security Guard responsible for the security of the project site 14 Building Material Officer responsible for the ordering and monitoring the building material 15 Electrical/Mechanic Goods Officer responsible for ordering and monitoring the electrical and mechanical goods 16 General Goods Officer responsible for providing day to day goods 17 Assistant Quality Control assisting the senior quantity surveyor 18 Quality Control Inspector inspecting and monitoring the quality standard 19 Surveyor surveyor of the whole project 20 Site Engineer Civil responsible for the structural, architectural and plumbing work 21 Site Engineer Electrical responsible for the electrical work 22 Assistant Surveyor assisting the surveyor 23 Foreman Civil managing the civil labor 24 Foreman Electric managing the electricians
  • 28. 25 Consultant making and designing the architectural and structural designs and drawings 26 Finance Manager Managing all the finances associated with the project 27 Human Resource Manager Managing all the employees associated with the project COMPENSATION AND BENEFITS (Year 1-2) Name of Position Nature of position No. of Position(s) Salary/ Remuneration (Rs) Managing Director Salary (Per Month) 1 35,000 Project Manager Salary (Per Month) 1 30,000 Security Incharge Salary (Per Month) 1 18,000 Store Keeper Salary (Per Month) 1 19,000 Purchase Incharge Remuneration (Contract) 1 22,000 Workshop Equipment Incharge Remuneration (Contract) 1 19,000 Senior Quantity Surveyor Remuneration (Contract) 1 21,000 Computer Engineer Remuneration (Contract) 1 12,000 Planning Engineer Remuneration (Contract) 1 21,000 Safety Engineer Remuneration (Contract) 1 18,000 Quality Control manager Salary (Per Month) 1 20,000 Construction Manager Salary (Per Month) 1 26,000 Security Guard Salary (Per Month) 1 8,000 Building Material Officer Remuneration (Contract) 1 12,000 Electrical/Mechani c Goods Officer Remuneration (Contract) 1 12,000 General Goods Officer Remuneration (Contract) 1 12,000 Assistant Quantity Control Remuneration (Contract) 1 12,000 Quality Control Inspector Remuneration (Contract) 1 14,000 Surveyor Remuneration (Contract) 1 12,000
  • 29. Site Engineer Civil Remuneration (Contract) 3 16,000 Site Engineer Electrical Remuneration (Contract) 1 16,000 Assistant Surveyor Remuneration (Contract) 1 9,000 Foreman Civil Remuneration (Contract) 3 11,000 Foreman Electric Remuneration (Contract) 1 11,000 Consultant Remuneration (Contract) 1 35,000 Totals: 441,000
  • 30. RISK MANAGEMENT PLAN RISK REGISTER Sr. No RISK RISK MANAGEMENT IMPACT 1 Over costing more than the budget allocated Blessings Builders (Pvt.) Limited (Contractor) will take a bank loan for the completion of the project High 2 In case the project does not completes in time The contractor will appoint more labor for the completion of the project High 3 Machinery Break Down We have on site workshop for equipment and machinery maintenance Low 4 Theft Store Keeper & Security Guard would be investigated and necessary action would be taken against them Medium 5 Employee Attrition Immediately new experienced employee will be hired for that position Medium 6 Material Shortage Forecasting would be done and materials would be procured Low 7 Political Envoirment Of Pakistan Measures will be taken to avoid such situation which will affect the project Medium 8 Competition Our company strategy distinguishes us from our competitors is to provide the best quality in the lowest cost and time possible Low 9 Changing Market conditions As the inflation rate of Pakistan is quite high so we will make an agreement with our suppliers for the purchase of materials Medium 10 Load shedding We will provide standby generators on the site to encounter load shedding High
  • 31. 11 Natural Disaster We will make the structure of the buildings strong enough to bear 8 rector scale of earthquake and build the boundary walls high enough to block flood Low 12 Material Damage Material will be replaced Low PROJECT PROCUREMENT PLAN Project Name: Construction Of Three Hostel Blocks At UET Peshawar Prepared by: Ahmed Ali Malik (Project Manager) Procurement Statement Blessings Builders (Pvt.) Limited will procure all the necessary materials required for the construction of the hostel blocks from approved sources which include the following: • Cement • Steel reinforcements • Sand • Bricks • Stone Ballast • Wood • Glass Windows • Electrical equipment • Plumbing equipment • Paint • PVC piping Estimated Cost Total estimated cost for all the procurements is twenty million rupees. i.e Rs. 20,000,000/- and keeping in reserve +/- 20% of the estimated cost. Vendor Selection Blessings Builder (Pvt.) limited will issue a tender through news papers regarding Request For Quotations (RFQ). The suppliers or vendors will submit their quotations through mails.
  • 32. Selection Process & Criteria The suppliers will be selected on the following criteria: • Low cost • Quality of the materials • Timely delivery • Reputation in the market Project Procurement team Sr. No JOB TITLE PROCUREMENT ROLE 1 Project Manager Overlooks the whole procurement team 2 Purchase Section Incharge Manages the procurement team and all the purchases made for the project 3 Building Material Incharge Responsible for procuring building material like cement, sand, wood etc. 4 Electrical Goods Incharge Responsible for procuring Electrical equipment and accessories 5 General Goods Incharge Responsible for procuring General Goods required for running day to day operations