SlideShare uma empresa Scribd logo
1 de 17
Baixar para ler offline
Standar Nasional Indonesia
SNI 2837:2008
Tata cara perhitungan harga satuan pekerjaan plesteran
untuk konstruksi bangunan gedung dan perumahan
ICS 91.010.20 Badan Standardisasi Nasional
SNI 2837:2008
i
Daftar isi
Daftar isi..........................................................................................................................................i
Prakata ......................................................................................................................................... iii
Pendahuluan................................................................................................................................. iv
1 Ruang lingkup.........................................................................................................................1
2 Acuan normatif........................................................................................................................1
3 Istilah dan definisi ...................................................................................................................1
4 Singkatan istilah......................................................................................................................2
5 Persyaratan ............................................................................................................................2
6 Penetapan indeks harga satuan pekerjaan plesteran ............................................................3
6.1 Membuat 1 m2
plesteran 1 PC : 1 PP, tebal 15 mm ....................................................3
6.2 Membuat 1 m2
plesteran 1 PC : 2 PP, tebal 15 mm ....................................................3
6.3 Membuat 1 m2
plesteran 1 PC : 3 PP, tebal 15 mm ....................................................3
6.4 Membuat 1 m2
plesteran 1 PC : 4 PP, tebal 15 mm ....................................................3
6.5 Membuat 1 m2
plesteran 1 PC : 5 PP, tebal 15 mm ....................................................4
6.6 Membuat 1 m2
plesteran 1 PC : 6 PP, tebal 15 mm ....................................................4
6.7 Membuat 1 m2
plesteran 1 PC : 7 PP, tebal 15 mm ....................................................4
6.8 Membuat 1 m2
plesteran 1 PC : 8 PP, tebal 15 mm ....................................................4
6.9 Membuat 1 m2
plesteran 1 PC : ½ KP : 3 PP, tebal 15 mm ........................................5
6.10 Membuat 1 m2
plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm .........................................5
6.11 Membuat 1 m2
plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm .........................................5
6.12 Membuat 1 m2
plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm .........................................5
6.13 Membuat 1 m2
plesteran 1 PC : 2 PP, tebal 20 mm ....................................................6
6.14 Membuat 1 m2
plesteran 1 PC : 3 PP, tebal 20 mm ....................................................6
6.15 Membuat 1 m2
plesteran 1 PC : 4 PP, tebal 20 mm ....................................................6
6.16 Membuat 1 m2
plesteran 1 PC : 5 PP, tebal 20 mm ....................................................6
6.17 Membuat 1 m2
plesteran 1 PC : 6 PP, tebal 20 mm ....................................................7
6.18 Membuat 1 m2
plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm .........................................7
6.19 Membuat 1 m2
Berapen 1 PC : 5 PP, tebal 15 mm .....................................................7
6.20 Membuat 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mmError! Bookmark not defined.
6.21 Membuat 1 m2
Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm .................................8
6.22 Membuat 1 m2
Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm.....................8
6.23 Membuat 1 m2
Plesteran Ciprat 1 PC : 2 PP .................................................................8
6.24 Membuat 1 m2
finishing siar pasangan dinding bata merah (=20 m’) ..........................8
6.25 Membuat 1 m2
finishing siar pasangan dinding conblock ekspose (=8 m’)..................9
SNI 2837:2008
ii
6.26 Membuat 1 m2
finishing siar pasangan batu kali adukan 1 PC : 2 PP ..........................9
6.27 Membuat 1 m2
acian......................................................................................................9
Lampiran A...................................................................................................................................10
Bibliografi .....................................................................................................................................11
SNI 2837:2008
iii
Prakata
Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan
plesteran untuk konstruksi bangunan dan perumahan adalah revisi dari SNI 03-2837-2002,
Analisis Biaya Konstruksi (ABK) Bangunan gedung dan Perumahan Pekerjaan Plesteran,
dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja.
Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil
pada Subpanitia Teknik Bahan, Sains, Struktur, dan Konstruksi Bangunan.
Tata cara penulisan disusun mengikuti Pedoman Standardisasi Nasional Nomor 8 Tahun
2007 dan dibahas pada forum rapat konsensus pada tanggal 7 s.d 8 Desember 2006 di
Pusat Penelitian dan Pengembangan Permukiman Bandung dengan melibatkan para nara
sumber, pakar dan lembaga terkait.
SNI 2837:2008
iv
Pendahuluan
Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian
Analisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan
dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis
biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis
yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data
dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data
primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama.
Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa
proyek pembangunan gedung dan perumahan serta penelitian laboratorium bahan
bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan
pendekatan kinerja/performance dari jenis pekerjaan terkait.
DATA LAPANGAN
WAKTU DASAR INDIVIDU
WAKTU NORMAL INDIVIDU
TABULASI DATA
TES KESERAGAMAN DATA
TES KECUKUPAN DATA
WAKTU NORMAL
WAKTU STANDAR
BAHAN ANALISIS BIAYA
KONSTRUKSI/ BARU
Waktu produktif
Rating keterampilan,
mutu kerja, kondisi
kerja, cuaca, dll
Tingkat ketelitian 10% dan
tingkat keyakinam 95%
Kelonggaran
waktu/allowance
Tidak Cukup Cukup
SNI 2837:2008
1 dari 11
Tata cara perhitungan harga satuan pekerjaan plesteran
untuk konstruksi bangunan gedung dan perumahan
1 Ruang lingkup
Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan
untuk tiap satuan pekerjaan plesteran yang dapat dijadikan acuan dasar yang seragam bagi
para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga
satuan pekerjaan plesteran untuk bangunan gedung dan perumahan.
Jenis pekerjaan plesteran yang ditetapkan meliputi pekerjaan plesteran dalam berbagai
ketebalan dan campuran, berapen dan penyelesaian akhir/ acian.
2 Acuan normatif
Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisis pekerjaan yang
telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921
dan penelitian analisis biaya konstruksi.
3 Istilah dan definisi
3.1
bangunan gedung dan perumahan
bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat
3.2
harga satuan bahan
harga yang sesuai dengan satuan jenis bahan bangunan
3.3
harga satuan pekerjaan
harga yang dihitung berdasarkan analisis harga satuan bahan dan upah
3.4
indeks
faktor pengali atau koefisien sebagai dasar perhitungan biaya bahan dan upah kerja
3.5
indeks bahan
indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis
pekerjaan
3.6
indeks tenaga kerja
indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis
pekerjaan
SNI 2837:2008
2 dari 11
3.7
