Semi-Real Time
Inclinometer readings
using Wire-less
Technologies
G.H. Tan, Y.K. Poh
SysEng (S) Pte Ltd
N. Osborne, C.C. Ng
Land Transport Authority, Singapore
Geotechnical Instruments are :-
•Site Investigation Work
•Design Verification
•Performance
•Safety
•Construction Control
•Quality Control
•Legal Protection
When safety is the highest
priority, it must have a reliable
and fast method to deliver on-
site results to decision
makers:-
•Safety
•Construction Control
•Quality Control
•Legal Protection
Lessons
learned from
a Major Past
incident
Inclinometers are used for monitoring
the soil movements over time
Daily
Automatic
Data
Processing of
Inclinometer
Readings
Current Industry
practice
Geokon Slope Indicator Encardio-rite
RST Instruments (PDA)
Inclinometers from various manufacturers
Soil Instruments (PDA)
There readout
boxes require a
PC to download
their data
Timing for measuring 10 bore holes in a site
10 mins
In Main office, switch on
PC to download,
process, verify and
email to Stake Holders
Drive back
for 60 mins
Case Study:
Total Throughput time
for Bore Hole#1 data to
reach end user is
60x10 + 10x9 + 60 + 30
mins = 780 mins (13 hrs)
30 mins for
processing data
60 minsBore
Hole#1
10 mins
60 minsBore
Hole#2
10 mins
60 minsBore
Hole#3
60 minsBore
Hole#10
Many challenges to ensure
consistency as construction sites
are far from ideal conditions with
practical constraints of :-
•Human Errors
•Measurement bore holes with
blockages
•Worker inexperience
•Inefficiencies due to manual work
•Weather (Rain, Lightning and Heat)
A new method to
reduce the time taken
from the
measurement until it
reaches the Stake
Holder using Wire-
less Technologies
Simple steps for Data retrieval from sites using
existing inclinometer, user’s mobile phone
Short Range
Device consists
of a battery
powered
embedded
computer with
Wire-less
Bluetooth
module
3 m
Central
Server
System
Transferring data from Mobile Phone to
Stake holder using Central Server
GPRS
Open
Public
Network
Email with
raw data &
Inclinometer
plot
Worker walks
to another
bore hole
Timing taken in the New Work Flow Process
2 mins
Case Study:
Total Throughput time
for Bore Hole#1 data to
reach end user is
60 + 2 + 8 mins = 70 mins
60 minsBore
Hole#1
8 mins
GPRS
Transmission
Automatic
Processing
and Emailing
10 mins
Comparison of the time taken to
obtain on site measurements
Current Practice : 780 minutes
Improve Method : 70 minutes
Throughput improvements :
= 780 / 70 = 11 !
+
Advantages of the Semi-Real Time
Inclinometer solution
• PC-less system to retrieve the data
• Preventing loss of PC on site
• Maximum use of inclinometer system
• Low Error possibility with less human
intervention of data processing
• Worker uses this own Mobile Phone with only
additional GPRS charges
• Consultant gets measured data immediately
• Any measurement re-confirmation can be done
immediately via a phone call rather than doing it
the next day
Site Workers Office staff gets
information and
discuss resultsMeasures and Transmit data
+
SDR
The feedback comments from
the users:-
• When the readings showed
unexpected movements, it
provides opportunity to
immediately phone the site staff
to re-measure and verify that
particular bore-hole.
• When there are Critical Lateral
Displacements to be monitored,
this is the best approach to
control the Site Work Activities
to enhance the Safety as well as
to allow Critical Activity to be
carried out
• Without this technology, the
technician needs to monitor all
the inclinometers of the project
before he comes back to office
at the end of the day to down
load the raw data readings
logged in the readout box to the
PC. It will take a few hours for
the readings of the inclinometer
to reach the user after it is taken
An added advantage for
the data security to
prevent unaware data
alteration in the system
to help Professional
Engineers minimize
their risks & liabilities
Current Data Flow Practice
Readout
Box and
Computer
for down
loading
Monitoring
Engineer
Process
Report with
justifiable
adjustment
Mistakes ?
Care-less ?
Forget ?
Authority
Consultant
Proposed Data Flow Security
Central
Server
Monitoring
Engineer
Process
Reports with
justifiable
adjustments
Raw data
kept intact
using Parallel
Information
Flow for
verification
Processed
Inclinometer
Information
Authority
Consultant
Benefits of the Proposed System
• The measured data is automatically plotted
and email simultaneously to all stake holders
• This processed information will be over-
ride, if the monitoring engineer has
correction with justifications
• Unique User ID tagged to Readout Box to
avoid mixed up information from various
Readout Boxes and Files
• Date & Time when the readings are carried
out are Logged at the Server, & NOT using
the clock of the Readout Box, which could
be altered at Box level

