SlideShare uma empresa Scribd logo
1 de 17
CONTRACT CONDITIONS-IV:
PRICE VARIATION
Dr K M Soni, ADG(Retd.), CPWD,
New Delhi
PRICE VARIATION
• Price variation in a works contract is the
variation of cost of contract in case of
increase or decrease of cost of items of work
undergoing during the period of last date of
submission of tenders and completion date
of work as per the contract
PRICE VARIATION
• Contractor submits his bids (Financial)
considering rates of items on the day of
submission of his tender
• Employer fixes the last date for submission of
tenders
• Therefore, the basis of rates are considered the
last day of submission of financial bids even if a
contractor might have submitted his bid earlier
VARIATION COMPONENTS
• A works contract has hundreds of items and
materials
• It is difficult to consider variation of rates in
each item hence a limited items are
considered for working out variations and
other included in a group of items
MAJOR COMPONENTS
• Labour
– Skilled
– unskilled
• Steel
– Reinforcement bars
– Structural steel
• Cement
– OPC
– PPC
• POL
• Bitumen
• Others
LABOUR
Unskilled 13584 13896 1.023
Semiskilled 14958 15296 1.023
Skilled 16468 16858 1.024
As seen, rate increase is almost with same percentage
hence rates for
unskilled worker are considered in the analysis
STEEL
• Reinforcement bars
– TMT
– Fe 415
– Fe 500
– FE550/600
– Fe500D
• Structural steel
• Dia of bars, manufacturer, rates at site or factory
CEMENT
• OPC
– 33 Grade
– 43 Grade
– 53 Grade
• PPC
• Manufacturer, rates at site or factory
MATERIALS
• Materials except the materials for which
escalation is paid separately
FORMULA
Pk = W * (X/100) * (Ki – Kio)/(Kio)
Where,
Pk = variation in cost of item
W = Cost of work done
X= component of item(s)
Ki = Price index of the item under consideration for the work
done on the date as mentioned in the contract
Kio = Price index of the item under consideration on the last
day of receipt of tenders
PRICE VARIATION
• Price variation is given on the cost of work excluding contractor’s profit and overheads and
excluding on advances paid including on materials earlier if any and amount of bills of work done,
adjusting recoveries if any and variations paid on market rates
• Gross value of work = A
• Gross value of work done in last bill for which price variation paid = B
• Cost of materials on which secured advance paid since previous bill = D
• Cost of materials recovered since previous bill = E
• Cost of materials on which secured advance paid since previous bill after adjusting recoveries of
materials used = D – E
• Advance payment made since previous bill = G
• Recoveries of advance payments made since previous bill = H
• Cost of variations paid on market rates since previous bill = J
• Cost on which price variation payable= M *(A-B+D-E+G-H-J)
• IN CASE CONTRACTOR’S PROFITS AND OH ARE CONSIDERED 15%, M=0.85. FOR CP&OH BEING
10%, M=0.90 AND IF CP&OH=25%, M=0.75
• SINCE PREVIOUS BILL MEANS IN THIS BILL AS PER THE PERIODICITY OF ESCALATION TO BE PAID
AS PER CONTRACT. IN CASE, IT IS QUARTERLY, IT WILL BE WORKED OUT ON QUARTERLY BILL
BASIS AND IF MONTHLY, ON MONTHLY BASIS.
LABOUR RATES
• Labour rates are taken as per government
notifications or as mentioned in the contract
• Whether the workers are really getting
benefit of minimum wages?
• Should they be paid as per notification?
• Should they be reimbursed? If so, how?
RATES OF MATERIALS
• Are taken as per wholesale price index for
civil/electrical components of construction
materials as published by economic advisor,
Govt. of India, Ministry of commerce and
industry or as mentioned in the contract
RATES OF STEEL
• Reinforcement bars
– TMT
– Fe 415
– Fe 500
– FE550/600
– Fe500D
• Structural steel
• Dia of bars, manufacturer, rates at site or factory
• IT SHOULD BE ENSURED THAT BASE RATES AND RATES OF OTHER
PERIODS ARE TAKEN OF SAME TYPE OF STEEL AND OF SAME
MANUFACTURER AND AT SAME PLACE (SITE OR FACTORY, BETTER
AT FACTORY AS RATES MAY VARY FROM SITE TO SITE)
RATES OF CEMENT
• OPC
– 33 Grade
– 43 Grade
– 53 Grade
• PPC
• Manufacturer, rates at site or factory
• IT SHOULD BE ENSURED THAT BASE RATES AND RATES OF
OTHER PERIODS ARE TAKEN OF SAME TYPE OF CEMENT
AND OF SAME MANUFACTURER AND AT SAME PLACE
(SITE OR FACTORY, BETTER AT FACTORY AS RATES MAY
VARY FROM SITE TO SITE)
PRICE VARIATION
• Sometimes price variations is not allowed, or allowed
for works having contract period more than specified
time.
• Price variation is normally paid quarterly
• It therefore appears that price variation may be paid
for all works having contract period more than 6
months to avoid uncertainties and risks of contractors
• Some EPC and Turn key contracts do not have
provisions of price variation clause
Thanks for attending
Dr K M Soni, ADG (Retd.), CPWD, New Delhi
Also available on Youtube: KRISHNA MURARI Soni at
https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw

Mais conteúdo relacionado

Mais procurados

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
Aszahari Aie
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
Mohammed Tanbouz
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 

Mais procurados (20)

Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Contracts
ContractsContracts
Contracts
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Epc contractor
Epc contractorEpc contractor
Epc contractor
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Construction contract
Construction contract Construction contract
Construction contract
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 

Semelhante a Price variation in works contracts

Unit4_Managing Contracts.ppt
Unit4_Managing Contracts.pptUnit4_Managing Contracts.ppt
Unit4_Managing Contracts.ppt
KGSCSEPSGCT
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbal
Zakee Kazmee
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
jairam131
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
Allan Berry
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
Mohib Ullah
 

Semelhante a Price variation in works contracts (20)

Unit4_Managing Contracts.ppt
Unit4_Managing Contracts.pptUnit4_Managing Contracts.ppt
Unit4_Managing Contracts.ppt
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
3. Contract Pricing.pdf
3. Contract Pricing.pdf3. Contract Pricing.pdf
3. Contract Pricing.pdf
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbal
 
Qsct tendering dr_clj
Qsct tendering dr_cljQsct tendering dr_clj
Qsct tendering dr_clj
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
NEW MRP CV 2016
NEW MRP CV 2016NEW MRP CV 2016
NEW MRP CV 2016
 
Application of price adjustment in civil works contract
Application of price adjustment in civil works contractApplication of price adjustment in civil works contract
Application of price adjustment in civil works contract
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Sagar_cv
Sagar_cv Sagar_cv
Sagar_cv
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
 

Mais de Dr K M SONI

Mais de Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
Maintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural PlanningMaintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural Planning
 
Safety in Public Works
Safety in Public WorksSafety in Public Works
Safety in Public Works
 
About me i.e. Dr. K M Soni
About me i.e. Dr. K M SoniAbout me i.e. Dr. K M Soni
About me i.e. Dr. K M Soni
 
Repair and Maintenance of Heritage Structures
Repair and Maintenance of Heritage StructuresRepair and Maintenance of Heritage Structures
Repair and Maintenance of Heritage Structures
 

Último

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Price variation in works contracts

