CONTRACTS AND
PAYMENT STRUCTURES
EMCM5103 TOPIC 2
TYPES OF CONTRACT STRUCTURE
• CONVENTIONAL / TRADITIONAL CONTRACT
• TURNKEY CONTRACT
• DESIGN AND BUILD CONTRACT
• CONSTRUCTION MANAGEMENT AND MANAGEMENT
CONTRACTING
• GUARANTEED MAXIMUM PRICE
CONVENTIONAL/TRADITIONAL CONTRACT
• Major responsibilities to architect/engineer
• Client’s roles : Planning and designing phases of project,
monitoring and supervision by PM or independent consultant
• Contractor selected by tendering process
CONVENTIONAL/TRADITIONAL CONTRACT
• Under this contract, the design responsibility primarily falls on the
architect or engineer employed by the client and the contractor.
• In the Malaysian context, the client’s organisation usually does all the
planning and designing phases of a project. The construction phase of the
project is done by the contractor who is selected and appointed through
the tender process.
• The Client’s organisation may carry out monitoring and supervision of the
project through the appointed project manager or may engage an
independent consultant to carry out monitoring of the project.
TURNKEY CONTRACT
- Contractor employed by client shall take major responsibilities in
design, procurement, construction and commissioning of entire works
including the management of project.
- Also known as Engineering, Procurement and Construction (EPC).
Commonly adopted for the design and construction under Private
Finance Initiative.
- Similar to Design and Build
- Used for government big project and clients roles limited to
inspection, payment and performance target.
- In Malaysia, normally JKR will provide the standards guidelines for
writing the need statement, format, requirements for contractor’s
proposal , contract sum analysis and other related contractual terms
for turnkey project.
TURNKEY CONTRACT
DESIGN AND BUILD CONTRACT
• Design and Build Contract similar to turnkey contract. Client
usually retain an agent (architect/engineer) who can monitor and
protect its interest.
CONSTRUCTION MANAGEMENT AND
MANAGEMENT CONTRACTING
• Under this contract structure, the subcontractors shall execute all the
construction works while the contractor is the one who manages the
entire project processes.
• Construction management – The subcontractors are contractually
responsible to the client and the project is usually manage by the
construction manager.
• Management contracting – The subcontractor is employed by the
management contractor. The success rely by the skills and experiences
of the personnel involved.
• Other features similar to D&B contract
CLIENT
CONSTRUCTION
MANAGER
PROJECT
MANAGER
CLIENT’S
DESIGNERS
WORKS
CONTRACTOR
WORKS
CONTRACTOR
WORKS
CONTRACTOR
CONSULTANTS
SUBCONTRACTOR SUPPLIERS
CONSTRUCTION MANAGEMENT
Management Contracting
GUARANTEED MAXIMUM PRICE CONTRACT
• Combination of construction mgmt. and D&B contract.
• The contractor/construction manager agrees to perform work within a price
ceiling. Contractor guarantees a max price for the work to be completed
according to the design.
• Contractor responsible for the design and tendering phases.
• Contractor fees for overhead and profit are contractually decided and agreed
upon once appointed by client.
• The price will not change except there is authorised modification.
• If the ceiling is exceeded, without change in scope, then the excess cost is
borne by the contractor.
• If the work is accomplished under the ceiling then the owner pays no more than
the actual cost and the profit is shared between the contractor and the owner.
• This method gives greater flexibility to the owner.
FACTORS DETERMINING THE ADOPTION OF
CONTRACT STRUCTURE
• PROJECT COMPLEXITY
• SPEED OF THE PROJECT
• CLIENT’S EXPERIENCE
• CONTRACT SUBJECT TO LOCAL REGULATIONS
• LIKELIHOOD OF PROJECT CHANGES
• NATURE OF THE PROJECT
• ALLOCATION OF RISKS
1. PROJECT COMPLEXITY
• The design of the building is complex and have high engineering content.
Complexity interrelated with issues such as expert and skills of consultant,
duration and cost of the project.
• More complex – more tedious – more difficult to handle the cost and longer
duration of project.
• For example, the lump-sum type of contract, is popular for the reason that the total cost
of the project is known in advance. But if the project is too complicated, it is not
possible to accurately determine the nature and quantity of the work prior to the start
of site activities, then lump sum type of contract pricing is not suitable.
2. SPEED OF THE PROJECT (Start to
Completion)
• The need to complete the project on time or earlier is a crucial issue
for projects especially those involving high traffic congestion or for low
cost projects where timing and costing are major challenges.
• The right choice of contract structure is crucial to ensure the success
of the project.
3. CLIENT’S EXPERIENCES
