Sample deliverables
The architecture and high level design of the application has been
performed iteratively and in parallel through themed workshops. Using
an offshore delivery center, it is recommended to apply standard
architectural & design patterns. Delivery should be phased so each
delivery feeds with requirement updates the following delivery.
Green-field clearing platform implementation situation
Sample deliverables
Objectives of the project were to identify a migration approach for each
type of data through the implementation of a toolset to migrate and
reconcile information from legacy systems to the new Murex platform.
Each migration rehearsal corresponds to a cycle of validation by the
Risk Department and concludes in the dress rehearsal of the phase
(with one phase per legacy system).
Data migrations for FO/Risk system rollout situation
Functional
Specification
& Interface Contracts
Secure Web Application
Mutualized Architecture
Super User
Create batch
View batches
Modify batch
<<include>>
Integrated Reporting Tool
Data Migration Strategy
and Team Setup
Data Acceptance
Reporting
Stream Dashboard,
Project Plan, Milestones,
KPI and Risk Log
ID Task Name Start Finish
1 Milestone View Tue 02/10/12Tue 08/10/13
2 Requirements Mon 08/10/12Thu 20/12/12
3 Murex scoping Tue 06/11/12Tue 06/11/12
4
5 Interfaces Mon 08/10/12Mon 10/12/12
6 REQ Interfaces requirements Mon 08/10/12Mon 10/12/12
14
15 Reporting Thu 15/11/12Fri 07/12/12
16 REQ Reporting requirements Thu 15/11/12Fri 07/12/12
30
31 Migration Fri 16/11/12 Thu 20/12/12
35
36 Design Tue 02/10/12Fri 01/03/13
37 Murex Tue 02/10/12Mon 25/02/13
38 DES Murex design Tue 02/10/12Mon 25/02/13
45
46 Interfaces Mon 12/11/12Fri 01/03/13
47 DES INT Drop 0 "Referentials" Mon 12/11/12Wed 19/12/12
50 DES Drop 1.1 design Wed 28/11/12Wed 28/11/12
51 DES Drop 1.2 design Fri 21/12/12 Fri 21/12/12
52 DES Drop 1.3 design Mon 07/01/13Mon 07/01/13
53 DES Drop 1.4 design Tue 01/01/13Tue 01/01/13
54 DES Drop 1.5 design Fri 01/03/13 Fri 01/03/13
55
56 Reporting Wed 31/10/12Mon 07/01/13
57 DES Datamart (design, development, setup) Wed 31/10/12Mon 07/01/13
73
74 Build Mon 29/10/12Wed 22/05/13
75 Murex Mon 29/10/12Fri 15/03/13
76 MX Drop 0 "out of the box, installed" Mon 29/10/12Mon 29/10/12
77 MX Drop 1 "pre-configured, installed" Thu 17/01/13Thu 17/01/13
78 MX Drop 2 "end-user customizations" Fri 15/03/13 Fri 15/03/13
79 Interfaces Mon 21/01/13Wed 22/05/13
80 BLD INT Drop 0 "Referentials" Mon 21/01/13Fri 08/02/13
83 BLD Drop 1.1 & 1.2 build "Intraday" Fri 15/03/13 Thu 21/03/13
86 BLD Drop 1.3 & 1.4 build "End of day" Fri 29/03/13 Thu 11/04/13
89 BLD Drop 1.5 build Wed 22/05/13Wed 22/05/13
90 Reporting Thu 21/03/13Fri 12/04/13
91 BLD Reporting "Intraday" Thu 21/03/13Thu 21/03/13
92 BLD Reporting "End of day" Fri 12/04/13 Fri 12/04/13
93 Migration tools Thu 20/12/12Fri 03/05/13
94 BLD Migration tools Thu 20/12/12Fri 03/05/13
98
99 Migration Wed 09/01/13Fri 14/06/13
100 MIG Static Data migrated for MX perf test Wed 09/01/13Wed 09/01/13
101 MIG Complete migrated data - Corp. & CDS Mon 25/03/13Mon 25/03/13
102 MIG Complete migrated data - Corp. & CDS - User validated Fri 05/04/13 Fri 05/04/13
103 MIG Complete migrated data - Govies & Repos Wed 22/05/13Wed 22/05/13
104 MIG Complete migrated data - Govies & Repos - User validated Fri 14/06/13 Fri 14/06/13
105
106 Tests Mon 21/01/13Fri 09/08/13
107 System integration tests Mon 21/01/13Fri 14/06/13
108 SIT Cycle A "Set-up and construct smoke test" Mon 21/01/13Fri 15/02/13
109 SIT Cycle B "Static data" Mon 18/02/13Fri 15/03/13
110 Corp. & CDS - SIT Cycle 1 "Intraday" Thu 21/03/13Wed 03/04/13
111 Corp. & CDS - SIT Cycle 2 " End of day" Thu 11/04/13Wed 24/04/13
112 Corp. & CDS - SIT Cycle 3 "Fix non-regression" Mon 20/05/13Fri 31/05/13
113
114 Govies & Repos - SIT Cycle Mon 03/06/13Fri 14/06/13
115
116 SIT Performance 1 Fri 08/02/13 Thu 21/02/13
117 SIT Performance 2 Mon 20/05/13Fri 31/05/13
118
119 User acceptance tests Mon 25/03/13Fri 09/08/13
120 Corp. & CDS - Data user validation Mon 25/03/13Fri 05/04/13
121 Corp. & CDS - UAT Cycle 1.a "Intraday" Mon 08/04/13Fri 26/04/13
122 Corp. & CDS - UAT Cycle 1.b "End of day" Thu 25/04/13Wed 08/05/13
123 Corp. & CDS - Fix after UAT Cycle 1 "Intraday and End of day" Tue 09/04/13Fri 17/05/13
124 Corp. & CDS - UAT Cycle 2 "End-to-end" Mon 03/06/13Fri 14/06/13
125 Corp. & CDS - Fix after UAT Cycle 2 "End-to-end" Tue 04/06/13Fri 21/06/13
126 Corp. & CDS - UAT Cycle 3 "Final run" Mon 24/06/13Fri 28/06/13
127
128 Govies & Repos - Data user validation Mon 03/06/13Fri 14/06/13
129 Govies & Repos - UAT Cycles 1 and 2 and fix after UAT Mon 17/06/13Fri 09/08/13
130
131 Go live Sat 13/07/13Tue 08/10/13
132 Corp. & CDS - Go live 1 Sat 13/07/13 Sun 14/07/13
133 Corp. & CDS - Go live 2 Sat 24/08/13 Sun 25/08/13
134 Govies & Repos - Go live 3 Sat 14/09/13 Sun 15/09/13
135 Govies & Repos - Go live 4 Mon 07/10/13Tue 08/10/13
Requirements 20/12
Murex scoping 06/11
REQ Interfaces requirements 10/12
REQ Reporting requirements 07/12
Design 01/03
DES Murex design 25/02
DES INT Drop 0 "Referentials" 19/12
DES Drop 1.1 design 28/11
DES Drop 1.2 design 21/12
DES Drop 1.3 design 07/01
DES Drop 1.4 design 01/01
DES Drop 1.5 design 01/03
DES Datamart (design, development, setup) 07/01
Build 22/05
MX Drop 0 "out of the box, installed" 29/10
MX Drop 1 "pre-configured, installed" 17/01
MX Drop 2 "end-user customizations" 15/03
BLD INT Drop 0 "Referentials" 08/02
BLD Drop 1.1 & 1.2 build "Intraday" 21/03
BLD Drop 1.3 & 1.4 build "End of day" 11/04
BLD Drop 1.5 build 22/05
BLD Reporting "Intraday" 21/03
BLD Reporting "End of day" 12/04
BLD Migration tools 03/05
Migration 14/06
MIG Static Data migrated for MX perf test 09/01
MIG Complete migrated data - Corp. & CDS 25/03
MIG Complete migrated data - Corp. & CDS - User validated 05/04
MIG Complete migrated data - Govies & Repos 22/05
MIG Complete migrated data - Govies & Repos - User validated 14/06
Tests 09/08
SIT Cycle A "Set-up and construct smoke test" 15/02
SIT Cycle B "Static data" 15/03
Corp. & CDS - SIT Cycle 1 "Intraday" 03/04
Corp. & CDS - SIT Cycle 2 " End of day" 24/04
Corp. & CDS - SIT Cycle 3 "Fix non-regression" 31/05
Govies & Repos - SIT Cycle 14/06
SIT Performance 1 21/02
SIT Performance 2 31/05
Corp. & CDS - Data user validation 05/04
Corp. & CDS - UAT Cycle 1.a "Intraday" 26/04
Corp. & CDS - UAT Cycle 1.b "End of day" 08/05
Corp. & CDS - Fix after UAT Cycle 1 "Intraday and End of day" 17/05