  • 1. CONTRACT CONDITIONS-IV: PRICE VARIATION Dr K M Soni, ADG(Retd.), CPWD, New Delhi
  • 2. PRICE VARIATION • Price variation in a works contract is the variation of cost of contract in case of increase or decrease of cost of items of work undergoing during the period of last date of submission of tenders and completion date of work as per the contract
  • 3. PRICE VARIATION • Contractor submits his bids (Financial) considering rates of items on the day of submission of his tender • Employer fixes the last date for submission of tenders • Therefore, the basis of rates are considered the last day of submission of financial bids even if a contractor might have submitted his bid earlier
  • 4. VARIATION COMPONENTS • A works contract has hundreds of items and materials • It is difficult to consider variation of rates in each item hence a limited items are considered for working out variations and other included in a group of items
  • 5. MAJOR COMPONENTS • Labour – Skilled – unskilled • Steel – Reinforcement bars – Structural steel • Cement – OPC – PPC • POL • Bitumen • Others
  • 6. LABOUR Unskilled 13584 13896 1.023 Semiskilled 14958 15296 1.023 Skilled 16468 16858 1.024 As seen, rate increase is almost with same percentage hence rates for unskilled worker are considered in the analysis
  • 7. STEEL • Reinforcement bars – TMT – Fe 415 – Fe 500 – FE550/600 – Fe500D • Structural steel • Dia of bars, manufacturer, rates at site or factory
  • 8. CEMENT • OPC – 33 Grade – 43 Grade – 53 Grade • PPC • Manufacturer, rates at site or factory
  • 9. MATERIALS • Materials except the materials for which escalation is paid separately
  • 10. FORMULA Pk = W * (X/100) * (Ki – Kio)/(Kio) Where, Pk = variation in cost of item W = Cost of work done X= component of item(s) Ki = Price index of the item under consideration for the work done on the date as mentioned in the contract Kio = Price index of the item under consideration on the last day of receipt of tenders
  • 11. PRICE VARIATION • Price variation is given on the cost of work excluding contractor’s profit and overheads and excluding on advances paid including on materials earlier if any and amount of bills of work done, adjusting recoveries if any and variations paid on market rates • Gross value of work = A • Gross value of work done in last bill for which price variation paid = B • Cost of materials on which secured advance paid since previous bill = D • Cost of materials recovered since previous bill = E • Cost of materials on which secured advance paid since previous bill after adjusting recoveries of materials used = D – E • Advance payment made since previous bill = G • Recoveries of advance payments made since previous bill = H • Cost of variations paid on market rates since previous bill = J • Cost on which price variation payable= M *(A-B+D-E+G-H-J) • IN CASE CONTRACTOR’S PROFITS AND OH ARE CONSIDERED 15%, M=0.85. FOR CP&OH BEING 10%, M=0.90 AND IF CP&OH=25%, M=0.75 • SINCE PREVIOUS BILL MEANS IN THIS BILL AS PER THE PERIODICITY OF ESCALATION TO BE PAID AS PER CONTRACT. IN CASE, IT IS QUARTERLY, IT WILL BE WORKED OUT ON QUARTERLY BILL BASIS AND IF MONTHLY, ON MONTHLY BASIS.
  • 12. LABOUR RATES • Labour rates are taken as per government notifications or as mentioned in the contract • Whether the workers are really getting benefit of minimum wages? • Should they be paid as per notification? • Should they be reimbursed? If so, how?
  • 13. RATES OF MATERIALS • Are taken as per wholesale price index for civil/electrical components of construction materials as published by economic advisor, Govt. of India, Ministry of commerce and industry or as mentioned in the contract
  • 14. RATES OF STEEL • Reinforcement bars – TMT – Fe 415 – Fe 500 – FE550/600 – Fe500D • Structural steel • Dia of bars, manufacturer, rates at site or factory • IT SHOULD BE ENSURED THAT BASE RATES AND RATES OF OTHER PERIODS ARE TAKEN OF SAME TYPE OF STEEL AND OF SAME MANUFACTURER AND AT SAME PLACE (SITE OR FACTORY, BETTER AT FACTORY AS RATES MAY VARY FROM SITE TO SITE)
  • 15. RATES OF CEMENT • OPC – 33 Grade – 43 Grade – 53 Grade • PPC • Manufacturer, rates at site or factory • IT SHOULD BE ENSURED THAT BASE RATES AND RATES OF OTHER PERIODS ARE TAKEN OF SAME TYPE OF CEMENT AND OF SAME MANUFACTURER AND AT SAME PLACE (SITE OR FACTORY, BETTER AT FACTORY AS RATES MAY VARY FROM SITE TO SITE)
  • 16. PRICE VARIATION • Sometimes price variations is not allowed, or allowed for works having contract period more than specified time. • Price variation is normally paid quarterly • It therefore appears that price variation may be paid for all works having contract period more than 6 months to avoid uncertainties and risks of contractors • Some EPC and Turn key contracts do not have provisions of price variation clause
  • 17. Thanks for attending Dr K M Soni, ADG (Retd.), CPWD, New Delhi Also available on Youtube: KRISHNA MURARI Soni at https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw