SlideShare uma empresa Scribd logo
1 de 42
Baixar para ler offline
Infrastructure/Logistical Networks' Risks:
                  What can Be Done?
      How Can it Be Done? Why Should it Be Done?




A presentation at RIMS 2011, Vancouver May 2nd 2011
By F. Oboni, C. Oboni, Oboni Riskope Associates Inc.
(c) Oboni Riskope Associates Inc., 2011
Riskope International SA © 2009 www.riskope.com
                                                       1
April 20, 2011                  Slide # 1
Cardio-vascular accidents
(stroke) have become one of the
      major causes of death.
    A cardio vascular accident
     occurs when blood flow is
  interrupted to part of the brain
  (our very own IT system…), a
   problem occurs in the heart...



Riskope International SA © 2009 www.riskope.com
                                                  2
April 20, 2011                  Slide # 2
Consider the heart as your extractive facility, and
  the circulatory system as your transportation/logistic
  network.

  You probably have
  learned to take good
  care of your heart and
  your blood vessels: is
  the mining industry
  doing the same for its
  “circulatory” system?


Riskope International SA © 2009 www.riskope.com
                                                       3
April 20, 2011                  Slide # 3
For years we have taken care of civil systems’
digestive/waste “organs”. In the mining world these are:
process, tailings, dumps, contamination....




Riskope International SA © 2009 www.riskope.com
                                                     4
April 20, 2011                  Slide # 4
Then large companies have asked us to review
 “supply chains” (e.g water, electricity, gas, acid etc.),
 but never used to ask about “moving products away”.

The progression generally was:
Tailings, Slopes, Access Road.

We generally had to insist to
include for example:

Concentrate pipelines,
Wharves, Ship-loaders,
IT systems...
Riskope International SA © 2009 www.riskope.com
                                                         5
April 20, 2011                  Slide # 5
Other industries/organizations were
ahead of miners.

For example:

The Olympics in Torino were
concerned by their road network (in
and out of the venues),

CCC (jewels, perfumes) was also
very concerned about moving their
products out, as they have very
precise schedules, and have “Ali
Baba caverns” in seismic areas.

Riskope International SA © 2009 www.riskope.com
                                                  6
April 20, 2011                  Slide # 6
CCC Japan asked Riskope
    in 1998 (three years after
    Kobe earthquake) to
    perform a

    Logistic Platform Disaster
    Recovery and Business
    Resumption Plan Review.



Riskope International SA © 2009 www.riskope.com
                                                  7
April 20, 2011                  Slide # 7
some of Riskope's notes were:

  -The plan is expecting a disaster to hit only during
  regular business hours!
  -The plan relies on a rosy scenario whereby major
  Highways, RR infrastructure and power supply
  (actually they had auxiliary power, but the tanks were
  empty...)!! would be running!
  -IT Servers were not mirrored by hardware located in
  a safer region!

  We sincerely hope they corrected their plans...these
  common errors have proven critical 13 years later...
Riskope International SA © 2009 www.riskope.com
                                                      8
April 20, 2011                  Slide # 8
Remarkably not one of Riskope’s notes required
detailed knowledge of seismology.

People claiming one cannot anticipate an Earthquake/
Terrorist attack/Failure scenario (or any other hazard)
because they do not know enough details of possible
hazards are missing the point:

Disruptive events can be anticipated and planned in
sustainable ways by performing sensible risk analyses.

Detailed knowledge is needed, but at a later stage.
Riskope International SA © 2009 www.riskope.com
                                                      9
April 20, 2011                  Slide # 9
You do not go to the doctor and ask him about the
genetic structure of a virus or a disease. You ask him
how it might affect YOUR life (scenarios), then you
ponder if the “cost of vaccination” vs “reward” is worth
time and effort, AND, the chance of secondary effects.




Riskope International SA © 2009 www.riskope.com
                                                     10
April 20, 2011                  Slide # 10
Mining “circulatory” systems encompass ingress and egress, like
the human one arteries and veins, all the way from the heart to the
end user!

Miners seemed to privilege ingress studies, but to neglect egress
studies, contrary to other industries.

Modern transportation systems require effective risk management
decision tools to:
 -help ensure critical transportation
 operations' reliability
 -ranking emergency alternatives
 -allocating mitigative resources


Riskope International SA © 2009 www.riskope.com
                                                              11
April 20, 2011                  Slide # 11
Transportation, loading/unloading contracts with third
parties have the effect to make companies feel
“comfortable” that the other parties are taking care of
their risks....

YET

when reality kicks in, severe disruptions result from
major snowstorms, avalanches, volcanoes or defective
valves, gearboxes!!


Let's look at some examples:
Riskope International SA © 2009 www.riskope.com
                                                     12
April 20, 2011                  Slide # 12
Winter 2010-2011




Riskope International SA © 2009 www.riskope.com
                                                  13
April 20, 2011                  Slide # 13
Volcano (Island, 2010)




Riskope International SA © 2009 www.riskope.com
                                                  14
April 20, 2011                  Slide # 14
Production of iron ore, uranium and alumina have all
been disrupted in the first three months of 2011 by
Cyclone Yasi




Riskope International SA © 2009 www.riskope.com
                                                   15
April 20, 2011                  Slide # 15
A gearbox in the loading equipment failed on Jan. xx, at
which time YYY estimated it could take up to two
weeks to fix the
damaged parts
leaving the ZZZ
terminal
operating at
about half
capacity.