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

MDC plus. Zyfra
MDC plus. ZyfraMDC plus. Zyfra
MDC plus. Zyfra
 
FMS intro
FMS introFMS intro
FMS intro
 
Further improvements
Further improvementsFurther improvements
Further improvements
 
Direct Digital Control
Direct Digital ControlDirect Digital Control
Direct Digital Control
 
K05137073
K05137073K05137073
K05137073
 
datalogger
dataloggerdatalogger
datalogger
 
Remote HVAC service presentation
Remote HVAC service presentationRemote HVAC service presentation
Remote HVAC service presentation
 
Design Of Cooling Tower With Iot
Design Of Cooling Tower With IotDesign Of Cooling Tower With Iot
Design Of Cooling Tower With Iot
 
JP Morgan North American Remote to Core Justification
JP Morgan North American Remote to Core JustificationJP Morgan North American Remote to Core Justification
JP Morgan North American Remote to Core Justification
 
2016_Brochure_Book
2016_Brochure_Book2016_Brochure_Book
2016_Brochure_Book
 
Top 9 issues in construction industry and how Ayoga can solve it
Top 9 issues in construction industry and how Ayoga can solve itTop 9 issues in construction industry and how Ayoga can solve it
Top 9 issues in construction industry and how Ayoga can solve it
 
Industrial Automation
Industrial AutomationIndustrial Automation
Industrial Automation
 
PointSense Portable Logger Data Sheet
PointSense Portable Logger Data SheetPointSense Portable Logger Data Sheet
PointSense Portable Logger Data Sheet
 
GE Oil & Gas Threatscan
GE Oil & Gas ThreatscanGE Oil & Gas Threatscan
GE Oil & Gas Threatscan
 
Data logger
Data loggerData logger
Data logger
 
Digital contrs
Digital contrsDigital contrs
Digital contrs
 
Take 5 Feedback Safety Monitoring Solutions
Take 5 Feedback Safety Monitoring SolutionsTake 5 Feedback Safety Monitoring Solutions
Take 5 Feedback Safety Monitoring Solutions
 
HGCM System2
HGCM System2HGCM System2
HGCM System2
 
Controller
ControllerController
Controller
 
Customer case: Health & Safety
Customer case: Health & SafetyCustomer case: Health & Safety
Customer case: Health & Safety
 

Destaque

Philosophies-in-full-mouth-rehabilitation-a-systematic-review
Philosophies-in-full-mouth-rehabilitation-a-systematic-reviewPhilosophies-in-full-mouth-rehabilitation-a-systematic-review
Philosophies-in-full-mouth-rehabilitation-a-systematic-review
Aravind Krishnan
 

Destaque (9)

P10 e2 diego_aranda_2bcd
P10 e2 diego_aranda_2bcdP10 e2 diego_aranda_2bcd
P10 e2 diego_aranda_2bcd
 
AWS RoadShow Dublin - Intro to AWS
AWS RoadShow Dublin - Intro to AWSAWS RoadShow Dublin - Intro to AWS
AWS RoadShow Dublin - Intro to AWS
 
TEL (TRASTORNO ESPECIFICO DEL LENGUAJE)
TEL (TRASTORNO ESPECIFICO DEL LENGUAJE)TEL (TRASTORNO ESPECIFICO DEL LENGUAJE)
TEL (TRASTORNO ESPECIFICO DEL LENGUAJE)
 
Fundamentos técnicos de internet
Fundamentos técnicos de internetFundamentos técnicos de internet
Fundamentos técnicos de internet
 
P10 e2 rodrigo_rivilla_2ºa
P10 e2 rodrigo_rivilla_2ºaP10 e2 rodrigo_rivilla_2ºa
P10 e2 rodrigo_rivilla_2ºa
 
Neurocoaching de equipos de Alto Rendimiento 2017
Neurocoaching de equipos de Alto Rendimiento 2017Neurocoaching de equipos de Alto Rendimiento 2017
Neurocoaching de equipos de Alto Rendimiento 2017
 