pelaksana pembangunan gedung dan perumahan
pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana,
konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan
3.8
perhitungan harga satuan pekerjaan konstruksi
suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian
indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar
pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi
3.9
satuan pekerjaan
satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas,
volume dan unit
4 Singkatan istilah
Singkatan Kepanjangan Istilah/arti
mm milimeter Satuan panjang
kg kilogram Satuan berat
m’ meter panjang Satuan panjang
m2
meter persegi Satuan luas
m3
meter kubik Satuan volume
OH Orang Hari Satuan tenaga kerja per hari
PC Portland Cement Semen portland
PP Pasir pasang Agregat halus ukuran ≤ 5 mm
KP Kapur padam Kapur tohor yang dipadamkan
SM Semen merah Semen hasil tumbukan bata merah
5 Persyaratan
5.1 Persyaratan umum
Persyaratan umum dalam perhitungan harga satuan:
a) Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia,
berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat;
b) Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar
spesifikasi teknis pekerjaan yang telah dibakukan.
5.2 Persyaratan teknis
Persyaratan teknis dalam perhitungan harga satuan pekerjaan:
a) Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan
rencana kerja serta syarat-syarat (RKS);
b) Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di
dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan
komposisi adukan;
c) Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam perhari.
SNI 2837:2008
3 dari 11
6 Penetapan indeks harga satuan pekerjaan plesteran
6.1 Membuat 1 m2
plesteran 1 PC : 1 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC Kg 15,504
PP M3
0,016
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.2 Membuat 1 m2
plesteran 1 PC : 2 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC Kg 10,224
PP M3
0,020
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.3 Membuat 1 m2
plesteran 1 PC : 3 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC Kg 7,776
PP M3
0,023
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.4 Membuat 1 m2
plesteran 1 PC : 4 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC Kg 6,240
PP M3
0,024
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
SNI 2837:2008
4 dari 11
6.5 Membuat 1 m2
plesteran 1 PC : 5 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 5,184
PP m3
0,026
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.6 Membuat 1 m2
plesteran 1 PC : 6 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 4,416
PP m3
0,027
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.7 Membuat 1 m2
plesteran 1 PC : 7 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 3,936
PP m3
0,028
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.8 Membuat 1 m2
plesteran 1 PC : 8 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 3,456
PP m3
0,029
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
SNI 2837:2008
5 dari 11
6.9 Membuat 1 m2
plesteran 1 PC : ½ KP : 3 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 5,760
KP m3
0,003
PP m3
0,013
Tenaga kerja
Pekerja OH 0,360
Tukang batu OH 0,120
Kepala tukang OH 0,012
Mandor OH 0,018
6.10 Membuat 1 m2
plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 3,000
KP m3
0,005
PP m3
0,020
Tenaga kerja
Pekerja OH 0,360
Tukang batu OH 0,120
Kepala tukang OH 0,012
Mandor OH 0,018
6.11 Membuat 1 m2
plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
SM m3
0,009
KP m3
0,009
PP m3
0,009
Tenaga kerja
Pekerja OH 0,360
Tukang batu OH 0,120
Kepala tukang OH 0,012
Mandor OH 0,018
6.12 Membuat 1 m2
plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
SM m3
0,007
KP m3
0,007
PP m3
0,015
Tenaga kerja
Pekerja OH 0,360
Tukang batu OH 0,120
Kepala tukang OH 0,012
Mandor OH 0,018
SNI 2837:2008
6 dari 11
6.13 Membuat 1 m2
plesteran 1 PC : 2 PP, tebal 20 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 13,632
PP m3
0,027
Tenaga kerja
Pekerja OH 0,400
Tukang batu OH 0,200
Kepala tukang OH 0,020
Mandor OH 0,022
6.14 Membuat 1 m2
plesteran 1 PC : 3 PP, tebal 20 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 10,368
PP m3
0,031
Tenaga kerja
Pekerja OH 0,260
Tukang batu OH 0,200
Kepala tukang OH 0,020
Mandor OH 0,013
6.15 Membuat 1 m2
plesteran 1 PC : 4 PP, tebal 20 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 8,320
PP m3
0,032
Tenaga kerja
Pekerja OH 0,400
Tukang batu OH 0,200
Kepala tukang OH 0,020
Mandor OH 0,022
6.16 Membuat 1 m2
plesteran 1 PC : 5 PP, tebal 20 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 6,912
PP m3
0,035
Tenaga kerja
Pekerja OH 0,400
Tukang batu OH 0,200
Kepala tukang OH 0,020
Mandor OH 0,022
SNI 2837:2008
7 dari 11
6.17 Membuat 1 m2
plesteran 1 PC : 6 PP, tebal 20 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 5,888
PP m3
0,036
Tenaga kerja
Pekerja OH 0,400
Tukang batu OH 0,200
Kepala tukang OH 0,020
Mandor OH 0,022
6.18 Membuat 1 m2
plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm
Kebutuhan Satuan Indeks
Bahan
SM m3
0,009
KP m3
0,009
PP m3
0,018
Tenaga kerja
Pekerja OH 0,440
Tukang batu OH 0,220
Kepala tukang OH 0,022
Mandor OH 0,022
6.19 Membuat 1 m2
Berapen 1 PC : 5 PP, tebal 15 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 5,184
PP m3
0,026
Tenaga kerja
Pekerja OH 0,150
Tukang batu OH 0,075
Kepala tukang OH 0,008
Mandor OH 0,008
6.20 Membuat 1 m’ Plesteran Skoning lebar 10 mm 1 PC : 2 PP.
Kebutuhan Satuan Indeks
Bahan
PC kg 0,500
PP m3
0,013
Tenaga kerja
Pekerja OH 0,080
Tukang batu OH 0,400
Kepala tukang OH 0,040
Mandor OH 0,004
SNI 2837:2008
8 dari 11
6.21 Membuat 1 m2
Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 10,000
Batu granit kg 15,000
Tenaga kerja
Pekerja OH 0,450
Tukang batu OH 0,225
Kepala tukang OH 0,023
Mandor OH 0,023
6.22 Membuat 1 m2
Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm
Kebutuhan Satuan Indeks
Bahan
PC kg 10,000
Batu teraso kg 15,000
Tenaga kerja
Pekerja OH 0,450
Tukang batu OH 0,225
Kepala tukang OH 0,023
Mandor OH 0,023
6.23 Membuat 1 m2
Plesteran Ciprat / Kamprotan 1 PC : 2 PP
Kebutuhan Satuan Indeks
Bahan
PC kg 4,320
PP m3
0,006
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,100
Kepala tukang OH 0,010
Mandor OH 0,015
6.24 Membuat 1 m2
finishing siar pasangan dinding bata merah (=20 m’)
Kebutuhan Satuan Indeks
Bahan PC kg 3,108
Tenaga kerja
Pekerja OH 0,150
Tukang batu OH 0,075
Kepala tukang OH 0,008
Mandor OH 0,008
SNI 2837:2008
9 dari 11
6.25 Membuat 1 m2
finishing siar pasangan dinding conblock ekspose (=8 m’)
Kebutuhan Satuan Indeks
Bahan PC kg 1,600
Tenaga kerja
Pekerja OH 0,070
Tukang batu OH 0,035
Kepala tukang OH 0,004
Mandor OH 0,004
6.26 Membuat 1 m2
finishing siar pasangan batu kali adukan 1 PC : 2 PP
Kebutuhan Satuan Indeks
Bahan
PC kg 6,340
PP m3
0,012
Tenaga kerja
Pekerja OH 0,300
Tukang batu OH 0,150
Kepala tukang OH 0,015
Mandor OH 0,015
6.27 Membuat 1 m2
acian
Kebutuhan Satuan Indeks
Bahan PC kg 3,250
Tenaga kerja
Pekerja OH 0,200
Tukang batu OH 0,100
Kepala tukang OH 0,010
Mandor OH 0,010
SNI 2837:2008
10 dari 11
Lampiran A
(Informatif)
Contoh penggunaan standar untuk menghitung harga satuan pekerjaan
A.1 Membuat 1 m2
acian
Kebutuhan Satuan Indeks
Harga Satuan
Bahan/Upah
(Rp.)
Jumlah
(Rp.)
Bahan PP kg 3,250 400 1.300
Tenaga kerja
Pekerja OH 0,200 30.000 6.000
Tukang batu OH 0,100 40.000 4.000
Kepala tukang OH 0,010 50.000 500
Mandor OH 0,010 60.000 450
Jumlah harga per satuan pekerjaan 12.250
SNI 2837:2008
11 dari 11
Bibliografi
SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam)
SNI 03-6862-2002, Spesifikasi peralatan pemasangan dinding bata dan plesteran
SNI 03-2410-1991, Tata cara pengecatan dinding tembok dengan cat emulsi
Pt-T-03-2000-C, Tata cara pengerjaan pasangan dan plesteran dinding
Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil
penelitian), tahun 1988–1991