Riskope International SA © 2009 www.riskope.com
                                                    16
April 20, 2011                  Slide # 16
This 2010 ship loader collapse still requires
emergency (and costly) truck transfers to a wharf
500km away….




Riskope International SA © 2009 www.riskope.com
                                                    17
April 20, 2011                  Slide # 17
Examples of hazards capable of generating egress
   disruptions:

   -Earthquakes
   -Hurricanes, cyclones and floods
   -Man-made and Natural slopes, rock-falls
   -Traffic and trackage, strikes
   -Fires of forests, railroad assets,
   -Dust, nuclear fall out, terrorism and organized
   criminality...
   -IT failures, ....
   -Maintenance, human error…!!

Riskope International SA © 2009 www.riskope.com
                                                      18
April 20, 2011                  Slide # 18
Once the system potentially hit by disruptive event(s) is
   studied, risks are ranked and checked towards
                  tolerability criteria.

     it is then possible to effectively allocate mitigative
          resources, select alternative routes etc. ($).

                      Not the other way around!

    Without clear understanding of tolerability, you will
                   waste your money!


Riskope International SA © 2009 www.riskope.com
                                                          19
April 20, 2011                  Slide # 19
Budgets available
      for risk analysis and risk-based planning of
               hazard protection measures
         for transport routes and infrastructure
                   is generally limited
                         because
              of the false sense of comfort
            brought by third parties contracts.



Riskope International SA © 2009 www.riskope.com
                                                     20
April 20, 2011                  Slide # 20
Important definitions like, for example,
Force Majeure,
are taken as granted boiler plate solutions, in the total
misunderstanding of what they do mean, and what they
will mean the day reality kicks-in.

All this while many people are starting to ask more
general questions, such as for example: was Katrina
really a natural disaster, or was it man-made, or man-
induced and to what extent?



Riskope International SA © 2009 www.riskope.com
                                                     21
April 20, 2011                  Slide # 21
On Jan 13 the FT published a short article explaining
                 th



how snow proofing UK's airports may force passengers
to pay higher fares if winters turn “permanently” colder.




Riskope International SA © 2009 www.riskope.com
                                                      22
April 20, 2011                  Slide # 22
Reportedly the “Arctic weather conditions” before Christmas
cost 37.7MUS$ in one week.
BAA said airlines “shared responsibility for the disruption as
they had agreed to a recovery plan that failed to account for
deep snow”.

Airlines needed to renegotiate the emergency plan, which
could lead to an increase in operating fees...

Needless to say BAA was heavily criticized for the
disruption.


Riskope International SA © 2009 www.riskope.com
                                                         23
April 20, 2011                  Slide # 23
Foreseeability, a key parameter in FM, indeed requires
the definition of a threshold likelihood: for example a
tornado in Salt Lake city was unforeseeable, by
scientific consensus, until one happened in 1999?!




Riskope International SA © 2009 www.riskope.com
                                                    24
April 20, 2011                  Slide # 24
The optimization of Force Majeure formulation, when
renegotiating contracts in the future, or for new
contracts, constitutes an important proactive mitigative
measure with very large ROI (Return On Investment).




Riskope International SA © 2009 www.riskope.com
                                                      25
April 20, 2011                  Slide # 25
There are numerous areas where optimization can take
place, for example under the form of a more detailed
explanation of terms, definition of threshold values,
definition of considered mitigative levels,
“common practices”
or “best practices”,
negligence.




Riskope International SA © 2009 www.riskope.com
                                                  26
April 20, 2011                  Slide # 26
Going back to our clairvoyant and planning oriented
        clients, their business areas range from:

                 Torino 2006 Winter Olympic Games
                               Military
                                Food
                             Jewellers,
                          and lately, Mining
                                 etc.



Riskope International SA © 2009 www.riskope.com
                                                    27
April 20, 2011                  Slide # 27
Modern transportation systems are complex and
therefore require effective risk management decision
tools.

These help to:

-rank alternatives, (literally hundreds)
-allocate resources, (how much is reasonable!?)
-avoid alternatives with major side-effects

the reason is in the following slide

Riskope International SA © 2009 www.riskope.com
                                                   28
April 20, 2011                  Slide # 28
As someone has said:

“The time to look for the emergency aisles and where
the exits are located is before takeoff, not after the
wings fall off the plane”.


We must always have a plan in place to deal with
unanticipated events,
a “just-in-case things head south” plan.



Riskope International SA © 2009 www.riskope.com
                                                    29
April 20, 2011                  Slide # 29
Ideally, one puts this plan together when you are
objective and unemotional and calmly contemplative —
not when things are figuratively and literally melting
down.
Or in the aftermath of an accident!


   “The Problem is when we
   don’t know what we
   don’t know we don’t know.”



Riskope International SA © 2009 www.riskope.com
                                                   30
April 20, 2011                  Slide # 30
An ingress-egress study covers:

The links between two or more geographic points
allowing transit of goods, energy, information or
people by means of discrete traffic (roads, railroads)
or continuous flow (pipelines, channels, cables, fibre-
optics) linear facilities LF.

LF are running in increasingly more congested
transportation corridors and are becoming absolutely
critical to our society...remember the Cardio-vascular
analogy?

Riskope International SA © 2009 www.riskope.com
                                                      31
April 20, 2011                  Slide # 31
Certain equipment, such a specialized ore ship loaders can take
up to one year to replace.

