SlideShare uma empresa Scribd logo
1 de 10
Project Management
Key Concepts
Cost Forecasting
What is it?
As the project progresses, the project team may
develop forecasts for how much it will cost to
complete the project, and compare these to the
planned Budget (Budget at Completion).
Cost Forecasting
What is it?
Project Forecasting techniques can include:
• Estimate at Completion (EAC)
• Estimate to Complete (ETC)
• Variance at Completion (VAC)
• To Complete Performance Index (TCPI)
Cost Forecasting
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
Cost Forecasting
Estimate at Completion (EAC)
Is the expected total cost of completing all the work.
EAC = AC + BAC – EV (If future work will be completed at planned rate)
EAC = BAC/CPI) (If CPI remains the same)
EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid)
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
EAC = $5,000 + ($10,000 - $3000)
= $5,000 + $7,000
= $12,000
Cost Forecasting
Estimate at Completion (EAC)
Is the expected total cost of completing all the work.
EAC = AC + BAC – EV (If future work will be completed at planned rate)
EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same)
EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid)
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
EAC = $10,000 / ($3,000/$5000)
= $10,000 / 0.60
= $16,667
Cost Forecasting
Estimate at Completion (EAC)
Is the expected total cost of completing all the work.
EAC = AC + BAC – EV (If future work will be completed at planned rate)
EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same)
EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid)
Project budget of $10,000, where 30% completed,
against 40% planned and $5,000 spent so far.
EAC = $5,000 + ($10,000-$3000)/((EV/AC) x (EV/PV))
(0.45)
= $5,000 + ($7,000/(0.60 x 0.75)) $15,555
= $20,555
Cost Forecasting
Estimate to Complete (ETC)
Is the expected cost to finish all the remaining project work.
ETC = EAC – AC (Estimate at Completion – Actual Cost)
Project budget of $10,000, where 30% completed,
against 40% planned and $5,000 spent so far.
($12,000)
ETC = ($5000 + ($10,000-$3,000)) - $5,000
= $7,000
Cost Forecasting
Variance at Completion (VAC)
Is the estimated difference in cost at the completion of the project.
VAC = BAC – EAC
Positive: Ahead of Schedule; Negative: Behind Schedule
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
($7,000)
VAC = $10,000 – ($5000 + ($10,000-$3,000))
= -$2,000
Cost Forecasting
To Complete Performance Index (TCPI)
The efficiency that must be maintained in order to complete your
project as planned.
• TCPI = (BAC – EV)/(BAC – AC)
• > 1 Harder to Complete, < 1 Easier to Complete
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
TCPI = ($10,000 - $3,000) / ($10,000 - $5000)
= $7,000 / $5,000
= 1.4 (harder to complete)

Mais conteúdo relacionado

Mais procurados

Techniques in black box testing
Techniques in black box testingTechniques in black box testing
Techniques in black box testing
Duy Tan Geek
 

Mais procurados (8)

PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
EV ِAV PV example
EV ِAV PV exampleEV ِAV PV example
EV ِAV PV example
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
Work Summary
Work SummaryWork Summary
Work Summary
 
Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
Techniques in black box testing
Techniques in black box testingTechniques in black box testing
Techniques in black box testing
 

Semelhante a 7.4 Forecasting Techniques

Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 

Semelhante a 7.4 Forecasting Techniques (20)

Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Project Management 3.2 cost
Project Management 3.2 costProject Management 3.2 cost
Project Management 3.2 cost
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 

Mais de DavidMcLachlan1

Mais de DavidMcLachlan1 (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 

Último

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 

Último (20)

Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 

7.4 Forecasting Techniques

  • 3. What is it? As the project progresses, the project team may develop forecasts for how much it will cost to complete the project, and compare these to the planned Budget (Budget at Completion). Cost Forecasting
  • 4. What is it? Project Forecasting techniques can include: • Estimate at Completion (EAC) • Estimate to Complete (ETC) • Variance at Completion (VAC) • To Complete Performance Index (TCPI) Cost Forecasting Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far.
  • 5. Cost Forecasting Estimate at Completion (EAC) Is the expected total cost of completing all the work. EAC = AC + BAC – EV (If future work will be completed at planned rate) EAC = BAC/CPI) (If CPI remains the same) EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work) EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EAC = $5,000 + ($10,000 - $3000) = $5,000 + $7,000 = $12,000
  • 6. Cost Forecasting Estimate at Completion (EAC) Is the expected total cost of completing all the work. EAC = AC + BAC – EV (If future work will be completed at planned rate) EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same) EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work) EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EAC = $10,000 / ($3,000/$5000) = $10,000 / 0.60 = $16,667
  • 7. Cost Forecasting Estimate at Completion (EAC) Is the expected total cost of completing all the work. EAC = AC + BAC – EV (If future work will be completed at planned rate) EAC = BAC/CPI [CPI = EV/AC] (If CPI remains the same) EAC = AC + [(BAC – EV)/(CPI x SPI)] (If both the CPI and SPI influence the remaining work) EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EAC = $5,000 + ($10,000-$3000)/((EV/AC) x (EV/PV)) (0.45) = $5,000 + ($7,000/(0.60 x 0.75)) $15,555 = $20,555
  • 8. Cost Forecasting Estimate to Complete (ETC) Is the expected cost to finish all the remaining project work. ETC = EAC – AC (Estimate at Completion – Actual Cost) Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. ($12,000) ETC = ($5000 + ($10,000-$3,000)) - $5,000 = $7,000
  • 9. Cost Forecasting Variance at Completion (VAC) Is the estimated difference in cost at the completion of the project. VAC = BAC – EAC Positive: Ahead of Schedule; Negative: Behind Schedule Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. ($7,000) VAC = $10,000 – ($5000 + ($10,000-$3,000)) = -$2,000
  • 10. Cost Forecasting To Complete Performance Index (TCPI) The efficiency that must be maintained in order to complete your project as planned. • TCPI = (BAC – EV)/(BAC – AC) • > 1 Harder to Complete, < 1 Easier to Complete Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. TCPI = ($10,000 - $3,000) / ($10,000 - $5000) = $7,000 / $5,000 = 1.4 (harder to complete)