Mais conteúdo relacionado

Mais procurados

Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...
Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...
Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...Ellan Syahnoorizal Siregar
 
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...Ellan Syahnoorizal Siregar
 
3. analisa harga satuan
3. analisa harga satuan3. analisa harga satuan
3. analisa harga satuanim4m90
 
Metoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet PileMetoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet PileIMRA MORALDY
 
Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)Ferdinand Nanubmat
 
Analisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjongAnalisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjongroxzjack
 
Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniter
Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan SaniterTata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniter
Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniterinfosanitasi
 
Sni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatanSni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatanterbott
 
Sni 20dt 2091-0008-2007-beton
Sni 20dt 2091-0008-2007-betonSni 20dt 2091-0008-2007-beton
Sni 20dt 2091-0008-2007-betoncakagha1307
 
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan GedungSNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan GedungMira Pemayun
 
Rsni t 12-2004
Rsni t 12-2004Rsni t 12-2004
Rsni t 12-2004iky
 
Analisa jembatan titian ulin
Analisa jembatan titian ulinAnalisa jembatan titian ulin
Analisa jembatan titian ulinFeby Kurniawan
 
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenPd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenSyukri Ghazali
 
Sni 03-2834-2000
Sni 03-2834-2000Sni 03-2834-2000
Sni 03-2834-2000frans1982
 

Mais procurados (20)

Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...
Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...
Sni 7393-2008-tata cara perhitungan harga satuan pekerjaan besi dan aluminium...
 
