5. Indore City Bus: Project Basics
Number of routes
::
Average route length ::
Number of bus stops ::
Fleet Size
::
Operating frequency ::
Avg. daily ridership ::
15
18 km
210
95 buses
8 - 26 minutes
80,000 pax
6. Indore City Bus: Contributions
Started in 2006
Lives saved due to Indore City
Bus : 6.25 /year
Hundreds of accidents avoided
CO2 Reduced : ~5.5 ton/day
16% passenger mode-shift from
private vehicles
8. What is the concept of BRTS…
In accordance with the National Urban
Transport Policy – 2006, the objective is to
“moving people, not vehicles”
9. iBus: Project Basics
Initiated
• 2007
Length of route
• 11.46 km
Road section
• 31.6 / 60 metres
System type
• Closed
• Median stations
Stations
• 21
# of buses
• 18
Type of bus
• 12 m long with AC
• 900 mm Semi Low Floor
• 245 hp, BS III engine
Completion
• 31st March 2013
Operations
• 10th May 2013
Ridership
• 30,700 pax/day (avg)
10. Features of iBus
Centralized Control
Distinctive Image
Large Buses
with Wide Doors
Stations with
Prepayment and Level
Boarding
Segregated
Median
Bus-ways
10
38. Comparison with other cities…
Network Length
Ridership On The System (Pax/km/day)
Delhi Metro
8.5 km
Janmarg
Indore BRT
2,000
2,670
4,100
12.5 km
44 km
65 km
6,900
144 km
9,000
188 km
11,100
COST
230 cr/km
2,200
10 cr/km
15 cr/km
44. What is Important?
Having a plan
A cohesive and comprehensive one
Communicate the plan
To stakeholders
To general public
Create a demo?
Citizen support groups… it has to be peoples project
45. What is Important?
Institution is essential
Like a metro authority
Support systems
Having a knowledge partner: no ad-hoc decisions
Industry participation
Know where you started from…
Record base conditions
Segregate issues and communicate