Corp. & CDS - UAT Cycle 2 "End-to-end" 14/06
Corp. & CDS - Fix after UAT Cycle 2 "End-to-end" 21/06
Corp. & CDS - UAT Cycle 3 "Final run" 28/06
Govies & Repos - Data user validation 14/06
Govies & Repos - UAT Cycles 1 and 2 and fix after UAT 09/08
Go live
Corp. & CDS - Go live 1 14/07
Corp. & CDS - Go live 2 25/08
Govies & Repos - Go live 3 15/09
Govies & Repos - Go live 4 08/10
Drop0 Referentials
Drop1.0 StressTest GDM
Drop1.1 Credit Pricer (RT)
Credit Pricer (Outbound)
Calypso (RT)
E-Murex(Tradeinbound RT)
Drop1.2 MurexGCM(RT)
GMI (RT)
Phase 3 (RT)
ISTAR(RT)
TRACE(Murexstandard)
TZERO/ICELINK(Murexstandard)
ION
Drop1.3 CCC
Omega
IPREO/eBook(Trade inboundRT)
BLOFI / MOCA
Card- Phase 3
Drop1.4 LORA&IMATCHFOFO/ FOBO(trade EOD)
QlikView
Glory(trade EOD)
ISMA-TRAX
GVRisk(trade EOD)
Pirat (Outbound)
Safir (Outbound)
PoleIRC
S-STR-Drp 1.5
Drop1.5 SUMMITBO(RT)
E-bonds
REPObulk&VCONimport
LIQUID
FRA/ IRSmirroring
BBSupertrade
02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20
09/12 10/12 11/12 12/12 01/13 02/13 03/13 04/13 05/13 06/13 07/13 08/13 09/13 10/13
STP Business
Scenario
Design
Planning of editor’s
intervention
As part of IT rationalization, some users were facing a new situation for
their migration to new systems. Decision was made to provide a
consistent view of equity, fixed income and securities lending positions
in a single place. Murex was the best option to support this aim through
an “horizontal” integration with peer systems to impact new trades and
trade events.
Consolidation of positions in Murex situation
File Processing
Business
Scenario
Design
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
WM WM WM WM WM WM
Deployment Deployment Deployment Deployment Deployment Deployment
WM WM WM WM WM WM
Run Run Run Run Run Run
TIBCO TIBCO TIBCO TIBCO TIBCO TIBCO
Deployment Deployment Deployment Deployment Deployment Deployment
TIBCO TIBCO TIBCO TIBCO TIBCO TIBCO
Run Run Run Run Run Run
Result Wrap-up Result Wrap-up Result Wrap-up
App
RV API
App
RV API
App
RV API
App
RV API
App
RV API
TCP/IP Network
Host 1 Host 3 Host 4Host 2
TCP/IP
UDP Broadcast TCP/IPUDP Multicast UDP Unicast
RVD RVD RVD
Technical design and setup
of dedicated injectors,
routers, environments
and servers
As part of simplification projects, when Murex becomes a critical
platform, it becomes necessary to create an automated testing factory
upfront to accompany the transformation project and then the
maintenance phase.
This typically encompass user interface tests, functional tests, negative
tests, regression tests, configuration tests and compatibility tests.
Murex automated testing factory situation
EUREX CORE SERVICES
TRADE MANAGEMENT
CLEARING SUPERVISIONTRADING LOCATIONS
PARTICIPANT SERVICES
EUREX MEMBER INTERFACES
EUREX
NYSE Liffe BRUSSELS
NYSE Liffe LISBON
COLLATERAL ENGINE
RISK ENGINE /
EDRE / PRISMA
ENHANCED RISK
SOLUTION
FixML Clearing API
COMMON
REPORTING ENGINE
VALUES API
MARKET
CONTROL
MARKET
MONITOR
STATISTICS
CONSOLIDATION
PRODUCT DATA
MAINTENANCE
MEMBER DATA
MAINTENANCE
CASHMANAGEMENTCOMMUNICATION
MEMBERCOMMUNICATION
NYSE Liffe AMSTERDAM
NYSE Liffe PARIS
EUREX
EEX
SUPPORT
SERVICES
@X - GUI
CARMEN
CASH
MANAGEMENT
TRADINGLOCATION
COMMUNICATION
PROPRIETARY
FixML
MISS/VALUES
DWH
PRICES
POSITION MANAGEMENT
POSITION ACCOUNT TRANSFER
TRANSFER btw MEMBERS
CORPORATE ACTION
POSITION CLOSE-OUT
LIFFE GUARDIAN
DELIVERY POSITION MAINTENANCE
DELIVERY PROCESSING MANAGEMENT
CCP
DvP SETTLEMENT MANAGEMENT
COMMODITY DELIVERY POSITION
LEGACY INTERFACES
SAP
GERMAN LEGAL
REPORTING
StatistiX
POSITION POSTING
GIVE-UP / TAKE-UP
TRADE ADJUSTMENT
LEGEND
CONFIGURATION
FUNCTIONAL
CHANGE
NEW LOCATION
service
group
function
OUT OF
SUBSTREAM SCOPE
TRADING
TRADE CAPTURE
TRADE CANCELLATION
CCP COMMUNICATION COMMODITY DELIVERY COMMUNICATION
EXPIRY / DELIVERY
NOTIFICATION /
ALLOCATION
COMMODITIES
PHYSICAL DELIVERY
EXPIRY
EXERCISE /
ASSIGNMENT
RISK MANAGEMENT
SETTLEMENT PRICES
UPDATE
UNDERLYING PRICES
UPDATE
RISK POSITION
DETERMINATION
COLLATERAL MANAGEMENT
COLLATERAL ACCOUNT
EVALUATION
MARGIN CALL
CALCULATION
COLLATERAL ACCOUNTS
UPDATE
VARIATION MARGIN
CALCULATION
MARGIN REQUIRE-
MENTS CALCULATION
Functional impacts
on clearing services
Technical impacts
on interfaces
Impacts on lifecycle
and on client profiles
Sample deliverablesSample deliverables
While driving IT transformation projects to ensure renewed capacity to
address business expansion, talent pool for system maintenance may
require to be optimized through different paradigms:
. Team extensions
. Service Centers
. Managed Services
Outsourced team management situation
Costs of IT and Operations was 20% of the cost base in 2005 and has
reached 30% in 2013 for investment banks. It is possible to enhance
and mutualize existing services to generate additional savings by
partnering more strongly with service providers. Aim is to keep such
costs in-line with competition mostly for Tier-2 banks needing to expand
their “flow” business.
Capital Markets Post-trade Utility situations
Sample deliverablesSample deliverables
Weekly
Progress
Report
Activities
Priority and Forecast
Delivery
Lifecycle
Change
Documents
Mutualization of
opportunities by area
Infrastructure
Deployment
Softw. Package
Deployment
Operational
Deployment
Governance
Deployment
Infrastructure
Deployment
Softw. Package
Deployment
Operational
Deployment
Governance
Deployment
Infrastructure
Deployment
Softw. Package
Deployment
Operational
Deployment
Governance
Deployment
Infrastructure
Deployment
Softw. Package
Deployment
Operational
Deployment
Governance
Deployment
LEVEL 0
Client-specific
LEVEL 3
FIS Post-trade Utility
LEVEL 2
Standardized Service
LEVEL 1
Mutualized Service
Financial
benefits
Maturity Level
Savings through productivity
improvements of shared
resources
Savings through use of
standard processes
Economies of scale
Execute
Single client
Bank A
Service O
Bank C
Service M
Commoditize
Bank B
Service O
Bank C
Service O
Bank B
Service O
Bank B
Service M
Bank A
Service M
Bank D
Service M
Break silos
between clients
- Standardize
Bank D
Service N
Mutualize
multiple
clients
Bank E
Service M
Bank A
Service N
Progressive
deployment and
benefits
Transformation
project cards
(to enable savings)Project Cost
COST: Effort estimates (total) 540 md incl. 400 md IMAGO
COST: Hardware estimates (new units) 200 k€ (21 servers)
COST: License and maintenance fees 100 k€ / Year for Xpress NG maintenance
SAVINGS: Maintenance FTE 0
SAVINGS: Hardware 0
SAVINGS: License and maintenance fees 0
Misc.