Retention in complete denture/ dental crown & bridge courses
Retention in complete denture/ dental crown & bridge coursesRetention in complete denture/ dental crown & bridge courses
Retention in complete denture/ dental crown & bridge courses
 
Philosophies-in-full-mouth-rehabilitation-a-systematic-review
Philosophies-in-full-mouth-rehabilitation-a-systematic-reviewPhilosophies-in-full-mouth-rehabilitation-a-systematic-review
Philosophies-in-full-mouth-rehabilitation-a-systematic-review
 
Vocabulário relacionado com o meio envolvente
Vocabulário relacionado com o meio envolventeVocabulário relacionado com o meio envolvente
Vocabulário relacionado com o meio envolvente
 

Semelhante a Semi-Real Time Inclinometer readings using Wireless Technologies

IT Transformation Proposal
IT Transformation ProposalIT Transformation Proposal
IT Transformation Proposal
davingray
 

Semelhante a Semi-Real Time Inclinometer readings using Wireless Technologies (20)

Automatic Real Time Monitoring using Machine to Machine (M2M) Technology
Automatic Real Time Monitoring using Machine to Machine (M2M) TechnologyAutomatic Real Time Monitoring using Machine to Machine (M2M) Technology
Automatic Real Time Monitoring using Machine to Machine (M2M) Technology
 
Machine Intelligence in Manufacturing Industry - Igor Mihajlovic
Machine Intelligence in Manufacturing Industry - Igor MihajlovicMachine Intelligence in Manufacturing Industry - Igor Mihajlovic
Machine Intelligence in Manufacturing Industry - Igor Mihajlovic
 
NAMICON - SimpleOilfield - Efficiency of EMAT Ultrasonic Thickness Measuremen...
NAMICON - SimpleOilfield - Efficiency of EMAT Ultrasonic Thickness Measuremen...NAMICON - SimpleOilfield - Efficiency of EMAT Ultrasonic Thickness Measuremen...
NAMICON - SimpleOilfield - Efficiency of EMAT Ultrasonic Thickness Measuremen...
 
Geotechnical & Structural Automated Real Time Monitoring and Alert Systems
Geotechnical & Structural Automated Real Time Monitoring and Alert SystemsGeotechnical & Structural Automated Real Time Monitoring and Alert Systems
Geotechnical & Structural Automated Real Time Monitoring and Alert Systems
 
IT Transformation Proposal
IT Transformation ProposalIT Transformation Proposal
IT Transformation Proposal
 
Remote HVAC Service Value and benefits
Remote HVAC Service Value and benefitsRemote HVAC Service Value and benefits
Remote HVAC Service Value and benefits
 
Real Time Monitoring and Electro Magnetic Interference causing Data corruption
Real Time Monitoring and Electro Magnetic Interference causing Data corruptionReal Time Monitoring and Electro Magnetic Interference causing Data corruption
Real Time Monitoring and Electro Magnetic Interference causing Data corruption
 
Digital workflow.pdf
Digital workflow.pdfDigital workflow.pdf
Digital workflow.pdf
 
Group6 presentation
Group6 presentationGroup6 presentation
Group6 presentation
 
PlantConnect insights
PlantConnect insightsPlantConnect insights
PlantConnect insights
 
Iot based industrial boiler temperature control
Iot based industrial boiler temperature controlIot based industrial boiler temperature control
Iot based industrial boiler temperature control
 
3.42211- CIS Audit.pdf
3.42211- CIS Audit.pdf3.42211- CIS Audit.pdf
3.42211- CIS Audit.pdf
 
Plant Maintenance & Condition Monitoring
Plant Maintenance & Condition MonitoringPlant Maintenance & Condition Monitoring
Plant Maintenance & Condition Monitoring
 
Mobile Apps or Else
Mobile Apps or ElseMobile Apps or Else
Mobile Apps or Else
 
Ischia ATEX Inspection - Paperless Efficiency Company Brochure
Ischia ATEX Inspection - Paperless Efficiency Company BrochureIschia ATEX Inspection - Paperless Efficiency Company Brochure
Ischia ATEX Inspection - Paperless Efficiency Company Brochure
 
Automated Tunnel Monitoring System (ATMS)
Automated Tunnel Monitoring System (ATMS)Automated Tunnel Monitoring System (ATMS)
Automated Tunnel Monitoring System (ATMS)
 