• The bigger or more experienced clients have their own preferred protocols which
involves specific choice of contract form. The credibility and commitment of the
client has always been an added value in project, thus client must be aware that
the contract structure has to fit well with the nature of project.
• For example, the client prefers competitive bidding to be able to compare and choose the most
suitable tender.
• The choice of contract form would therefore depend on the client’s experience.
4. CONTRACT SUBJECT TO LOCAL
REGULATIONS
• For international projects, legal conditions must be synchronised, the
commercial terms must be agreed on and the risk must be apportioned.
• Project will involve various legal systems and global organisation has to
deal with different practices in different countries, thus project team
need to select the right strategy of contract structure for the global
project.
5. LIKELIHOOD OF PROJECT CHANGES
• Some contractors/clients will allow the changes of the design when
construction stage start but some will not allow and every design must
follow the tender, and these two required different contract form.
• Each project is susceptible to change because of the complexities which
are unique to each project. The level of changes projection in a project
is to influence the type of contract structure selected.
6. NATURE OF THE PROJECT
• Different types of project will affect the choice of contract form.
• For example, the project can be build a new building, extension of
building, renovation works, industrial building and more.
• Different projects have different requirements therefore required
different type of contract form.
7. ALLOCATION OF RISK
• All sorts of risks arising from both the internal and external
environment of a project or organization and affecting the project
performance,
• In terms of successful delivery of project on of time, within budget
and of the specified performance.
• Important to know how much risk is shared in the project and how
much risk is allocated to the contractor and client.
CONTRACT PRICING
Contract Pricing consists of 3 types:
a.Lump Sum or Fixed Price
b.Re measurement or Bill of Quantities
c.Cost Reimbursement
- Possible to combine more than 1 type of pricing within a project.
- Pricing depend on information given to the contractor during tendering
phase, the level of risk involved and the conditions under which the
work will be carried out.
- The nature of contract structure also plays important role in
determining the pricing basis.
LUMP SUM , MEASUREMENT & COST
REIMBURSEMENT CONTRACT
• Lump sum contracts — where the contract sum is
determined before construction work is started.
• Measurement contracts — where the contract sum is
assessed on re-measurement to a previously agreed
basis.
• Cost reimbursement contracts — where the contract sum
is set based on the prime costs (of labour, plant and
materials) plus an agreed amount for overheads and
profit.
LUMP SUM BASIS (FIXED PRICE CONTRACT)
• Client-contractor agree on a price for the proposed work. Price remains
fixed unless both agree to any changes.
• Less risks to client (buyer) as they will no pay any extra cost incurred.
Contractor (seller) has to be very accurate in computing the cost
estimates and to include sufficient contingency cost. Bigger risk is borne
by contractor.
• Suit to low risk and well defined projects.
• High commitment needed in advance and reduces the amount of
administrative work after contract is in effect.
LUMP SUM BASIS
REMEASUREMENT / BILL OF QUANTITIES
• Work is measured and costed as it is performed in accordance with a priced
bill of quantities agreed between parties. 2 types of BQ used :
i. BQ for Building Contract
- Contract is segregated in accordance to the quantity of work described in BQ.
- Usually the quantity of work of this nature is an accurate estimation of the
actual work done unless the approximate estimation of the quantity of work
is of concerned.
ii. BQ for Civil Engineering Contract
- The price usually based on the approximate estimation of the quantity of
work to be performed; no lump sum amount is stated as the measurement is
to be determined accurately by the work done.
- The valuation of work shall be represented by the rates given in the BQ.
REMEASUREMENT CONTRACT/BILL OF
QUANTITIES
REMEASUREMENT CONTRACT/BILL OF
QUANTITIES
COST REIMBURSEMENT CONTRACT
• Most convenient basis of contract pricing if inadequate designs/drawings or
definite specifications.
• Contractor/subcontractors supply all resources as and when required, and
shall invoice the client at cost plus an agreed percentage to cover
overheads and profit.
• 2 main components:
i. A fee component which covers design costs, site and project management
costs, overheads and profits and;
ii.A prime cost component which covers equipment, materials,
consumables, plant, site labour, subcontracts and site establishment.