+ 0.5 FTE dedicated to Test factory maintenance
+ 1.5 FTE dedicated to Xpress NG maintenance
Some FTE to be allocated by CACIB to EFIRA maintenance
man-days
Team Role 2014 Q4 2015 Q1 2015 Q2 2015 Q3 2015 Q4 2016 Q1 2016 Q2 2016 Q3 2016 Q4 2017 Q1 2017 Q2 2017 Q3 2017 Q4 Total
FIS_OnS PMO 21 38 2 0 0 0 0 0 0 0 0 0 0 50
FIS_OffS Architect 5 45 3 0 0 0 0 0 0 0 0 0 0 53
FIS_OnS BA 25 22 0 0 0 0 0 0 0 0 0 0 0 48
FIS_OffS Dev 42 112 6 0 0 0 0 0 0 0 0 0 0 160
FIS_OffS Test_Factory 21 56 3 0 0 0 0 0 0 0 0 0 0 80
CACIB ITS 26 70 4 0 0 0 0 0 0 0 0 0 0 100
CACIB BA 5 2 0 0 0 0 0 0 0 0 0 0 0 18
CACIB CibML_exp 11 21 1 0 0 0 0 0 0 0 0 0 0 32
CACIB Split Dev 0 0 0 0 0 0 0 0 0 0 0 0 0 0
CACIB Split Test 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total by quarter 156 366 18 0 0 0 0 0 0 0 0 0 0 540
Xpress NG Core
(EFIRA NG)
Standard
Financial
Data ModelFpML
Engine / Router
Entry Point
to FIS Services
Utility data
FIS Services
Portfolio
FIS Data
Dictionary
Services
Directory
Standard Service 3
Standard Service 1
Standard Service 2
Standard Service ..
Standard
Monitor
EFIRA
Monitor
Xpress NG
Adapters
FpML
CibML
BankY
XML
CACIB data
Bank Y data
Application A
Application YC
CACIB
format
Bank Y
format
Application YF
Application YD
Application K
Application G
Application B
To finalize a product selection process, a benchmarking of short-listed
solutions allows to guarantee compliance, resilience and support quality
from the software vendors. It also allows to demonstrate performances
without necessarily establishing a guarantee on performances.
Product benchmarking situation
As part of a merger, the systems and operational processes to be
retained are first selected. However, once this is done clients being
transferred from previous services to the new ones must be managed. It
is necessary to perform a review of changes that will be necessary from
clients, changes necessary from operations and changes necessary
from IT. All this needs finally to be validated at a regulatory and legal
level.
Post-merger impact study situation
Sample deliverablesSample deliverables
Test Results and Screenshots
Reporting (HP Quality Center)
Automated Testing Tool
enhancements and setup
Test Definition
Enrichment
MurexDealInput
FeedintoMurexfromLeadingSystem
Bloomberg(Interface)
StockLendSystem(Interface)
ULLink(Interface)
Xetra(TradeEntry)
EurexorLIFFE(TradeEntry)
TradeFeedBroker(Interface)
DWP-WP2(InterfaceorPrinter)
SEBIS(Printer)
Kondor+(Interface)
Pricing(AHSforEOD)
Pricing(ReutersforRT)
TradeEntryinMurex
TradeValidation/TradeWorkflow
Query
SecuritiesInventory
Liquidity
Blotter
IntradayReporting-Risk
IntradayReporting-P&L
Confirmation/Tickets
MPCC
MLC
LogicalPackageIDAssignment
Fixing
Exercise
Expiry/Termination(EOD)
Modify
ForwardRestructure
AccountClosing
RateAmendment
SeclendingAgreement
Cancel
Cancel&Reissue
Products
Sec Fin Stock Loan Borrow Bond X T X X X T T X X X T T T T T
Stock Loan Borrow Equity X T X X X T T X X X T T T T T
Repo Bond X T X T X T X X X X T T
Repo Equity X T T T T T T T T T T T T T T T T T T X T X T T X T T
BSB Bond X T X T X T X X X X X
BSB Equity X T T T T T T T T T T T T T T T T T T X T X X X T T
EQD ET Cash Equities Equity X T T T T T T T T T T T T T X
OTC Cash Equities Equity X T T T T T T T T T T T T T X T T
OTC Equity Swaps Equity X X X T X X X T T T T T X X X X X
Ex Tr Eq Future Equity X T T X T T T T X X T T
Ex Tr Eq Options Equity X T T X T T T X T X X X T X
OTC Eq Futures (LIFFE) Equity X X X T T T T T T X X X X X X X
IR Futures Rate X T T X X T T X X X X
IRD Cash Bond Bond X T X X X T X X X X
Ex Tr Bond Futures Bond X T X X X T X X X X X
Ex Tr Bond Future Options Future X T X X X X T X X X X X X
OTC Bond Futures Bond X T X X X T X X X X X
Cash Loan Borrow Cash X T T T T T X X T T T
X: This Functionality/ Process/ Activity
applies to the listed product
T: This Functionality/ Process/ Activity
applies to the listed product and is in
scope for UAT
Other Systems and
Trade Transmission
Mx EventsMx Deal Lifecycle
F ield name Screen
name
F ield
reference
n°
Enumerate
d
F ield name
target
structure
F ield
descriptio n
target
structure
Sample
value in
target field
F o rmat o f
target field
1 /MxML version="1-1"/events/mainEvent/action action insertion
2 /MxML version="1-1"/events/mainEvent/object href="#new_contract"/objectNatureobjectNature contract
3 /MxML version="1-1"/events/mainEvent/inputBy/userName userName Username used to book the tradeOPEREQ
4 /MxML version="1-1"/events/mainEvent/inputBy/group group The group under which the trade will be bookedMX
5 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractBusinessObjectTemplate/businessObjectId/identifieridentifier 397
6 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractBusinessObjectTemplate/businessObjectId/displayLabeldisplayLabelThe name that Murex will display to identify the productIRD Lending Borrowing
7 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractHeadercontractHeader
8 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractComponents/contractComponent/tradeReference href="#trade_23612tradeReference href="????"#trade_23612
9 /MxML version="1-1"/trades/trade id="trade_23612" mefClass="mxContractITRADE" mefClassInstanceType="57.000000"/parties/party id="MUREX"/partyNamepartyName MUREX
19 /MxML version="1-1"/trades/trade id="trade_23612" mefClass="mxContractITRADE" mefClassInstanceType="57.000000"/tradeBody/bondLb/templateID/templateLabeltemplateLabel SFMA01
21 /MxML version="1-1"/trades/trade id="trade_23612" mefClass="mxContractITRADE" mefClassInstanceType="57.000000"/tradeBody/bondLb/structure/numberOfLegsnumberOfLegsWe will use two legs: one represents the financial definition of the Equity, while the other one represents the informatio2
Stock Lend Murex
F ield path target structure
2
3
6
12
13
14
19
Leg 1
29
30
79
84
85
87
64
67
58
Leg 2
Markets Exchanges EUREX REPO OTCXETRA EUREX LIFFE
Stock Lend
DWP
Printer
Feed
Report
SEBIS
Printer
Reuters
MDS
Trade
capture
Data
Mart
Bloomberg
Manual
MxML
EXCHANGE
Bloomberg
TOMS
TFB
TFB
UL BridgeEurex & OTC Bond Future
Eurex Bond Future Options
OTC & Eurex Bond Repo
Buy Sell Back
Bond Positions
Eurex Equity Future
Eurex Equity Index Future
Eurex Equity Option
Interest Rate Futures
Exchange Cash Equity
Sec Lend Bond & Equity
Equity Forwards
OTC & Exchange Cash Equity
Equity BSB
Equity Repos
Integration architecture
decision point
Specification of interfaces
(attributes and event map)
Integration and acceptance test reports