How to reduce more than 10% cost of printing supplies in your operation
How to reduce more than 10% cost of printing supplies in your operationHow to reduce more than 10% cost of printing supplies in your operation
How to reduce more than 10% cost of printing supplies in your operation
 
weatherstationusingiotfyp-190505230304 (1).pdf
weatherstationusingiotfyp-190505230304 (1).pdfweatherstationusingiotfyp-190505230304 (1).pdf
weatherstationusingiotfyp-190505230304 (1).pdf
 
Envirotech live Presenation
Envirotech live PresenationEnvirotech live Presenation
Envirotech live Presenation
 
Dasbox
DasboxDasbox
Dasbox
 

Mais de RekaNext Capital

Mais de RekaNext Capital (20)

Root cause of Magnetic Humming due to Transformer
Root cause of Magnetic Humming due to TransformerRoot cause of Magnetic Humming due to Transformer
Root cause of Magnetic Humming due to Transformer
 
Design for Product Assembly#4
Design for Product Assembly#4Design for Product Assembly#4
Design for Product Assembly#4
 
Design for Product Assembly#3
Design for Product Assembly#3Design for Product Assembly#3
Design for Product Assembly#3
 
Design for Product Assembly#2
Design for Product Assembly#2Design for Product Assembly#2
Design for Product Assembly#2
 
Henderson Bridge Report.pdf
Henderson Bridge Report.pdfHenderson Bridge Report.pdf
Henderson Bridge Report.pdf
 
Assessment of the dynamic characteristics of the Helix Bridge at Marina Bay, ...
Assessment of the dynamic characteristics of the Helix Bridge at Marina Bay, ...Assessment of the dynamic characteristics of the Helix Bridge at Marina Bay, ...
Assessment of the dynamic characteristics of the Helix Bridge at Marina Bay, ...
 
MBFC Test Report Dec2008.doc
MBFC Test Report Dec2008.docMBFC Test Report Dec2008.doc
MBFC Test Report Dec2008.doc
 
Z Vibration Monitoring for pre-cast slab
Z Vibration Monitoring for pre-cast slab Z Vibration Monitoring for pre-cast slab
Z Vibration Monitoring for pre-cast slab
 
Pre-load results.ppt
Pre-load results.pptPre-load results.ppt
Pre-load results.ppt
 
IDA Mission Critical M2M of SysEng.pdf
IDA Mission Critical M2M of SysEng.pdfIDA Mission Critical M2M of SysEng.pdf
IDA Mission Critical M2M of SysEng.pdf
 
Dr Tan Guan Hong PhD Thesis 1980.pdf
Dr Tan Guan Hong PhD Thesis 1980.pdfDr Tan Guan Hong PhD Thesis 1980.pdf
Dr Tan Guan Hong PhD Thesis 1980.pdf
 
ZigBee Personnel Tracking System
ZigBee Personnel Tracking SystemZigBee Personnel Tracking System
ZigBee Personnel Tracking System
 
AV Latency Measurement
AV Latency MeasurementAV Latency Measurement
AV Latency Measurement
 
Computer Vision for Measurement & FR
Computer Vision for Measurement & FRComputer Vision for Measurement & FR
Computer Vision for Measurement & FR
 
Business Transformation V6
Business Transformation V6Business Transformation V6
Business Transformation V6
 
Business Transformation V5
Business Transformation V5Business Transformation V5
Business Transformation V5
 
Building and Construction Authority GeoSS Seminar 2010
Building and Construction Authority GeoSS Seminar 2010Building and Construction Authority GeoSS Seminar 2010
Building and Construction Authority GeoSS Seminar 2010
 
SysEng Water India 2011 conference presentation
SysEng Water India 2011 conference presentationSysEng Water India 2011 conference presentation
SysEng Water India 2011 conference presentation
 
SysEng Environmental Projects
SysEng Environmental ProjectsSysEng Environmental Projects
SysEng Environmental Projects
 
SysEng Computer Vison Systems
SysEng Computer Vison SystemsSysEng Computer Vison Systems
SysEng Computer Vison Systems
 

Último

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 

Último (20)

Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

Semi-Real Time Inclinometer readings using Wireless Technologies

  • 1. Semi-Real Time Inclinometer readings using Wire-less Technologies G.H. Tan, Y.K. Poh SysEng (S) Pte Ltd N. Osborne, C.C. Ng Land Transport Authority, Singapore
  • 2. Geotechnical Instruments are :- •Site Investigation Work •Design Verification •Performance •Safety •Construction Control •Quality Control •Legal Protection
  • 3. When safety is the highest priority, it must have a reliable and fast method to deliver on- site results to decision makers:- •Safety •Construction Control •Quality Control •Legal Protection
  • 5. Inclinometers are used for monitoring the soil movements over time Daily Automatic Data Processing of Inclinometer Readings
  • 7. Geokon Slope Indicator Encardio-rite RST Instruments (PDA) Inclinometers from various manufacturers Soil Instruments (PDA) There readout boxes require a PC to download their data
  • 8. Timing for measuring 10 bore holes in a site 10 mins In Main office, switch on PC to download, process, verify and email to Stake Holders Drive back for 60 mins Case Study: Total Throughput time for Bore Hole#1 data to reach end user is 60x10 + 10x9 + 60 + 30 mins = 780 mins (13 hrs) 30 mins for processing data 60 minsBore Hole#1 10 mins 60 minsBore Hole#2 10 mins 60 minsBore Hole#3 60 minsBore Hole#10
  • 9. Many challenges to ensure consistency as construction sites are far from ideal conditions with practical constraints of :- •Human Errors •Measurement bore holes with blockages •Worker inexperience •Inefficiencies due to manual work •Weather (Rain, Lightning and Heat)
  • 10. A new method to reduce the time taken from the measurement until it reaches the Stake Holder using Wire- less Technologies
  • 11. Simple steps for Data retrieval from sites using existing inclinometer, user’s mobile phone Short Range Device consists of a battery powered embedded computer with Wire-less Bluetooth module 3 m
  • 12. Central Server System Transferring data from Mobile Phone to Stake holder using Central Server GPRS Open Public Network Email with raw data & Inclinometer plot
  • 13. Worker walks to another bore hole Timing taken in the New Work Flow Process 2 mins Case Study: Total Throughput time for Bore Hole#1 data to reach end user is 60 + 2 + 8 mins = 70 mins 60 minsBore Hole#1 8 mins GPRS Transmission Automatic Processing and Emailing 10 mins
  • 14. Comparison of the time taken to obtain on site measurements Current Practice : 780 minutes Improve Method : 70 minutes Throughput improvements : = 780 / 70 = 11 ! +
  • 15. Advantages of the Semi-Real Time Inclinometer solution • PC-less system to retrieve the data • Preventing loss of PC on site • Maximum use of inclinometer system • Low Error possibility with less human intervention of data processing • Worker uses this own Mobile Phone with only additional GPRS charges • Consultant gets measured data immediately • Any measurement re-confirmation can be done immediately via a phone call rather than doing it the next day
  • 16. Site Workers Office staff gets information and discuss resultsMeasures and Transmit data + SDR
  • 17. The feedback comments from the users:- • When the readings showed unexpected movements, it provides opportunity to immediately phone the site staff to re-measure and verify that particular bore-hole.
  • 18. • When there are Critical Lateral Displacements to be monitored, this is the best approach to control the Site Work Activities to enhance the Safety as well as to allow Critical Activity to be carried out
  • 19. • Without this technology, the technician needs to monitor all the inclinometers of the project before he comes back to office at the end of the day to down load the raw data readings logged in the readout box to the PC. It will take a few hours for the readings of the inclinometer to reach the user after it is taken
  • 20. An added advantage for the data security to prevent unaware data alteration in the system to help Professional Engineers minimize their risks & liabilities
  • 21. Current Data Flow Practice Readout Box and Computer for down loading Monitoring Engineer Process Report with justifiable adjustment Mistakes ? Care-less ? Forget ? Authority Consultant
  • 22. Proposed Data Flow Security Central Server Monitoring Engineer Process Reports with justifiable adjustments Raw data kept intact using Parallel Information Flow for verification Processed Inclinometer Information Authority Consultant
  • 23. Benefits of the Proposed System • The measured data is automatically plotted and email simultaneously to all stake holders • This processed information will be over- ride, if the monitoring engineer has correction with justifications • Unique User ID tagged to Readout Box to avoid mixed up information from various Readout Boxes and Files • Date & Time when the readings are carried out are Logged at the Server, & NOT using the clock of the Readout Box, which could be altered at Box level