Restoration time for port facilities, can be very long and
daunting....it's like being on a waiting list for a cardiac operation!

Finally, the destruction or damage of the IT assets (for example
Network Management Center) could also cripple the egress from
a mine,

and that's exactly why a European army has contracted us to
deliver a consistent and rational Risk approach (not an IT
approach! An information RM approach) for a whole country.


Riskope International SA © 2009 www.riskope.com
                                                                   32
April 20, 2011                  Slide # 32
Although managers try to avoid “complex
        mathematics”, hard numbers are crucial in
differentiating risks incurred, sometimes by hundreds of
      components of a similar system (which can be
    anything, from a road homogeneous segment to a
 valve, a tank along a pipeline) leading to the need for
                           QRAs.




Riskope International SA © 2009 www.riskope.com
                                                    33
April 20, 2011                  Slide # 33
CS1: Seismic BI




Riskope International SA © 2009 www.riskope.com
                                                  34
April 20, 2011                  Slide # 34
Riskope International SA © 2009 www.riskope.com
                                                  35
April 20, 2011                  Slide # 35
Conclusion was to propose a B2B strategy whereby the
client would actually team-up with RR and buy
replacement bridges. Insurance could be reduced and
serviceability ensured in a far better way.




Riskope International SA © 2009 www.riskope.com
                                                  36
April 20, 2011                  Slide # 36
CS2: Multimodal/ multihazard logistical transportation
network


         Production                                    End
                                  Ships to W zzzT                Possible mitigation
          Centre X                                    User A
                                                                       Routes
                                                                                                       Export
         XX                                                                                              B
           %
               pr
                 od
                      uc              RR
                        tio
                              n
                                                                                       Tunnels and
                                                                  Loading                Bridges


                                   Tunnels and                   Wharves                             End
                                     Bridges
                                                                                                     User C
                                                                                       Tunnels and
                                  Ships to W zzzT                                        Bridges
      Production Centre                                           Unloader
              Y




Riskope International SA © 2009 www.riskope.com
                                                                                                                37
April 20, 2011                                      Slide # 37
Insurance can be cut in half. Authorizations and
agreements should be passed in view of possible future
occurrences.




Riskope International SA © 2009 www.riskope.com
                                                  38
April 20, 2011                  Slide # 38
CS3: Mine’s personnel shuttling: Air plane vs buses

Risk assessments can be used to help decide whether
a different transportation system would be better than
an existing one.

Several levels of analysis are possible, the top one
including CDA-ESM, an alternative comparison tool
which allows considering risks and avoids all the pitfalls
of NPV.



Riskope International SA © 2009 www.riskope.com
                                                      39
April 20, 2011                  Slide # 39
Riskope International SA © 2009 www.riskope.com
                                                  40
April 20, 2011                  Slide # 40
Infrastructure/Logistical Networks' Risks:

What can Be Done?
  Once the system potentially hit by disruptive event(s) is studied evaluating the
              limits of Force Majeure events, risks are ranked and
                      checked towards tolerability criteria.


How Can it be done?
Alternatives, emergencies routes are studied and ranked, including side effects.
Force Majeure clause from 3rd parties contracts should be (re)-negotiated and
sustainable solutions designed.

Why Should it Be Done?
   -help ensure critical transportation operations' reliability
   -rank emergency alternatives
   -allocate mitigative resources
   -faster understanding on the situation in case of a crisis situation regarding 3rd parties

Riskope International SA © 2009 www.riskope.com
                                                                                      41
April 20, 2011                      Slide # 41
The benefits
 Create the basis to avoid
   a slide into a crisis, by
   proactively controlling
        the situation.
   Mind your heart and
      your circulatory
           system!


Riskope International SA © 2009 www.riskope.com
                                                  42
April 20, 2011                  Slide # 42

Mais conteúdo relacionado

Destaque

Accurate biochemical knowledge starting with precise structure-based criteria...
Accurate biochemical knowledge starting with precise structure-based criteria...Accurate biochemical knowledge starting with precise structure-based criteria...
Accurate biochemical knowledge starting with precise structure-based criteria...Michel Dumontier
 
OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...
OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...
OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...Michel Dumontier
 
AgilePalooza - BigScrum - Scaling Team To Program
AgilePalooza - BigScrum - Scaling Team To ProgramAgilePalooza - BigScrum - Scaling Team To Program
AgilePalooza - BigScrum - Scaling Team To ProgramThinkLouder
 
IVI Workshop Value Creation in European Pe
IVI Workshop Value Creation in European PeIVI Workshop Value Creation in European Pe
IVI Workshop Value Creation in European PeThomas Nastas
 
7+1 myths about presentation
7+1 myths about presentation 7+1 myths about presentation
7+1 myths about presentation Samuel Titěra
 
Outsourcing to India Publication IJAS 2010
Outsourcing to India Publication IJAS 2010Outsourcing to India Publication IJAS 2010
Outsourcing to India Publication IJAS 2010Debopriyo Roy
 
ABTCP-Tappi Presentation 2010
ABTCP-Tappi Presentation 2010ABTCP-Tappi Presentation 2010
ABTCP-Tappi Presentation 2010SteveScheibe
 
Reputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, finalReputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, finalDamjana Kocjanc
 
Balangero Asbestos Tailings Dump Environmental Rehabilitation
Balangero Asbestos Tailings Dump Environmental RehabilitationBalangero Asbestos Tailings Dump Environmental Rehabilitation
Balangero Asbestos Tailings Dump Environmental RehabilitationOboni Riskope Associates Inc.
 