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
Sni 2835-2008-tata cara perhitungan harga satuan pekerjaan tanah untuk konstr...
 
3. analisa harga satuan
3. analisa harga satuan3. analisa harga satuan
3. analisa harga satuan
 
Analisa harga satuan
Analisa harga satuanAnalisa harga satuan
Analisa harga satuan
 
Analisa harga satuan jasa
Analisa harga satuan jasaAnalisa harga satuan jasa
Analisa harga satuan jasa
 
Pekerjaan pondasi
Pekerjaan pondasiPekerjaan pondasi
Pekerjaan pondasi
 
Metoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet PileMetoda pelaksanaan Sheet Pile
Metoda pelaksanaan Sheet Pile
 
Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)Analisa harga satuan pekerjaan (1)
Analisa harga satuan pekerjaan (1)
 
Desa sukaratu
Desa sukaratuDesa sukaratu
Desa sukaratu
 
Analisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjongAnalisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjong
 
Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniter
Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan SaniterTata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniter
Tata Cara Perhitungan Harga Satuan Pekerjaan Pipa dan Saniter
 
Sni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatanSni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatan
 
Sni 2008
Sni 2008Sni 2008
Sni 2008
 
Sni pekbeton 2008
Sni pekbeton 2008Sni pekbeton 2008
Sni pekbeton 2008
 
Sni 20dt 2091-0008-2007-beton
Sni 20dt 2091-0008-2007-betonSni 20dt 2091-0008-2007-beton
Sni 20dt 2091-0008-2007-beton
 
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan GedungSNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
SNI 2847-2013 Persyaratan Beton Struktural Untuk Bangunan Gedung
 
Rsni t 12-2004
Rsni t 12-2004Rsni t 12-2004
Rsni t 12-2004
 
Analisa jembatan titian ulin
Analisa jembatan titian ulinAnalisa jembatan titian ulin
Analisa jembatan titian ulin
 
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenPd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
 
Sni 03-2834-2000
Sni 03-2834-2000Sni 03-2834-2000
Sni 03-2834-2000
 

Semelhante a Sni 2837-2008-tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumamahan

Sni 7394-2008 hit beton tulang
Sni 7394-2008 hit beton tulangSni 7394-2008 hit beton tulang
Sni 7394-2008 hit beton tulangRonny wisanggeni
 
SNI 3434_2008 Pekerjaan Kayu SNI.pdf
SNI 3434_2008 Pekerjaan Kayu SNI.pdfSNI 3434_2008 Pekerjaan Kayu SNI.pdf
SNI 3434_2008 Pekerjaan Kayu SNI.pdfssuser1c78c8
 
Revisi sni 03 2835-2002
Revisi sni 03 2835-2002Revisi sni 03 2835-2002
Revisi sni 03 2835-2002Erwin Rakasi
 
50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...
50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...
50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...yna962
 
Sni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dinding
Sni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dindingSni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dinding
Sni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dindingWiwin Kurniawan
 
PENGANTAR RAB.pptx
PENGANTAR RAB.pptxPENGANTAR RAB.pptx
PENGANTAR RAB.pptxAanAlFikri
 
Lembar pengesahan dan daftar isi
Lembar pengesahan dan daftar  isiLembar pengesahan dan daftar  isi
Lembar pengesahan dan daftar isiAndriansyah Tsk
 
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air MinumPedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minuminfosanitasi
 
Research Proposal Business Presentation in Dark Green Orange Geometric Style....
Research Proposal Business Presentation in Dark Green Orange Geometric Style....Research Proposal Business Presentation in Dark Green Orange Geometric Style....
Research Proposal Business Presentation in Dark Green Orange Geometric Style....RyoAryawan2
 
Analisa biaya dan waktu
Analisa biaya dan waktuAnalisa biaya dan waktu
Analisa biaya dan waktuudin2234
 
KAK Gedung Sekwan 2022.pdf
KAK Gedung  Sekwan 2022.pdfKAK Gedung  Sekwan 2022.pdf
KAK Gedung Sekwan 2022.pdfBUATDONLOTAJA
 
Sni 1742 2008 (proctor)
Sni 1742 2008 (proctor)Sni 1742 2008 (proctor)
Sni 1742 2008 (proctor)MuhammadToyeb
 
Pedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdf
Pedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdfPedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdf
Pedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdfHeruPrasetyaA1
 
2. sni-2835-2008-pekerjaan-tanah
2. sni-2835-2008-pekerjaan-tanah2. sni-2835-2008-pekerjaan-tanah
2. sni-2835-2008-pekerjaan-tanahEka Faisal
 
SNI 06-4829-1998_Pipa PE untuk Air Minum.pdf
SNI 06-4829-1998_Pipa PE untuk Air Minum.pdfSNI 06-4829-1998_Pipa PE untuk Air Minum.pdf
SNI 06-4829-1998_Pipa PE untuk Air Minum.pdfKiaraLeswara
 
MAKALAH PEMBUATAN SILINDER BETON.docx
MAKALAH PEMBUATAN SILINDER BETON.docxMAKALAH PEMBUATAN SILINDER BETON.docx
MAKALAH PEMBUATAN SILINDER BETON.docxHANIFAZAHRAAMALIA
 