COST REIMBURSEMENT CONTRACT
COST REIMBURSEMENT CONTRACTS
COST REIMBURSEMENT CONTRACT
• This type of contract pricing is of high risk to the client if the
contracting job costs overrun from the proposed price.
• Thus, in cost reimbursement pricing, the client usually requires
the contractor to regularly compare the actual expenditures with
the proposed budget, re-forecast costs at completion and
compare those against the original proposed price.
COST REIMBURSEMENT CONTRACTS
• There are three kinds of cost-reimbursable contracts:
1.Cost plus fee (CPF) or cost plus percentage of cost (CPPC)
2.Cost plus fixed fee (CPFF)
3.Cost plus incentive fee (CPIF)
• Here the seller is reimbursed for allowable costs plus a fee
that’s calculated as a percentage of costs.
• Obviously, there is no incentive for the seller to complete the
work quickly with this type of contract.
Cost plus percentage fee (CPF)
Cost plus fixed fee (CPFF)
• Here all allowable expenses are charged back plus a fixed fee at
the end of the contract.
• The fixed fee is how the seller makes their profit.
• The aim of the fixed fee is to encourage the seller to complete
the work as quickly as possible.
Cost plus incentive fee (CPIF)
• Here all allowable expenses are charged back and in addition an
incentive fee for exceeding the performance criteria specified in
the contract.
• The incentive fee is designed to encourage increased cost
performance by the seller. There is the potential of both buyer and
seller saving if the performance criteria is exceeded.
TERMS OF PAYMENT
• The best benefit to offer the tenderers who bid for the project is a term of
payment that is able to achieve both the commercial and technical results while
still able to provide the client with reasonable contractual safeguards. The
approach provides numerous benefits to the client such as :
a. Able to offer the project not to only to larger firm whose overheads and prices
are likely to be higher but also to the smaller but competent companies as well;
b.Tenderers who bid the project do not have to inflate their tender prices due to
financing charges as a result of having to pay the interest from having to take out
a loan for the project;
c.Enable the companies who possess technical expertise but lack liquid cash to also
bid along with other companies
d.Minimise the risk of having to straddle with the contractor who has insufficient
cash to carry out the project to completion phase and will save both parties
from terminating the contract before the project is completed.
TERMS OF PAYMENT
• In addition , not all payments can be tendered for lump sum basis due to prevalent
uncertainties especially when assessing the quantity of work that needs to have the
approximate valuation in their bill of quantities. It is more reasonable to pay them
on monthly basis for the value of work that already has been completed. It is also
good practice to tie the payment with the completion of certain milestones which
can be identified from the work program.
• However, to offer the terms of payment of such kind will also bring few
disadvantages to the client such as :
a.Client has to finance the work in progress which in a way might hold up their capital
for the respective short-term period;
b.Paying by term might encourage incompetent small contractors who do not possess
technical competencies to undertake the work that offers low price;
c.Monthly payment especially under remeasurement contract may have the tendency
to be over-measured during the early months of the contract.
DELAY IN PAYMENT
• Delay payment = breach of contract
• Payment period stipulated clearly in the contract
• Specified period of payment = ( from the issuance of certificate from the
architect/engineer) (from the invoice submitted by contractor depending on the
context of the contract)
• Contract imposes interests on delayed payments.
• Payment delay after the stipulated period, contractor have rights to suspend
work/ even terminate the contract (under The Construction Industry Act)
• If not mentioned in contact, – generally, imposed 8% interest above base rate
under the Late Payment of Commercial Debt Act under UK law.
ADVANCE PAYMENT, PROGRESS PAYMENT AND
RETENTION MONEY
ADVANCE PAYMENT
-In general, payment cannot be made in advance
- but the practice is in the form of various types of bond
PROGRESS PAYMENTS DURING MANUFACTURE
- Stated in the contract that the plant, in accordance to the payments made, will
become the property of the purchaser accordingly.
- The manufacturer shall bear the risk up to completion phase and has been approved
and accepted by the purchaser.
RETENTION MONEY
- Under contract, client withhold 10%-20% from the contract price until work fully
completed and accepted by purchaser.
- Will be released in portion during defect liability period as security .
THANK YOU