The Globalized Patient
The Globalized PatientThe Globalized Patient
The Globalized PatientdiversityRx
 
Designing a Customer Feedback Program to Measure and Improve User Satisfaction
Designing a Customer Feedback Program to Measure and Improve User SatisfactionDesigning a Customer Feedback Program to Measure and Improve User Satisfaction
Designing a Customer Feedback Program to Measure and Improve User SatisfactionUserZoom
 
Model Organism Linked Data
Model Organism Linked DataModel Organism Linked Data
Model Organism Linked DataMichel Dumontier
 

Destaque (17)

Accurate biochemical knowledge starting with precise structure-based criteria...
Accurate biochemical knowledge starting with precise structure-based criteria...Accurate biochemical knowledge starting with precise structure-based criteria...
Accurate biochemical knowledge starting with precise structure-based criteria...
 
OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...
OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...
OWLED 2009 - Conjunctive Query Answering in Distributed Ontology Systems for ...
 
AgilePalooza - BigScrum - Scaling Team To Program
AgilePalooza - BigScrum - Scaling Team To ProgramAgilePalooza - BigScrum - Scaling Team To Program
AgilePalooza - BigScrum - Scaling Team To Program
 
IVI Workshop Value Creation in European Pe
IVI Workshop Value Creation in European PeIVI Workshop Value Creation in European Pe
IVI Workshop Value Creation in European Pe
 
7+1 myths about presentation
7+1 myths about presentation 7+1 myths about presentation
7+1 myths about presentation
 
Burlata
BurlataBurlata
Burlata
 
Outsourcing to India Publication IJAS 2010
Outsourcing to India Publication IJAS 2010Outsourcing to India Publication IJAS 2010
Outsourcing to India Publication IJAS 2010
 
Ishii presentation
Ishii presentationIshii presentation
Ishii presentation
 
ABTCP-Tappi Presentation 2010
ABTCP-Tappi Presentation 2010ABTCP-Tappi Presentation 2010
ABTCP-Tappi Presentation 2010
 
Reputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, finalReputation snapshot for the banking industry, 2012, final
Reputation snapshot for the banking industry, 2012, final
 
Balangero Asbestos Tailings Dump Environmental Rehabilitation
Balangero Asbestos Tailings Dump Environmental RehabilitationBalangero Asbestos Tailings Dump Environmental Rehabilitation
Balangero Asbestos Tailings Dump Environmental Rehabilitation
 
The Globalized Patient
The Globalized PatientThe Globalized Patient
The Globalized Patient
 
Free Software
Free SoftwareFree Software
Free Software
 
Designing a Customer Feedback Program to Measure and Improve User Satisfaction
Designing a Customer Feedback Program to Measure and Improve User SatisfactionDesigning a Customer Feedback Program to Measure and Improve User Satisfaction
Designing a Customer Feedback Program to Measure and Improve User Satisfaction
 
Nozawa presentation
Nozawa presentationNozawa presentation
Nozawa presentation
 
Earth Day
Earth DayEarth Day
Earth Day
 
Model Organism Linked Data
Model Organism Linked DataModel Organism Linked Data
Model Organism Linked Data
 

Semelhante a Rims Metals and Mining Session

software failures
 software failures software failures
software failuresRespa Peter
 
Know4 ddr ir_mav2
Know4 ddr ir_mav2Know4 ddr ir_mav2
Know4 ddr ir_mav2know4drr
 
Ir ma know4_ddr
Ir ma know4_ddrIr ma know4_ddr
Ir ma know4_ddrknow4drr
 
Raoul Chiesa Hacking A Impianti Industriali
Raoul Chiesa   Hacking A Impianti IndustrialiRaoul Chiesa   Hacking A Impianti Industriali
Raoul Chiesa Hacking A Impianti IndustrialiGoWireless
 
May 2009 IAPH WB: state of the port sector
May 2009 IAPH WB: state of the port sector May 2009 IAPH WB: state of the port sector
May 2009 IAPH WB: state of the port sector Michel_Donner
 
Crisis Communications in the YouTube Age (updated)
Crisis Communications in the YouTube Age (updated)Crisis Communications in the YouTube Age (updated)
Crisis Communications in the YouTube Age (updated)Julian Matthews
 
PROMPT. Describe a potential unanticipated risk that an organization .pdf
 PROMPT. Describe a potential unanticipated risk that an organization .pdf PROMPT. Describe a potential unanticipated risk that an organization .pdf
PROMPT. Describe a potential unanticipated risk that an organization .pdfaltajhaji20
 
06.Crisis communications
06.Crisis communications06.Crisis communications
06.Crisis communicationsJulian Matthews
 
Boosing Resilience Through Innovative Risk Governance - OECD Report
Boosing Resilience Through Innovative Risk Governance - OECD ReportBoosing Resilience Through Innovative Risk Governance - OECD Report
Boosing Resilience Through Innovative Risk Governance - OECD ReportOECD Governance
 
Right track issue 6
Right track issue 6Right track issue 6
Right track issue 6Cubeworks
 
CSM Module 6: Crisis communications
CSM Module 6: Crisis communicationsCSM Module 6: Crisis communications
CSM Module 6: Crisis communicationsJulian Matthews
 