Mais conteúdo relacionado

Semelhante a Project Portfolio Francois Bourcier

Mud2010 bettenburg presentation
Mud2010 bettenburg presentationMud2010 bettenburg presentation
Mud2010 bettenburg presentation
SAIL_QU
 
Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...
Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...
Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...
RootedCON
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
Captainsamcox
 
Argonne Win7 Closeout
Argonne Win7 CloseoutArgonne Win7 Closeout
Argonne Win7 Closeout
Chad Karkos
 
Hailey_Database_Performance_Made_Easy_through_Graphics.pdf
Hailey_Database_Performance_Made_Easy_through_Graphics.pdfHailey_Database_Performance_Made_Easy_through_Graphics.pdf
Hailey_Database_Performance_Made_Easy_through_Graphics.pdf
cookie1969
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
yashchotaliyael21
 
2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt
AsBali1
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
Mohammed Feroze
 

Semelhante a Project Portfolio Francois Bourcier (20)

Mud2010 bettenburg presentation
Mud2010 bettenburg presentationMud2010 bettenburg presentation
Mud2010 bettenburg presentation
 
ICEflo Implementation Management Solution V1d1
ICEflo Implementation Management Solution V1d1ICEflo Implementation Management Solution V1d1
ICEflo Implementation Management Solution V1d1
 
Keith odom sample microsoft project template data center move
Keith odom sample microsoft project template data center moveKeith odom sample microsoft project template data center move
Keith odom sample microsoft project template data center move
 
Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...
Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...
Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...
 
Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...
Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...
Beyond Horizon: Open Source Management On the Go for OpenStack and the Rest o...
 
Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...
Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...
Juan Vazquez & Julián Vilas – Tú a Barcelona y yo a Tejas, a patadas con mi S...
 