Mais conteúdo relacionado

Mais procurados

Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.pptMohammedAbdu46
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxsurekha1287
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their typesTouqeer1
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project managementAravind Samala
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 

Mais procurados (20)

Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.ppt
 
Risk management
Risk managementRisk management
Risk management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
 
Claims
ClaimsClaims
Claims
 
Schedule-Delay Analysis
Schedule-Delay AnalysisSchedule-Delay Analysis
Schedule-Delay Analysis
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
Fidic
FidicFidic
Fidic
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
 

Semelhante a TOPIC2.pdf

Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptxssuser42980c
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptxjairam131
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZmianmohsinmumtazshb
 

Semelhante a TOPIC2.pdf (20)

Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Construction contract
Construction contract Construction contract
Construction contract
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 

Mais de HASMANIRA

Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
International Project Management - Core Concept and Theory of Projects
International Project Management - Core Concept and Theory of ProjectsInternational Project Management - Core Concept and Theory of Projects
International Project Management - Core Concept and Theory of ProjectsHASMANIRA
 
OSHConstructionLecture_Legal Requirements .pdf
OSHConstructionLecture_Legal Requirements .pdfOSHConstructionLecture_Legal Requirements .pdf
OSHConstructionLecture_Legal Requirements .pdfHASMANIRA
 

Mais de HASMANIRA (9)

Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
International Project Management - Core Concept and Theory of Projects
International Project Management - Core Concept and Theory of ProjectsInternational Project Management - Core Concept and Theory of Projects
International Project Management - Core Concept and Theory of Projects
 
OSHConstructionLecture_Legal Requirements .pdf
OSHConstructionLecture_Legal Requirements .pdfOSHConstructionLecture_Legal Requirements .pdf
OSHConstructionLecture_Legal Requirements .pdf
 
topic9.pdf
topic9.pdftopic9.pdf
topic9.pdf
 
TOPIC8.pdf
TOPIC8.pdfTOPIC8.pdf
TOPIC8.pdf
 
TOPIC6.pdf
TOPIC6.pdfTOPIC6.pdf
TOPIC6.pdf
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
TOPIC5.pdf
TOPIC5.pdfTOPIC5.pdf
TOPIC5.pdf
 
TOPIC3.pdf
TOPIC3.pdfTOPIC3.pdf
TOPIC3.pdf
 

Último

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 

Último (20)