STINGS online mine tailings monitoring solution
STINGS online mine tailings monitoring solutionSTINGS online mine tailings monitoring solution
STINGS online mine tailings monitoring solutionDMT GROUP
 
Aftab Hasan Speaking At Ship Tek 2011
Aftab Hasan Speaking At Ship Tek   2011Aftab Hasan Speaking At Ship Tek   2011
Aftab Hasan Speaking At Ship Tek 2011aftabhasan
 
New Models and New Technologies for an Integrated Risk Management in Complex ...
New Models and New Technologies for an Integrated Risk Management in Complex ...New Models and New Technologies for an Integrated Risk Management in Complex ...
New Models and New Technologies for an Integrated Risk Management in Complex ...Community Protection Forum
 
Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...
Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...
Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...Simon Spencer
 
Lampiran profiting from uncertainty
Lampiran profiting from uncertaintyLampiran profiting from uncertainty
Lampiran profiting from uncertaintyFuturum2
 
Cyber piracy threat analysis
Cyber piracy threat analysisCyber piracy threat analysis
Cyber piracy threat analysisYongHyun Jo
 
Barclays Disaster Preparedness Presentation | BCCJ
Barclays Disaster Preparedness Presentation | BCCJBarclays Disaster Preparedness Presentation | BCCJ
Barclays Disaster Preparedness Presentation | BCCJSam Maddicott
 

Semelhante a Rims Metals and Mining Session (20)

Force Majeure: a Time Bomb
Force Majeure: a Time BombForce Majeure: a Time Bomb
Force Majeure: a Time Bomb
 
software failures
 software failures software failures
software failures
 
Know4 ddr ir_mav2
Know4 ddr ir_mav2Know4 ddr ir_mav2
Know4 ddr ir_mav2
 
Ir ma know4_ddr
Ir ma know4_ddrIr ma know4_ddr
Ir ma know4_ddr
 
Raoul Chiesa Hacking A Impianti Industriali
Raoul Chiesa   Hacking A Impianti IndustrialiRaoul Chiesa   Hacking A Impianti Industriali
Raoul Chiesa Hacking A Impianti Industriali
 
May 2009 IAPH WB: state of the port sector
May 2009 IAPH WB: state of the port sector May 2009 IAPH WB: state of the port sector
May 2009 IAPH WB: state of the port sector
 
Crisis Communications in the YouTube Age (updated)
Crisis Communications in the YouTube Age (updated)Crisis Communications in the YouTube Age (updated)
Crisis Communications in the YouTube Age (updated)
 
PROMPT. Describe a potential unanticipated risk that an organization .pdf
 PROMPT. Describe a potential unanticipated risk that an organization .pdf PROMPT. Describe a potential unanticipated risk that an organization .pdf
PROMPT. Describe a potential unanticipated risk that an organization .pdf
 
06.Crisis communications
06.Crisis communications06.Crisis communications
06.Crisis communications
 
Emerging Trends in the Insurance Market
Emerging Trends in the Insurance MarketEmerging Trends in the Insurance Market
Emerging Trends in the Insurance Market
 
Boosing Resilience Through Innovative Risk Governance - OECD Report
Boosing Resilience Through Innovative Risk Governance - OECD ReportBoosing Resilience Through Innovative Risk Governance - OECD Report
Boosing Resilience Through Innovative Risk Governance - OECD Report
 
Right track issue 6
Right track issue 6Right track issue 6
Right track issue 6
 
CSM Module 6: Crisis communications
CSM Module 6: Crisis communicationsCSM Module 6: Crisis communications
CSM Module 6: Crisis communications
 
STINGS online mine tailings monitoring solution
STINGS online mine tailings monitoring solutionSTINGS online mine tailings monitoring solution
STINGS online mine tailings monitoring solution
 
Aftab Hasan Speaking At Ship Tek 2011
Aftab Hasan Speaking At Ship Tek   2011Aftab Hasan Speaking At Ship Tek   2011
Aftab Hasan Speaking At Ship Tek 2011
 
New Models and New Technologies for an Integrated Risk Management in Complex ...
New Models and New Technologies for an Integrated Risk Management in Complex ...New Models and New Technologies for an Integrated Risk Management in Complex ...
New Models and New Technologies for an Integrated Risk Management in Complex ...
 
Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...
Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...
Simon Spencer Blog - Safety Hazards You Should Know About in Toronto's Bigges...
 
Lampiran profiting from uncertainty
Lampiran profiting from uncertaintyLampiran profiting from uncertainty
Lampiran profiting from uncertainty
 
Cyber piracy threat analysis
Cyber piracy threat analysisCyber piracy threat analysis
Cyber piracy threat analysis
 
Barclays Disaster Preparedness Presentation | BCCJ
Barclays Disaster Preparedness Presentation | BCCJBarclays Disaster Preparedness Presentation | BCCJ
Barclays Disaster Preparedness Presentation | BCCJ
 

Mais de Oboni Riskope Associates Inc.

Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Oboni Riskope Associates Inc.
 
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Oboni Riskope Associates Inc.
 
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, ColombiaOboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, ColombiaOboni Riskope Associates Inc.
 
Rims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, RiskopeRims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, RiskopeOboni Riskope Associates Inc.
 

Mais de Oboni Riskope Associates Inc. (20)

Riskope new web site announcement
Riskope new web site announcementRiskope new web site announcement
Riskope new web site announcement
 
Rational Risk and Crisis Management Course
Rational Risk and Crisis Management CourseRational Risk and Crisis Management Course
Rational Risk and Crisis Management Course
 
Cim2013 oboni oboni_zabolotoniuk
Cim2013 oboni oboni_zabolotoniukCim2013 oboni oboni_zabolotoniuk
Cim2013 oboni oboni_zabolotoniuk
 
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
 
Riskope for christmas 2012
Riskope for christmas 2012Riskope for christmas 2012
Riskope for christmas 2012
 
Ore cockpit castellano
Ore cockpit castellanoOre cockpit castellano
Ore cockpit castellano
 
Mining 012 riskope is it true that pi_gs
Mining 012 riskope  is it true that pi_gsMining 012 riskope  is it true that pi_gs
Mining 012 riskope is it true that pi_gs
 
Bogota 02 10-011 Risk Management Mining Summit
Bogota 02 10-011 Risk Management Mining SummitBogota 02 10-011 Risk Management Mining Summit
Bogota 02 10-011 Risk Management Mining Summit
 
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
 
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, ColombiaOboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
Oboni Riskope Conference on Risk Based Decision Making in Bogotà, Colombia
 
Review ICS Guidelines
Review ICS GuidelinesReview ICS Guidelines
Review ICS Guidelines
 
Cassass presentation WLF2 Rome
Cassass presentation WLF2 RomeCassass presentation WLF2 Rome
Cassass presentation WLF2 Rome
 
Road Safety- Sicurezza Stradale
Road Safety- Sicurezza StradaleRoad Safety- Sicurezza Stradale
Road Safety- Sicurezza Stradale
 
Tolerability and Decision Making Discussion
Tolerability and Decision Making DiscussionTolerability and Decision Making Discussion
Tolerability and Decision Making Discussion
 
Rims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, RiskopeRims Metal and Mining Session talk by F+C Oboni, Riskope
Rims Metal and Mining Session talk by F+C Oboni, Riskope
 
Oboni02 castellano
Oboni02 castellanoOboni02 castellano
Oboni02 castellano
 
Oboni01 castellano
Oboni01 castellanoOboni01 castellano
Oboni01 castellano
 
Cda esm waste oil disposal application part 2
Cda esm waste oil disposal application part 2Cda esm waste oil disposal application part 2
Cda esm waste oil disposal application part 2
 
Force Majeure Clause in Contracts
Force Majeure Clause in ContractsForce Majeure Clause in Contracts
Force Majeure Clause in Contracts
 
Comparing Alternatives Using CDA-ESM
Comparing Alternatives Using CDA-ESMComparing Alternatives Using CDA-ESM
Comparing Alternatives Using CDA-ESM
 

Último

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 

Último (20)

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 

Rims Metals and Mining Session

  • 1. Infrastructure/Logistical Networks' Risks: What can Be Done? How Can it Be Done? Why Should it Be Done? A presentation at RIMS 2011, Vancouver May 2nd 2011 By F. Oboni, C. Oboni, Oboni Riskope Associates Inc. (c) Oboni Riskope Associates Inc., 2011 Riskope International SA © 2009 www.riskope.com 1 April 20, 2011 Slide # 1
  • 2. Cardio-vascular accidents (stroke) have become one of the major causes of death. A cardio vascular accident occurs when blood flow is interrupted to part of the brain (our very own IT system…), a problem occurs in the heart... Riskope International SA © 2009 www.riskope.com 2 April 20, 2011 Slide # 2
  • 3. Consider the heart as your extractive facility, and the circulatory system as your transportation/logistic network. You probably have learned to take good care of your heart and your blood vessels: is the mining industry doing the same for its “circulatory” system? Riskope International SA © 2009 www.riskope.com 3 April 20, 2011 Slide # 3
  • 4. For years we have taken care of civil systems’ digestive/waste “organs”. In the mining world these are: process, tailings, dumps, contamination.... Riskope International SA © 2009 www.riskope.com 4 April 20, 2011 Slide # 4
  • 5. Then large companies have asked us to review “supply chains” (e.g water, electricity, gas, acid etc.), but never used to ask about “moving products away”. The progression generally was: Tailings, Slopes, Access Road. We generally had to insist to include for example: Concentrate pipelines, Wharves, Ship-loaders, IT systems... Riskope International SA © 2009 www.riskope.com 5 April 20, 2011 Slide # 5
  • 6. Other industries/organizations were ahead of miners. For example: The Olympics in Torino were concerned by their road network (in and out of the venues), CCC (jewels, perfumes) was also very concerned about moving their products out, as they have very precise schedules, and have “Ali Baba caverns” in seismic areas. Riskope International SA © 2009 www.riskope.com 6 April 20, 2011 Slide # 6
  • 7. CCC Japan asked Riskope in 1998 (three years after Kobe earthquake) to perform a Logistic Platform Disaster Recovery and Business Resumption Plan Review. Riskope International SA © 2009 www.riskope.com 7 April 20, 2011 Slide # 7
  • 8. some of Riskope's notes were: -The plan is expecting a disaster to hit only during regular business hours! -The plan relies on a rosy scenario whereby major Highways, RR infrastructure and power supply (actually they had auxiliary power, but the tanks were empty...)!! would be running! -IT Servers were not mirrored by hardware located in a safer region! We sincerely hope they corrected their plans...these common errors have proven critical 13 years later... Riskope International SA © 2009 www.riskope.com 8 April 20, 2011 Slide # 8
  • 9. Remarkably not one of Riskope’s notes required detailed knowledge of seismology. People claiming one cannot anticipate an Earthquake/ Terrorist attack/Failure scenario (or any other hazard) because they do not know enough details of possible hazards are missing the point: Disruptive events can be anticipated and planned in sustainable ways by performing sensible risk analyses. Detailed knowledge is needed, but at a later stage. Riskope International SA © 2009 www.riskope.com 9 April 20, 2011 Slide # 9
  • 10. You do not go to the doctor and ask him about the genetic structure of a virus or a disease. You ask him how it might affect YOUR life (scenarios), then you ponder if the “cost of vaccination” vs “reward” is worth time and effort, AND, the chance of secondary effects. Riskope International SA © 2009 www.riskope.com 10 April 20, 2011 Slide # 10
  • 11. Mining “circulatory” systems encompass ingress and egress, like the human one arteries and veins, all the way from the heart to the end user! Miners seemed to privilege ingress studies, but to neglect egress studies, contrary to other industries. Modern transportation systems require effective risk management decision tools to: -help ensure critical transportation operations' reliability -ranking emergency alternatives -allocating mitigative resources Riskope International SA © 2009 www.riskope.com 11 April 20, 2011 Slide # 11
  • 12. Transportation, loading/unloading contracts with third parties have the effect to make companies feel “comfortable” that the other parties are taking care of their risks.... YET when reality kicks in, severe disruptions result from major snowstorms, avalanches, volcanoes or defective valves, gearboxes!! Let's look at some examples: Riskope International SA © 2009 www.riskope.com 12 April 20, 2011 Slide # 12
  • 13. Winter 2010-2011 Riskope International SA © 2009 www.riskope.com 13 April 20, 2011 Slide # 13
  • 14. Volcano (Island, 2010) Riskope International SA © 2009 www.riskope.com 14 April 20, 2011 Slide # 14
  • 15. Production of iron ore, uranium and alumina have all been disrupted in the first three months of 2011 by Cyclone Yasi Riskope International SA © 2009 www.riskope.com 15 April 20, 2011 Slide # 15
  • 16. A gearbox in the loading equipment failed on Jan. xx, at which time YYY estimated it could take up to two weeks to fix the damaged parts leaving the ZZZ terminal operating at about half capacity. Riskope International SA © 2009 www.riskope.com 16 April 20, 2011 Slide # 16
  • 17. This 2010 ship loader collapse still requires emergency (and costly) truck transfers to a wharf 500km away…. Riskope International SA © 2009 www.riskope.com 17 April 20, 2011 Slide # 17
  • 18. Examples of hazards capable of generating egress disruptions: -Earthquakes -Hurricanes, cyclones and floods -Man-made and Natural slopes, rock-falls -Traffic and trackage, strikes -Fires of forests, railroad assets, -Dust, nuclear fall out, terrorism and organized criminality... -IT failures, .... -Maintenance, human error…!! Riskope International SA © 2009 www.riskope.com 18 April 20, 2011 Slide # 18
  • 19. Once the system potentially hit by disruptive event(s) is studied, risks are ranked and checked towards tolerability criteria. it is then possible to effectively allocate mitigative resources, select alternative routes etc. ($). Not the other way around! Without clear understanding of tolerability, you will waste your money! Riskope International SA © 2009 www.riskope.com 19 April 20, 2011 Slide # 19
  • 20. Budgets available for risk analysis and risk-based planning of hazard protection measures for transport routes and infrastructure is generally limited because of the false sense of comfort brought by third parties contracts. Riskope International SA © 2009 www.riskope.com 20 April 20, 2011 Slide # 20
  • 21. Important definitions like, for example, Force Majeure, are taken as granted boiler plate solutions, in the total misunderstanding of what they do mean, and what they will mean the day reality kicks-in. All this while many people are starting to ask more general questions, such as for example: was Katrina really a natural disaster, or was it man-made, or man- induced and to what extent? Riskope International SA © 2009 www.riskope.com 21 April 20, 2011 Slide # 21