02. Definisi DED, RKS dan RAB.pdf
02. Definisi DED, RKS dan RAB.pdf02. Definisi DED, RKS dan RAB.pdf
02. Definisi DED, RKS dan RAB.pdfAsriAdi20
 

Semelhante a Sni 2837-2008-tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumamahan (20)

Sni 7394-2008 hit beton tulang
Sni 7394-2008 hit beton tulangSni 7394-2008 hit beton tulang
Sni 7394-2008 hit beton tulang
 
SNI 3434_2008 Pekerjaan Kayu SNI.pdf
SNI 3434_2008 Pekerjaan Kayu SNI.pdfSNI 3434_2008 Pekerjaan Kayu SNI.pdf
SNI 3434_2008 Pekerjaan Kayu SNI.pdf
 
Revisi sni 03 2835-2002
Revisi sni 03 2835-2002Revisi sni 03 2835-2002
Revisi sni 03 2835-2002
 
50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...
50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...
50125213 sni-dt-91-0014-2007-tata-cara-perhitungan-harga-satuan-pek-besi-alum...
 
Sni 7393 2008
Sni 7393 2008Sni 7393 2008
Sni 7393 2008
 
Sni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dinding
Sni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dindingSni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dinding
Sni dt-91-0009-2007-tata-cara-perhitungan-harga-satuan-pekerjaan-dinding
 
PENGANTAR RAB.pptx
PENGANTAR RAB.pptxPENGANTAR RAB.pptx
PENGANTAR RAB.pptx
 
Lembar pengesahan dan daftar isi
Lembar pengesahan dan daftar  isiLembar pengesahan dan daftar  isi
Lembar pengesahan dan daftar isi
 
Galo2 kp
Galo2 kpGalo2 kp
Galo2 kp
 
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air MinumPedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
 
Sni 2827 2008
Sni 2827 2008Sni 2827 2008
Sni 2827 2008
 
Research Proposal Business Presentation in Dark Green Orange Geometric Style....
Research Proposal Business Presentation in Dark Green Orange Geometric Style....Research Proposal Business Presentation in Dark Green Orange Geometric Style....
Research Proposal Business Presentation in Dark Green Orange Geometric Style....
 
Analisa biaya dan waktu
Analisa biaya dan waktuAnalisa biaya dan waktu
Analisa biaya dan waktu
 
KAK Gedung Sekwan 2022.pdf
KAK Gedung  Sekwan 2022.pdfKAK Gedung  Sekwan 2022.pdf
KAK Gedung Sekwan 2022.pdf
 
Sni 1742 2008 (proctor)
Sni 1742 2008 (proctor)Sni 1742 2008 (proctor)
Sni 1742 2008 (proctor)
 
Pedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdf
Pedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdfPedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdf
Pedoman Pelaksanaan Konstruksi Bangunan Dan Bukit Tes Tsunami - Buku 10 (1).pdf
 
2. sni-2835-2008-pekerjaan-tanah
2. sni-2835-2008-pekerjaan-tanah2. sni-2835-2008-pekerjaan-tanah
2. sni-2835-2008-pekerjaan-tanah
 
SNI 06-4829-1998_Pipa PE untuk Air Minum.pdf
SNI 06-4829-1998_Pipa PE untuk Air Minum.pdfSNI 06-4829-1998_Pipa PE untuk Air Minum.pdf
SNI 06-4829-1998_Pipa PE untuk Air Minum.pdf
 
MAKALAH PEMBUATAN SILINDER BETON.docx
MAKALAH PEMBUATAN SILINDER BETON.docxMAKALAH PEMBUATAN SILINDER BETON.docx
MAKALAH PEMBUATAN SILINDER BETON.docx
 
02. Definisi DED, RKS dan RAB.pdf
02. Definisi DED, RKS dan RAB.pdf02. Definisi DED, RKS dan RAB.pdf
02. Definisi DED, RKS dan RAB.pdf
 

Último

Stoikiometri kelas 10 kurikulum Merdeka.ppt
Stoikiometri kelas 10 kurikulum Merdeka.pptStoikiometri kelas 10 kurikulum Merdeka.ppt
Stoikiometri kelas 10 kurikulum Merdeka.pptannanurkhasanah2
 
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdfMODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdfAndiCoc
 
Kanvas BAGJA prakarsa perubahan Ahyar.pdf
Kanvas BAGJA prakarsa perubahan Ahyar.pdfKanvas BAGJA prakarsa perubahan Ahyar.pdf
Kanvas BAGJA prakarsa perubahan Ahyar.pdfAkhyar33
 
MODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdfAndiCoc
 
Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...
Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...
Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...pipinafindraputri1
 
Aksi Nyata PMM Topik Refleksi Diri (1).pdf
Aksi Nyata PMM Topik Refleksi Diri (1).pdfAksi Nyata PMM Topik Refleksi Diri (1).pdf
Aksi Nyata PMM Topik Refleksi Diri (1).pdfEniNuraeni29
 
RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...
RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...
RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...Kanaidi ken
 
Refleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptx
Refleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptxRefleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptx
Refleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptxIrfanAudah1
 
Materi Sosialisasi US 2024 Sekolah Dasar pptx
Materi Sosialisasi US 2024 Sekolah Dasar pptxMateri Sosialisasi US 2024 Sekolah Dasar pptx
Materi Sosialisasi US 2024 Sekolah Dasar pptxSaujiOji
 
BAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptx
BAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptxBAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptx
BAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptxJuliBriana2
 
MODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKA
MODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKAMODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKA
MODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKAAndiCoc
 
PPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptx
PPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptxPPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptx
PPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptxdpp11tya
 
Contoh PPT Seminar Proposal Teknik Informatika.pptx
Contoh PPT Seminar Proposal Teknik Informatika.pptxContoh PPT Seminar Proposal Teknik Informatika.pptx
Contoh PPT Seminar Proposal Teknik Informatika.pptxIvvatulAini
 
KELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKA
KELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKAKELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKA
KELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKAppgauliananda03
 
SOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAY
SOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAYSOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAY
SOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAYNovitaDewi98
 
power point bahasa indonesia "Karya Ilmiah"
power point bahasa indonesia "Karya Ilmiah"power point bahasa indonesia "Karya Ilmiah"
power point bahasa indonesia "Karya Ilmiah"baimmuhammad71
 
Pelaksana Lapangan Pekerjaan Jalan .pptx
Pelaksana Lapangan Pekerjaan Jalan .pptxPelaksana Lapangan Pekerjaan Jalan .pptx
Pelaksana Lapangan Pekerjaan Jalan .pptxboynugraha727
 
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptxPPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptxriscacriswanda
 
Kenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).pptKenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).pptnovibernadina
 
PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...
PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...
PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...Kanaidi ken
 

Último (20)

Stoikiometri kelas 10 kurikulum Merdeka.ppt
Stoikiometri kelas 10 kurikulum Merdeka.pptStoikiometri kelas 10 kurikulum Merdeka.ppt
Stoikiometri kelas 10 kurikulum Merdeka.ppt
 
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdfMODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL PENDIDIKAN PANCASILA KELAS 6 KURIKULUM MERDEKA.pdf
 
Kanvas BAGJA prakarsa perubahan Ahyar.pdf
Kanvas BAGJA prakarsa perubahan Ahyar.pdfKanvas BAGJA prakarsa perubahan Ahyar.pdf
Kanvas BAGJA prakarsa perubahan Ahyar.pdf
 
MODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INDONESIA KELAS 6 KURIKULUM MERDEKA.pdf
 
Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...
Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...
Modul 2 - Bagaimana membangun lingkungan belajar yang mendukung transisi PAUD...
 
Aksi Nyata PMM Topik Refleksi Diri (1).pdf
Aksi Nyata PMM Topik Refleksi Diri (1).pdfAksi Nyata PMM Topik Refleksi Diri (1).pdf
Aksi Nyata PMM Topik Refleksi Diri (1).pdf
 
RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...
RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...
RENCANA & Link2 Materi Pelatihan_ "Teknik Perhitungan TKDN, BMP, Preferensi H...
 
Refleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptx
Refleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptxRefleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptx
Refleksi Mandiri Modul 1.3 - KANVAS BAGJA.pptx.pptx
 
Materi Sosialisasi US 2024 Sekolah Dasar pptx
Materi Sosialisasi US 2024 Sekolah Dasar pptxMateri Sosialisasi US 2024 Sekolah Dasar pptx
Materi Sosialisasi US 2024 Sekolah Dasar pptx
 
BAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptx
BAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptxBAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptx
BAB 5 KERJASAMA DALAM BERBAGAI BIDANG KEHIDUPAN.pptx
 
MODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKA
MODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKAMODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKA
MODUL AJAR IPAS KELAS 6 KURIKULUM MERDEKA
 
PPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptx
PPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptxPPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptx
PPT PERUBAHAN LINGKUNGAN MATA PELAJARAN BIOLOGI KELAS X.pptx
 
Contoh PPT Seminar Proposal Teknik Informatika.pptx
Contoh PPT Seminar Proposal Teknik Informatika.pptxContoh PPT Seminar Proposal Teknik Informatika.pptx
Contoh PPT Seminar Proposal Teknik Informatika.pptx
 
KELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKA
KELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKAKELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKA
KELAS 10 PERUBAHAN LINGKUNGAN SMA KURIKULUM MERDEKA
 
SOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAY
SOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAYSOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAY
SOAL PUBLIC SPEAKING UNTUK PEMULA PG & ESSAY
 
power point bahasa indonesia "Karya Ilmiah"
power point bahasa indonesia "Karya Ilmiah"power point bahasa indonesia "Karya Ilmiah"
power point bahasa indonesia "Karya Ilmiah"
 
Pelaksana Lapangan Pekerjaan Jalan .pptx
Pelaksana Lapangan Pekerjaan Jalan .pptxPelaksana Lapangan Pekerjaan Jalan .pptx
Pelaksana Lapangan Pekerjaan Jalan .pptx
 
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptxPPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
PPT MODUL 6 DAN 7 PDGK4105 KELOMPOK.pptx
 
Kenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).pptKenakalan Remaja (Penggunaan Narkoba).ppt
Kenakalan Remaja (Penggunaan Narkoba).ppt
 
PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...
PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...
PELAKSANAAN + Link2 Materi BimTek _PTK 007 Rev-5 Thn 2023 (PENGADAAN) & Perhi...
 