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 

TOPIC2.pdf

  • 2. TYPES OF CONTRACT STRUCTURE • CONVENTIONAL / TRADITIONAL CONTRACT • TURNKEY CONTRACT • DESIGN AND BUILD CONTRACT • CONSTRUCTION MANAGEMENT AND MANAGEMENT CONTRACTING • GUARANTEED MAXIMUM PRICE
  • 3. CONVENTIONAL/TRADITIONAL CONTRACT • Major responsibilities to architect/engineer • Client’s roles : Planning and designing phases of project, monitoring and supervision by PM or independent consultant • Contractor selected by tendering process
  • 4. CONVENTIONAL/TRADITIONAL CONTRACT • Under this contract, the design responsibility primarily falls on the architect or engineer employed by the client and the contractor. • In the Malaysian context, the client’s organisation usually does all the planning and designing phases of a project. The construction phase of the project is done by the contractor who is selected and appointed through the tender process. • The Client’s organisation may carry out monitoring and supervision of the project through the appointed project manager or may engage an independent consultant to carry out monitoring of the project.
  • 5. TURNKEY CONTRACT - Contractor employed by client shall take major responsibilities in design, procurement, construction and commissioning of entire works including the management of project. - Also known as Engineering, Procurement and Construction (EPC). Commonly adopted for the design and construction under Private Finance Initiative. - Similar to Design and Build - Used for government big project and clients roles limited to inspection, payment and performance target. - In Malaysia, normally JKR will provide the standards guidelines for writing the need statement, format, requirements for contractor’s proposal , contract sum analysis and other related contractual terms for turnkey project.
  • 7. DESIGN AND BUILD CONTRACT • Design and Build Contract similar to turnkey contract. Client usually retain an agent (architect/engineer) who can monitor and protect its interest.
  • 8. CONSTRUCTION MANAGEMENT AND MANAGEMENT CONTRACTING • Under this contract structure, the subcontractors shall execute all the construction works while the contractor is the one who manages the entire project processes. • Construction management – The subcontractors are contractually responsible to the client and the project is usually manage by the construction manager. • Management contracting – The subcontractor is employed by the management contractor. The success rely by the skills and experiences of the personnel involved. • Other features similar to D&B contract
  • 10.
  • 12.
  • 13. GUARANTEED MAXIMUM PRICE CONTRACT • Combination of construction mgmt. and D&B contract. • The contractor/construction manager agrees to perform work within a price ceiling. Contractor guarantees a max price for the work to be completed according to the design. • Contractor responsible for the design and tendering phases. • Contractor fees for overhead and profit are contractually decided and agreed upon once appointed by client. • The price will not change except there is authorised modification. • If the ceiling is exceeded, without change in scope, then the excess cost is borne by the contractor. • If the work is accomplished under the ceiling then the owner pays no more than the actual cost and the profit is shared between the contractor and the owner. • This method gives greater flexibility to the owner.
  • 14. FACTORS DETERMINING THE ADOPTION OF CONTRACT STRUCTURE • PROJECT COMPLEXITY • SPEED OF THE PROJECT • CLIENT’S EXPERIENCE • CONTRACT SUBJECT TO LOCAL REGULATIONS • LIKELIHOOD OF PROJECT CHANGES • NATURE OF THE PROJECT • ALLOCATION OF RISKS
  • 15. 1. PROJECT COMPLEXITY • The design of the building is complex and have high engineering content. Complexity interrelated with issues such as expert and skills of consultant, duration and cost of the project. • More complex – more tedious – more difficult to handle the cost and longer duration of project. • For example, the lump-sum type of contract, is popular for the reason that the total cost of the project is known in advance. But if the project is too complicated, it is not possible to accurately determine the nature and quantity of the work prior to the start of site activities, then lump sum type of contract pricing is not suitable.
  • 16. 2. SPEED OF THE PROJECT (Start to Completion) • The need to complete the project on time or earlier is a crucial issue for projects especially those involving high traffic congestion or for low cost projects where timing and costing are major challenges. • The right choice of contract structure is crucial to ensure the success of the project.
  • 17. 3. CLIENT’S EXPERIENCES • The bigger or more experienced clients have their own preferred protocols which involves specific choice of contract form. The credibility and commitment of the client has always been an added value in project, thus client must be aware that the contract structure has to fit well with the nature of project. • For example, the client prefers competitive bidding to be able to compare and choose the most suitable tender. • The choice of contract form would therefore depend on the client’s experience.
  • 18. 4. CONTRACT SUBJECT TO LOCAL REGULATIONS • For international projects, legal conditions must be synchronised, the commercial terms must be agreed on and the risk must be apportioned. • Project will involve various legal systems and global organisation has to deal with different practices in different countries, thus project team need to select the right strategy of contract structure for the global project.
  • 19. 5. LIKELIHOOD OF PROJECT CHANGES • Some contractors/clients will allow the changes of the design when construction stage start but some will not allow and every design must follow the tender, and these two required different contract form. • Each project is susceptible to change because of the complexities which are unique to each project. The level of changes projection in a project is to influence the type of contract structure selected.
  • 20. 6. NATURE OF THE PROJECT • Different types of project will affect the choice of contract form. • For example, the project can be build a new building, extension of building, renovation works, industrial building and more. • Different projects have different requirements therefore required different type of contract form.
  • 21. 7. ALLOCATION OF RISK • All sorts of risks arising from both the internal and external environment of a project or organization and affecting the project performance, • In terms of successful delivery of project on of time, within budget and of the specified performance. • Important to know how much risk is shared in the project and how much risk is allocated to the contractor and client.
  • 22. CONTRACT PRICING Contract Pricing consists of 3 types: a.Lump Sum or Fixed Price b.Re measurement or Bill of Quantities c.Cost Reimbursement - Possible to combine more than 1 type of pricing within a project. - Pricing depend on information given to the contractor during tendering phase, the level of risk involved and the conditions under which the work will be carried out. - The nature of contract structure also plays important role in determining the pricing basis.
  • 23. LUMP SUM , MEASUREMENT & COST REIMBURSEMENT CONTRACT • Lump sum contracts — where the contract sum is determined before construction work is started. • Measurement contracts — where the contract sum is assessed on re-measurement to a previously agreed basis. • Cost reimbursement contracts — where the contract sum is set based on the prime costs (of labour, plant and materials) plus an agreed amount for overheads and profit.
  • 24. LUMP SUM BASIS (FIXED PRICE CONTRACT) • Client-contractor agree on a price for the proposed work. Price remains fixed unless both agree to any changes. • Less risks to client (buyer) as they will no pay any extra cost incurred. Contractor (seller) has to be very accurate in computing the cost estimates and to include sufficient contingency cost. Bigger risk is borne by contractor. • Suit to low risk and well defined projects. • High commitment needed in advance and reduces the amount of administrative work after contract is in effect.
  • 26. REMEASUREMENT / BILL OF QUANTITIES • Work is measured and costed as it is performed in accordance with a priced bill of quantities agreed between parties. 2 types of BQ used : i. BQ for Building Contract - Contract is segregated in accordance to the quantity of work described in BQ. - Usually the quantity of work of this nature is an accurate estimation of the actual work done unless the approximate estimation of the quantity of work is of concerned. ii. BQ for Civil Engineering Contract - The price usually based on the approximate estimation of the quantity of work to be performed; no lump sum amount is stated as the measurement is to be determined accurately by the work done. - The valuation of work shall be represented by the rates given in the BQ.
  • 29. COST REIMBURSEMENT CONTRACT • Most convenient basis of contract pricing if inadequate designs/drawings or definite specifications. • Contractor/subcontractors supply all resources as and when required, and shall invoice the client at cost plus an agreed percentage to cover overheads and profit. • 2 main components: i. A fee component which covers design costs, site and project management costs, overheads and profits and; ii.A prime cost component which covers equipment, materials, consumables, plant, site labour, subcontracts and site establishment.