MODES Route - 27may98
MODES Route - 27may98MODES Route - 27may98
MODES Route - 27may98
 
Archive Documents
Archive DocumentsArchive Documents
Archive Documents
 
Agile project management in heavy engineering design (John Underhill, Babcock)
Agile project management in heavy engineering design (John Underhill, Babcock)Agile project management in heavy engineering design (John Underhill, Babcock)
Agile project management in heavy engineering design (John Underhill, Babcock)
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
 
Argonne Win7 Closeout
Argonne Win7 CloseoutArgonne Win7 Closeout
Argonne Win7 Closeout
 
Hailey_Database_Performance_Made_Easy_through_Graphics.pdf
Hailey_Database_Performance_Made_Easy_through_Graphics.pdfHailey_Database_Performance_Made_Easy_through_Graphics.pdf
Hailey_Database_Performance_Made_Easy_through_Graphics.pdf
 
Presentation 12c grid_upgrade
Presentation 12c grid_upgradePresentation 12c grid_upgrade
Presentation 12c grid_upgrade
 
Highway to heaven - Voxxed Days Belgrade
Highway to heaven - Voxxed Days BelgradeHighway to heaven - Voxxed Days Belgrade
Highway to heaven - Voxxed Days Belgrade
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
Automated LiDAR Data Quality Control
Automated LiDAR Data Quality ControlAutomated LiDAR Data Quality Control
Automated LiDAR Data Quality Control
 
2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt2002, Advanced Schedule RiskPresentation Lisbon.ppt
2002, Advanced Schedule RiskPresentation Lisbon.ppt
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
 
Meet Magento Spain 2019 - Our Experience with Magento Cloud
Meet Magento Spain 2019 - Our Experience with Magento CloudMeet Magento Spain 2019 - Our Experience with Magento Cloud
Meet Magento Spain 2019 - Our Experience with Magento Cloud
 
Transport SDN & OpenDaylight Use Cases in Korea
Transport SDN & OpenDaylight Use Cases in KoreaTransport SDN & OpenDaylight Use Cases in Korea
Transport SDN & OpenDaylight Use Cases in Korea
 

Último

Call Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night StandCall Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
amitlee9823
 
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
amitlee9823
 
Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........
deejay178
 
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
ZurliaSoop
 
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
amitlee9823
 
➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men 🔝Satara🔝 Escorts S...
➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men  🔝Satara🔝   Escorts S...➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men  🔝Satara🔝   Escorts S...
➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men 🔝Satara🔝 Escorts S...
amitlee9823
 
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdfreStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
Ken Fuller
 
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
poojakaurpk09
 
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night StandCall Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 

Último (20)

Call Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night StandCall Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Sarjapur Road ☎ 7737669865 🥵 Book Your One night Stand
 
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
 
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jayanagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
 
Résumé (2 pager - 12 ft standard syntax)
Résumé (2 pager -  12 ft standard syntax)Résumé (2 pager -  12 ft standard syntax)
Résumé (2 pager - 12 ft standard syntax)
 
Booking open Available Pune Call Girls Ambegaon Khurd 6297143586 Call Hot In...
Booking open Available Pune Call Girls Ambegaon Khurd  6297143586 Call Hot In...Booking open Available Pune Call Girls Ambegaon Khurd  6297143586 Call Hot In...
Booking open Available Pune Call Girls Ambegaon Khurd 6297143586 Call Hot In...
 
Presentation for the country presentation
Presentation for the country presentationPresentation for the country presentation
Presentation for the country presentation
 
Personal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando NegronPersonal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando Negron
 
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
 
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfMiletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
 
Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Sa...
 
Rearing technique of lac insect and their management
Rearing technique of lac insect and their managementRearing technique of lac insect and their management
Rearing technique of lac insect and their management
 
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
 
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men  🔝bhavnagar🔝   Esc...
➥🔝 7737669865 🔝▻ bhavnagar Call-girls in Women Seeking Men 🔝bhavnagar🔝 Esc...
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.
 
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Janakpuri ☎ 9711199171 Book Your One night Stand
 
➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men 🔝Satara🔝 Escorts S...
➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men  🔝Satara🔝   Escorts S...➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men  🔝Satara🔝   Escorts S...
➥🔝 7737669865 🔝▻ Satara Call-girls in Women Seeking Men 🔝Satara🔝 Escorts S...
 
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdfreStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
 
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
 
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night StandCall Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
 

Project Portfolio Francois Bourcier

  • 2. Sample deliverables The architecture and high level design of the application has been performed iteratively and in parallel through themed workshops. Using an offshore delivery center, it is recommended to apply standard architectural & design patterns. Delivery should be phased so each delivery feeds with requirement updates the following delivery. Green-field clearing platform implementation situation Sample deliverables Objectives of the project were to identify a migration approach for each type of data through the implementation of a toolset to migrate and reconcile information from legacy systems to the new Murex platform. Each migration rehearsal corresponds to a cycle of validation by the Risk Department and concludes in the dress rehearsal of the phase (with one phase per legacy system). Data migrations for FO/Risk system rollout situation Functional Specification & Interface Contracts Secure Web Application Mutualized Architecture Super User Create batch View batches Modify batch <<include>> Integrated Reporting Tool Data Migration Strategy and Team Setup Data Acceptance Reporting Stream Dashboard, Project Plan, Milestones, KPI and Risk Log ID Task Name Start Finish 1 Milestone View Tue 02/10/12Tue 08/10/13 2 Requirements Mon 08/10/12Thu 20/12/12 3 Murex scoping Tue 06/11/12Tue 06/11/12 4 5 Interfaces Mon 08/10/12Mon 10/12/12 6 REQ Interfaces requirements Mon 08/10/12Mon 10/12/12 14 15 Reporting Thu 15/11/12Fri 07/12/12 16 REQ Reporting requirements Thu 15/11/12Fri 07/12/12 30 31 Migration Fri 16/11/12 Thu 20/12/12 35 36 Design Tue 02/10/12Fri 01/03/13 37 Murex Tue 02/10/12Mon 25/02/13 38 DES Murex design Tue 02/10/12Mon 25/02/13 45 46 Interfaces Mon 12/11/12Fri 01/03/13 47 DES INT Drop 0 "Referentials" Mon 12/11/12Wed 19/12/12 50 DES Drop 1.1 design Wed 28/11/12Wed 28/11/12 51 DES Drop 1.2 design Fri 21/12/12 Fri 21/12/12 52 DES Drop 1.3 design Mon 07/01/13Mon 07/01/13 53 DES Drop 1.4 design Tue 01/01/13Tue 01/01/13 54 DES Drop 1.5 design Fri 01/03/13 Fri 01/03/13 55 56 Reporting Wed 31/10/12Mon 07/01/13 57 DES Datamart (design, development, setup) Wed 31/10/12Mon 07/01/13 73 74 Build Mon 29/10/12Wed 22/05/13 75 Murex Mon 29/10/12Fri 15/03/13 76 MX Drop 0 "out of the box, installed" Mon 29/10/12Mon 29/10/12 77 MX Drop 1 "pre-configured, installed" Thu 17/01/13Thu 17/01/13 78 MX Drop 2 "end-user customizations" Fri 15/03/13 Fri 15/03/13 79 Interfaces Mon 21/01/13Wed 22/05/13 80 BLD INT Drop 0 "Referentials" Mon 21/01/13Fri 08/02/13 83 BLD Drop 1.1 & 1.2 build "Intraday" Fri 15/03/13 Thu 21/03/13 86 BLD Drop 1.3 & 1.4 build "End of day" Fri 29/03/13 Thu 11/04/13 89 BLD Drop 1.5 build Wed 22/05/13Wed 22/05/13 90 Reporting Thu 21/03/13Fri 12/04/13 91 BLD Reporting "Intraday" Thu 21/03/13Thu 21/03/13 92 BLD Reporting "End of day" Fri 12/04/13 Fri 12/04/13 93 Migration tools Thu 20/12/12Fri 03/05/13 94 BLD Migration tools Thu 20/12/12Fri 03/05/13 98 99 Migration Wed 09/01/13Fri 14/06/13 100 MIG Static Data migrated for MX perf test Wed 09/01/13Wed 09/01/13 101 MIG Complete migrated data - Corp. & CDS Mon 25/03/13Mon 25/03/13 102 MIG Complete migrated data - Corp. & CDS - User validated Fri 05/04/13 Fri 05/04/13 103 MIG Complete migrated data - Govies & Repos Wed 22/05/13Wed 22/05/13 104 MIG Complete migrated data - Govies & Repos - User validated Fri 14/06/13 Fri 14/06/13 105 106 Tests Mon 21/01/13Fri 09/08/13 107 System integration tests Mon 21/01/13Fri 14/06/13 108 SIT Cycle A "Set-up and construct smoke test" Mon 21/01/13Fri 15/02/13 109 SIT Cycle B "Static data" Mon 18/02/13Fri 15/03/13 110 Corp. & CDS - SIT Cycle 1 "Intraday" Thu 21/03/13Wed 03/04/13 111 Corp. & CDS - SIT Cycle 2 " End of day" Thu 11/04/13Wed 24/04/13 112 Corp. & CDS - SIT Cycle 3 "Fix non-regression" Mon 20/05/13Fri 31/05/13 113 114 Govies & Repos - SIT Cycle Mon 03/06/13Fri 14/06/13 115 116 SIT Performance 1 Fri 08/02/13 Thu 21/02/13 117 SIT Performance 2 Mon 20/05/13Fri 31/05/13 118 119 User acceptance tests Mon 25/03/13Fri 09/08/13 120 Corp. & CDS - Data user validation Mon 25/03/13Fri 05/04/13 121 Corp. & CDS - UAT Cycle 1.a "Intraday" Mon 08/04/13Fri 26/04/13 122 Corp. & CDS - UAT Cycle 1.b "End of day" Thu 25/04/13Wed 08/05/13 123 Corp. & CDS - Fix after UAT Cycle 1 "Intraday and End of day" Tue 09/04/13Fri 17/05/13 124 Corp. & CDS - UAT Cycle 2 "End-to-end" Mon 03/06/13Fri 14/06/13 125 Corp. & CDS - Fix after UAT Cycle 2 "End-to-end" Tue 04/06/13Fri 21/06/13 126 Corp. & CDS - UAT Cycle 3 "Final run" Mon 24/06/13Fri 28/06/13 127 128 Govies & Repos - Data user validation Mon 03/06/13Fri 14/06/13 129 Govies & Repos - UAT Cycles 1 and 2 and fix after UAT Mon 17/06/13Fri 09/08/13 130 131 Go live Sat 13/07/13Tue 08/10/13 132 Corp. & CDS - Go live 1 Sat 13/07/13 Sun 14/07/13 133 Corp. & CDS - Go live 2 Sat 24/08/13 Sun 25/08/13 134 Govies & Repos - Go live 3 Sat 14/09/13 Sun 15/09/13 135 Govies & Repos - Go live 4 Mon 07/10/13Tue 08/10/13 Requirements 20/12 Murex scoping 06/11 REQ Interfaces requirements 10/12 REQ Reporting requirements 07/12 Design 01/03 DES Murex design 25/02 DES INT Drop 0 "Referentials" 19/12 DES Drop 1.1 design 28/11 DES Drop 1.2 design 21/12 DES Drop 1.3 design 07/01 DES Drop 1.4 design 01/01 DES Drop 1.5 design 01/03 DES Datamart (design, development, setup) 07/01 Build 22/05 MX Drop 0 "out of the box, installed" 29/10 MX Drop 1 "pre-configured, installed" 17/01 MX Drop 2 "end-user customizations" 15/03 BLD INT Drop 0 "Referentials" 08/02 BLD Drop 1.1 & 1.2 build "Intraday" 21/03 BLD Drop 1.3 & 1.4 build "End of day" 11/04 BLD Drop 1.5 build 22/05 BLD Reporting "Intraday" 21/03 BLD Reporting "End of day" 12/04 BLD Migration tools 03/05 Migration 14/06 MIG Static Data migrated for MX perf test 09/01 MIG Complete migrated data - Corp. & CDS 25/03 MIG Complete migrated data - Corp. & CDS - User validated 05/04 MIG Complete migrated data - Govies & Repos 22/05 MIG Complete migrated data - Govies & Repos - User validated 14/06 Tests 09/08 SIT Cycle A "Set-up and construct smoke test" 15/02 SIT Cycle B "Static data" 15/03 Corp. & CDS - SIT Cycle 1 "Intraday" 03/04 Corp. & CDS - SIT Cycle 2 " End of day" 24/04 Corp. & CDS - SIT Cycle 3 "Fix non-regression" 31/05 Govies & Repos - SIT Cycle 14/06 SIT Performance 1 21/02 SIT Performance 2 31/05 Corp. & CDS - Data user validation 05/04 Corp. & CDS - UAT Cycle 1.a "Intraday" 26/04 Corp. & CDS - UAT Cycle 1.b "End of day" 08/05 Corp. & CDS - Fix after UAT Cycle 1 "Intraday and End of day" 17/05 Corp. & CDS - UAT Cycle 2 "End-to-end" 14/06 Corp. & CDS - Fix after UAT Cycle 2 "End-to-end" 21/06 Corp. & CDS - UAT Cycle 3 "Final run" 28/06 Govies & Repos - Data user validation 14/06 Govies & Repos - UAT Cycles 1 and 2 and fix after UAT 09/08 Go live Corp. & CDS - Go live 1 14/07 Corp. & CDS - Go live 2 25/08 Govies & Repos - Go live 3 15/09 Govies & Repos - Go live 4 08/10 Drop0 Referentials Drop1.0 StressTest GDM Drop1.1 Credit Pricer (RT) Credit Pricer (Outbound) Calypso (RT) E-Murex(Tradeinbound RT) Drop1.2 MurexGCM(RT) GMI (RT) Phase 3 (RT) ISTAR(RT) TRACE(Murexstandard) TZERO/ICELINK(Murexstandard) ION Drop1.3 CCC Omega IPREO/eBook(Trade inboundRT) BLOFI / MOCA Card- Phase 3 Drop1.4 LORA&IMATCHFOFO/ FOBO(trade EOD) QlikView Glory(trade EOD) ISMA-TRAX GVRisk(trade EOD) Pirat (Outbound) Safir (Outbound) PoleIRC S-STR-Drp 1.5 Drop1.5 SUMMITBO(RT) E-bonds REPObulk&VCONimport LIQUID FRA/ IRSmirroring BBSupertrade 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 09/12 10/12 11/12 12/12 01/13 02/13 03/13 04/13 05/13 06/13 07/13 08/13 09/13 10/13
  • 3. STP Business Scenario Design Planning of editor’s intervention As part of IT rationalization, some users were facing a new situation for their migration to new systems. Decision was made to provide a consistent view of equity, fixed income and securities lending positions in a single place. Murex was the best option to support this aim through an “horizontal” integration with peer systems to impact new trades and trade events. Consolidation of positions in Murex situation File Processing Business Scenario Design Sunday Monday Tuesday Wednesday Thursday Friday Saturday WM WM WM WM WM WM Deployment Deployment Deployment Deployment Deployment Deployment WM WM WM WM WM WM Run Run Run Run Run Run TIBCO TIBCO TIBCO TIBCO TIBCO TIBCO Deployment Deployment Deployment Deployment Deployment Deployment TIBCO TIBCO TIBCO TIBCO TIBCO TIBCO Run Run Run Run Run Run Result Wrap-up Result Wrap-up Result Wrap-up App RV API App RV API App RV API App RV API App RV API TCP/IP Network Host 1 Host 3 Host 4Host 2 TCP/IP UDP Broadcast TCP/IPUDP Multicast UDP Unicast RVD RVD RVD Technical design and setup of dedicated injectors, routers, environments and servers As part of simplification projects, when Murex becomes a critical platform, it becomes necessary to create an automated testing factory upfront to accompany the transformation project and then the maintenance phase. This typically encompass user interface tests, functional tests, negative tests, regression tests, configuration tests and compatibility tests. Murex automated testing factory situation EUREX CORE SERVICES TRADE MANAGEMENT CLEARING SUPERVISIONTRADING LOCATIONS PARTICIPANT SERVICES EUREX MEMBER INTERFACES EUREX NYSE Liffe BRUSSELS NYSE Liffe LISBON COLLATERAL ENGINE RISK ENGINE / EDRE / PRISMA ENHANCED RISK SOLUTION FixML Clearing API COMMON REPORTING ENGINE VALUES API MARKET CONTROL MARKET MONITOR STATISTICS CONSOLIDATION PRODUCT DATA MAINTENANCE MEMBER DATA MAINTENANCE CASHMANAGEMENTCOMMUNICATION MEMBERCOMMUNICATION NYSE Liffe AMSTERDAM NYSE Liffe PARIS EUREX EEX SUPPORT SERVICES @X - GUI CARMEN CASH MANAGEMENT TRADINGLOCATION COMMUNICATION PROPRIETARY FixML MISS/VALUES DWH PRICES POSITION MANAGEMENT POSITION ACCOUNT TRANSFER TRANSFER btw MEMBERS CORPORATE ACTION POSITION CLOSE-OUT LIFFE GUARDIAN DELIVERY POSITION MAINTENANCE DELIVERY PROCESSING MANAGEMENT CCP DvP SETTLEMENT MANAGEMENT COMMODITY DELIVERY POSITION LEGACY INTERFACES SAP GERMAN LEGAL REPORTING StatistiX POSITION POSTING GIVE-UP / TAKE-UP TRADE ADJUSTMENT LEGEND CONFIGURATION FUNCTIONAL CHANGE NEW LOCATION service group function OUT OF SUBSTREAM SCOPE TRADING TRADE CAPTURE TRADE CANCELLATION CCP COMMUNICATION COMMODITY DELIVERY COMMUNICATION EXPIRY / DELIVERY NOTIFICATION / ALLOCATION COMMODITIES PHYSICAL DELIVERY EXPIRY EXERCISE / ASSIGNMENT RISK MANAGEMENT SETTLEMENT PRICES UPDATE UNDERLYING PRICES UPDATE RISK POSITION DETERMINATION COLLATERAL MANAGEMENT COLLATERAL ACCOUNT EVALUATION MARGIN CALL CALCULATION COLLATERAL ACCOUNTS UPDATE VARIATION MARGIN CALCULATION MARGIN REQUIRE- MENTS CALCULATION Functional impacts on clearing services Technical impacts on interfaces Impacts on lifecycle and on client profiles Sample deliverablesSample deliverables
  • 4. While driving IT transformation projects to ensure renewed capacity to address business expansion, talent pool for system maintenance may require to be optimized through different paradigms: . Team extensions . Service Centers . Managed Services Outsourced team management situation Costs of IT and Operations was 20% of the cost base in 2005 and has reached 30% in 2013 for investment banks. It is possible to enhance and mutualize existing services to generate additional savings by partnering more strongly with service providers. Aim is to keep such costs in-line with competition mostly for Tier-2 banks needing to expand their “flow” business. Capital Markets Post-trade Utility situations Sample deliverablesSample deliverables Weekly Progress Report Activities Priority and Forecast Delivery Lifecycle Change Documents Mutualization of opportunities by area Infrastructure Deployment Softw. Package Deployment Operational Deployment Governance Deployment Infrastructure Deployment Softw. Package Deployment Operational Deployment Governance Deployment Infrastructure Deployment Softw. Package Deployment Operational Deployment Governance Deployment Infrastructure Deployment Softw. Package Deployment Operational Deployment Governance Deployment LEVEL 0 Client-specific LEVEL 3 FIS Post-trade Utility LEVEL 2 Standardized Service LEVEL 1 Mutualized Service Financial benefits Maturity Level Savings through productivity improvements of shared resources Savings through use of standard processes Economies of scale Execute Single client Bank A Service O Bank C Service M Commoditize Bank B Service O Bank C Service O Bank B Service O Bank B Service M Bank A Service M Bank D Service M Break silos between clients - Standardize Bank D Service N Mutualize multiple clients Bank E Service M Bank A Service N Progressive deployment and benefits Transformation project cards (to enable savings)Project Cost COST: Effort estimates (total) 540 md incl. 400 md IMAGO COST: Hardware estimates (new units) 200 k€ (21 servers) COST: License and maintenance fees 100 k€ / Year for Xpress NG maintenance SAVINGS: Maintenance FTE 0 SAVINGS: Hardware 0 SAVINGS: License and maintenance fees 0 Misc. + 0.5 FTE dedicated to Test factory