Sni 2837-2008-tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumamahan

  • 1. Standar Nasional Indonesia SNI 2837:2008 Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumahan ICS 91.010.20 Badan Standardisasi Nasional
  • 2.
  • 3. SNI 2837:2008 i Daftar isi Daftar isi..........................................................................................................................................i Prakata ......................................................................................................................................... iii Pendahuluan................................................................................................................................. iv 1 Ruang lingkup.........................................................................................................................1 2 Acuan normatif........................................................................................................................1 3 Istilah dan definisi ...................................................................................................................1 4 Singkatan istilah......................................................................................................................2 5 Persyaratan ............................................................................................................................2 6 Penetapan indeks harga satuan pekerjaan plesteran ............................................................3 6.1 Membuat 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm ....................................................3 6.2 Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm ....................................................3 6.3 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm ....................................................3 6.4 Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm ....................................................3 6.5 Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm ....................................................4 6.6 Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm ....................................................4 6.7 Membuat 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm ....................................................4 6.8 Membuat 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm ....................................................4 6.9 Membuat 1 m2 plesteran 1 PC : ½ KP : 3 PP, tebal 15 mm ........................................5 6.10 Membuat 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm .........................................5 6.11 Membuat 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm .........................................5 6.12 Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm .........................................5 6.13 Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm ....................................................6 6.14 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm ....................................................6 6.15 Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm ....................................................6 6.16 Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm ....................................................6 6.17 Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm ....................................................7 6.18 Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm .........................................7 6.19 Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm .....................................................7 6.20 Membuat 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mmError! Bookmark not defined. 6.21 Membuat 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm .................................8 6.22 Membuat 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm.....................8 6.23 Membuat 1 m2 Plesteran Ciprat 1 PC : 2 PP .................................................................8 6.24 Membuat 1 m2 finishing siar pasangan dinding bata merah (=20 m’) ..........................8 6.25 Membuat 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’)..................9
  • 4. SNI 2837:2008 ii 6.26 Membuat 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP ..........................9 6.27 Membuat 1 m2 acian......................................................................................................9 Lampiran A...................................................................................................................................10 Bibliografi .....................................................................................................................................11
  • 5. SNI 2837:2008 iii Prakata Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan dan perumahan adalah revisi dari SNI 03-2837-2002, Analisis Biaya Konstruksi (ABK) Bangunan gedung dan Perumahan Pekerjaan Plesteran, dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja. Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil pada Subpanitia Teknik Bahan, Sains, Struktur, dan Konstruksi Bangunan. Tata cara penulisan disusun mengikuti Pedoman Standardisasi Nasional Nomor 8 Tahun 2007 dan dibahas pada forum rapat konsensus pada tanggal 7 s.d 8 Desember 2006 di Pusat Penelitian dan Pengembangan Permukiman Bandung dengan melibatkan para nara sumber, pakar dan lembaga terkait.
  • 6. SNI 2837:2008 iv Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Analisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan serta penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait. DATA LAPANGAN WAKTU DASAR INDIVIDU WAKTU NORMAL INDIVIDU TABULASI DATA TES KESERAGAMAN DATA TES KECUKUPAN DATA WAKTU NORMAL WAKTU STANDAR BAHAN ANALISIS BIAYA KONSTRUKSI/ BARU Waktu produktif Rating keterampilan, mutu kerja, kondisi kerja, cuaca, dll Tingkat ketelitian 10% dan tingkat keyakinam 95% Kelonggaran waktu/allowance Tidak Cukup Cukup
  • 7. SNI 2837:2008 1 dari 11 Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumahan 1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan plesteran yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan plesteran untuk bangunan gedung dan perumahan. Jenis pekerjaan plesteran yang ditetapkan meliputi pekerjaan plesteran dalam berbagai ketebalan dan campuran, berapen dan penyelesaian akhir/ acian. 2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisis pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi. 3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar perhitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan 3.6 indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan
  • 8. SNI 2837:2008 2 dari 11 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, volume dan unit 4 Singkatan istilah Singkatan Kepanjangan Istilah/arti mm milimeter Satuan panjang kg kilogram Satuan berat m’ meter panjang Satuan panjang m2 meter persegi Satuan luas m3 meter kubik Satuan volume OH Orang Hari Satuan tenaga kerja per hari PC Portland Cement Semen portland PP Pasir pasang Agregat halus ukuran ≤ 5 mm KP Kapur padam Kapur tohor yang dipadamkan SM Semen merah Semen hasil tumbukan bata merah 5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a) Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b) Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a) Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b) Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c) Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam perhari.
  • 9. SNI 2837:2008 3 dari 11 6 Penetapan indeks harga satuan pekerjaan plesteran 6.1 Membuat 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC Kg 15,504 PP M3 0,016 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.2 Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC Kg 10,224 PP M3 0,020 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.3 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC Kg 7,776 PP M3 0,023 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.4 Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC Kg 6,240 PP M3 0,024 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015
  • 10. SNI 2837:2008 4 dari 11 6.5 Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 5,184 PP m3 0,026 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.6 Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 4,416 PP m3 0,027 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.7 Membuat 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 3,936 PP m3 0,028 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.8 Membuat 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 3,456 PP m3 0,029 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015
  • 11. SNI 2837:2008 5 dari 11 6.9 Membuat 1 m2 plesteran 1 PC : ½ KP : 3 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 5,760 KP m3 0,003 PP m3 0,013 Tenaga kerja Pekerja OH 0,360 Tukang batu OH 0,120 Kepala tukang OH 0,012 Mandor OH 0,018 6.10 Membuat 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 3,000 KP m3 0,005 PP m3 0,020 Tenaga kerja Pekerja OH 0,360 Tukang batu OH 0,120 Kepala tukang OH 0,012 Mandor OH 0,018 6.11 Membuat 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan SM m3 0,009 KP m3 0,009 PP m3 0,009 Tenaga kerja Pekerja OH 0,360 Tukang batu OH 0,120 Kepala tukang OH 0,012 Mandor OH 0,018 6.12 Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan SM m3 0,007 KP m3 0,007 PP m3 0,015 Tenaga kerja Pekerja OH 0,360 Tukang batu OH 0,120 Kepala tukang OH 0,012 Mandor OH 0,018
  • 12. SNI 2837:2008 6 dari 11 6.13 Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm Kebutuhan Satuan Indeks Bahan PC kg 13,632 PP m3 0,027 Tenaga kerja Pekerja OH 0,400 Tukang batu OH 0,200 Kepala tukang OH 0,020 Mandor OH 0,022 6.14 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm Kebutuhan Satuan Indeks Bahan PC kg 10,368 PP m3 0,031 Tenaga kerja Pekerja OH 0,260 Tukang batu OH 0,200 Kepala tukang OH 0,020 Mandor OH 0,013 6.15 Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm Kebutuhan Satuan Indeks Bahan PC kg 8,320 PP m3 0,032 Tenaga kerja Pekerja OH 0,400 Tukang batu OH 0,200 Kepala tukang OH 0,020 Mandor OH 0,022 6.16 Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm Kebutuhan Satuan Indeks Bahan PC kg 6,912 PP m3 0,035 Tenaga kerja Pekerja OH 0,400 Tukang batu OH 0,200 Kepala tukang OH 0,020 Mandor OH 0,022
  • 13. SNI 2837:2008 7 dari 11 6.17 Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm Kebutuhan Satuan Indeks Bahan PC kg 5,888 PP m3 0,036 Tenaga kerja Pekerja OH 0,400 Tukang batu OH 0,200 Kepala tukang OH 0,020 Mandor OH 0,022 6.18 Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm Kebutuhan Satuan Indeks Bahan SM m3 0,009 KP m3 0,009 PP m3 0,018 Tenaga kerja Pekerja OH 0,440 Tukang batu OH 0,220 Kepala tukang OH 0,022 Mandor OH 0,022 6.19 Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm Kebutuhan Satuan Indeks Bahan PC kg 5,184 PP m3 0,026 Tenaga kerja Pekerja OH 0,150 Tukang batu OH 0,075 Kepala tukang OH 0,008 Mandor OH 0,008 6.20 Membuat 1 m’ Plesteran Skoning lebar 10 mm 1 PC : 2 PP. Kebutuhan Satuan Indeks Bahan PC kg 0,500 PP m3 0,013 Tenaga kerja Pekerja OH 0,080 Tukang batu OH 0,400 Kepala tukang OH 0,040 Mandor OH 0,004
  • 14. SNI 2837:2008 8 dari 11 6.21 Membuat 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm Kebutuhan Satuan Indeks Bahan PC kg 10,000 Batu granit kg 15,000 Tenaga kerja Pekerja OH 0,450 Tukang batu OH 0,225 Kepala tukang OH 0,023 Mandor OH 0,023 6.22 Membuat 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm Kebutuhan Satuan Indeks Bahan PC kg 10,000 Batu teraso kg 15,000 Tenaga kerja Pekerja OH 0,450 Tukang batu OH 0,225 Kepala tukang OH 0,023 Mandor OH 0,023 6.23 Membuat 1 m2 Plesteran Ciprat / Kamprotan 1 PC : 2 PP Kebutuhan Satuan Indeks Bahan PC kg 4,320 PP m3 0,006 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,100 Kepala tukang OH 0,010 Mandor OH 0,015 6.24 Membuat 1 m2 finishing siar pasangan dinding bata merah (=20 m’) Kebutuhan Satuan Indeks Bahan PC kg 3,108 Tenaga kerja Pekerja OH 0,150 Tukang batu OH 0,075 Kepala tukang OH 0,008 Mandor OH 0,008
  • 15. SNI 2837:2008 9 dari 11 6.25 Membuat 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’) Kebutuhan Satuan Indeks Bahan PC kg 1,600 Tenaga kerja Pekerja OH 0,070 Tukang batu OH 0,035 Kepala tukang OH 0,004 Mandor OH 0,004 6.26 Membuat 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP Kebutuhan Satuan Indeks Bahan PC kg 6,340 PP m3 0,012 Tenaga kerja Pekerja OH 0,300 Tukang batu OH 0,150 Kepala tukang OH 0,015 Mandor OH 0,015 6.27 Membuat 1 m2 acian Kebutuhan Satuan Indeks Bahan PC kg 3,250 Tenaga kerja Pekerja OH 0,200 Tukang batu OH 0,100 Kepala tukang OH 0,010 Mandor OH 0,010
  • 16. SNI 2837:2008 10 dari 11 Lampiran A (Informatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Membuat 1 m2 acian Kebutuhan Satuan Indeks Harga Satuan Bahan/Upah (Rp.) Jumlah (Rp.) Bahan PP kg 3,250 400 1.300 Tenaga kerja Pekerja OH 0,200 30.000 6.000 Tukang batu OH 0,100 40.000 4.000 Kepala tukang OH 0,010 50.000 500 Mandor OH 0,010 60.000 450 Jumlah harga per satuan pekerjaan 12.250
  • 17. SNI 2837:2008 11 dari 11 Bibliografi SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) SNI 03-6862-2002, Spesifikasi peralatan pemasangan dinding bata dan plesteran SNI 03-2410-1991, Tata cara pengecatan dinding tembok dengan cat emulsi Pt-T-03-2000-C, Tata cara pengerjaan pasangan dan plesteran dinding Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil penelitian), tahun 1988–1991