  • 32. COST REIMBURSEMENT CONTRACT • This type of contract pricing is of high risk to the client if the contracting job costs overrun from the proposed price. • Thus, in cost reimbursement pricing, the client usually requires the contractor to regularly compare the actual expenditures with the proposed budget, re-forecast costs at completion and compare those against the original proposed price.
  • 33. COST REIMBURSEMENT CONTRACTS • There are three kinds of cost-reimbursable contracts: 1.Cost plus fee (CPF) or cost plus percentage of cost (CPPC) 2.Cost plus fixed fee (CPFF) 3.Cost plus incentive fee (CPIF)
  • 34.
  • 35. • Here the seller is reimbursed for allowable costs plus a fee that’s calculated as a percentage of costs. • Obviously, there is no incentive for the seller to complete the work quickly with this type of contract. Cost plus percentage fee (CPF)
  • 36. Cost plus fixed fee (CPFF) • Here all allowable expenses are charged back plus a fixed fee at the end of the contract. • The fixed fee is how the seller makes their profit. • The aim of the fixed fee is to encourage the seller to complete the work as quickly as possible.
  • 37. Cost plus incentive fee (CPIF) • Here all allowable expenses are charged back and in addition an incentive fee for exceeding the performance criteria specified in the contract. • The incentive fee is designed to encourage increased cost performance by the seller. There is the potential of both buyer and seller saving if the performance criteria is exceeded.
  • 38. TERMS OF PAYMENT • The best benefit to offer the tenderers who bid for the project is a term of payment that is able to achieve both the commercial and technical results while still able to provide the client with reasonable contractual safeguards. The approach provides numerous benefits to the client such as : a. Able to offer the project not to only to larger firm whose overheads and prices are likely to be higher but also to the smaller but competent companies as well; b.Tenderers who bid the project do not have to inflate their tender prices due to financing charges as a result of having to pay the interest from having to take out a loan for the project; c.Enable the companies who possess technical expertise but lack liquid cash to also bid along with other companies d.Minimise the risk of having to straddle with the contractor who has insufficient cash to carry out the project to completion phase and will save both parties from terminating the contract before the project is completed.
  • 39. TERMS OF PAYMENT • In addition , not all payments can be tendered for lump sum basis due to prevalent uncertainties especially when assessing the quantity of work that needs to have the approximate valuation in their bill of quantities. It is more reasonable to pay them on monthly basis for the value of work that already has been completed. It is also good practice to tie the payment with the completion of certain milestones which can be identified from the work program. • However, to offer the terms of payment of such kind will also bring few disadvantages to the client such as : a.Client has to finance the work in progress which in a way might hold up their capital for the respective short-term period; b.Paying by term might encourage incompetent small contractors who do not possess technical competencies to undertake the work that offers low price; c.Monthly payment especially under remeasurement contract may have the tendency to be over-measured during the early months of the contract.
  • 40. DELAY IN PAYMENT • Delay payment = breach of contract • Payment period stipulated clearly in the contract • Specified period of payment = ( from the issuance of certificate from the architect/engineer) (from the invoice submitted by contractor depending on the context of the contract) • Contract imposes interests on delayed payments. • Payment delay after the stipulated period, contractor have rights to suspend work/ even terminate the contract (under The Construction Industry Act) • If not mentioned in contact, – generally, imposed 8% interest above base rate under the Late Payment of Commercial Debt Act under UK law.
  • 41. ADVANCE PAYMENT, PROGRESS PAYMENT AND RETENTION MONEY ADVANCE PAYMENT -In general, payment cannot be made in advance - but the practice is in the form of various types of bond PROGRESS PAYMENTS DURING MANUFACTURE - Stated in the contract that the plant, in accordance to the payments made, will become the property of the purchaser accordingly. - The manufacturer shall bear the risk up to completion phase and has been approved and accepted by the purchaser. RETENTION MONEY - Under contract, client withhold 10%-20% from the contract price until work fully completed and accepted by purchaser. - Will be released in portion during defect liability period as security .