maintenance + 1.5 FTE dedicated to Xpress NG maintenance Some FTE to be allocated by CACIB to EFIRA maintenance man-days Team Role 2014 Q4 2015 Q1 2015 Q2 2015 Q3 2015 Q4 2016 Q1 2016 Q2 2016 Q3 2016 Q4 2017 Q1 2017 Q2 2017 Q3 2017 Q4 Total FIS_OnS PMO 21 38 2 0 0 0 0 0 0 0 0 0 0 50 FIS_OffS Architect 5 45 3 0 0 0 0 0 0 0 0 0 0 53 FIS_OnS BA 25 22 0 0 0 0 0 0 0 0 0 0 0 48 FIS_OffS Dev 42 112 6 0 0 0 0 0 0 0 0 0 0 160 FIS_OffS Test_Factory 21 56 3 0 0 0 0 0 0 0 0 0 0 80 CACIB ITS 26 70 4 0 0 0 0 0 0 0 0 0 0 100 CACIB BA 5 2 0 0 0 0 0 0 0 0 0 0 0 18 CACIB CibML_exp 11 21 1 0 0 0 0 0 0 0 0 0 0 32 CACIB Split Dev 0 0 0 0 0 0 0 0 0 0 0 0 0 0 CACIB Split Test 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Total by quarter 156 366 18 0 0 0 0 0 0 0 0 0 0 540 Xpress NG Core (EFIRA NG) Standard Financial Data ModelFpML Engine / Router Entry Point to FIS Services Utility data FIS Services Portfolio FIS Data Dictionary Services Directory Standard Service 3 Standard Service 1 Standard Service 2 Standard Service .. Standard Monitor EFIRA Monitor Xpress NG Adapters FpML CibML BankY XML CACIB data Bank Y data Application A Application YC CACIB format Bank Y format Application YF Application YD Application K Application G Application B
  • 5. To finalize a product selection process, a benchmarking of short-listed solutions allows to guarantee compliance, resilience and support quality from the software vendors. It also allows to demonstrate performances without necessarily establishing a guarantee on performances. Product benchmarking situation As part of a merger, the systems and operational processes to be retained are first selected. However, once this is done clients being transferred from previous services to the new ones must be managed. It is necessary to perform a review of changes that will be necessary from clients, changes necessary from operations and changes necessary from IT. All this needs finally to be validated at a regulatory and legal level. Post-merger impact study situation Sample deliverablesSample deliverables Test Results and Screenshots Reporting (HP Quality Center) Automated Testing Tool enhancements and setup Test Definition Enrichment MurexDealInput FeedintoMurexfromLeadingSystem Bloomberg(Interface) StockLendSystem(Interface) ULLink(Interface) Xetra(TradeEntry) EurexorLIFFE(TradeEntry) TradeFeedBroker(Interface) DWP-WP2(InterfaceorPrinter) SEBIS(Printer) Kondor+(Interface) Pricing(AHSforEOD) Pricing(ReutersforRT) TradeEntryinMurex TradeValidation/TradeWorkflow Query SecuritiesInventory Liquidity Blotter IntradayReporting-Risk IntradayReporting-P&L Confirmation/Tickets MPCC MLC LogicalPackageIDAssignment Fixing Exercise Expiry/Termination(EOD) Modify ForwardRestructure AccountClosing RateAmendment SeclendingAgreement Cancel Cancel&Reissue Products Sec Fin Stock Loan Borrow Bond X T X X X T T X X X T T T T T Stock Loan Borrow Equity X T X X X T T X X X T T T T T Repo Bond X T X T X T X X X X T T Repo Equity X T T T T T T T T T T T T T T T T T T X T X T T X T T BSB Bond X T X T X T X X X X X BSB Equity X T T T T T T T T T T T T T T T T T T X T X X X T T EQD ET Cash Equities Equity X T T T T T T T T T T T T T X OTC Cash Equities Equity X T T T T T T T T T T T T T X T T OTC Equity Swaps Equity X X X T X X X T T T T T X X X X X Ex Tr Eq Future Equity X T T X T T T T X X T T Ex Tr Eq Options Equity X T T X T T T X T X X X T X OTC Eq Futures (LIFFE) Equity X X X T T T T T T X X X X X X X IR Futures Rate X T T X X T T X X X X IRD Cash Bond Bond X T X X X T X X X X Ex Tr Bond Futures Bond X T X X X T X X X X X Ex Tr Bond Future Options Future X T X X X X T X X X X X X OTC Bond Futures Bond X T X X X T X X X X X Cash Loan Borrow Cash X T T T T T X X T T T X: This Functionality/ Process/ Activity applies to the listed product T: This Functionality/ Process/ Activity applies to the listed product and is in scope for UAT Other Systems and Trade Transmission Mx EventsMx Deal Lifecycle F ield name Screen name F ield reference n° Enumerate d F ield name target structure F ield descriptio n target structure Sample value in target field F o rmat o f target field 1 /MxML version="1-1"/events/mainEvent/action action insertion 2 /MxML version="1-1"/events/mainEvent/object href="#new_contract"/objectNatureobjectNature contract 3 /MxML version="1-1"/events/mainEvent/inputBy/userName userName Username used to book the tradeOPEREQ 4 /MxML version="1-1"/events/mainEvent/inputBy/group group The group under which the trade will be bookedMX 5 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractBusinessObjectTemplate/businessObjectId/identifieridentifier 397 6 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractBusinessObjectTemplate/businessObjectId/displayLabeldisplayLabelThe name that Murex will display to identify the productIRD Lending Borrowing 7 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractHeadercontractHeader 8 /MxML version="1-1"/contracts/contract id="new_contract" mefClass="mxContractISINGLE" mefClassInstanceType="57.000000"/contractComponents/contractComponent/tradeReference href="#trade_23612tradeReference href="????"#trade_23612 9 /MxML version="1-1"/trades/trade id="trade_23612" mefClass="mxContractITRADE" mefClassInstanceType="57.000000"/parties/party id="MUREX"/partyNamepartyName MUREX 19 /MxML version="1-1"/trades/trade id="trade_23612" mefClass="mxContractITRADE" mefClassInstanceType="57.000000"/tradeBody/bondLb/templateID/templateLabeltemplateLabel SFMA01 21 /MxML version="1-1"/trades/trade id="trade_23612" mefClass="mxContractITRADE" mefClassInstanceType="57.000000"/tradeBody/bondLb/structure/numberOfLegsnumberOfLegsWe will use two legs: one represents the financial definition of the Equity, while the other one represents the informatio2 Stock Lend Murex F ield path target structure 2 3 6 12 13 14 19 Leg 1 29 30 79 84 85 87 64 67 58 Leg 2 Markets Exchanges EUREX REPO OTCXETRA EUREX LIFFE Stock Lend DWP Printer Feed Report SEBIS Printer Reuters MDS Trade capture Data Mart Bloomberg Manual MxML EXCHANGE Bloomberg TOMS TFB TFB UL BridgeEurex & OTC Bond Future Eurex Bond Future Options OTC & Eurex Bond Repo Buy Sell Back Bond Positions Eurex Equity Future Eurex Equity Index Future Eurex Equity Option Interest Rate Futures Exchange Cash Equity Sec Lend Bond & Equity Equity Forwards OTC & Exchange Cash Equity Equity BSB Equity Repos Integration architecture decision point Specification of interfaces (attributes and event map) Integration and acceptance test reports