  • 22. On Jan 13 the FT published a short article explaining th how snow proofing UK's airports may force passengers to pay higher fares if winters turn “permanently” colder. Riskope International SA © 2009 www.riskope.com 22 April 20, 2011 Slide # 22
  • 23. Reportedly the “Arctic weather conditions” before Christmas cost 37.7MUS$ in one week. BAA said airlines “shared responsibility for the disruption as they had agreed to a recovery plan that failed to account for deep snow”. Airlines needed to renegotiate the emergency plan, which could lead to an increase in operating fees... Needless to say BAA was heavily criticized for the disruption. Riskope International SA © 2009 www.riskope.com 23 April 20, 2011 Slide # 23
  • 24. Foreseeability, a key parameter in FM, indeed requires the definition of a threshold likelihood: for example a tornado in Salt Lake city was unforeseeable, by scientific consensus, until one happened in 1999?! Riskope International SA © 2009 www.riskope.com 24 April 20, 2011 Slide # 24
  • 25. The optimization of Force Majeure formulation, when renegotiating contracts in the future, or for new contracts, constitutes an important proactive mitigative measure with very large ROI (Return On Investment). Riskope International SA © 2009 www.riskope.com 25 April 20, 2011 Slide # 25
  • 26. There are numerous areas where optimization can take place, for example under the form of a more detailed explanation of terms, definition of threshold values, definition of considered mitigative levels, “common practices” or “best practices”, negligence. Riskope International SA © 2009 www.riskope.com 26 April 20, 2011 Slide # 26
  • 27. Going back to our clairvoyant and planning oriented clients, their business areas range from: Torino 2006 Winter Olympic Games Military Food Jewellers, and lately, Mining etc. Riskope International SA © 2009 www.riskope.com 27 April 20, 2011 Slide # 27
  • 28. Modern transportation systems are complex and therefore require effective risk management decision tools. These help to: -rank alternatives, (literally hundreds) -allocate resources, (how much is reasonable!?) -avoid alternatives with major side-effects the reason is in the following slide Riskope International SA © 2009 www.riskope.com 28 April 20, 2011 Slide # 28
  • 29. As someone has said: “The time to look for the emergency aisles and where the exits are located is before takeoff, not after the wings fall off the plane”. We must always have a plan in place to deal with unanticipated events, a “just-in-case things head south” plan. Riskope International SA © 2009 www.riskope.com 29 April 20, 2011 Slide # 29
  • 30. Ideally, one puts this plan together when you are objective and unemotional and calmly contemplative — not when things are figuratively and literally melting down. Or in the aftermath of an accident! “The Problem is when we don’t know what we don’t know we don’t know.” Riskope International SA © 2009 www.riskope.com 30 April 20, 2011 Slide # 30
  • 31. An ingress-egress study covers: The links between two or more geographic points allowing transit of goods, energy, information or people by means of discrete traffic (roads, railroads) or continuous flow (pipelines, channels, cables, fibre- optics) linear facilities LF. LF are running in increasingly more congested transportation corridors and are becoming absolutely critical to our society...remember the Cardio-vascular analogy? Riskope International SA © 2009 www.riskope.com 31 April 20, 2011 Slide # 31
  • 32. Certain equipment, such a specialized ore ship loaders can take up to one year to replace. Restoration time for port facilities, can be very long and daunting....it's like being on a waiting list for a cardiac operation! Finally, the destruction or damage of the IT assets (for example Network Management Center) could also cripple the egress from a mine, and that's exactly why a European army has contracted us to deliver a consistent and rational Risk approach (not an IT approach! An information RM approach) for a whole country. Riskope International SA © 2009 www.riskope.com 32 April 20, 2011 Slide # 32
  • 33. Although managers try to avoid “complex mathematics”, hard numbers are crucial in differentiating risks incurred, sometimes by hundreds of components of a similar system (which can be anything, from a road homogeneous segment to a valve, a tank along a pipeline) leading to the need for QRAs. Riskope International SA © 2009 www.riskope.com 33 April 20, 2011 Slide # 33
  • 34. CS1: Seismic BI Riskope International SA © 2009 www.riskope.com 34 April 20, 2011 Slide # 34
  • 35. Riskope International SA © 2009 www.riskope.com 35 April 20, 2011 Slide # 35
  • 36. Conclusion was to propose a B2B strategy whereby the client would actually team-up with RR and buy replacement bridges. Insurance could be reduced and serviceability ensured in a far better way. Riskope International SA © 2009 www.riskope.com 36 April 20, 2011 Slide # 36
  • 37. CS2: Multimodal/ multihazard logistical transportation network Production End Ships to W zzzT Possible mitigation Centre X User A Routes Export XX B % pr od uc RR tio n Tunnels and Loading Bridges Tunnels and Wharves End Bridges User C Tunnels and Ships to W zzzT Bridges Production Centre Unloader Y Riskope International SA © 2009 www.riskope.com 37 April 20, 2011 Slide # 37
  • 38. Insurance can be cut in half. Authorizations and agreements should be passed in view of possible future occurrences. Riskope International SA © 2009 www.riskope.com 38 April 20, 2011 Slide # 38
  • 39. CS3: Mine’s personnel shuttling: Air plane vs buses Risk assessments can be used to help decide whether a different transportation system would be better than an existing one. Several levels of analysis are possible, the top one including CDA-ESM, an alternative comparison tool which allows considering risks and avoids all the pitfalls of NPV. Riskope International SA © 2009 www.riskope.com 39 April 20, 2011 Slide # 39
  • 40. Riskope International SA © 2009 www.riskope.com 40 April 20, 2011 Slide # 40
  • 41. Infrastructure/Logistical Networks' Risks: What can Be Done? Once the system potentially hit by disruptive event(s) is studied evaluating the limits of Force Majeure events, risks are ranked and checked towards tolerability criteria. How Can it be done? Alternatives, emergencies routes are studied and ranked, including side effects. Force Majeure clause from 3rd parties contracts should be (re)-negotiated and sustainable solutions designed. Why Should it Be Done? -help ensure critical transportation operations' reliability -rank emergency alternatives -allocate mitigative resources -faster understanding on the situation in case of a crisis situation regarding 3rd parties Riskope International SA © 2009 www.riskope.com 41 April 20, 2011 Slide # 41
  • 42. The benefits Create the basis to avoid a slide into a crisis, by proactively controlling the situation. Mind your heart and your circulatory system! Riskope International SA © 2009 www.riskope.com 42 April 20, 2011 Slide # 42